This document provides an overview of the Sydney Metro Northwest Project, including its budget, social and economic rationale, key statistics, funding mechanisms, and risk analysis. It also discusses the mitigation plan for potential risks. Find study material and solved assignments on Desklib.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
Running head:SYDNEY METRO NORTHWEST PROJECT Sydney Metro Northwest Project Name of the Student Name of the University Author’s note
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
1SYDNEY METRO NORTHWEST PROJECT Table of Contents Part A: Project Overview.................................................................................................................2 1.1 Overall Budget.......................................................................................................................2 1.2 Social and Economic Rationale.............................................................................................2 1.3 Key Statistics.........................................................................................................................3 1.4 Funding Mechanisms.............................................................................................................4 1.5 Key Stakeholders...................................................................................................................4 Part B: Risk Analysis.......................................................................................................................5 Part C: Risk Mitigation Plan............................................................................................................7 References......................................................................................................................................10
2SYDNEY METRO NORTHWEST PROJECT Part A: Project Overview 1.1 Overall Budget During the design of the project, three major contracts were awared during the year 2013 and 2014 in order to deliver and operate the functions within Sydney Metro Northwest. Stations and Tunnels Civil Works– A contract of $1.15 billion was awarded to CPB John Holland Dragados. The primary purpose of the contract was to involve the building of the 15 kilometre long twin tunnels between Epping and Bella Vista(Sydneymetro.info 2019). It was thus considered as one of the longest railway tunnels that had been ever built in Australia. Viaduct and Surface Civil Works– A major contract of $340 million was awarded to Impregilo-Salini joint venture on 17thDecember 2013. The contract had involved the building of the four kilometre long elevated form of skytrain between Rouse Hill and Bella Vista (Clifton, Mulley and Hensher 2014). This had also included a 270-metre cabled bridge at Windsor Road situated at Rouse Hill. Trains, Systems and Operations– The contract of $3.7 billion operators was majorly awarded to Northwest Rapid Transit on 15thSeptember 2014 (Chalker and Loosemore 2016). The contract had involved the delivery of eight new railway stations, new metro trains in Sydney, upgrading of the railway connection between Epping and Chatswood and also building a major space for accomodating 4000 cars. 1.2 Social and Economic Rationale The Sydney Metro Project is considered as one of the largest public transport project in Australia that had approximately costed up to $12.5 billion. The benefits from the project is that the new trains would have a capacity of carrying approximately 46,000 people within every hour
3SYDNEY METRO NORTHWEST PROJECT (Cardew 2017). The addition of this project would also enable a fast and reliable network within the North West area of Sydney. It would also improve the commute for people who choose public transport and would also decrease the congestion on roads. Apart from such benefits, one another important benefit is that it would also increase the position of job market. The drawbacks, which could be estimated from the project are that it would lead to a negative economic impact (Weisbrod, Mulley and Hensher 2016). With the introduction of the metro project, large numbers of railway staff could lose their jobs in the long term. The rail link between Epping to Chastwood Rail Link would be shut down for almost half a year. 1.3 Key Statistics Scope and Size– The scope of the Sydney metro Project is to deliver a quality service that had been never experienced by the people of Australia. The project would deliver a capacity to increase the number of existing trains to enter the CBD (Legaspi, Hensher and Wang 2015). The massive size of the project could be estimated from the fact that the metro would have enough room for accommodating 100,000 commuters in an hour during the peak times. This would thus help a lot of people to travel from one part of the city and reach to their destinations. Budget and Estimated Cost– The budget and estimated cost for the project has been confirmed as $8.3 billion. Time required to complete the Project– The time required to complete the entire project would take a time period of 7 years. The project had initially started in the year 2013 and is expected to be completed by the year 2019. Key Construction Elements or Phases– The key construction elements or phases that would form a major part of the project are:
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
4SYDNEY METRO NORTHWEST PROJECT 1. Strategic Assessment Phase 2. Investment Decision Phase 3. Phase of planning for approvals 4. Phase of Procurement 5. Delivery Phase 6. Operations Phase Environmental benefits– The certain environmental benefits that have been addressed whiledesigningtheprojectarebasedontheConstructionEnvironmentalManagement Framework (CEMF). Based on this framework, the government had set out standards for environmental and sustainability management (Gharehbaghi and Sagoo 2016). This would also help in ensuring the Sydney Metro and their contractors to comply as per the required planning and statutory requirements. 1.4 Funding Mechanisms The NSW and Australian Government are the initial funding partners for the Sydney Metro Project. The government has also signed several contract to grant the funding for the project. They had also secured a 20-month agreement over electric supply with ERM Power. A total amount of $8.3 billion have been invested for the growth of the project. 1.5 Key Stakeholders The key stakeholders that have been identified within the project include the Australian and NSW Governments, the Minister for Transport and Infrastructure, Premier of NSW and Minister for Western Sydney. Other stakeholders involved are the project manager, technicians,
5SYDNEY METRO NORTHWEST PROJECT architects, site managers and workers. These stakeholders would form a major part of the project as they would be responsible for maintaining each of the aspects of the project. They would also hold responsibility over seeing each of the necessary work that would be done over the project. Part B: Risk Analysis Based on the focus over qualitative and quantitative measures for the identification of potentialrisksthatcouldbeincurredfortheproject,thelikelihoodandthepossible consequences for such risks could be discussed. A consideration over the Project Management Body of Knowledge could be assessed (A guide to the project management body of knowledge 2017). The following risks could approach towards the project: Delay in getting approvals of project plan– The project plan might have to pass through several stages in order to get it approved by the governing body. This includes huge risks that the project might get cancelled due to excessive need of funds. Delay in getting proper approval would lead to delay in starting the project (Flyvbjerg 2014). The governing body might think that the time required for the completion of the project might be longer than expected. Hence, it might not be feasible to start the project. Conflict between the infrastructure companies– There might be several conflicts between the companies who would be responsible for building the project. They might be given the required amount of funds that would be needed by them while designing and constructing the project. Other problems could be based on the problems of bidding as who would perform the construction activity over the project. These kind of conflicts could hamper the decisions taken by the governing body to decide on the best contractor who would be given the responsibility for the start of the project.
6SYDNEY METRO NORTHWEST PROJECT Disputes in acquisition of land– The government might not accept the issue of providing sufficient land for the project. This would also be considered as a major factor for delaying the project. The construction company would not be able to initiate the project without a proper form of approval from the government body about the approval of land. This could hamper and delay the start activity for the project. Delay in sponsorship and fund gathering– There might not be a proper source for funding of the project. The government might not accept the project plan or might not provide enough funds for the start of the project (Jardine and Riley 2017). This might also prove to be a negative impact over the project. Technical Issues– Testing issues such as during the technical design over the project could also be considered as a major risk for the project. Electric failure or low supply of electric could also be considered as a major factor for the project (Hwang, Zhao and Yu 2016). The instruments or devices that need to be used within the project might not be able to provide sufficient output during the construction period. This could be a negative factor for the project and might harm the project badly. Unavoidablecircumstanceswithintheproject–Severalkindofunavoidable circumstances could lead the project towards a negative outcome. There might be accidents during the construction period that might put a negative impact over the project (Duet al.2016). Labour agitation based on payment disputes could arise during the construction period at any point of time. On the other hand, negative impacts could also incur within the project during unforeseenweatherconditionssuchasheavyrainsthatcouldhampertheprojectand construction activities. Due to heavy rains, the people involved within the construction would not
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
7SYDNEY METRO NORTHWEST PROJECT be able to initiate the project activities. Hence, this could lead to tremendous negative outcomes for the project.
8SYDNEY METRO NORTHWEST PROJECT RisksLikelihood of RiskConsequence of Risks Delay in getting an approval of the project report LowHigh Conflict between the infrastructure provider companies LowHigh DisputeswithinAcquisitionof Land HighHigh Delayingettingsponsorsand approval of funds LowHigh Technical issues during performing of construction operations LowMedium Unavoidable circumstances such as constructionalaccidents,terror attacks or worst weather conditions LowHigh Part C: Risk Mitigation Plan Based on the discussed scenarios of risks, it can be discussed that a proper form of mitigation plan would be taken to assess each of the risks. Based on the assessment over each of the discussed scenarios of risks, a proper mitigation plan could be framed. The mitigation plan for the above risks could be described as: Delayingettingapprovalsofprojectplan–Thegovernmentbodyshouldbe approached with more efforts. They should be provided with the exact details over each of the activities, the cost of resources and other aspects in relation to the project (Qaziet al.2016). The governing body and other stakeholders involved within the project should be given all the possible details based on which they would be able to understand the scenario and thus give a proper approval to the project. The financial plan over the project should be discussed with the stakeholder groups.
9SYDNEY METRO NORTHWEST PROJECT Conflict between the infrastructure companies –After the approval for the project has been made, the plan should be discussed with the companies who would be providing the infrastructural facilities. The financial and project plan should be discussed with them and all the possible measures should be taken to convince them regarding the project (O’Brien and Pike 2017). Based on a proper kind of bidding over the project, the appropriate infrastructural company would be given the responsibility to initiate the project. the governing body should assign a responsibility to each of the stakeholders and thus should also look into each of the working progress that would be made within the project. Disputes in acquisition of land –There might in disputes with the acquisition of land needed for the project. The primary project sponsor and the governing bodies involved within the project should approach to the government about a proper approval for land. These sponsorship providers should invest highly in order to use the land that would be provided to them on a lease basis. Funds should also be allocated for paying the annual revenues for the land and the other facilities that would be provided to them during the project phases. Delay in sponsorship and fund gathering –In order to get a proper approval about the sanctioning of funds for the project, the government should timely pay each of the amount that would be required for the project. A timely paying of the interests and shares to the concerned organisations would ensure that the project is on proper tracks and there are no difficulties arising during the project work (Wiesel, Liu and Buckle 2018). Each of the sponsorship bodies should be detailed out with the project plan and thus they could be convinced about the idea and future outcomes after the completion of the project. A commitment from the stakeholder bodies would be necessary to start the work over the project.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
10SYDNEY METRO NORTHWEST PROJECT Technical Issues –Before the start of the project, it would be the primary responsibility of the technical stakeholders and project manager to check each of the technical resources that would be required during the project. The project manager and the project sponsor should individually look into each of the resources that would be procured for the project (Powellet al. 2016). A periodic form of inspection into each of the technical inputs needed during the project should be properly checked. The electronic equipment should be highly inspected so that they would not create a problem during the works over the project. The technical glitches should thus be properly be focused in order to gain a firm foothold over the project. Unavoidable circumstances within the project –There might be several situations in which environmental factors might negatively impact the project. The chances of accidents are always high during a construction project. In order to mitigate such situations, the disaster management team should develop a plan that would be able to secure the area of construction. Each of the workers should be provided with safety equipment that would be necessary during the work over the project (Santamouriset al.2018). The workers working within the project should be provided with helmets and other equipment that would help them in time of emergency. On the other hand, the weather forecasting team should provide weather reports that would help the disaster management team in procuring such equipment meant to protect the equipment needed during the project. They should thus be proactive in taking necessary actions during such times of crises (Sahinet al.2017). A proper insurance policy should also be signed among the parties who are involved in the construction work. The disaster management team should also take eco-friendly steps in order to gain proper reports about the impacts that might be
11SYDNEY METRO NORTHWEST PROJECT made during the project. This would also help in ensuring the performing of work over the project in a successful manner.
12SYDNEY METRO NORTHWEST PROJECT References Cardew,R.,2017.PrivatisationofinfrastructureinSydney,Australia.InInfrastructure Provision and the Negotiating Process(pp. 129-146). Routledge. Chalker, M. and Loosemore, M., 2016. Trust and productivity in Australian construction projects:asubcontractorperspective.Engineering,ConstructionandArchitectural Management,23(2), pp.192-210. Clifton, G.T., Mulley, C. and Hensher, D.A., 2014. Bus Rapid Transit versus Heavy Rail in suburban Sydney–Comparing successive iterations of a proposed heavy rail line project to the pre-existing BRT network.Research in Transportation Economics,48, pp.126-141. Du, L., Tang, W., Liu, C., Wang, S., Wang, T., Shen, W., Huang, M. and Zhou, Y., 2016. Enhancingengineer–procure–constructprojectperformancebypartneringininternational markets: Perspective from Chinese construction companies.International Journal of Project Management,34(1), pp.30-43. Flyvbjerg, B., 2014. What you should know about megaprojects and why: An overview.Project management journal,45(2), pp.6-19. Gharehbaghi, K. and Sagoo, A., 2016. Environmental Implications of the Sydney Metro: A Case Study.InternationalProceedingsofChemical,BiologicalandEnvironmentalEngineering (IPCBEE),97(3), pp.15-21. Hwang, B.G., Zhao, X. and Yu, G.S., 2016. Risk identification and allocation in underground rail construction joint ventures: contractors’ perspective.Journal of Civil Engineering and Management,22(6), pp.758-767.
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
13SYDNEY METRO NORTHWEST PROJECT Jardine, D. and Riley, M., 2017. Tunnel vision: Optimising procurement models to deliver successful tunnelling projects. In16th Australasian Tunnelling Conference 2017: Challenging Underground Space: Bigger, Better, More(p. 632). Engineers Australia. Legaspi, J., Hensher, D. and Wang, B., 2015. Estimating the wider economic benefits of transport investments: The case of the Sydney North West Rail Link project.Case Studies on Transport Policy,3(2), pp.182-195. O’Brien,P.andPike,A.,2017.10.Thefinancializationandgovernanceof infrastructure.Handbook on the Geographies of Money and Finance, p.223. Powell, J.P., Fraszczyk, A., Cheong, C.N. and Yeung, H.K., 2016. Potential benefits and obstacles of implementing driverless train operation on the tyne and wear metro: a simulation exercise.Urban Rail Transit,2(3-4), pp.114-127. Project Management Institute. (2017).A guide to the project management body ofknowledge (PMBOK guide). (6th ed.). Newton Square, PA: Project Management Institute. Qazi, A., Quigley, J., Dickson, A. and Kirytopoulos, K., 2016. Project Complexity and Risk Management(ProCRiM):Towardsmodellingprojectcomplexitydrivenriskpathsin construction projects.International Journal of Project Management,34(7), pp.1183-1198. Sahin, O., Stewart, R.A., Giurco, D. and Porter, M.G., 2017. Renewable hydropower generation asaco-benefitofbalancedurbanwaterportfoliomanagementandfloodrisk mitigation.Renewable and Sustainable Energy Reviews,68, pp.1076-1087.
14SYDNEY METRO NORTHWEST PROJECT Santamouris, M., Haddad, S., Saliari, M., Vasilakopoulou, K., Synnefa, A., Paolini, R., Ulpiani, G., Garshasbi, S. and Fiorito, F., 2018. On the energy impact of urban heat island in Sydney: Climate and energy potential of mitigation technologies.Energy and Buildings,166, pp.154-164. Sydneymetro.info. (2019).Sydney Metro Northwest Project Overview | Sydney Metro. [online] Availableat:https://www.sydneymetro.info/northwest/project-overview[Accessed18Apr. 2019]. Weisbrod, G., Mulley, C. and Hensher, D., 2016. Recognising the complementary contributions of cost benefit analysis and economic impact analysis to an understanding of the worth of public transport investment: A case study of bus rapid transit in Sydney, Australia.Research in Transportation Economics,59, pp.450-461. Wiesel, I., Liu, F. and Buckle, C., 2018. Locational disadvantage and the spatial distribution of government expenditure on urban infrastructure and services in metropolitan Sydney (1988– 2015).Geographical Research,56(3), pp.285-297.