Running head: PROJECT PROPOSAL DOCUMENT Project Proposal Document: Teaching room refurbishment of Queen's building of Roehamption University Name of the Student: Student ID: Name of the University: Author’s note:
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
1PROJECT PROPOSAL DOCUMENT Table of Contents Introduction......................................................................................................................................2 1. Project Initiation Document.........................................................................................................2 2. Gantt chart...................................................................................................................................7 3. Risk Register................................................................................................................................8 4. Short Report to Project Sponsor..................................................................................................9 Conclusion.....................................................................................................................................13 Bibliography..................................................................................................................................14
2PROJECT PROPOSAL DOCUMENT Introduction As stated byKerzner and Kerzner (2017), the project management hold a critical role for forming the successive alignment of the activities favouring the alignment of the successful project activity completion. The formation of the operations favouring the alignment of the successful project completion and development is helpful for aligning the development of the operations. The intrusion of the activities would also help in forming the completion of the project. The following assignment had been made considering the elements of project ‘Teaching rooms refurbishment of Queen's building of Roehamption University’. The assignment would include the Project Initiation Document involving the initial budget information and time scales, Gantt chart representing the project schedule, fully developed risk register, and a short report to the project sponsor. 1. Project Initiation Document Project Background:The project of‘Teaching rooms refurbishment of Queen's building of Roehamption University’ is developed for refurnishing the teaching rooms. The Queen’s building of Roehamption University requires re-modification as it has become very old. The completion of the project would be dependent on the alignment of the successful alignment of the operations favoring the involvement of the successive development of the activities. The involvement of the construction activities was dependent on the alignment of the activities of the project. The refurbishment of the teaching rooms would include cleaning the teaching rooms, fixing the electricity lines, fixing the damps and breaks on the walls, windows and doors are
3PROJECT PROPOSAL DOCUMENT fixed, painting the walls, seats, tables, and desks are added, new fans, lights, and switches are added, and fire extinguishers are re-added activities. Aims:Theprojectof‘TeachingroomsrefurbishmentofQueen'sbuildingof Roehamption University’ has the aims of refurbishment of teaching rooms so that effective alignmentof the activitieswould favor the incrementof the constructionactivities. The deployment of the operations would also be helpful for forming the allowance of the activities for construction of the project activities. The fixing of walls, floors, and electric lines, painting walls, and addition of seats, tables, chairs, desks, fans, lights, switches, and fire extinguisher are also the aims of the project. Objectives:The objectives of the‘Teaching rooms refurbishment of Queen's building of Roehamption University’ project are, To refurbish the teaching rooms of Queen’s building of Roehamption University would be dependent on the construction project management Touseprinciplesofprojectmanagementfordevelopingprojectplanand documents for aligning the formation of the operations To utilize the successive alignment of the activities favoring the management of the operations Scope:Theprojectof‘TeachingroomsrefurbishmentofQueen'sbuildingof Roehamption University’ would be deployed for listing the alignment of the operations of construction activities. The scope of the project is,
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
4PROJECT PROPOSAL DOCUMENT In scope of the project:The project plan, construction activities,fixing of walls, floors, and electric lines, painting walls, and addition of seats, tables, chairs, desks, fans, lights, switches, and fire extinguisher are all in scope items of the project. Out of scope of the project:The communication plan, scope change management, and control implementation plan are out of scope items for this project. Deliverables:The deliverables of the project of‘Teaching rooms refurbishment of Queen's building of Roehamption University’ include, a)Fixed Windows, Doors, and Walls b)Repainted Walls c)Addition of newseats, tables, chairs, desks, fans, lights, switches, and fire extinguisher d)Final project Plan Constraints:The time, budget, and scope of the project of‘Teaching rooms refurbishment of Queen's building of Roehamption University’ to refurbishment construction activities would act as the main constraints of the project. Assumptions:The assumptions of the project of‘Teaching rooms refurbishment of Queen's building of Roehamption University’ would include the completion of the project in estimated time duration, accumulation of the resources required for the project completion, and keeping the quality of operations as required by the client. Risk Analysis:The identified risks of the project of‘Teaching rooms refurbishment of Queen's building of Roehamption University’ are, a)Human Accidents and Sickness
5PROJECT PROPOSAL DOCUMENT b)Equipments Failure c)Climatic Hindrance d)Power Failure e)Collapsing of Structure f)Cost Over Run g)Excess Time Consumption h)Complaints from Local Community i)Quality issues in raw material j)Client Disagreement Key Staff and Stakeholder Analysis:The project team for the project of‘Teaching rooms refurbishment of Queen's building of Roehamption University’ would include the following team members, a)Analyst b)Project Manager c)Documenter d)Planner e)Workers f)Contractor g)Electrician h)Painter The stakeholders of the project of‘Teaching rooms refurbishment of Queen's building of Roehamption University’ would include,
6PROJECT PROPOSAL DOCUMENT a)Investors b)Client c)Steering Committee d)Teachers and Students of the University e)Project Manager f)Contractor Timescales:The expected timescale for the project of ‘Teaching rooms refurbishment of Queen's building of Roehamption University’ is shown in the table below, WBSTask NameDuratio nStartFinish 0Teaching rooms refurbishment of Queen's building of Roehamption University80 daysMon 5/7/18Fri 8/24/18 1Project Initiation20 daysMon 5/7/18Fri 6/1/18 2Project Planning14 daysMon 5/14/18 Thu 5/31/18 3Execution Phase60 daysMon 6/4/18Fri 8/24/18 4Project is Closed0 daysWed 8/22/18 Wed 8/22/18 Table 1: Timescale for the project
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
7PROJECT PROPOSAL DOCUMENT 2. Gantt chart The Gantt chart for the project of ‘Teaching rooms refurbishment of Queen's building of Roehamption University’ is shown in the diagram below, IDTask Mode WBSTask NameDurationStartFinish 00Teaching rooms refurbishment of Queen's building of Roehamption University 80 daysMon 5/7/18Fri 8/24/18 11Project Initiation20 daysMon 5/7/18Fri 6/1/18 21.1Analysis of requirements2 daysMon 5/7/18Tue 5/8/18 31.2Hiring the contractor3 daysWed 5/9/18Fri 5/11/18 41.3Project Initiation Documentation2 daysMon 5/21/18Tue 5/22/18 51.4Charter Documentation2 daysMon 5/28/18Tue 5/29/18 61.5Submitting the documents1 dayWed 5/30/18Wed 5/30/18 71.6Review and Sign up1 dayFri 6/1/18Fri 6/1/18 82Project Planning14 daysMon 5/14/18Thu 5/31/18 92.1Development of task list3 daysMon 5/14/18Wed 5/16/18 102.2Aligning Resources2 daysThu 5/17/18Fri 5/18/18 112.3Schedule development5 daysMon 5/21/18Fri 5/25/18 122.4Plan Approval1 dayThu 5/31/18Thu 5/31/18 133Execution Phase60 daysMon 6/4/18Fri 8/24/18 143.1Cleaning the teaching rooms7 daysMon 6/4/18Tue 6/12/18 153.2Fixing the Electricity Lines10 daysWed 6/13/18Tue 6/26/18 163.3Fixing the damps and breaks on the walls 15 daysMon 7/16/18Fri 8/3/18 173.4Windows and Doors are fixed7 daysThu 7/5/18Fri 7/13/18 183.5Painting the walls10 daysMon 8/6/18Fri 8/17/18 193.6Seats, Tables, and Desks are added5 daysMon 8/20/18Fri 8/24/18 203.7New fans, lights, and switches are added 6 daysWed 6/27/18Wed 7/4/18 213.8Fire Extinguishers are re-added3 daysMon 8/20/18Wed 8/22/18 223.9Checking the electricity connection4 daysThu 7/5/18Tue 7/10/18 234Project is Closed0 daysWed 8/22/18Wed 8/22/18 Analyst Project Manager Documenter,Documents[1] Documenter,Documents[1] Documenter Project Manager Planner Project Manager Planner Project Manager Workers,Contractor Electrician,Electric Wires[1] Contractor,Workers,Construction raw materials[1] Workers,Doors and windows[1] Painter,Paints[1] Workers,Furniture[1] Electrician,Electric appliances[1] Contractor,Fire Extinguisher[1] Electrician 8/22 WSTMFTSWSTMFTSWS Apr 8, '18May 6, '18Jun 3, '18Jul 1, '18Jul 29, '18Aug 26, '18Sep 23, '18 Figure 1: Project Gantt chart showing dependencies and critical path
8PROJECT PROPOSAL DOCUMENT 3. Risk Register The risk register for the project of ‘Teaching rooms refurbishment of Queen's building of Roehamption University’ is given below, Ref No.Risk NameRisk descriptionProbability (P) Severity (S) Impact (P*S) Mitigation Strategy #000201Human Accidents and Sickness The human accidents and sickness is resulted when thehumanfellwhile workingatthe construction site or fell ill due to climatic change. Possible(3)Critical (5) 15Avoid #000202Equipments Failure The failure of equipments would be resulted when themachinesandtools wouldwearoutandit becomesobsoletefor being used at the project. Possible(3)Major(4)12Reduce #000203Climatic Hindrance Thechangeinclimatic condition would result in forming the major issues in carrying out the project activities. Unlikely (2) Major(4)8Accept #000204Power FailureThepowerfailureis anothertechnicalissue that would tend to form the issues in aligning the developmentofthe operations,. Negligible (1) Moderate (3) 3Accept #000205Collapsingof Structure Thecollapsingof structure is another major factor that would tend to demolish the constructed parts due to any error in construction phase. Unlikely (2) Critical (5) 10Transfer #000206Cost Over RunThe excess spending of budgetwouldresultin forming the issue of cost overrunandinthis problem the costs of the projectwouldbe exhausted. Likely(4)Major(4)16Avoid #000207ExcessTime Consumption Duetoanyissueof problem,the consumption of the time for the project would be Likely(4)Moderate (3) 12Reduce
9PROJECT PROPOSAL DOCUMENT increasedanditwould resultindelayof activities. #000208Complaints fromLocal Community Duetoconstruction activities a huge amount of waste and noise would be generated. The locals mightcomplainforthe noise and dust generated duetoconstruction activities. Possible(3)Minor (2) 6Accept #000209Qualityissues inraw material Thebadqualityof materials for the project would result in forming themajorissuesinthe completion of the project Possible(3)Major(4)12Reduce #000210Client Disagreement The disagreement of the clientonthefinal deliverableisanother majorissueofthe project.Theimplication of the operations would alsotendtoformthe issueinimplementation ofthefinalproject deliverable. Unlikely (2) Critical (5) 10Transfer 4. Short Report to Project Sponsor Sponsor Report- Teaching rooms refurbishment of Queen's building of Roehamption University Introduction The role of risk management holds an integral role for the deployment of the activities favouring the deployment of the improved operations. Risk management holds an integral role for aligning the factors of risk and forming mitigation strategies for supporting the deployment of the effective operations for the organization. The risk management is also helpful for supporting the deployment of the operations favouring the management of the successive integration of the improved operation development. The project of Teaching rooms refurbishment of Queen's
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
10PROJECT PROPOSAL DOCUMENT buildingofRoehamptionUniversityisaconstructionprojectanditwouldinvolvethe implication of the successive risk mitigation strategies so that the project can be successfully mitigated. The formation of the operations would also be helpful for forming the deployment of the risk assessment. The use of Prince2 methodology is helpful for overcoming the deployment of the project activities. Importance of quality risk management The quality risk management is helpful for analysing the risk factors that are associated with the deployment of the successive improvement operations. The quality risk management holds an integralrolefortheprojectof‘TeachingroomsrefurbishmentofQueen'sbuildingof Roehamption University’. The benefits of implying quality risk management are, Improved efficiency:The major benefit of using quality risk management holds an integral role for increasing the performance of the operations of the project. The development of the activities favouring the implication of the effective functions would help in easing the operations of teaching rooms refurbishment. Work Safety:The work safety would be implied for forming the utilization of the activities supporting the implication of the operations favouring the alignment of the activities favouring the effective work safety modulation. The construction project would require the work safety implication so that the refurbishment can be done while the workers would stay in safe working environment. Efficient Resource Distribution:The efficient distribution of the resources is a major factor that would be helpful for using the implication of the distribution of the resources would be eased by the use of the project operations. The utilization of the improved resource analysis would be helpful for listing the modification of the teaching rooms.
11PROJECT PROPOSAL DOCUMENT Potential Impact of ignoring risk management processes The risks in construction project can result in forming major hindrance in forming completion of the project of‘Teaching rooms refurbishment of Queen's building of Roehamption University’. The problems of ignoring the risk management process are, Absence of Project Monitoring:The absence of project monitoring is a major factor that would form the impact on the development of the project completion. The project of refurbishment would require the constant monitoring for construction activities. The ignorance of monitoring would result in forming the problems of completion of the project. The slackness in monitor would result in forming the issues of the project completion. Issues in health and safety:The construction activities of ‘Teaching rooms refurbishment of Queen's building of Roehamption University’ project would require the assurance of health safety for the workers involved in the project. It is possible that due to the ignorance of safety facilities would result in forming the major hindrance in completion of the activities of the project. Critical Analysis of Prince2 methodology According toDemirkesen and Ozorhon (2017), the Prince2 methodology is an innovative methodology for managing the progress of the project. The term Prince stands of Projects in controlled environment and it is a process based methodology that is structured for overcoming the issue of disasters in the project operations. The implication of the effective management of the operations for listing the deployment of the operations. The Prince2 framework for the project of‘Teaching rooms refurbishment of Queen's building of Roehamption University’ would involve the inclusion of the elements of organized and control planning, organized and control execution, and controlled closure. Prince2 have a series of processes favoring the
12PROJECT PROPOSAL DOCUMENT involvement of the activities so that improved operation can be implemented (Kuchta and Ptaszynska 2017). Prince2 forms a single common goal for all the stakeholders of the project and it would narrow down the scope in detail so that all the activities can be aligned successfully. Conclusion Hence, it is evident from the report that the risk management is very crucial for the‘Teaching rooms refurbishment of Queen's building of Roehamption University’project completion. The quality risk management would ensure that the activities would be aligned for overcoming the probability of developing the finite solution to the appropriate deliverance to the project. The implementation of the successive risk assessment would also be helpful for listing the factors that would harm the project and kitchen refurbishment. The quality risk management is a must for the alignment of the operations favouring the deployment of the operations for the‘Teaching rooms refurbishment of Queen's building of Roehamption University’ project. Recommendations Some recommendations for effective risk management of the project of‘Teaching rooms refurbishment of Queen's building of Roehamption University’is given in below, Use of Risk Management tools:Risk management tools risk priority matrix and risk assessment matrix would be helpful for forming the development of the activities favouring the alignment of the improved operational development. Implementation of Quality Management Process:The implication of the quality management is a major factor that would help in forming the alignment of the quality assessment for the construction activities of teaching rooms refurbishment. Conclusion
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
13PROJECT PROPOSAL DOCUMENT It can be concluded from the report that the project of‘Teaching rooms refurbishment of Queen's building of Roehamption University’ had been developed by aligning project management principles and operations. The implementation of the project initiation report had tended to form the use of the tools like project initiation document, risk management strategy, project schedule, and a short report for the project sponsor. The project initiation document had included the elementsofprojectbackground,projectdefinition(aims,objectives,scope,deliverables, constraints, and assumptions), risk analysis, key staff and stakeholder analysis, and timescales had been represented. The Gantt chart had been made for showing the project plan of ‘Teaching rooms refurbishment of Queen's building of Roehamption University’ and it would also be helpful for aligning the use of the effective operation development. The risk register developed has shown 10 risks of the project. The risk management strategy was developed for easing the flow of successive integration of the operations for the project.
14PROJECT PROPOSAL DOCUMENT Bibliography Aarikka-Stenroos, L., Aaboen, L., Cova, B. and Rolfsen, A., 2018. Building B2B relationships via initiation contributors: Three cases from the Norwegian-South Korean international project business.Industrial Marketing Management,68, pp.74-85. Bessis, J., 2015.Risk management in banking. John Wiley & Sons. Burtonshaw-Gunn, S.A., 2017.Risk and financial management in construction. Routledge. Chance, D.M. and Brooks, R., 2015.Introduction to derivatives and risk management. Cengage Learning. Demirkesen, S. and Ozorhon, B., 2017. Impact of integration management on construction project management performance.International Journal of Project Management,35(8), pp.1639-1654. Fleming, Q.W. and Koppelman, J.M., 2016, December. Earned value project management. Project Management Institute. Glendon, A.I., Clarke, S. and McKenna, E., 2016.Human safety and risk management. Crc Press. Harrison, F. and Lock, D., 2017.Advanced project management: a structured approach. Routledge. Hewitt, K., Graham, J., Swiderek, T. and Kalt, D., 2016.Aerial Refueling Clearance Initiation Request(No. ARSAG-16-88-98RD). Aerial Refueling Systems Advisory Group (ARSAG) Xenia United States. Hopkin, P., 2017.Fundamentals of risk management: understanding, evaluating and implementing effective risk management. Kogan Page Publishers.
15PROJECT PROPOSAL DOCUMENT Kerzner, H. and Kerzner, H.R., 2017.Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons. Kuchta, D. and Ptaszyńska, E., 2017, July. Fuzzy based risk register for construction project risk assessment. InAIP Conference Proceedings(Vol. 1863, No. 1, p. 230006). AIP Publishing. Lock, D., 2017.The essentials of project management. Routledge. McNeil, A.J., Frey, R. and Embrechts, P., 2015.Quantitative risk management: Concepts, techniques and tools. Princeton university press. Mullaly, M., 2016.Exercising Agency: Decision Making and Project Initiation. Routledge. Schwalbe, K., 2015.Information technology project management. Cengage Learning. Sears, S.K., Sears, G.A., Clough, R.H., Rounds, J.L. and Segner, R.O., 2015.Construction project management. John Wiley & Sons. Shen, Y., Tuuli, M.M., Xia, B., Koh, T.Y. and Rowlinson, S., 2015. Toward a model for forming psychological safety climate in construction project management.International journal of project management,33(1), pp.223-235. Walker, A., 2015.Project management in construction. John Wiley & Sons. Zheng, X., Le, Y., Chan, A.P., Hu, Y. and Li, Y., 2016. Review of the application of social network analysis (SNA) in construction project management research.International journal of project management,34(7), pp.1214-1225.