TowerCo Greenfield Operation: A Project Charter and Implementation Plan

Verified

Added on  2023/06/10

|11
|537
|263
AI Summary
This presentation discusses TowerCo's Greenfield Operation project charter and implementation plan to launch 1000 mobile telephony tower sites in a new country within a year while maximizing CO2 savings. It includes a cost-benefit analysis, scope, risks, and key stakeholders. The presentation also includes a tentative implementation plan with a Gantt chart and network diagram, as well as a governance mechanism to ensure project success. References are also provided.
tabler-icon-diamond-filled.svg

Contribute Materials

Your contribution can guide someone’s learning journey. Share your documents today.
Document Page
Case Study
TowerCo
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
TABLE OF CONTENT
A Project Charter
A tentative Implementation Plan
A governance mechanism to ensure success of the project
References
Document Page
A PROJECT CHARTER
Project Name: TowerCo Greenfield Operation
Purpose:
The purpose of project is to launch TowerCo greenfield operation in a new country.
Objective:
To build a portfolio of 1000 sites within the timeframe of one year.
To maximized the savings of CO2 with the TowerCo model of telecom site sharing.
Project Specification:
Focus on capital and operating efficiencies.
Active marketing driver sharing and optimal QoS.
Deliverables:
This project will deliver 1000 mobile telephony tower sites in the next one year.
Document Page
CONTINUED
Cost Benefit Analysis of 1000 Tower Sites:
Particulars Details Amount
Benefits:
Revenue from anchor tenant (after adjusting inflation) (2500*12*1000)* 102.5% 30750000
Revenue from colocation lease rate (after adjusting inflation) (2800*12*1000)*102.5% 34440000
Total benefit 65190000
Cost:
Initial cost of tower construction:
Tower Equipment and Installation 130000
Power generator 20000
Investment on colocation capex 5000
Maintenance Capex (3000*1000 sites) 3000000
Site opex (Power) (12000*1000) 12000000
Site opex (Ground rent) (3000*1000) 3000000
Site opex (other) (5000*1000) 5000000
Total Cost 23155000
Profit 42035000
Cost-Benefit Ratio 2.82
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
CONTINUED
Scope:
The project is limited to construction of mobile telephony tower site in and around new country and
developing a logistic model in relation to supply chain managements.
Risks:
Uncertainty of resources and availability of materials
Environmental risk such as natural disaster, weather etc.
Cost overrun due to fluctuation in foreign exchange.
Custom and import restrictions
Delay in project completion
Key Stakeholders:
Primary Contractors, Regulators, government, Board of director, Operators, Media, Local community,
sponsors etc.
Document Page
Gantt ChartA TENTATIVE IMPLEMENTATION PLAN
Document Page
CONTINUED
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
CONTINUED
Network Diagram:
Document Page
A governance mechanism to ensure success
of the project
Project Governance is basically linked with the project success as without top management support
ensuring project success is difficult.
The seniors and top management of TowerCo are closely look out the work or activities of building the
tower sites in new country in order to ensure success of the project.
Further, the project manager will also implement the key performance indicators in order to measure
the success of the project.
After implementing the KPI, the project manager will timely monitor this for ensuring the success of
project.
Document Page
REFERENCES
Bröchner, J., 2021. Construction project management fiction: Individual values. International Journal
of Project Management, 39(6), pp.594-604.
Zhou, Z., Alcalá, J. and Yepes, V., 2021. Optimized Application of Sustainable Development Strategy
in International Engineering Project Management. Mathematics, 9(14), p.1633.
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
THNAK YOU
chevron_up_icon
1 out of 11
circle_padding
hide_on_mobile
zoom_out_icon
[object Object]

Your All-in-One AI-Powered Toolkit for Academic Success.

Available 24*7 on WhatsApp / Email

[object Object]