VUIS CONSULTING PTY LTD.
PROJECT PLAN [1]
[SAP HANA Deployment]
[29-05-19]
[INSERT AUTHOR NAME HERE]
[Project Manager]
[INSERT AUTHOR EMAIL HERE]
The following template is for educational purposes only.
PROJECT PLAN [1]
[SAP HANA Deployment]
[29-05-19]
[INSERT AUTHOR NAME HERE]
[Project Manager]
[INSERT AUTHOR EMAIL HERE]
The following template is for educational purposes only.
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
CONTENTS
Glossary
Term Definition
Business
Case
The justification of execution of a chosen business is generally provided in
form of a business case
Scope The opportunity or possibility of dealing with something or delivering
something is defined as the scope of the project.
VUIS Consulting Project Plan Page 2
[Insert Author name here]
Glossary
Term Definition
Business
Case
The justification of execution of a chosen business is generally provided in
form of a business case
Scope The opportunity or possibility of dealing with something or delivering
something is defined as the scope of the project.
VUIS Consulting Project Plan Page 2
[Insert Author name here]
Introduction
The plan for execution of the project related to implementation of SAP HANA is delivered. It
is required to develop a project plan as the plan ascertain the strategic goals linked with the
project are executed in a successful manner. The project manager ascertains that the major
tasks are accomplished by breaking up of the project in a varied form of manageable tasks
and timely accomplishment of the said tasks ascertain the project completion as per the
clients requirements. The project plan for deploying SAP HANA in Yes chemist is developed
which provides the details of the project scope, the business case, the scheduling and the
roll out strategy, the resources, risks and the budget constraint in the project. The plan
further discusses the basic communication activities to be followed to ascertain that the
project team members are communicating the basic needs and the issues to the other team
members. The plan further provides an idea of the significant risks that can affect the
execution approach and the completion of SAP deployment. Since this particular project is
operationally complex, development of a realistic project plan is a necessity. The plan further
identifies the schedule and approach of managing the issues and the risks in a project. The
plan has been prepared to guide the project team in their process of project execution.
Project scope
Defining the project scope is necessary to execute the project in a successful manner. It is
quite critical to identify the most significant deliverables and the milestone of the project so
that the team members follow the same in execution of the project as per the plan. The
identification of the project scope is linked with the identification of the objectives as well as
the aim behind execution of this particular project.
Aim: The project aims to plan and deploy the SAP HANA to the pharmacy yes chemist to
ensure elimination of the present operational issues persisting in the pharmacy.
Objectives: The plan of the project documents the most significant objectives of the project.
The fulfilment of all these major objectives are necessary in order to execute the project as
per the needs and specifications of the Yes Chemist.
ï‚· To identify the operational weakness of the Yes Chemist pharmacy
ï‚· To analyse the approaches that can help in reducing the operational issues
ï‚· To ascertain that SAP deployment can help in reducing the major operational issues
faced
ï‚· To identify the prominent risks associated with the SAP deployment project
The major deliverables of the project is prepared as per the plan. The key deliverables and
the quality standard on which the deliverables will be accepted is shown in the table below-
Deliverables Quality standard to be accepted
Preparing the server room As per the specifications set by the Yes
chemist pharmacy, it is necessary to
complete the preparation of the server room
in 15 days.
VUIS Consulting Project Plan Page 3
[Insert Author name here]
The plan for execution of the project related to implementation of SAP HANA is delivered. It
is required to develop a project plan as the plan ascertain the strategic goals linked with the
project are executed in a successful manner. The project manager ascertains that the major
tasks are accomplished by breaking up of the project in a varied form of manageable tasks
and timely accomplishment of the said tasks ascertain the project completion as per the
clients requirements. The project plan for deploying SAP HANA in Yes chemist is developed
which provides the details of the project scope, the business case, the scheduling and the
roll out strategy, the resources, risks and the budget constraint in the project. The plan
further discusses the basic communication activities to be followed to ascertain that the
project team members are communicating the basic needs and the issues to the other team
members. The plan further provides an idea of the significant risks that can affect the
execution approach and the completion of SAP deployment. Since this particular project is
operationally complex, development of a realistic project plan is a necessity. The plan further
identifies the schedule and approach of managing the issues and the risks in a project. The
plan has been prepared to guide the project team in their process of project execution.
Project scope
Defining the project scope is necessary to execute the project in a successful manner. It is
quite critical to identify the most significant deliverables and the milestone of the project so
that the team members follow the same in execution of the project as per the plan. The
identification of the project scope is linked with the identification of the objectives as well as
the aim behind execution of this particular project.
Aim: The project aims to plan and deploy the SAP HANA to the pharmacy yes chemist to
ensure elimination of the present operational issues persisting in the pharmacy.
Objectives: The plan of the project documents the most significant objectives of the project.
The fulfilment of all these major objectives are necessary in order to execute the project as
per the needs and specifications of the Yes Chemist.
ï‚· To identify the operational weakness of the Yes Chemist pharmacy
ï‚· To analyse the approaches that can help in reducing the operational issues
ï‚· To ascertain that SAP deployment can help in reducing the major operational issues
faced
ï‚· To identify the prominent risks associated with the SAP deployment project
The major deliverables of the project is prepared as per the plan. The key deliverables and
the quality standard on which the deliverables will be accepted is shown in the table below-
Deliverables Quality standard to be accepted
Preparing the server room As per the specifications set by the Yes
chemist pharmacy, it is necessary to
complete the preparation of the server room
in 15 days.
VUIS Consulting Project Plan Page 3
[Insert Author name here]
Conversion of data and validation of the
converted data
The legacy data structure of the data that
already exists in the Yes Chemist is followed
in conversion and validation of the data.
Integration of the system to be developed
and system testing
The testing process within the organization
will follow the legacy data structure. The
Testing should be completed prior to the
launch of the system.
Imparting the training to all the staffs of
VUISC
Training the staffs of Yes Chemist should be
completed as a part of project execution
Documentation and preparation of Software
Maintenance
The documentation phase is needed to be
completed prior to the project launch. After
the launch the VUISC should provide
maximum support and maintenance to the
Yes Chemist pharmacy.
The above table discusses the deliverables considered for successful end of the project and
the acceptable quality standard of the major deliverables linked with the project. However, in
preparing the project schedule and in deliverable identification of the project, certain
assumptions are considered. The assumptions are as follows-
1. The staffs of the Yes chemist pharmacy will be ready to accept the change
2. A maximum number of staff members will be participating the training program
The successful execution of this project is linked with certain major constraints which are
identified as follows-
1. The training that will be provided to the staffs of the organization will be only once.
However, periodic training was a necessity for the project team to consider.
2. The project is linked with a scheduling constraint as well. For example, it is needed to
demolish the server room and making is ready for the project in 15 days.
Business case
Yes Chemist is in need of improving their information system particularly because the
organization was operating on a significantly older operating system which gave rise to
major operational issues. The project is expected to be highly beneficial for Yes chemist and
therefore, successful execution of this project is considered. The advantages that the SAP
implementation project will provide to the client of Yes chemist, is indicated in the following
table-
Benefits Benefit measure
The streamlining and easier management of
all the work processes is possible.
The organization should be able to achieve
25% of operational improvement within 6
VUIS Consulting Project Plan Page 4
[Insert Author name here]
converted data
The legacy data structure of the data that
already exists in the Yes Chemist is followed
in conversion and validation of the data.
Integration of the system to be developed
and system testing
The testing process within the organization
will follow the legacy data structure. The
Testing should be completed prior to the
launch of the system.
Imparting the training to all the staffs of
VUISC
Training the staffs of Yes Chemist should be
completed as a part of project execution
Documentation and preparation of Software
Maintenance
The documentation phase is needed to be
completed prior to the project launch. After
the launch the VUISC should provide
maximum support and maintenance to the
Yes Chemist pharmacy.
The above table discusses the deliverables considered for successful end of the project and
the acceptable quality standard of the major deliverables linked with the project. However, in
preparing the project schedule and in deliverable identification of the project, certain
assumptions are considered. The assumptions are as follows-
1. The staffs of the Yes chemist pharmacy will be ready to accept the change
2. A maximum number of staff members will be participating the training program
The successful execution of this project is linked with certain major constraints which are
identified as follows-
1. The training that will be provided to the staffs of the organization will be only once.
However, periodic training was a necessity for the project team to consider.
2. The project is linked with a scheduling constraint as well. For example, it is needed to
demolish the server room and making is ready for the project in 15 days.
Business case
Yes Chemist is in need of improving their information system particularly because the
organization was operating on a significantly older operating system which gave rise to
major operational issues. The project is expected to be highly beneficial for Yes chemist and
therefore, successful execution of this project is considered. The advantages that the SAP
implementation project will provide to the client of Yes chemist, is indicated in the following
table-
Benefits Benefit measure
The streamlining and easier management of
all the work processes is possible.
The organization should be able to achieve
25% of operational improvement within 6
VUIS Consulting Project Plan Page 4
[Insert Author name here]
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
months of system deployment
The new system provides an opportunity of
secure data storage and retrieval of the data
The efficiency in data management should
be improved by 50% in 6 months
The manual input and labour needed for
sales and order processing will be reduced
A reduction in the managerial cost by 25%
within 6 months.
The above section gives an idea of the major benefits that can be achieve by the execution
of SAP HANA in Yes Chemist. The dis-benefits associated with the deployment of SAP
HANA in yes chemist is indicated as follows-
1. It is quite costly to deploy SAP HANA within an organization and a huge investment is
needed for the same. It is one significant dis-benefit of implementation of SAP HANA within
an organization
2. Without accurate training, the staffs of the organization may not understand the operations
of the new system leading to decrease in productivity of the organization.
Project Schedule and Approach (Rollout strategy)
A planned implementation approach is chosen for the execution of the project that is
considered. The details of the tasks to be completed along with the sequencing and the
duration of the task is indicated in the following figures.
The milestone and the tasks are shown as follows-
VUIS Consulting Project Plan Page 5
[Insert Author name here]
The new system provides an opportunity of
secure data storage and retrieval of the data
The efficiency in data management should
be improved by 50% in 6 months
The manual input and labour needed for
sales and order processing will be reduced
A reduction in the managerial cost by 25%
within 6 months.
The above section gives an idea of the major benefits that can be achieve by the execution
of SAP HANA in Yes Chemist. The dis-benefits associated with the deployment of SAP
HANA in yes chemist is indicated as follows-
1. It is quite costly to deploy SAP HANA within an organization and a huge investment is
needed for the same. It is one significant dis-benefit of implementation of SAP HANA within
an organization
2. Without accurate training, the staffs of the organization may not understand the operations
of the new system leading to decrease in productivity of the organization.
Project Schedule and Approach (Rollout strategy)
A planned implementation approach is chosen for the execution of the project that is
considered. The details of the tasks to be completed along with the sequencing and the
duration of the task is indicated in the following figures.
The milestone and the tasks are shown as follows-
VUIS Consulting Project Plan Page 5
[Insert Author name here]
VUIS Consulting Project Plan Page 6
[Insert Author name here]
[Insert Author name here]
Figure 1: Showing the Task and the Milestone
The tasks and the milestone linked with the SAP HANA deployment project is indicated in
the following figure-
VUIS Consulting Project Plan Page 7
[Insert Author name here]
The tasks and the milestone linked with the SAP HANA deployment project is indicated in
the following figure-
VUIS Consulting Project Plan Page 7
[Insert Author name here]
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
VUIS Consulting Project Plan Page 8
[Insert Author name here]
[Insert Author name here]
Figure 2: Showing the Gantt Chart of the Project
Resources
The project has been undertaken by VUISC and therefore, the resources considered for this
project involve the staffs of VUISC. The resources considered for execution of the tasks are
indicated as follows.
Figure 3: The Resources Considered
The resources overview matrix is indicated in the figure below-
VUIS Consulting Project Plan Page 9
[Insert Author name here]
Resources
The project has been undertaken by VUISC and therefore, the resources considered for this
project involve the staffs of VUISC. The resources considered for execution of the tasks are
indicated as follows.
Figure 3: The Resources Considered
The resources overview matrix is indicated in the figure below-
VUIS Consulting Project Plan Page 9
[Insert Author name here]
Figure 4: The Resource Overview Matrix
Budget
The project is a high budget project. The cost of delivering the particular project is indicated
as follows.
VUIS Consulting Project Plan Page 10
[Insert Author name here]
Budget
The project is a high budget project. The cost of delivering the particular project is indicated
as follows.
VUIS Consulting Project Plan Page 10
[Insert Author name here]
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
VUIS Consulting Project Plan Page 11
[Insert Author name here]
[Insert Author name here]
Figure 5: The Cost of the Project
Figure 6: The Task Cost Overview
Risk
It is quite critical to identify and analyse the major risks as well as the uncertainties linked
with the project. The SAP HANA implementation project in Yes Chemist is linked certain
technical and the operational risks which are indicated as follows-
Risk category Description Likelihood of
occurrences
Severity/Impact
Technical The technical risk is
related to server
issues and issues in
integration of the
new system with the
existing system
High High
Financial This is a high budget
project. Budget
issues can increase
the risk and the
Medium Medium
VUIS Consulting Project Plan Page 12
[Insert Author name here]
Figure 6: The Task Cost Overview
Risk
It is quite critical to identify and analyse the major risks as well as the uncertainties linked
with the project. The SAP HANA implementation project in Yes Chemist is linked certain
technical and the operational risks which are indicated as follows-
Risk category Description Likelihood of
occurrences
Severity/Impact
Technical The technical risk is
related to server
issues and issues in
integration of the
new system with the
existing system
High High
Financial This is a high budget
project. Budget
issues can increase
the risk and the
Medium Medium
VUIS Consulting Project Plan Page 12
[Insert Author name here]
issues in the project
Schedule Unexpected project
delays result in
increase of the
schedule risks
Mow Medium
Resource Unavailability of the
estimated resources
in the project can
result in resource
shortage and
increase in the
issues with the
resources.
Low Low
Operational Since the system is
new to the
organization, there
are high chances of
increase in the
operational risks
High High
Communication
Identification of the effective communication approaches and the communication activities
are necessary for the stakeholders and the project team to communicate issues and the
project needs. The communication activities that are needed to be carried out during the
execution of the SAP HANA implementation project is indicated as follows-
Communication
Activities
Intended Audience Vehicle of
Communication
Frequency of
Communication
Discussing the
project specification
Project Team and
Project Manager
Telephone, email Weekly
Communication of
the status of the
project
Project Team Email Daily
Communication
related to the
resources needed
Project Manager and
Project Team
Email and face to
face meeting
Weekly
Communication
related to the issues
in the Budget
Resource manager
and Project Team
Email Weekly
Communication Project Manager and Email Weekly
VUIS Consulting Project Plan Page 13
[Insert Author name here]
Schedule Unexpected project
delays result in
increase of the
schedule risks
Mow Medium
Resource Unavailability of the
estimated resources
in the project can
result in resource
shortage and
increase in the
issues with the
resources.
Low Low
Operational Since the system is
new to the
organization, there
are high chances of
increase in the
operational risks
High High
Communication
Identification of the effective communication approaches and the communication activities
are necessary for the stakeholders and the project team to communicate issues and the
project needs. The communication activities that are needed to be carried out during the
execution of the SAP HANA implementation project is indicated as follows-
Communication
Activities
Intended Audience Vehicle of
Communication
Frequency of
Communication
Discussing the
project specification
Project Team and
Project Manager
Telephone, email Weekly
Communication of
the status of the
project
Project Team Email Daily
Communication
related to the
resources needed
Project Manager and
Project Team
Email and face to
face meeting
Weekly
Communication
related to the issues
in the Budget
Resource manager
and Project Team
Email Weekly
Communication Project Manager and Email Weekly
VUIS Consulting Project Plan Page 13
[Insert Author name here]
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
related to the
execution of
the Team
Summary
The project plan that is prepared for the Yes Chemist pharmacy provides a detailed
description of the project needs and the business case linked with the execution of the
project. The benefits as well as the risks are identified in the plan along with the
communication needs of the project. The plan identifies the major communication activities
that the project team needs to follow in execution of the project in time and within the set
budget.
VUIS Consulting Project Plan Page 14
[Insert Author name here]
execution of
the Team
Summary
The project plan that is prepared for the Yes Chemist pharmacy provides a detailed
description of the project needs and the business case linked with the execution of the
project. The benefits as well as the risks are identified in the plan along with the
communication needs of the project. The plan identifies the major communication activities
that the project team needs to follow in execution of the project in time and within the set
budget.
VUIS Consulting Project Plan Page 14
[Insert Author name here]
1 out of 14
Related Documents
Your All-in-One AI-Powered Toolkit for Academic Success.
 +13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
© 2024  |  Zucol Services PVT LTD  |  All rights reserved.