Water Supply Management Project in Remote Areas
VerifiedAdded on 2024/05/23
|34
|8954
|232
AI Summary
This project focuses on managing the delivery of water supply in remote areas, addressing the challenges of water scarcity and the need for sustainable solutions. It involves identifying key stakeholders, developing a comprehensive project plan, and implementing a water management system that includes rainwater harvesting and water reuse techniques. The project utilizes a waterfall model methodology and employs SMART goals to ensure effective project execution. It also includes a detailed Work Breakdown Structure (WBS) and Gantt chart for project scheduling and monitoring.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
ENGG3500 (2018), Managing
Engineering Projects
1
Engineering Projects
1
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
Table of Contents
1. Introduction.............................................................................................................................................5
2.Project charter...........................................................................................................................................6
2.1 Project background and business need...............................................................................................6
2.2 project objectives/goal.................................................................................................................7
2.3 project scope......................................................................................................................................7
2.3.1 Requirements..............................................................................................................................7
2.3.2 Deliverables................................................................................................................................8
2.3.3 Inclusions....................................................................................................................................8
2.3.4 Exclusions...................................................................................................................................9
2.3.5 Assumptions...............................................................................................................................9
2.3.6 Constraints..................................................................................................................................9
2.4. Significant milestones.....................................................................................................................10
2.5 Project budget summery..................................................................................................................10
2.6 Key stakeholders..............................................................................................................................11
3. Project management approach...............................................................................................................12
3.1. Project management methodology..................................................................................................12
3.2 Strategy and procedures to achieve project goals/objectives............................................................13
4. Scope management............................................................................................................................16
4.1 Project scope statement..............................................................................................................16
4.2 Work Breakdown Structure.............................................................................................................17
4.3. Scope control plan..........................................................................................................................18
5. Requirements management....................................................................................................................19
5.1. Requirements management plan.....................................................................................................19
5.2 Requirements traceability matrix...............................................................................................20
6. Stakeholder management...................................................................................................................21
6.1 Stakeholder analysis........................................................................................................................21
6.2 Stakeholder management plan.........................................................................................................21
7. Schedule management.......................................................................................................................22
7.1. Schedule management methodology/approach...............................................................................22
7.1.1. Software...................................................................................................................................22
7.2. Schedule monitoring and control plan............................................................................................23
7.3 The critical path...............................................................................................................................24
7.4. Activity list, sequencing and duration estimates.............................................................................25
2
1. Introduction.............................................................................................................................................5
2.Project charter...........................................................................................................................................6
2.1 Project background and business need...............................................................................................6
2.2 project objectives/goal.................................................................................................................7
2.3 project scope......................................................................................................................................7
2.3.1 Requirements..............................................................................................................................7
2.3.2 Deliverables................................................................................................................................8
2.3.3 Inclusions....................................................................................................................................8
2.3.4 Exclusions...................................................................................................................................9
2.3.5 Assumptions...............................................................................................................................9
2.3.6 Constraints..................................................................................................................................9
2.4. Significant milestones.....................................................................................................................10
2.5 Project budget summery..................................................................................................................10
2.6 Key stakeholders..............................................................................................................................11
3. Project management approach...............................................................................................................12
3.1. Project management methodology..................................................................................................12
3.2 Strategy and procedures to achieve project goals/objectives............................................................13
4. Scope management............................................................................................................................16
4.1 Project scope statement..............................................................................................................16
4.2 Work Breakdown Structure.............................................................................................................17
4.3. Scope control plan..........................................................................................................................18
5. Requirements management....................................................................................................................19
5.1. Requirements management plan.....................................................................................................19
5.2 Requirements traceability matrix...............................................................................................20
6. Stakeholder management...................................................................................................................21
6.1 Stakeholder analysis........................................................................................................................21
6.2 Stakeholder management plan.........................................................................................................21
7. Schedule management.......................................................................................................................22
7.1. Schedule management methodology/approach...............................................................................22
7.1.1. Software...................................................................................................................................22
7.2. Schedule monitoring and control plan............................................................................................23
7.3 The critical path...............................................................................................................................24
7.4. Activity list, sequencing and duration estimates.............................................................................25
2
7.5. Milestones......................................................................................................................................27
7.6. Gantt chart......................................................................................................................................28
8. Appendices........................................................................................................................................29
References.................................................................................................................................................34
3
7.6. Gantt chart......................................................................................................................................28
8. Appendices........................................................................................................................................29
References.................................................................................................................................................34
3
List of Figures
Figure 1: Project needs................................................................................................................................6
Figure 2: Developing project.......................................................................................................................7
Figure 3: Project constraints........................................................................................................................9
Figure 4: Stakeholders...............................................................................................................................11
Figure 5: Waterfall model..........................................................................................................................12
Figure 6: Smart Goal.................................................................................................................................14
Figure 7: WBS structure............................................................................................................................17
Figure 8: Stakeholder analysis...................................................................................................................21
Figure 9: MS project..................................................................................................................................22
Figure 10 Earned values............................................................................................................................23
Figure 11: Network diagram of critical path..............................................................................................24
Figure 12: Critical task..............................................................................................................................24
Figure 13: Activity list...............................................................................................................................25
Figure 14: Cost overview..........................................................................................................................26
Figure 15: Cost Status................................................................................................................................26
Figure 16: Progress versus cost.................................................................................................................26
Figure 17: Gantt chart................................................................................................................................28
4
Figure 1: Project needs................................................................................................................................6
Figure 2: Developing project.......................................................................................................................7
Figure 3: Project constraints........................................................................................................................9
Figure 4: Stakeholders...............................................................................................................................11
Figure 5: Waterfall model..........................................................................................................................12
Figure 6: Smart Goal.................................................................................................................................14
Figure 7: WBS structure............................................................................................................................17
Figure 8: Stakeholder analysis...................................................................................................................21
Figure 9: MS project..................................................................................................................................22
Figure 10 Earned values............................................................................................................................23
Figure 11: Network diagram of critical path..............................................................................................24
Figure 12: Critical task..............................................................................................................................24
Figure 13: Activity list...............................................................................................................................25
Figure 14: Cost overview..........................................................................................................................26
Figure 15: Cost Status................................................................................................................................26
Figure 16: Progress versus cost.................................................................................................................26
Figure 17: Gantt chart................................................................................................................................28
4
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
1. Introduction
Managing the delivery of water-supply in a remote area is all about to manage the water flow in the
remote areas. Refers to the remote areas, then these are far away from the main city and there are not all
the services are available to the peoples are living in that area. Due to the shortage of the water, the life of
the peoples is stopped and it is easy, not easy to survive in that particular area. For this project lot of
research are done and analysis the of the analysis. Provides the information about the different type of the
key stakeholders and develops the process steps for the development of the project (Pmi, 2018).
For that there are need to develops the Work breakdown structure and the Gantt chart for the analysis of
the working of the project. Analysis of the management plan and develops the traceability matrix for this
project. For managing the schedule there will be the development of the Gantt chart is developed.
5
Managing the delivery of water-supply in a remote area is all about to manage the water flow in the
remote areas. Refers to the remote areas, then these are far away from the main city and there are not all
the services are available to the peoples are living in that area. Due to the shortage of the water, the life of
the peoples is stopped and it is easy, not easy to survive in that particular area. For this project lot of
research are done and analysis the of the analysis. Provides the information about the different type of the
key stakeholders and develops the process steps for the development of the project (Pmi, 2018).
For that there are need to develops the Work breakdown structure and the Gantt chart for the analysis of
the working of the project. Analysis of the management plan and develops the traceability matrix for this
project. For managing the schedule there will be the development of the Gantt chart is developed.
5
2. Project charter
2.1 Project background and business need
This project is all about to provides the supply of water in the remote area. There are need to develops
the project to provides the water supply and need to analyse how the process is carried away. The need of
the project is to develops the system that helps to complete the supply of at the remote area. The business
need of the project is in terms to fulfil the need of the peoples of the remote area and need to creates the
some of the profit by this project.
Figure 1: Project needs
Some of the major need for the project are:
Develops the project that fulfils the need of water supply.
Develops the project that provides the profit.
The project helps to develop the team that can able to handle a variety of project.
This project helps to understand the various conditions of the project.
The background of the project is developing the water supply in the remote station. There is a need to
develop the project to fulfil the requirement of the water in the particular area. some of the major
requirement of the project are:
Need to identify the stakeholders
Need to identify the major areas.
Need to identify the process of completion of the project.
Develops the team.
Develops the project manager for the organization.
Develops the schedule of for completion of the project (Brighthub, 2018).
6
2.1 Project background and business need
This project is all about to provides the supply of water in the remote area. There are need to develops
the project to provides the water supply and need to analyse how the process is carried away. The need of
the project is to develops the system that helps to complete the supply of at the remote area. The business
need of the project is in terms to fulfil the need of the peoples of the remote area and need to creates the
some of the profit by this project.
Figure 1: Project needs
Some of the major need for the project are:
Develops the project that fulfils the need of water supply.
Develops the project that provides the profit.
The project helps to develop the team that can able to handle a variety of project.
This project helps to understand the various conditions of the project.
The background of the project is developing the water supply in the remote station. There is a need to
develop the project to fulfil the requirement of the water in the particular area. some of the major
requirement of the project are:
Need to identify the stakeholders
Need to identify the major areas.
Need to identify the process of completion of the project.
Develops the team.
Develops the project manager for the organization.
Develops the schedule of for completion of the project (Brighthub, 2018).
6
2.2 project objectives/goal
The aim of the project is developing the project and fulfil the need to water in the remote areas. For that,
there is a need to develops the team, that has the good efficiency to complete the work and the work.
Some of the common objectives of this project are listed below:
Develops the project that fulfils the supply of the water in the remote area.
Need to find out the stakeholders.
Need to arrange the components that provide the healthy water in the remote area.
Analysis the requirement of the stakeholders.
Other than this the aim of the project is to develops the system and components that fulfil the
requirement of the supply of water. After that develops the components that provide the healthy water
to the remote area.
Figure 2: Developing project
For the development of the project, there is a need to develops the team, after that, there is a need to
develops the project manager for this project. The project manager is the person who is responsible for
the development of the project. The project manager is the person who is responsible for the development
of the project (Sacriver, 2018).
2.3 project scope
2.3.1 Requirements
As the project started then there is a lot of requirement in the project. There are a lot of the requirement of
the system, there are stakeholder requirements, project requirement. All the requirements are listed below:
System requirements
Management plan
Schedule plan
Stakeholder requirements
There are three types of the stakeholder for the project development. Below list down all the type of the
stakeholders.
Internal stakeholders
7
The aim of the project is developing the project and fulfil the need to water in the remote areas. For that,
there is a need to develops the team, that has the good efficiency to complete the work and the work.
Some of the common objectives of this project are listed below:
Develops the project that fulfils the supply of the water in the remote area.
Need to find out the stakeholders.
Need to arrange the components that provide the healthy water in the remote area.
Analysis the requirement of the stakeholders.
Other than this the aim of the project is to develops the system and components that fulfil the
requirement of the supply of water. After that develops the components that provide the healthy water
to the remote area.
Figure 2: Developing project
For the development of the project, there is a need to develops the team, after that, there is a need to
develops the project manager for this project. The project manager is the person who is responsible for
the development of the project. The project manager is the person who is responsible for the development
of the project (Sacriver, 2018).
2.3 project scope
2.3.1 Requirements
As the project started then there is a lot of requirement in the project. There are a lot of the requirement of
the system, there are stakeholder requirements, project requirement. All the requirements are listed below:
System requirements
Management plan
Schedule plan
Stakeholder requirements
There are three types of the stakeholder for the project development. Below list down all the type of the
stakeholders.
Internal stakeholders
7
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
o Employees
o Project Team
o Project manager
o Upper-level management
o owner
External stakeholders
o Supplier
o Customers
o Shareholders
o Society
o Creditors
Government
o Refers to the government, then this is the type of the stakeholder, the government are
developing the rules for the organization and for the development of the project. All the
organizations need to follow all the rules and if there any rule is broken, then legal
actions are against towards the organization.
The major requirement of the stakeholders is to get involved in the project and gain the profit
from the project.
Project requirements
Need to establish the system that supplies the water in the remote areas.
Need to develop the plan that required less cost to complete the project.
identifies the key stakeholders.
Develops the plan for the project.
Develops the efficient schedule for the project.
2.3.2 Deliverables
This is something that is related to the outcomes of the project. The outcomes of the project are in terms
to provides the water supplies in the remote area and develops a water management resources at that place
that will be good enough to fulfil all the water requirements of the remote areas. Some of the major
deliverables from the project are listed below:
Water supply to the remote areas.
Develops the relations with the stakeholders.
Develops the teams that have the good coordination with each other.
Time and schedule management.
2.3.3 Inclusions
This is part of the charter that provides the details about the task, items and actions that are included in the
project scope. Some of the common tasks that are related to the project scope are listed below:
Project schedule.
Resource management.
Components of water supply.
Stakeholders.
8
o Project Team
o Project manager
o Upper-level management
o owner
External stakeholders
o Supplier
o Customers
o Shareholders
o Society
o Creditors
Government
o Refers to the government, then this is the type of the stakeholder, the government are
developing the rules for the organization and for the development of the project. All the
organizations need to follow all the rules and if there any rule is broken, then legal
actions are against towards the organization.
The major requirement of the stakeholders is to get involved in the project and gain the profit
from the project.
Project requirements
Need to establish the system that supplies the water in the remote areas.
Need to develop the plan that required less cost to complete the project.
identifies the key stakeholders.
Develops the plan for the project.
Develops the efficient schedule for the project.
2.3.2 Deliverables
This is something that is related to the outcomes of the project. The outcomes of the project are in terms
to provides the water supplies in the remote area and develops a water management resources at that place
that will be good enough to fulfil all the water requirements of the remote areas. Some of the major
deliverables from the project are listed below:
Water supply to the remote areas.
Develops the relations with the stakeholders.
Develops the teams that have the good coordination with each other.
Time and schedule management.
2.3.3 Inclusions
This is part of the charter that provides the details about the task, items and actions that are included in the
project scope. Some of the common tasks that are related to the project scope are listed below:
Project schedule.
Resource management.
Components of water supply.
Stakeholders.
8
2.3.4 Exclusions
This is part of the charter that provides the details about the task, items and actions that are not included
in the project scope. Some of the common tasks that are related to the project scope are listed below:
Labours
External risk.
Natural hazards
Unwanted fault in the project.
Failure in the execution phase (project, 2018).
2.3.5 Assumptions
This is most important part of the development of the project. This is the assumptions of the activity that
may be happening in future, this assumption can be based on the knowledge, information about the
current scenario or the experience. Some of the assumptions are taken for the project are listed below:
Kept some of the extra resources to overcome hazards.
Kept some of the stakeholders on hold as per the requirements.
There is always the availability of the extra supplier and resources.
2.3.6 Constraints
this is also the important part of the development of the project. This provides the limitation to the project
resources and provides the limitation to the costing and scheduling of the project. There are two different
type of the constraints are present for the development of the project
Figure 3: Project constraints
Business constraints
This is depending upon the state of the organization or the developer. This is mainly containing the time,
cost and resources of the project.
9
This is part of the charter that provides the details about the task, items and actions that are not included
in the project scope. Some of the common tasks that are related to the project scope are listed below:
Labours
External risk.
Natural hazards
Unwanted fault in the project.
Failure in the execution phase (project, 2018).
2.3.5 Assumptions
This is most important part of the development of the project. This is the assumptions of the activity that
may be happening in future, this assumption can be based on the knowledge, information about the
current scenario or the experience. Some of the assumptions are taken for the project are listed below:
Kept some of the extra resources to overcome hazards.
Kept some of the stakeholders on hold as per the requirements.
There is always the availability of the extra supplier and resources.
2.3.6 Constraints
this is also the important part of the development of the project. This provides the limitation to the project
resources and provides the limitation to the costing and scheduling of the project. There are two different
type of the constraints are present for the development of the project
Figure 3: Project constraints
Business constraints
This is depending upon the state of the organization or the developer. This is mainly containing the time,
cost and resources of the project.
9
Technical constraints
This is the part of the system, that is used to apply the constraint over the design of the project. As refers
to the current scenario, then there are need to develop the pipelines that should contain the water to the
remote areas, then there is technical constraint regarding the pressure of the water (Resources, 2016).
2.4. Significant milestones
The milestones in the project management are something related to the achievement of the project. This is
generally developing after the completion of every stage in the project. After the completion of the
milestone, there must be a break or there is a meeting with the team and with the stakeholder to discuss
the next steps of the development process. Some of the common milestones of the project are listed
below:
Milestone 1: Project kick-off
Milestone 2: Planning phase completed
Milestone 3: Analysis phase completed
Milestone 4: Design phase completed
Milestone 5: Implementation phase completed
Milestone 6: Testing phase completed
Milestones 7: Maintenance phase completed
Milestones 8: the whole project is completed.
2.5 Project budget summary
The budget of the project is related or depend upon the schedule of the project and the costing of each
resource. There are different resources are required to develops the project and all the resources have the
different costing as per the time and the duration of the project. Below list done the list of the resources as
per the costing of each resource.
S. No Resource name Cost of resources per hour
1 Business Analysis $60
2 Mechanical engineer $42
3 Electrical engineer $32
4 Civil engineer $65
5 Test engineer $31
6 Supplier $62
7 Technical writer $40
The above shows the list of all the resources and as per the resource, the costing of the project is
depended. One of the other major factors of the costing is the scheduling of the project. As the
development of project duration increases the costing of the project also increases (Planning, 2018).
Refers to the costing of each phase of the project, then the list of each phase of the costing are listed
below:
S. No Resource name Cost of resources per hour
1 Planning phase $ 11,200.00
2 Analysis phase $ 27,240.00
10
This is the part of the system, that is used to apply the constraint over the design of the project. As refers
to the current scenario, then there are need to develop the pipelines that should contain the water to the
remote areas, then there is technical constraint regarding the pressure of the water (Resources, 2016).
2.4. Significant milestones
The milestones in the project management are something related to the achievement of the project. This is
generally developing after the completion of every stage in the project. After the completion of the
milestone, there must be a break or there is a meeting with the team and with the stakeholder to discuss
the next steps of the development process. Some of the common milestones of the project are listed
below:
Milestone 1: Project kick-off
Milestone 2: Planning phase completed
Milestone 3: Analysis phase completed
Milestone 4: Design phase completed
Milestone 5: Implementation phase completed
Milestone 6: Testing phase completed
Milestones 7: Maintenance phase completed
Milestones 8: the whole project is completed.
2.5 Project budget summary
The budget of the project is related or depend upon the schedule of the project and the costing of each
resource. There are different resources are required to develops the project and all the resources have the
different costing as per the time and the duration of the project. Below list done the list of the resources as
per the costing of each resource.
S. No Resource name Cost of resources per hour
1 Business Analysis $60
2 Mechanical engineer $42
3 Electrical engineer $32
4 Civil engineer $65
5 Test engineer $31
6 Supplier $62
7 Technical writer $40
The above shows the list of all the resources and as per the resource, the costing of the project is
depended. One of the other major factors of the costing is the scheduling of the project. As the
development of project duration increases the costing of the project also increases (Planning, 2018).
Refers to the costing of each phase of the project, then the list of each phase of the costing are listed
below:
S. No Resource name Cost of resources per hour
1 Planning phase $ 11,200.00
2 Analysis phase $ 27,240.00
10
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
3 Design phase $ 65,272.00
4 Implementation phase $ 16,680.00
5 Testing phase $ 9,088.00
6 Maintenance phase $ 6,136.00
2.6 Key stakeholders
Below list done the some of the of the common stakeholders of the project.
Figure 4: Stakeholders
Internal stakeholders
o Employees
o Project Team
o Project manager
o Upper-level management
o owner
External stakeholders
o Supplier
o Customers
o Shareholders
o Society
o Creditors
Government
Refers to the government, then this is the type of the stakeholder, the government are developing the rules
for the organization and for the development of the project. All the organizations need to follow all the
11
4 Implementation phase $ 16,680.00
5 Testing phase $ 9,088.00
6 Maintenance phase $ 6,136.00
2.6 Key stakeholders
Below list done the some of the of the common stakeholders of the project.
Figure 4: Stakeholders
Internal stakeholders
o Employees
o Project Team
o Project manager
o Upper-level management
o owner
External stakeholders
o Supplier
o Customers
o Shareholders
o Society
o Creditors
Government
Refers to the government, then this is the type of the stakeholder, the government are developing the rules
for the organization and for the development of the project. All the organizations need to follow all the
11
rules and if there any rule is broken, then legal actions are against towards the organization (Bizfluent,
2018).
3. Project management approach
3.1. Project management methodology
For the development of the project, there is need to use the project methodology, there is a different
type of the project methodology are present and all have the different advantages and disadvantages
as per the requirement of the project. For the development of the project. For the development of the
project, there are using the waterfall model.
Figure 5: Waterfall model
The above figure shows the steps of the development of the project by the use of the waterfall model.
This follows the five major steps for the development of the project. Below describe all the stages of the
development of the development of the project.
Requirements:
This is the initial stage of the development of the project. In this phase the working of over the
planning phase of the project, after that need to analysis the all the outcomes in the planning
phase.
In this, there are a need to analysis the stakeholders and the need for the stakeholders.
After the arrange the meeting with the stakeholders and with the team.
Then analysis the need for the requirement of the stakeholders.
Then analysis the schedule and cost of the project.
Develop the cost and then develops the schedule of the project.
Then discuss the cost and schedule of the project, with the team and find out the changes into the
schedule.
12
2018).
3. Project management approach
3.1. Project management methodology
For the development of the project, there is need to use the project methodology, there is a different
type of the project methodology are present and all have the different advantages and disadvantages
as per the requirement of the project. For the development of the project. For the development of the
project, there are using the waterfall model.
Figure 5: Waterfall model
The above figure shows the steps of the development of the project by the use of the waterfall model.
This follows the five major steps for the development of the project. Below describe all the stages of the
development of the development of the project.
Requirements:
This is the initial stage of the development of the project. In this phase the working of over the
planning phase of the project, after that need to analysis the all the outcomes in the planning
phase.
In this, there are a need to analysis the stakeholders and the need for the stakeholders.
After the arrange the meeting with the stakeholders and with the team.
Then analysis the need for the requirement of the stakeholders.
Then analysis the schedule and cost of the project.
Develop the cost and then develops the schedule of the project.
Then discuss the cost and schedule of the project, with the team and find out the changes into the
schedule.
12
Design
This is the second stage of the development of the project. This is the second stage of the
development of the project, after the analysis in the previous stage need to work on the design of the
project.
In this stage, there is need to analyse all the requirement and then works on the design of the
project.
Develops the meeting with the resources and works over the schedule.
Analysis the schedule of the project and the then start the development of the project on the
large scale.
Need to develops system for storage of the rainwater.
Need to develop the system to reuse of the water.
Need to the system, that manages the water system in the remote areas.
Implementation
This is the third stage of the development of the project. In this start the working of the implementation of
the project in the remote areas. This part of the system needs to works and implement the project in the
remote area.
All the design of the project is done in the above phase of the project. After that need to
implement the project into the system.
Develops the water management system in the remote areas
After that implement the reuse techniques into the water management system.
Verification
This is the fourth stage of the project development of the project, before this stage all the development of
the project is completed.
In this stage verifies the working of all the components.
After that analysis the working of the team.
After that need analysis the requirement of the stakeholders.
After that need to analysis the functions of all the developing tools.
For this case, there is a need to analyse the working of the all the component that is used for reuse the
water at the remote area other than this analysis the working of the rainwater storage system in the remote
areas. In this stage of the project, there are need to verifies the working of each resource of the project
development.
Maintenance
This is the final stage of the for the development of the project. In this, all the development of the project
is completed and testing of the project is completed. After that need to maintain the working of the
system. for that there are need some of the steps that are followed in this stage are:
Develops the team that has the manage the working of the all the components.
Time to time checkup of all the devices (Digital, 2018).
13
This is the second stage of the development of the project. This is the second stage of the
development of the project, after the analysis in the previous stage need to work on the design of the
project.
In this stage, there is need to analyse all the requirement and then works on the design of the
project.
Develops the meeting with the resources and works over the schedule.
Analysis the schedule of the project and the then start the development of the project on the
large scale.
Need to develops system for storage of the rainwater.
Need to develop the system to reuse of the water.
Need to the system, that manages the water system in the remote areas.
Implementation
This is the third stage of the development of the project. In this start the working of the implementation of
the project in the remote areas. This part of the system needs to works and implement the project in the
remote area.
All the design of the project is done in the above phase of the project. After that need to
implement the project into the system.
Develops the water management system in the remote areas
After that implement the reuse techniques into the water management system.
Verification
This is the fourth stage of the project development of the project, before this stage all the development of
the project is completed.
In this stage verifies the working of all the components.
After that analysis the working of the team.
After that need analysis the requirement of the stakeholders.
After that need to analysis the functions of all the developing tools.
For this case, there is a need to analyse the working of the all the component that is used for reuse the
water at the remote area other than this analysis the working of the rainwater storage system in the remote
areas. In this stage of the project, there are need to verifies the working of each resource of the project
development.
Maintenance
This is the final stage of the for the development of the project. In this, all the development of the project
is completed and testing of the project is completed. After that need to maintain the working of the
system. for that there are need some of the steps that are followed in this stage are:
Develops the team that has the manage the working of the all the components.
Time to time checkup of all the devices (Digital, 2018).
13
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
3.2 Strategy and procedures to achieve project goals/objectives
For achieving the goal, there are various of the approaches are present, that will help to develop the better
project for the system. there is need to use the some of the specific objectives of the project. For the
development of this project, then there are using the SMART approach to achieve the goal of the project.
Below show the steps of the SMART approach for the development of the project.
SMART defines as:
Specific.
Measurable
Acceptable.
Realistic.
Time-frame.
Figure 6: Smart Goal
Specific:
This is one of the basic steps of this process, this step is defining as the value of the project in the single
direction. This is one of the best approaches to start the project, that is defined in the project in the single
direction. By the help of this, it is easy to manage the work in the project and analysis the requirements of
the project. For this case there are need to develop the system, that has to maintain the supply of the water
14
For achieving the goal, there are various of the approaches are present, that will help to develop the better
project for the system. there is need to use the some of the specific objectives of the project. For the
development of this project, then there are using the SMART approach to achieve the goal of the project.
Below show the steps of the SMART approach for the development of the project.
SMART defines as:
Specific.
Measurable
Acceptable.
Realistic.
Time-frame.
Figure 6: Smart Goal
Specific:
This is one of the basic steps of this process, this step is defining as the value of the project in the single
direction. This is one of the best approaches to start the project, that is defined in the project in the single
direction. By the help of this, it is easy to manage the work in the project and analysis the requirements of
the project. For this case there are need to develop the system, that has to maintain the supply of the water
14
in the remote areas. For that need to develops the Rainwater harvesting in the remote areas. Other than
this need to develop the system, with the help of that, is easy to reuse the used water.
Measurable:
This is the other part of the system or this is the second step of the development of the project. In
this need to measure the effectiveness of the project. There are various of the project that has the
no use in other words the effectiveness of that project is at the zero level.
There is need to measure the effectiveness of the project, so it is easy to except by the remote
area. There is need a measure of the effectiveness of the project.
Acceptable:
This is the major part of the project. As the project planning is started at that time, in the planning
the project needs to accept by all the members of the team.
The project needs to accept by the stakeholders.
The project needs to accepted by the other member of the system and the people of the remote
area.
The criteria for the selection of the project are how much value the project.
Other than this there are need to develop the project that has the better scheduling.
Realistic:
While thinking of the project, there are need to analysis the possibility of the project. In that
comes all the process of the project.
There are major of the project area decline in the phase of the planning as they are possible to
implement in the real life.
Same for this case, there is a need to analyse all the working prototype in the real life.
Timeframe:
This is another most important part while selecting the project, then there is need to verifies the
schedule of the project.
While deciding the schedule of the project, then there is a need to develop the system, that
account all the risk that are associated with the project.
Need to verify the whole schedule of the project for the development of the project as to complete
the project over the required time and schedule.
While developing any schedule for the project, then need to analyse all the risk that is associated
with the project (Balance, 2018).
15
this need to develop the system, with the help of that, is easy to reuse the used water.
Measurable:
This is the other part of the system or this is the second step of the development of the project. In
this need to measure the effectiveness of the project. There are various of the project that has the
no use in other words the effectiveness of that project is at the zero level.
There is need to measure the effectiveness of the project, so it is easy to except by the remote
area. There is need a measure of the effectiveness of the project.
Acceptable:
This is the major part of the project. As the project planning is started at that time, in the planning
the project needs to accept by all the members of the team.
The project needs to accept by the stakeholders.
The project needs to accepted by the other member of the system and the people of the remote
area.
The criteria for the selection of the project are how much value the project.
Other than this there are need to develop the project that has the better scheduling.
Realistic:
While thinking of the project, there are need to analysis the possibility of the project. In that
comes all the process of the project.
There are major of the project area decline in the phase of the planning as they are possible to
implement in the real life.
Same for this case, there is a need to analyse all the working prototype in the real life.
Timeframe:
This is another most important part while selecting the project, then there is need to verifies the
schedule of the project.
While deciding the schedule of the project, then there is a need to develop the system, that
account all the risk that are associated with the project.
Need to verify the whole schedule of the project for the development of the project as to complete
the project over the required time and schedule.
While developing any schedule for the project, then need to analyse all the risk that is associated
with the project (Balance, 2018).
15
4. Scope management
4.1 Project scope statement
This is the part of the project design that is used to defines the project scope, deliverables and then find
out the constraints, assumptions and key success factors of the project. Other than this it is used to
defines the boundaries of the project. Below listed down all these elements.
Deliverables of the project
This is something that is related to the outcomes of the project. The outcomes of the project are in terms
to provides the water supplies in the remote area and develops a water management resources at that place
that will be good enough to fulfil all the water requirements of the remote areas. Some of the major
deliverables from the project are listed below:
Water supply to the remote areas.
Develops the relations with the stakeholders.
Develops the teams that have the good coordination with each other.
Time and schedule management.
Inclusion of project
This is part of the charter that provides the details about the task, items and actions that are included in the
project scope. Some of the common tasks that are related to the project scope are listed below:
Project schedule.
Resource management.
Components of water supply.
Stakeholders.
Exclusions
This is part of the charter that provides the details about the task, items and actions that are not included
in the project scope. Some of the common tasks that are related to the project scope are listed below:
Labours
External risk.
Natural hazards
Unwanted fault in the project.
Failure in the execution phase.
Business constraints
This is depending upon the state of the organization or the developer. This is mainly containing
the time, cost and resources of the project.
Technical constraints
This is the part of the system, that is used to apply the constraint over the design of the project.
As refers to the current scenario, then there are need to develop the pipelines that should contain
the water to the remote areas, then there is technical constraint regarding the pressure of the water
(Pmi, 2018).
16
4.1 Project scope statement
This is the part of the project design that is used to defines the project scope, deliverables and then find
out the constraints, assumptions and key success factors of the project. Other than this it is used to
defines the boundaries of the project. Below listed down all these elements.
Deliverables of the project
This is something that is related to the outcomes of the project. The outcomes of the project are in terms
to provides the water supplies in the remote area and develops a water management resources at that place
that will be good enough to fulfil all the water requirements of the remote areas. Some of the major
deliverables from the project are listed below:
Water supply to the remote areas.
Develops the relations with the stakeholders.
Develops the teams that have the good coordination with each other.
Time and schedule management.
Inclusion of project
This is part of the charter that provides the details about the task, items and actions that are included in the
project scope. Some of the common tasks that are related to the project scope are listed below:
Project schedule.
Resource management.
Components of water supply.
Stakeholders.
Exclusions
This is part of the charter that provides the details about the task, items and actions that are not included
in the project scope. Some of the common tasks that are related to the project scope are listed below:
Labours
External risk.
Natural hazards
Unwanted fault in the project.
Failure in the execution phase.
Business constraints
This is depending upon the state of the organization or the developer. This is mainly containing
the time, cost and resources of the project.
Technical constraints
This is the part of the system, that is used to apply the constraint over the design of the project.
As refers to the current scenario, then there are need to develop the pipelines that should contain
the water to the remote areas, then there is technical constraint regarding the pressure of the water
(Pmi, 2018).
16
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
4.2 Work Breakdown Structure
Figure 7: WBS structure
17
Water supply
management
Planning
Develops team
Find out
stakeholder
Meeting with
stakeholders
Analysis need of
stakeholders
Team meeting
Planning Phase
completed
Analysis
Stakeholder
Requriments
Project
Requriments
Busniess
Requriments
Risk
Components
Team meeting
Analysis phase
completed
Design
Develops
catchment area
Develops Pipes
Develops storgae
tank
Develops Filters
Develops Pump
Design phase
completed
Implementation
Implementation
water Harvesting
system
Implementation
water Reuse
system
Implementation
phase completed
Testing
Test Harvesting
system
Test water Reuse
system
Test Filers
Test Storage tank
Test Pumps
Test phase
completed
Maintenance
Maintenance of
Harvest system
Maintenance of
water reuse
system
Maintenance of
filters
Maintenance of
Pump
Maintenance
phase completed
Project
completed
Figure 7: WBS structure
17
Water supply
management
Planning
Develops team
Find out
stakeholder
Meeting with
stakeholders
Analysis need of
stakeholders
Team meeting
Planning Phase
completed
Analysis
Stakeholder
Requriments
Project
Requriments
Busniess
Requriments
Risk
Components
Team meeting
Analysis phase
completed
Design
Develops
catchment area
Develops Pipes
Develops storgae
tank
Develops Filters
Develops Pump
Design phase
completed
Implementation
Implementation
water Harvesting
system
Implementation
water Reuse
system
Implementation
phase completed
Testing
Test Harvesting
system
Test water Reuse
system
Test Filers
Test Storage tank
Test Pumps
Test phase
completed
Maintenance
Maintenance of
Harvest system
Maintenance of
water reuse
system
Maintenance of
filters
Maintenance of
Pump
Maintenance
phase completed
Project
completed
4.3. Scope control plan
This is the part of the project, that is used for monitoring of the development of the project. There is a
different type of the system that is used to monitoring the project progress. There is a need to develops the
proper schedule of the project, this can be done in the planning phase of the project. There is a different
type of the project monitoring techniques are listed below:
1. Schedule
This is the one of the technique by the use of this it is easy to measure the progress of the project. All the
task has the definite time and duration of completion. There is need to analysis the working of the current
development part of the project. After that compare the current schedule of the project to the planned
schedule of the project. If the project is ahead of the schedule then it is good for the system, if it up to the
mark than also this is good, but if it is behind then there is need to work over the schedule.
2. Quality
The schedule of the project is important for the development of the project, but at the same time, there is
need to monitor the quality of the project. There is need to measure the quality of the project, after
achieving every milestone in the project. This can be done with the help of the test engineer in the project.
3. Cost
the whole project is depended upon the costing of the project. All the cost of the resources and the cost of
the project are analysis in the planning and the analysis phase of the project. After that, there is need to
analysis the costing of the project at every stage of the project. There is need to measure the actual cost of
the project to the analysis cost of the project at every sub-stages of the project.
4. Stakeholder satisfaction
This is the major part of the project development, there is need to arrange the meetings with the
stakeholder after completion of every stage of the project. In the meeting, there is a need to provide the
information about the progress of the project to the stakeholder. If the stakeholder is happy with the rate
and progress of the project, then there are many problems are solved related to the project.
5. Performance to business care
This is related in terms of the business through the project, that means how the project is going through at
the success of the project for the system. There are need to analyse every factor that is related to the
project and needs to analyse the progression of the project (Scope, 2018).
18
This is the part of the project, that is used for monitoring of the development of the project. There is a
different type of the system that is used to monitoring the project progress. There is a need to develops the
proper schedule of the project, this can be done in the planning phase of the project. There is a different
type of the project monitoring techniques are listed below:
1. Schedule
This is the one of the technique by the use of this it is easy to measure the progress of the project. All the
task has the definite time and duration of completion. There is need to analysis the working of the current
development part of the project. After that compare the current schedule of the project to the planned
schedule of the project. If the project is ahead of the schedule then it is good for the system, if it up to the
mark than also this is good, but if it is behind then there is need to work over the schedule.
2. Quality
The schedule of the project is important for the development of the project, but at the same time, there is
need to monitor the quality of the project. There is need to measure the quality of the project, after
achieving every milestone in the project. This can be done with the help of the test engineer in the project.
3. Cost
the whole project is depended upon the costing of the project. All the cost of the resources and the cost of
the project are analysis in the planning and the analysis phase of the project. After that, there is need to
analysis the costing of the project at every stage of the project. There is need to measure the actual cost of
the project to the analysis cost of the project at every sub-stages of the project.
4. Stakeholder satisfaction
This is the major part of the project development, there is need to arrange the meetings with the
stakeholder after completion of every stage of the project. In the meeting, there is a need to provide the
information about the progress of the project to the stakeholder. If the stakeholder is happy with the rate
and progress of the project, then there are many problems are solved related to the project.
5. Performance to business care
This is related in terms of the business through the project, that means how the project is going through at
the success of the project for the system. There are need to analyse every factor that is related to the
project and needs to analyse the progression of the project (Scope, 2018).
18
5. Requirements management
5.1. Requirements management plan
This is the part of the system that is used to defines the working of the resources in the system. there are
different resources are used in this case to fulfil all the system, user and stakeholder requirements. Below
shows the data of the resources.
Resource
Name Type Material
Label Initials Group Max.
Units Std. Rate Ovt. Rate Cost/Use Accrue
At
Base
Calendar
Business
Analysis Work B 100% $60.00/hr $0.00/hr $0.00 Prorated Standard
Mechanical
engineer Work M 100% $42.00/hr $0.00/hr $0.00 Prorated Standard
Electrical
engineer Work E 100% $32.00/hr $0.00/hr $0.00 Prorated Standard
Civil engineer Work C 100% $65.00/hr $0.00/hr $0.00 Prorated Standard
Test engineer Work T 100% $31.00/hr $0.00/hr $0.00 Prorated Standard
Supplier Work S 100% $62.00/hr $0.00/hr $0.00 Prorated Standard
Technical
writer Work T 100% $40.00/hr $0.00/hr $0.00 Prorated Standard
19
5.1. Requirements management plan
This is the part of the system that is used to defines the working of the resources in the system. there are
different resources are used in this case to fulfil all the system, user and stakeholder requirements. Below
shows the data of the resources.
Resource
Name Type Material
Label Initials Group Max.
Units Std. Rate Ovt. Rate Cost/Use Accrue
At
Base
Calendar
Business
Analysis Work B 100% $60.00/hr $0.00/hr $0.00 Prorated Standard
Mechanical
engineer Work M 100% $42.00/hr $0.00/hr $0.00 Prorated Standard
Electrical
engineer Work E 100% $32.00/hr $0.00/hr $0.00 Prorated Standard
Civil engineer Work C 100% $65.00/hr $0.00/hr $0.00 Prorated Standard
Test engineer Work T 100% $31.00/hr $0.00/hr $0.00 Prorated Standard
Supplier Work S 100% $62.00/hr $0.00/hr $0.00 Prorated Standard
Technical
writer Work T 100% $40.00/hr $0.00/hr $0.00 Prorated Standard
19
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
5.2 Requirements traceability matrix
For fulfilling the requirement there is a need to develops the matrix, the matrix is described below:
Task owners
Task
numbe
r
Task Business
Analysis
t
Civil
enginee
r
Test
enginee
r
Owner Supplie
r
Mechanical
engineer
Stakeholder
s
1 Provides the
fund for the
project.
2 Analysis the
need for
stakeholders
3 Develops
catchment area
4 Develops Pipes
5 Develops
storage tank
6 Develops Filters
7 Develops Pump
8 Test Harvesting
system
9 Test water
Reuse system
20
For fulfilling the requirement there is a need to develops the matrix, the matrix is described below:
Task owners
Task
numbe
r
Task Business
Analysis
t
Civil
enginee
r
Test
enginee
r
Owner Supplie
r
Mechanical
engineer
Stakeholder
s
1 Provides the
fund for the
project.
2 Analysis the
need for
stakeholders
3 Develops
catchment area
4 Develops Pipes
5 Develops
storage tank
6 Develops Filters
7 Develops Pump
8 Test Harvesting
system
9 Test water
Reuse system
20
6. Stakeholder management
6.1 Stakeholder analysis
Figure 8: Stakeholder analysis
6.2 Stakeholder management plan
Stakeholder Role Interest
(1,2,3)
Influenc
e
(1,2,3)
What is the
most important
goal of the
stakeholder
How will
he/she
contribute
Contact
information
Jon Owner 3 2 Manage the
project
Invest in
the project.
55524562482
Johnston Project
manager
3 2 Manage the
schedule and cost
of the project
Manage
the project.
2132458975
Utility
employee
Workers 2 2 Working as per
the instructions.
Invest time
and efforts.
1254523657
Society Remote area
peoples
2 2 Use the outcomes
of the project.
Waiting for
outcomes.
2102101236
Government Government 1 1 Analysis the
working of the
project.
Develops
rules for
the project.
1021452369
21
6.1 Stakeholder analysis
Figure 8: Stakeholder analysis
6.2 Stakeholder management plan
Stakeholder Role Interest
(1,2,3)
Influenc
e
(1,2,3)
What is the
most important
goal of the
stakeholder
How will
he/she
contribute
Contact
information
Jon Owner 3 2 Manage the
project
Invest in
the project.
55524562482
Johnston Project
manager
3 2 Manage the
schedule and cost
of the project
Manage
the project.
2132458975
Utility
employee
Workers 2 2 Working as per
the instructions.
Invest time
and efforts.
1254523657
Society Remote area
peoples
2 2 Use the outcomes
of the project.
Waiting for
outcomes.
2102101236
Government Government 1 1 Analysis the
working of the
project.
Develops
rules for
the project.
1021452369
21
7. Schedule management
7.1. Schedule management methodology/approach
Refers to the schedule management then there are a lot of the tools are present in the schedule
management. The aim of the tools is to manage the cost of the development process, other than
this it is used to manage the time duration and schedule of the project. By the use of the schedule
management, it is easy to manage the resources and it is easy to understand the resources of the
project. For this case one of the software are using for the schedule management that is MS
project.
7.1.1. Software
This is one of the common software that is used to develops the project plan. This provides the
interface to the user, with the help of that it is easy to manage all the resources, scheduling of the
project and helps to manage the costing of the project. Some of the major advantages of the MS
project are:
Figure 9: MS project
It provides the easy interface to the user that helps to manage the resources.
There is no need to performs the calculation over this software.
In this easy to understand the critical tasks.
Easy to manage the schedule and easy to manage the costing of the project.
Resource allocation in a simpler way (Greycampus, 2018).
22
7.1. Schedule management methodology/approach
Refers to the schedule management then there are a lot of the tools are present in the schedule
management. The aim of the tools is to manage the cost of the development process, other than
this it is used to manage the time duration and schedule of the project. By the use of the schedule
management, it is easy to manage the resources and it is easy to understand the resources of the
project. For this case one of the software are using for the schedule management that is MS
project.
7.1.1. Software
This is one of the common software that is used to develops the project plan. This provides the
interface to the user, with the help of that it is easy to manage all the resources, scheduling of the
project and helps to manage the costing of the project. Some of the major advantages of the MS
project are:
Figure 9: MS project
It provides the easy interface to the user that helps to manage the resources.
There is no need to performs the calculation over this software.
In this easy to understand the critical tasks.
Easy to manage the schedule and easy to manage the costing of the project.
Resource allocation in a simpler way (Greycampus, 2018).
22
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
7.2. Schedule monitoring and control plan
Refer to the schedule monitoring plan and controlling plan, then this is used to manage the cost of the
project, or this is used to verifies the progress of the project. This can be done with the help of the earned
value analysis. In this, there are two types of the calculation, one if cost variance and other is schedule
variance. As the project started, then the project is divided into the task, and each task needs to two pieces
of the information that are budget and the start or end date.
There are carried outcome of the cost values of the project, that are listed below:
Planned values: this is budget of the project.
Earned values: this is the actual amount of the project
Actual cost: this is actual cost required for each task.
After calculating all these values, there are some of the measure values need to be analysis, that is
Cost variance: CV= EV-AC (this is the amount that project in cost overrun)
Schedule variance: SV= EV-PV (this is the amount of project behind the schedule)
The cist is used as the base variable for the calculation of the schedule and cost variance, that is output in
the percentage of the performance index.
Cost performance index: CPI= EV/AC
Schedule performance index: SPI = EV/PV (Bernie Roseke, 2018).
Figure 10 Earned values
23
Refer to the schedule monitoring plan and controlling plan, then this is used to manage the cost of the
project, or this is used to verifies the progress of the project. This can be done with the help of the earned
value analysis. In this, there are two types of the calculation, one if cost variance and other is schedule
variance. As the project started, then the project is divided into the task, and each task needs to two pieces
of the information that are budget and the start or end date.
There are carried outcome of the cost values of the project, that are listed below:
Planned values: this is budget of the project.
Earned values: this is the actual amount of the project
Actual cost: this is actual cost required for each task.
After calculating all these values, there are some of the measure values need to be analysis, that is
Cost variance: CV= EV-AC (this is the amount that project in cost overrun)
Schedule variance: SV= EV-PV (this is the amount of project behind the schedule)
The cist is used as the base variable for the calculation of the schedule and cost variance, that is output in
the percentage of the performance index.
Cost performance index: CPI= EV/AC
Schedule performance index: SPI = EV/PV (Bernie Roseke, 2018).
Figure 10 Earned values
23
7.3 The critical path
The below image shows the critical path of the project in the network diagram.
Figure 11: Network diagram of the critical path
The below image shows the critical path of all the activities. This shows that there is two type of lines,
one is blue that is non-critical and other is red that is a critical task.
Business Analysist ,Technical writer
Business Analysist ,Technical writer
Business Analysist ,Technical writer
Business Analysist ,Technical writer
Business Analysist ,Technical writer
5/16
Business Analysist ,Civil engineer ,Supplier ,Technical writer
Business Analysist ,Civil engineer ,Supplier ,Technical writer
Business Analysist ,Civil engineer ,Supplier ,Technical writer
Business Analysist ,Civil engineer ,Supplier ,Technical writer
Business Analysist ,Civil engineer ,Supplier ,Technical writer
Business Analysist ,Civil engineer ,Supplier ,Technical writer
6/20
Business Analysist ,Electrical engineer ,Mechanical engineer ,Civil engineer
Business Analysist ,Electrical engineer ,Mechanical engineer ,Civil engineer
Business Analysist ,Electrical engineer ,Mechanical engineer ,Civil engineer
Business Analysist ,Electrical engineer ,Mechanical engineer ,Civil engineer
Business Analysist ,Electrical engineer ,Mechanical engineer ,Civil engineer
8/1
Electrical engineer ,Mechanical engineer ,Civil engineer
Electrical engineer ,Mechanical engineer ,Civil engineer
8/1
Technical writer ,Test engineer
Technical writer ,Test engineer
Technical writer ,Test engineer
Technical writer ,Test engineer
Technical writer ,Test engineer
6/19
Electrical engineer ,Mechanical engineer
Civil engineer
Mechanical engineer ,Civil engineer
Supplier
8/9
8/9
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
Apr 15, '18 Apr 22, '18 Apr 29, '18 May 6, '18 May 13, '18 May 20, '18 May 27, '18 Jun 3, '18 Jun 10, '18 Jun 17, '18 Jun 24, '18 Jul 1, '18 Jul 8, '18 Jul 15, '18 Jul 22, '18 Jul 29, '18 Aug 5, '18
Figure 12: Critical task
24
The below image shows the critical path of the project in the network diagram.
Figure 11: Network diagram of the critical path
The below image shows the critical path of all the activities. This shows that there is two type of lines,
one is blue that is non-critical and other is red that is a critical task.
Business Analysist ,Technical writer
Business Analysist ,Technical writer
Business Analysist ,Technical writer
Business Analysist ,Technical writer
Business Analysist ,Technical writer
5/16
Business Analysist ,Civil engineer ,Supplier ,Technical writer
Business Analysist ,Civil engineer ,Supplier ,Technical writer
Business Analysist ,Civil engineer ,Supplier ,Technical writer
Business Analysist ,Civil engineer ,Supplier ,Technical writer
Business Analysist ,Civil engineer ,Supplier ,Technical writer
Business Analysist ,Civil engineer ,Supplier ,Technical writer
6/20
Business Analysist ,Electrical engineer ,Mechanical engineer ,Civil engineer
Business Analysist ,Electrical engineer ,Mechanical engineer ,Civil engineer
Business Analysist ,Electrical engineer ,Mechanical engineer ,Civil engineer
Business Analysist ,Electrical engineer ,Mechanical engineer ,Civil engineer
Business Analysist ,Electrical engineer ,Mechanical engineer ,Civil engineer
8/1
Electrical engineer ,Mechanical engineer ,Civil engineer
Electrical engineer ,Mechanical engineer ,Civil engineer
8/1
Technical writer ,Test engineer
Technical writer ,Test engineer
Technical writer ,Test engineer
Technical writer ,Test engineer
Technical writer ,Test engineer
6/19
Electrical engineer ,Mechanical engineer
Civil engineer
Mechanical engineer ,Civil engineer
Supplier
8/9
8/9
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
Apr 15, '18 Apr 22, '18 Apr 29, '18 May 6, '18 May 13, '18 May 20, '18 May 27, '18 Jun 3, '18 Jun 10, '18 Jun 17, '18 Jun 24, '18 Jul 1, '18 Jul 8, '18 Jul 15, '18 Jul 22, '18 Jul 29, '18 Aug 5, '18
Figure 12: Critical task
24
7.4. Activity list, sequencing and duration estimates
Below shows the list of the activities for the development of the project.
ID Task
Mode
WBS Task Name Duration Start Finish Predecessors Resource Names Cost
0 0 Water supply
management
83 days Tue
4/17/18
Thu
8/9/18
$135,616.00
1 1 1 Planning 57 days Tue 4/17/18Wed 7/4/18 $11,200.00
2 1.1 1.1 Develops team2 days Tue 4/17/18Wed 4/18/18 Business Analysist ,Technical writer$1,600.00
3 1.2 1.2 Find out stakeholder6 days Mon 4/30/18Wed 5/16/182 Business Analysist ,Technical writer$2,400.00
4 1.3 1.3 Meeting
with
stakeholders
8 days Thu
5/17/18
Wed
6/13/18
3 Business
Analysist
,Technical
$3,200.00
5 1.4 1.4 Analysis
need of
stakeholders
6 days Mon
6/18/18
Wed
7/4/18
4 Business
Analysist
,Technical
$2,400.00
6 1.5 1.5 Team meeting2 days Thu 4/19/18Fri 4/20/18 2 Business Analysist ,Technical writer$1,600.00
7 M1 1.6 Planning
Phase
completed
0 days Wed
5/16/18
Wed
5/16/18
3 $0.00
8 2 2 Analysis 63 days Mon 4/23/18Wed 7/18/18 $27,240.00
9 2.1 2.1 Stakeholder
Requriments
12 days Thu
6/14/18
Wed
7/11/18
4 Business
Analysist ,Civil
engineer
$5,448.00
10 2.2 2.2 Project Requriments3 days Mon 4/23/18Wed 4/25/186 Business Analysist ,Civil engineer ,Supplier ,Technical writer$5,448.00
11 2.3 2.3 Busniess
Requriments
8 days Thu
5/17/18
Wed
6/20/18
7 Business
Analysist ,Civil
engineer
$3,632.00
12 2.4 2.4 Risk 4 days Thu 7/5/18 Wed 7/18/185 Business Analysist ,Civil engineer ,Supplier ,Technical writer$3,632.00
13 2.5 2.5 Components 12 days Mon 4/30/18Thu 6/7/18 6 Business Analysist ,Civil engineer ,Supplier ,Technical writer$5,448.00
14 2.6 2.6 Team meeting2 days Thu 4/26/18Fri 4/27/18 10 Business Analysist ,Civil engineer ,Supplier ,Technical writer$3,632.00
15 M2 2.7 Analysis
phase
completed
0 days Wed
6/20/18
Wed
6/20/18
11 $0.00
16 3 3 Design 68 days Mon 4/30/18Wed 8/1/18 $65,272.00
17 3.1 3.1 Develops
catchment area
10 days Mon
4/30/18
Fri 5/11/18 14 Business
Analysist
,Electrical
$15,920.00
18 3.2 3.2 Develops Pipes16 days Mon 5/14/18Mon 6/4/1817 Business Analysist ,Electrical engineer ,Mechanical engineer ,Civil e$20,696.00
19 3.3 3.3 Develops storgae tank8 days Tue 6/5/18 Mon 6/18/1818 Business Analysist ,Electrical engineer ,Mechanical engineer ,Civil e$4,776.00
20 3.4 3.4 Develops Filters9 days Tue 6/19/18Fri 6/29/18 19 Business Analysist ,Electrical engineer ,Mechanical engineer ,Civil e$11,144.00
21 3.5 3.5 Develops Pump13 days Mon 7/16/18Wed 8/1/1820 Business Analysist ,Electrical engineer ,Mechanical engineer ,Civil e$12,736.00
22 M3 3.6 Design
phase
completed
0 days Wed
8/1/18
Wed
8/1/18
21 $0.00
23 4 4 Implementation 43 days Mon 6/4/18Wed 8/1/18 $16,680.00
24 4.1 4.1
Implementation
water
Harvesting
8 days Mon
6/4/18
Wed
6/13/18
17 Electrical
engineer
,Mechanical
engineer ,Civil
$5,560.00
25 4.2 4.2
Implementation
water Reuse
10 days Tue 7/3/18 Mon
7/16/18
19 Electrical
engineer
,Mechanical
$11,120.00
26 M4 4.3
Implementation
phase
0 days Wed
8/1/18
Wed
8/1/18
21 $0.00
27 5 5 Testing 35 days Thu 6/14/18Wed 8/1/18 $9,088.00
28 5.1 5.1 Test
Harvesting
system
3 days Mon
7/30/18
Wed
8/1/18
25 Technical
writer ,Test
engineer
$1,704.00
29 5.2 5.2 Test water
Reuse system
4 days Tue
7/24/18
Fri 7/27/18 25 Technical
writer ,Test
engineer
$2,272.00
30 5.3 5.3 Test Filers 2 days Tue 7/17/18Wed 7/18/1825 Technical writer ,Test engineer$1,136.00
31 5.4 5.4 Test Storage tank4 days Thu 6/14/18Tue 6/19/1824 Technical writer ,Test engineer$2,272.00
32 5.5 5.5 Test Pumps 3 days Thu 7/19/18Mon 7/23/1830 Technical writer ,Test engineer$1,704.00
33 M5 5.6 Test phase
completed
0 days Tue
6/19/18
Tue
6/19/18
31 $0.00
34 6 6 Maintenance 37 days Wed 6/20/18Thu 8/9/18 $6,136.00
35 6.1 6.1
Maintenance of
Harvest system
4 days Wed
6/20/18
Wed
7/4/18
33 Electrical
engineer
,Mechanical
$2,368.00
36 6.2 6.2
Maintenance of
water reuse
3 days Thu 8/2/18 Mon
8/6/18
35 Civil engineer $1,560.00
37 6.3 6.3 Maintenance of filters2 days Tue 8/7/18 Wed 8/8/1836 Mechanical engineer ,Civil engineer$1,712.00
38 6.4 6.4 Maintenance of Pump1 day Thu 8/9/18 Thu 8/9/18 37 Supplier $496.00
39 M6 6.5
Maintenance
phase
0 days Thu 8/9/18 Thu 8/9/18 38 Mechanical
engineer ,Civil
engineer
$0.00
40 M7 6.6 Project completed0 days Thu 8/9/18 Thu 8/9/18 39 $0.00
Business Analysist ,Technical
Business Analysist ,T
Bu
T
Apr 15, '18
Figure 13: Activity list
25
Below shows the list of the activities for the development of the project.
ID Task
Mode
WBS Task Name Duration Start Finish Predecessors Resource Names Cost
0 0 Water supply
management
83 days Tue
4/17/18
Thu
8/9/18
$135,616.00
1 1 1 Planning 57 days Tue 4/17/18Wed 7/4/18 $11,200.00
2 1.1 1.1 Develops team2 days Tue 4/17/18Wed 4/18/18 Business Analysist ,Technical writer$1,600.00
3 1.2 1.2 Find out stakeholder6 days Mon 4/30/18Wed 5/16/182 Business Analysist ,Technical writer$2,400.00
4 1.3 1.3 Meeting
with
stakeholders
8 days Thu
5/17/18
Wed
6/13/18
3 Business
Analysist
,Technical
$3,200.00
5 1.4 1.4 Analysis
need of
stakeholders
6 days Mon
6/18/18
Wed
7/4/18
4 Business
Analysist
,Technical
$2,400.00
6 1.5 1.5 Team meeting2 days Thu 4/19/18Fri 4/20/18 2 Business Analysist ,Technical writer$1,600.00
7 M1 1.6 Planning
Phase
completed
0 days Wed
5/16/18
Wed
5/16/18
3 $0.00
8 2 2 Analysis 63 days Mon 4/23/18Wed 7/18/18 $27,240.00
9 2.1 2.1 Stakeholder
Requriments
12 days Thu
6/14/18
Wed
7/11/18
4 Business
Analysist ,Civil
engineer
$5,448.00
10 2.2 2.2 Project Requriments3 days Mon 4/23/18Wed 4/25/186 Business Analysist ,Civil engineer ,Supplier ,Technical writer$5,448.00
11 2.3 2.3 Busniess
Requriments
8 days Thu
5/17/18
Wed
6/20/18
7 Business
Analysist ,Civil
engineer
$3,632.00
12 2.4 2.4 Risk 4 days Thu 7/5/18 Wed 7/18/185 Business Analysist ,Civil engineer ,Supplier ,Technical writer$3,632.00
13 2.5 2.5 Components 12 days Mon 4/30/18Thu 6/7/18 6 Business Analysist ,Civil engineer ,Supplier ,Technical writer$5,448.00
14 2.6 2.6 Team meeting2 days Thu 4/26/18Fri 4/27/18 10 Business Analysist ,Civil engineer ,Supplier ,Technical writer$3,632.00
15 M2 2.7 Analysis
phase
completed
0 days Wed
6/20/18
Wed
6/20/18
11 $0.00
16 3 3 Design 68 days Mon 4/30/18Wed 8/1/18 $65,272.00
17 3.1 3.1 Develops
catchment area
10 days Mon
4/30/18
Fri 5/11/18 14 Business
Analysist
,Electrical
$15,920.00
18 3.2 3.2 Develops Pipes16 days Mon 5/14/18Mon 6/4/1817 Business Analysist ,Electrical engineer ,Mechanical engineer ,Civil e$20,696.00
19 3.3 3.3 Develops storgae tank8 days Tue 6/5/18 Mon 6/18/1818 Business Analysist ,Electrical engineer ,Mechanical engineer ,Civil e$4,776.00
20 3.4 3.4 Develops Filters9 days Tue 6/19/18Fri 6/29/18 19 Business Analysist ,Electrical engineer ,Mechanical engineer ,Civil e$11,144.00
21 3.5 3.5 Develops Pump13 days Mon 7/16/18Wed 8/1/1820 Business Analysist ,Electrical engineer ,Mechanical engineer ,Civil e$12,736.00
22 M3 3.6 Design
phase
completed
0 days Wed
8/1/18
Wed
8/1/18
21 $0.00
23 4 4 Implementation 43 days Mon 6/4/18Wed 8/1/18 $16,680.00
24 4.1 4.1
Implementation
water
Harvesting
8 days Mon
6/4/18
Wed
6/13/18
17 Electrical
engineer
,Mechanical
engineer ,Civil
$5,560.00
25 4.2 4.2
Implementation
water Reuse
10 days Tue 7/3/18 Mon
7/16/18
19 Electrical
engineer
,Mechanical
$11,120.00
26 M4 4.3
Implementation
phase
0 days Wed
8/1/18
Wed
8/1/18
21 $0.00
27 5 5 Testing 35 days Thu 6/14/18Wed 8/1/18 $9,088.00
28 5.1 5.1 Test
Harvesting
system
3 days Mon
7/30/18
Wed
8/1/18
25 Technical
writer ,Test
engineer
$1,704.00
29 5.2 5.2 Test water
Reuse system
4 days Tue
7/24/18
Fri 7/27/18 25 Technical
writer ,Test
engineer
$2,272.00
30 5.3 5.3 Test Filers 2 days Tue 7/17/18Wed 7/18/1825 Technical writer ,Test engineer$1,136.00
31 5.4 5.4 Test Storage tank4 days Thu 6/14/18Tue 6/19/1824 Technical writer ,Test engineer$2,272.00
32 5.5 5.5 Test Pumps 3 days Thu 7/19/18Mon 7/23/1830 Technical writer ,Test engineer$1,704.00
33 M5 5.6 Test phase
completed
0 days Tue
6/19/18
Tue
6/19/18
31 $0.00
34 6 6 Maintenance 37 days Wed 6/20/18Thu 8/9/18 $6,136.00
35 6.1 6.1
Maintenance of
Harvest system
4 days Wed
6/20/18
Wed
7/4/18
33 Electrical
engineer
,Mechanical
$2,368.00
36 6.2 6.2
Maintenance of
water reuse
3 days Thu 8/2/18 Mon
8/6/18
35 Civil engineer $1,560.00
37 6.3 6.3 Maintenance of filters2 days Tue 8/7/18 Wed 8/8/1836 Mechanical engineer ,Civil engineer$1,712.00
38 6.4 6.4 Maintenance of Pump1 day Thu 8/9/18 Thu 8/9/18 37 Supplier $496.00
39 M6 6.5
Maintenance
phase
0 days Thu 8/9/18 Thu 8/9/18 38 Mechanical
engineer ,Civil
engineer
$0.00
40 M7 6.6 Project completed0 days Thu 8/9/18 Thu 8/9/18 39 $0.00
Business Analysist ,Technical
Business Analysist ,T
Bu
T
Apr 15, '18
Figure 13: Activity list
25
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Figure 14: Cost overview
Figure 15: Cost Status
Figure 16: Progress versus cost
26
Figure 15: Cost Status
Figure 16: Progress versus cost
26
7.5. Milestones
S. No. Milestones Details Start date End date Duration
1 Milestone 1: Planning phase
completed start
Wed 5/16/18 Wed 5/16/18 O days
2 Milestone 2: Analysis phase
completed
Wed 6/20/18 Wed 6/20/18 O days
3 Milestone 3: Design phase
completed
Wed 8/1/18 Wed 8/1/18 O days
4 Milestone 4: Implementation
phase
completed
Wed 8/1/18 Wed 8/1/18 O days
5 Milestone 5: Testing phase
completed
Tue 6/19/18 Tue 6/19/18 O days
6 Milestones 6: Maintenance
phase
completed
Thu 8/9/18 Thu 8/9/18 O days
7 Milestones 7: the whole
project is
completed.
Thu 8/9/18 Thu 8/9/18 O days
27
S. No. Milestones Details Start date End date Duration
1 Milestone 1: Planning phase
completed start
Wed 5/16/18 Wed 5/16/18 O days
2 Milestone 2: Analysis phase
completed
Wed 6/20/18 Wed 6/20/18 O days
3 Milestone 3: Design phase
completed
Wed 8/1/18 Wed 8/1/18 O days
4 Milestone 4: Implementation
phase
completed
Wed 8/1/18 Wed 8/1/18 O days
5 Milestone 5: Testing phase
completed
Tue 6/19/18 Tue 6/19/18 O days
6 Milestones 6: Maintenance
phase
completed
Thu 8/9/18 Thu 8/9/18 O days
7 Milestones 7: the whole
project is
completed.
Thu 8/9/18 Thu 8/9/18 O days
27
7.6. Gantt chart
ID Tas k
Mode
WBS Task Name Duration Start Finish
0 0 Water supply
management
83 days Tue
4/17/18
Thu
8/9/18
1 1 1 Planning 57 days Tue 4/17/18Wed 7/4/18
2 1.1 1.1 Develops team2 days Tue 4/17/18Wed 4/18/18
3 1.2 1.2 Find out stakeholder6 days Mon 4/30/18Wed 5/16/18
4 1.3 1.3 Meeting
with
stakeholders
8 days Thu
5/17/18
Wed
6/13/18
5 1.4 1.4 Analysis
need of
stakeholders
6 days Mon
6/18/18
Wed
7/4/18
6 1.5 1.5 Team meeting2 days Thu 4/19/18Fri 4/20/18
7 M1 1.6 Planning
Phase
completed
0 days Wed
5/16/18
Wed
5/16/18
8 2 2 Analysis 63 days Mon 4/23/18Wed 7/18/18
9 2.1 2.1 Stakeholder
Requriments
12 days Thu
6/14/18
Wed
7/11/18
10 2.2 2.2 Project Requriments3 days Mon 4/23/18Wed 4/25/18
11 2.3 2.3 Busniess
Requriments
8 days Thu
5/17/18
Wed
6/20/18
12 2.4 2.4 Risk 4 days Thu 7/5/18Wed 7/18/18
13 2.5 2.5 Components 12 days Mon 4/30/18Thu 6/7/18
14 2.6 2.6 Team meeting2 days Thu 4/26/18Fri 4/27/18
15 M2 2.7 Analysis
phase
completed
0 days Wed
6/20/18
Wed
6/20/18
16 3 3 Design 68 days Mon 4/30/18Wed 8/1/18
17 3.1 3.1 Develops
catchment area
10 days Mon
4/30/18
Fri 5/11/18
18 3.2 3.2 Develops Pipes16 days Mon 5/14/18Mon 6/4/18
19 3.3 3.3 Develops storgae tank8 days Tue 6/5/18Mon 6/18/18
20 3.4 3.4 Develops Filters9 days Tue 6/19/18Fri 6/29/18
21 3.5 3.5 Develops Pump13 days Mon 7/16/18Wed 8/1/18
22 M3 3.6 Design
phase
completed
0 days Wed
8/1/18
Wed
8/1/18
23 4 4 Implementation 43 days Mon 6/4/18Wed 8/1/18
24 4.1 4.1
Implementation
water
Harvesting
8 days Mon
6/4/18
Wed
6/13/18
25 4.2 4.2
Implementation
water Reuse
10 days Tue 7/3/18Mon
7/16/18
26 M4 4.3
Implementation
phase
0 days Wed
8/1/18
Wed
8/1/18
27 5 5 Testing 35 days Thu 6/14/18Wed 8/1/18
28 5.1 5.1 Test
Harvesting
system
3 days Mon
7/30/18
Wed
8/1/18
29 5.2 5.2 Test water
Reuse system
4 days Tue
7/24/18
Fri 7/27/18
30 5.3 5.3 Test Filers 2 days Tue 7/17/18Wed 7/18/18
31 5.4 5.4 Test Storage tank4 days Thu 6/14/18Tue 6/19/18
32 5.5 5.5 Test Pumps 3 days Thu 7/19/18Mon 7/23/18
33 M5 5.6 Test phase
completed
0 days Tue
6/19/18
Tue
6/19/18
34 6 6 Maintenance 37 days Wed 6/20/18Thu 8/9/18
35 6.1 6.1
Maintenance of
Harvest system
4 days Wed
6/20/18
Wed
7/4/18
36 6.2 6.2
Maintenance of
water reuse
3 days Thu 8/2/18Mon
8/6/18
37 6.3 6.3 Maintenance of filters2 days Tue 8/7/18Wed 8/8/18
38 6.4 6.4 Maintenance of Pump1 day Thu 8/9/18Thu 8/9/18
39 M6 6.5
Maintenance
phase
0 days Thu 8/9/18Thu 8/9/18
40 M7 6.6 Project completed0 days Thu 8/9/18Thu 8/9/18
Business Analysist ,Technical writer
Business Analysist ,Technical writer
Business Analysist ,Technical writer
Business Analysist ,Technical writer
Business Analysist ,Technical writer
5/16
Business Analysist ,Civil engineer ,Supplier ,Technical writer
Business Analysist ,Civil engineer ,Supplier ,Technical writer
Business Analysist ,Civil engineer ,Supplier ,Technical writer
Business Analysist ,Civil engineer ,Supplier ,Technical writer
Business Analysist ,Civil engineer ,Supplier ,Technical writer
Business Analysist ,Civil engineer ,Supplier ,Technical writer
6/20
Business Analysist ,Electrical engineer ,Mechanical engineer ,Civil engineer
Business Analysist ,Electrical engineer ,Mechanical engineer ,Civil engineer
Business Analysist ,Electrical engineer ,Mechanical engineer ,Civil engineer
Business Analysist ,Electrical engineer ,Mechanical engineer ,Civil engineer
Business Analysist ,Electrical engineer ,Mechanical engineer ,Civil engineer
8/1
Electrical engineer ,Mechanical engineer ,Civil engineer
Electrical engineer ,Mechanical engineer ,Civil engineer
8/1
Technical writer ,Test engineer
Technical writer ,Test engineer
Technical writer ,Test engineer
Technical writer ,Test engineer
Technical writer ,Test engineer
6/19
Electrical engineer ,Mechanical engineer
Civil engineer
Mechanical engineer ,Civil engineer
Supplier
8/9
8/9
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
Apr 15, '18 Apr 22, '18 Apr 29, '18 May 6, '18 May 13, '18 May 20, '18 May 27, '18 Jun 3, '18 Jun 10, '18 Jun 17, '18 Jun 24, '18 Jul 1, '18 Jul 8, '18 Jul 15, '18 Jul 22, '18 Jul 29, '18 Aug 5, '18
Figure 17: Gantt chart
28
ID Tas k
Mode
WBS Task Name Duration Start Finish
0 0 Water supply
management
83 days Tue
4/17/18
Thu
8/9/18
1 1 1 Planning 57 days Tue 4/17/18Wed 7/4/18
2 1.1 1.1 Develops team2 days Tue 4/17/18Wed 4/18/18
3 1.2 1.2 Find out stakeholder6 days Mon 4/30/18Wed 5/16/18
4 1.3 1.3 Meeting
with
stakeholders
8 days Thu
5/17/18
Wed
6/13/18
5 1.4 1.4 Analysis
need of
stakeholders
6 days Mon
6/18/18
Wed
7/4/18
6 1.5 1.5 Team meeting2 days Thu 4/19/18Fri 4/20/18
7 M1 1.6 Planning
Phase
completed
0 days Wed
5/16/18
Wed
5/16/18
8 2 2 Analysis 63 days Mon 4/23/18Wed 7/18/18
9 2.1 2.1 Stakeholder
Requriments
12 days Thu
6/14/18
Wed
7/11/18
10 2.2 2.2 Project Requriments3 days Mon 4/23/18Wed 4/25/18
11 2.3 2.3 Busniess
Requriments
8 days Thu
5/17/18
Wed
6/20/18
12 2.4 2.4 Risk 4 days Thu 7/5/18Wed 7/18/18
13 2.5 2.5 Components 12 days Mon 4/30/18Thu 6/7/18
14 2.6 2.6 Team meeting2 days Thu 4/26/18Fri 4/27/18
15 M2 2.7 Analysis
phase
completed
0 days Wed
6/20/18
Wed
6/20/18
16 3 3 Design 68 days Mon 4/30/18Wed 8/1/18
17 3.1 3.1 Develops
catchment area
10 days Mon
4/30/18
Fri 5/11/18
18 3.2 3.2 Develops Pipes16 days Mon 5/14/18Mon 6/4/18
19 3.3 3.3 Develops storgae tank8 days Tue 6/5/18Mon 6/18/18
20 3.4 3.4 Develops Filters9 days Tue 6/19/18Fri 6/29/18
21 3.5 3.5 Develops Pump13 days Mon 7/16/18Wed 8/1/18
22 M3 3.6 Design
phase
completed
0 days Wed
8/1/18
Wed
8/1/18
23 4 4 Implementation 43 days Mon 6/4/18Wed 8/1/18
24 4.1 4.1
Implementation
water
Harvesting
8 days Mon
6/4/18
Wed
6/13/18
25 4.2 4.2
Implementation
water Reuse
10 days Tue 7/3/18Mon
7/16/18
26 M4 4.3
Implementation
phase
0 days Wed
8/1/18
Wed
8/1/18
27 5 5 Testing 35 days Thu 6/14/18Wed 8/1/18
28 5.1 5.1 Test
Harvesting
system
3 days Mon
7/30/18
Wed
8/1/18
29 5.2 5.2 Test water
Reuse system
4 days Tue
7/24/18
Fri 7/27/18
30 5.3 5.3 Test Filers 2 days Tue 7/17/18Wed 7/18/18
31 5.4 5.4 Test Storage tank4 days Thu 6/14/18Tue 6/19/18
32 5.5 5.5 Test Pumps 3 days Thu 7/19/18Mon 7/23/18
33 M5 5.6 Test phase
completed
0 days Tue
6/19/18
Tue
6/19/18
34 6 6 Maintenance 37 days Wed 6/20/18Thu 8/9/18
35 6.1 6.1
Maintenance of
Harvest system
4 days Wed
6/20/18
Wed
7/4/18
36 6.2 6.2
Maintenance of
water reuse
3 days Thu 8/2/18Mon
8/6/18
37 6.3 6.3 Maintenance of filters2 days Tue 8/7/18Wed 8/8/18
38 6.4 6.4 Maintenance of Pump1 day Thu 8/9/18Thu 8/9/18
39 M6 6.5
Maintenance
phase
0 days Thu 8/9/18Thu 8/9/18
40 M7 6.6 Project completed0 days Thu 8/9/18Thu 8/9/18
Business Analysist ,Technical writer
Business Analysist ,Technical writer
Business Analysist ,Technical writer
Business Analysist ,Technical writer
Business Analysist ,Technical writer
5/16
Business Analysist ,Civil engineer ,Supplier ,Technical writer
Business Analysist ,Civil engineer ,Supplier ,Technical writer
Business Analysist ,Civil engineer ,Supplier ,Technical writer
Business Analysist ,Civil engineer ,Supplier ,Technical writer
Business Analysist ,Civil engineer ,Supplier ,Technical writer
Business Analysist ,Civil engineer ,Supplier ,Technical writer
6/20
Business Analysist ,Electrical engineer ,Mechanical engineer ,Civil engineer
Business Analysist ,Electrical engineer ,Mechanical engineer ,Civil engineer
Business Analysist ,Electrical engineer ,Mechanical engineer ,Civil engineer
Business Analysist ,Electrical engineer ,Mechanical engineer ,Civil engineer
Business Analysist ,Electrical engineer ,Mechanical engineer ,Civil engineer
8/1
Electrical engineer ,Mechanical engineer ,Civil engineer
Electrical engineer ,Mechanical engineer ,Civil engineer
8/1
Technical writer ,Test engineer
Technical writer ,Test engineer
Technical writer ,Test engineer
Technical writer ,Test engineer
Technical writer ,Test engineer
6/19
Electrical engineer ,Mechanical engineer
Civil engineer
Mechanical engineer ,Civil engineer
Supplier
8/9
8/9
T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
Apr 15, '18 Apr 22, '18 Apr 29, '18 May 6, '18 May 13, '18 May 20, '18 May 27, '18 Jun 3, '18 Jun 10, '18 Jun 17, '18 Jun 24, '18 Jul 1, '18 Jul 8, '18 Jul 15, '18 Jul 22, '18 Jul 29, '18 Aug 5, '18
Figure 17: Gantt chart
28
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
8. Appendices
Task
Mode WBS Task Name Duration Start Finish Predecessors Resource
Names Cost
Auto
Scheduled 0 Water supply
management 83 days Tue
4/17/18
Thu
8/9/18 $135,616.00
Auto
Scheduled 1 Planning 57 days Tue
4/17/18
Wed
7/4/18 $11,200.00
Auto
Scheduled 1.1 Develops
team 2 days Tue
4/17/18
Wed
4/18/18
Business
Analysist ,T
echnical
writer
$1,600.00
Auto
Scheduled 1.2 Find out
stakeholder 6 days Mon
4/30/18
Wed
5/16/18 2
Business
Analysis,
Technical
writer
$2,400.00
Auto
Scheduled 1.3 Meeting with
stakeholders 8 days Thu
5/17/18
Wed
6/13/18 3
Business
Analysis,
Technical
writer
$3,200.00
Auto
Scheduled 1.4 Analysis need
of stakeholders 6 days Mon
6/18/18
Wed
7/4/18 4
Business
Analysis,
Technical
writer
$2,400.00
Auto
Scheduled 1.5 Team meeting 2 days Thu
4/19/18
Fri
4/20/18 2
Business
Analysist ,T
echnical
writer
$1,600.00
Auto
Scheduled M1 Planning
Phase completed 0 days Wed
5/16/18
Wed
5/16/18 3 $0.00
Auto
Scheduled 2 Analysis 63 days Mon
4/23/18
Wed
7/18/18 $27,240.00
Auto
Scheduled 2.1 Stakeholder
Requirements 12 days Thu
6/14/18
Wed
7/11/18 4
Business
Analysis,
Civil
engineer,
Supplier,
Technical
writer
$5,448.00
29
Task
Mode WBS Task Name Duration Start Finish Predecessors Resource
Names Cost
Auto
Scheduled 0 Water supply
management 83 days Tue
4/17/18
Thu
8/9/18 $135,616.00
Auto
Scheduled 1 Planning 57 days Tue
4/17/18
Wed
7/4/18 $11,200.00
Auto
Scheduled 1.1 Develops
team 2 days Tue
4/17/18
Wed
4/18/18
Business
Analysist ,T
echnical
writer
$1,600.00
Auto
Scheduled 1.2 Find out
stakeholder 6 days Mon
4/30/18
Wed
5/16/18 2
Business
Analysis,
Technical
writer
$2,400.00
Auto
Scheduled 1.3 Meeting with
stakeholders 8 days Thu
5/17/18
Wed
6/13/18 3
Business
Analysis,
Technical
writer
$3,200.00
Auto
Scheduled 1.4 Analysis need
of stakeholders 6 days Mon
6/18/18
Wed
7/4/18 4
Business
Analysis,
Technical
writer
$2,400.00
Auto
Scheduled 1.5 Team meeting 2 days Thu
4/19/18
Fri
4/20/18 2
Business
Analysist ,T
echnical
writer
$1,600.00
Auto
Scheduled M1 Planning
Phase completed 0 days Wed
5/16/18
Wed
5/16/18 3 $0.00
Auto
Scheduled 2 Analysis 63 days Mon
4/23/18
Wed
7/18/18 $27,240.00
Auto
Scheduled 2.1 Stakeholder
Requirements 12 days Thu
6/14/18
Wed
7/11/18 4
Business
Analysis,
Civil
engineer,
Supplier,
Technical
writer
$5,448.00
29
Auto
Scheduled 2.2 Project
Requirements 3 days Mon
4/23/18
Wed
4/25/18 6
Business
Analysis,
Civil
engineer,
Supplier,
Technical
writer
$5,448.00
Auto
Scheduled 2.3 Business
Requirements 8 days Thu
5/17/18
Wed
6/20/18 7
Business
Analysis,
Civil
engineer,
Supplier,
Technical
writer
$3,632.00
Auto
Scheduled 2.4 Risk 4 days Thu
7/5/18
Wed
7/18/18 5
Business
Analysist ,Ci
vil
engineer ,Su
pplier ,Tech
nical writer
$3,632.00
Auto
Scheduled 2.5 Components 12 days Mon
4/30/18
Thu
6/7/18 6
Business
Analysist ,Ci
vil
engineer ,Su
pplier ,Tech
nical writer
$5,448.00
Auto
Scheduled 2.6 Team meeting 2 days Thu
4/26/18
Fri
4/27/18 10
Business
Analysis,
Civil
engineer,
Supplier,
Technical
writer
$3,632.00
Auto
Scheduled M2 Analysis
phase completed 0 days Wed
6/20/18
Wed
6/20/18 11 $0.00
Auto
Scheduled 3 Design 68 days Mon
4/30/18
Wed
8/1/18 $65,272.00
Auto
Scheduled
3.1 Develops
catchment area
10 days Mon
4/30/18
Fri
5/11/18
14 Business
Analysist ,El
ectrical
engineer ,M
echanical
$15,920.00
30
Scheduled 2.2 Project
Requirements 3 days Mon
4/23/18
Wed
4/25/18 6
Business
Analysis,
Civil
engineer,
Supplier,
Technical
writer
$5,448.00
Auto
Scheduled 2.3 Business
Requirements 8 days Thu
5/17/18
Wed
6/20/18 7
Business
Analysis,
Civil
engineer,
Supplier,
Technical
writer
$3,632.00
Auto
Scheduled 2.4 Risk 4 days Thu
7/5/18
Wed
7/18/18 5
Business
Analysist ,Ci
vil
engineer ,Su
pplier ,Tech
nical writer
$3,632.00
Auto
Scheduled 2.5 Components 12 days Mon
4/30/18
Thu
6/7/18 6
Business
Analysist ,Ci
vil
engineer ,Su
pplier ,Tech
nical writer
$5,448.00
Auto
Scheduled 2.6 Team meeting 2 days Thu
4/26/18
Fri
4/27/18 10
Business
Analysis,
Civil
engineer,
Supplier,
Technical
writer
$3,632.00
Auto
Scheduled M2 Analysis
phase completed 0 days Wed
6/20/18
Wed
6/20/18 11 $0.00
Auto
Scheduled 3 Design 68 days Mon
4/30/18
Wed
8/1/18 $65,272.00
Auto
Scheduled
3.1 Develops
catchment area
10 days Mon
4/30/18
Fri
5/11/18
14 Business
Analysist ,El
ectrical
engineer ,M
echanical
$15,920.00
30
engineer ,Ci
vil engineer
Auto
Scheduled 3.2 Develops
Pipes 16 days Mon
5/14/18
Mon
6/4/18 17
Business
Analysist ,El
ectrical
engineer ,M
echanical
engineer ,Ci
vil engineer
$20,696.00
Auto
Scheduled 3.3 Develops
storage tank 8 days Tue
6/5/18
Mon
6/18/18 18
Business
Analysis,
Electrical
engineer,
Mechanical
engineer,
Civil
engineer
$4,776.00
Auto
Scheduled 3.4 Develops
Filters 9 days Tue
6/19/18
Fri
6/29/18 19
Business
Analysist ,El
ectrical
engineer ,M
echanical
engineer ,Ci
vil engineer
$11,144.00
Auto
Scheduled 3.5 Develops
Pump 13 days Mon
7/16/18
Wed
8/1/18 20
Business
Analysist ,El
ectrical
engineer ,M
echanical
engineer ,Ci
vil engineer
$12,736.00
Auto
Scheduled M3 Design phase
completed 0 days Wed
8/1/18
Wed
8/1/18 21 $0.00
Auto
Scheduled 4 Implementation 43 days Mon
6/4/18
Wed
8/1/18 $16,680.00
Auto
Scheduled 4.1 Implementation
water Harvesting
system
8 days Mon
6/4/18
Wed
6/13/18 17
Electrical
engineer ,M
echanical
engineer ,Ci
vil engineer
$5,560.00
Auto 4.2 10 days Tue Mon 19 Electrical $11,120.00
31
vil engineer
Auto
Scheduled 3.2 Develops
Pipes 16 days Mon
5/14/18
Mon
6/4/18 17
Business
Analysist ,El
ectrical
engineer ,M
echanical
engineer ,Ci
vil engineer
$20,696.00
Auto
Scheduled 3.3 Develops
storage tank 8 days Tue
6/5/18
Mon
6/18/18 18
Business
Analysis,
Electrical
engineer,
Mechanical
engineer,
Civil
engineer
$4,776.00
Auto
Scheduled 3.4 Develops
Filters 9 days Tue
6/19/18
Fri
6/29/18 19
Business
Analysist ,El
ectrical
engineer ,M
echanical
engineer ,Ci
vil engineer
$11,144.00
Auto
Scheduled 3.5 Develops
Pump 13 days Mon
7/16/18
Wed
8/1/18 20
Business
Analysist ,El
ectrical
engineer ,M
echanical
engineer ,Ci
vil engineer
$12,736.00
Auto
Scheduled M3 Design phase
completed 0 days Wed
8/1/18
Wed
8/1/18 21 $0.00
Auto
Scheduled 4 Implementation 43 days Mon
6/4/18
Wed
8/1/18 $16,680.00
Auto
Scheduled 4.1 Implementation
water Harvesting
system
8 days Mon
6/4/18
Wed
6/13/18 17
Electrical
engineer ,M
echanical
engineer ,Ci
vil engineer
$5,560.00
Auto 4.2 10 days Tue Mon 19 Electrical $11,120.00
31
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Scheduled
Implementation
water Reuse
system
7/3/18 7/16/18
engineer ,M
echanical
engineer ,Ci
vil engineer
Auto
Scheduled M4 Implementation
phase completed
0 days Wed
8/1/18
Wed
8/1/18 21 $0.00
Auto
Scheduled 5 Testing 35 days Thu
6/14/18
Wed
8/1/18 $9,088.00
Auto
Scheduled 5.1 Test
Harvesting system 3 days Mon
7/30/18
Wed
8/1/18 25
Technical
writer ,Test
engineer
$1,704.00
Auto
Scheduled 5.2 Test water
Reuse system 4 days Tue
7/24/18
Fri
7/27/18 25
Technical
writer ,Test
engineer
$2,272.00
Auto
Scheduled 5.3 Test Filers 2 days Tue
7/17/18
Wed
7/18/18 25
Technical
writer ,Test
engineer
$1,136.00
Auto
Scheduled 5.4 Test Storage
tank 4 days Thu
6/14/18
Tue
6/19/18 24
Technical
writer ,Test
engineer
$2,272.00
Auto
Scheduled 5.5 Test Pumps 3 days Thu
7/19/18
Mon
7/23/18 30
Technical
writer ,Test
engineer
$1,704.00
Auto
Scheduled M5 Test phase
completed 0 days Tue
6/19/18
Tue
6/19/18 31 $0.00
Auto
Scheduled 6 Maintenance 37 days Wed
6/20/18
Thu
8/9/18 $6,136.00
Auto
Scheduled 6.1 Maintenance
of Harvest system 4 days Wed
6/20/18
Wed
7/4/18 33
Electrical
engineer ,M
echanical
engineer
$2,368.00
Auto
Scheduled 6.2
Maintenance
of water reuse
system
3 days Thu
8/2/18
Mon
8/6/18 35 Civil
engineer $1,560.00
Auto
Scheduled
6.3 Maintenance
of filters
2 days Tue
8/7/18
Wed
8/8/18
36 Mechanical
engineer,
Civil
$1,712.00
32
Implementation
water Reuse
system
7/3/18 7/16/18
engineer ,M
echanical
engineer ,Ci
vil engineer
Auto
Scheduled M4 Implementation
phase completed
0 days Wed
8/1/18
Wed
8/1/18 21 $0.00
Auto
Scheduled 5 Testing 35 days Thu
6/14/18
Wed
8/1/18 $9,088.00
Auto
Scheduled 5.1 Test
Harvesting system 3 days Mon
7/30/18
Wed
8/1/18 25
Technical
writer ,Test
engineer
$1,704.00
Auto
Scheduled 5.2 Test water
Reuse system 4 days Tue
7/24/18
Fri
7/27/18 25
Technical
writer ,Test
engineer
$2,272.00
Auto
Scheduled 5.3 Test Filers 2 days Tue
7/17/18
Wed
7/18/18 25
Technical
writer ,Test
engineer
$1,136.00
Auto
Scheduled 5.4 Test Storage
tank 4 days Thu
6/14/18
Tue
6/19/18 24
Technical
writer ,Test
engineer
$2,272.00
Auto
Scheduled 5.5 Test Pumps 3 days Thu
7/19/18
Mon
7/23/18 30
Technical
writer ,Test
engineer
$1,704.00
Auto
Scheduled M5 Test phase
completed 0 days Tue
6/19/18
Tue
6/19/18 31 $0.00
Auto
Scheduled 6 Maintenance 37 days Wed
6/20/18
Thu
8/9/18 $6,136.00
Auto
Scheduled 6.1 Maintenance
of Harvest system 4 days Wed
6/20/18
Wed
7/4/18 33
Electrical
engineer ,M
echanical
engineer
$2,368.00
Auto
Scheduled 6.2
Maintenance
of water reuse
system
3 days Thu
8/2/18
Mon
8/6/18 35 Civil
engineer $1,560.00
Auto
Scheduled
6.3 Maintenance
of filters
2 days Tue
8/7/18
Wed
8/8/18
36 Mechanical
engineer,
Civil
$1,712.00
32
engineer
Auto
Scheduled 6.4 Maintenance
of Pump 1 day Thu
8/9/18
Thu
8/9/18 37 Supplier $496.00
Auto
Scheduled M6 Maintenance
phase completed 0 days Thu
8/9/18
Thu
8/9/18 38
Mechanical
engineer,
Civil
engineer
$0.00
Auto
Scheduled M7 Project
completed 0 days Thu
8/9/18
Thu
8/9/18 39 $0.00
33
Auto
Scheduled 6.4 Maintenance
of Pump 1 day Thu
8/9/18
Thu
8/9/18 37 Supplier $496.00
Auto
Scheduled M6 Maintenance
phase completed 0 days Thu
8/9/18
Thu
8/9/18 38
Mechanical
engineer,
Civil
engineer
$0.00
Auto
Scheduled M7 Project
completed 0 days Thu
8/9/18
Thu
8/9/18 39 $0.00
33
References
Balance (2018). 5 Elements of a SMART Business Goal. [online] The Balance. Available at:
https://www.thebalance.com/elements-of-a-smart-business-goal-2951530 [Accessed 17 Apr. 2018].
Bernie Roseke, P. (2018). Project Monitoring and Control. [online] ProjectEngineer. Available at:
http://www.projectengineer.net/project-monitoring-and-control/ [Accessed 17 Apr. 2018].
Bizfluent (2018). Who Are the Key Stakeholders in an Organization?. [online] Bizfluent.com.
Available at: https://bizfluent.com/info-8397448-key-stakeholders-organization.html [Accessed 17
Apr. 2018].
Brighthub (2018). Difference Between Project Charter vs Project Plan. [online] Brighthub Project
Management. Available at: https://www.brighthubpm.com/project-planning/75050-project-charter-vs-
project-plan/ [Accessed 17 Apr. 2018].
Digital (2018). 9 Project Management Methodologies Made Simple - The Digital Project Manager.
[online] The Digital Project Manager. Available at: https://thedigitalprojectmanager.com/project-
management-methodologies-made-simple/ [Accessed 17 Apr. 2018].
Greycampus (2018). Monitor and Control Project Work | Project Management Professional (PMP).
[online] Greycampus.com. Available at: https://www.greycampus.com/opencampus/project-
management-professional/monitor-and-control-project-work [Accessed 17 Apr. 2018].
Planning (2018). 12. Budget Planning – Project Management. [online] Opentextbc.ca. Available at:
https://opentextbc.ca/projectmanagement/chapter/chapter-12-budget-planning-project-management/
[Accessed 17 Apr. 2018].
Pmi (2018). Developing a complete project scope statement in 2 days. [online] Pmi.org. Available at:
https://www.pmi.org/learning/library/project-scope-statement-skills-tools-7981 [Accessed 17 Apr.
2018].
Pmi (2018). What is Project Management?. [online] Pmi.org. Available at:
https://www.pmi.org/about/learn-about-pmi/what-is-project-management [Accessed 17 Apr. 2018].
project (2018). How to define the scope of a project - Totally Communications. [online]
Totallycommunications.com. Available at: https://www.totallycommunications.com/latest/how-to-
define-the-scope-of-a-project/ [Accessed 17 Apr. 2018].
Resources (2016). The 6 Project Constraints. [online] Resources.workfront.com. Available at:
https://resources.workfront.com/project-management-blog/the-6-project-constraints [Accessed 17
Apr. 2018].
Sacriver (2018). 2.1 Goals and objectives | Sacramento River Watershed Program. [online]
Sacriver.org. Available at: http://www.sacriver.org/aboutwatershed/reportcard/section2/21-goals-and-
objectives [Accessed 17 Apr. 2018].
Scope (2018). Scope Management Plan Template. [online] Projectmanagementdocs.com. Available
at: http://www.projectmanagementdocs.com/project-planning-templates/scope-management-
plan.html [Accessed 17 Apr. 2018].
34
Balance (2018). 5 Elements of a SMART Business Goal. [online] The Balance. Available at:
https://www.thebalance.com/elements-of-a-smart-business-goal-2951530 [Accessed 17 Apr. 2018].
Bernie Roseke, P. (2018). Project Monitoring and Control. [online] ProjectEngineer. Available at:
http://www.projectengineer.net/project-monitoring-and-control/ [Accessed 17 Apr. 2018].
Bizfluent (2018). Who Are the Key Stakeholders in an Organization?. [online] Bizfluent.com.
Available at: https://bizfluent.com/info-8397448-key-stakeholders-organization.html [Accessed 17
Apr. 2018].
Brighthub (2018). Difference Between Project Charter vs Project Plan. [online] Brighthub Project
Management. Available at: https://www.brighthubpm.com/project-planning/75050-project-charter-vs-
project-plan/ [Accessed 17 Apr. 2018].
Digital (2018). 9 Project Management Methodologies Made Simple - The Digital Project Manager.
[online] The Digital Project Manager. Available at: https://thedigitalprojectmanager.com/project-
management-methodologies-made-simple/ [Accessed 17 Apr. 2018].
Greycampus (2018). Monitor and Control Project Work | Project Management Professional (PMP).
[online] Greycampus.com. Available at: https://www.greycampus.com/opencampus/project-
management-professional/monitor-and-control-project-work [Accessed 17 Apr. 2018].
Planning (2018). 12. Budget Planning – Project Management. [online] Opentextbc.ca. Available at:
https://opentextbc.ca/projectmanagement/chapter/chapter-12-budget-planning-project-management/
[Accessed 17 Apr. 2018].
Pmi (2018). Developing a complete project scope statement in 2 days. [online] Pmi.org. Available at:
https://www.pmi.org/learning/library/project-scope-statement-skills-tools-7981 [Accessed 17 Apr.
2018].
Pmi (2018). What is Project Management?. [online] Pmi.org. Available at:
https://www.pmi.org/about/learn-about-pmi/what-is-project-management [Accessed 17 Apr. 2018].
project (2018). How to define the scope of a project - Totally Communications. [online]
Totallycommunications.com. Available at: https://www.totallycommunications.com/latest/how-to-
define-the-scope-of-a-project/ [Accessed 17 Apr. 2018].
Resources (2016). The 6 Project Constraints. [online] Resources.workfront.com. Available at:
https://resources.workfront.com/project-management-blog/the-6-project-constraints [Accessed 17
Apr. 2018].
Sacriver (2018). 2.1 Goals and objectives | Sacramento River Watershed Program. [online]
Sacriver.org. Available at: http://www.sacriver.org/aboutwatershed/reportcard/section2/21-goals-and-
objectives [Accessed 17 Apr. 2018].
Scope (2018). Scope Management Plan Template. [online] Projectmanagementdocs.com. Available
at: http://www.projectmanagementdocs.com/project-planning-templates/scope-management-
plan.html [Accessed 17 Apr. 2018].
34
1 out of 34
Related Documents
Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
© 2024 | Zucol Services PVT LTD | All rights reserved.