[Type here] ITC505-Project Management Project Final Report Website and Application Development for I-Crop Name of the Student: Wasif Numan Student ID: 11640426
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
ITC505-Assignment 3 Table of Contents 1. Part One: MOV - Measurable Organisational Value...................................................................2 2. Part Two:Define Scope and produce a Scope Management Plan...............................................4 3. Part Three: WBS..........................................................................................................................6 4. Part Four: Project Risk Analysis and Plan.................................................................................15 5. Part Five: Quality Management Plan.........................................................................................16 6. Part Six: Closure and Evaluation...............................................................................................17 MS PROJECT FILE......................................................................................................................20 Bibliography..................................................................................................................................21 1|W a s i f N u m a n - 1 1 6 4 0 4 2 6
ITC505-Assignment 3 1. Part One: MOV - Measurable Organisational Value FinancialArea:Financialareaoftheprojectofwebsiteandmobileapplication development of I-Crop Project is the most crucial aspect of delivering the effective project execution as the economic value of the projects. CustomerArea:Customerareaoftheprojectofwebsiteandmobileapplication development of I-Crop Project is the second most aspect of delivering the effective project outcome as the alignment of the client’s requirement is a major factor for the project execution. Operational Area: Operational area of the project of website and mobile application development of I-Crop Project is third most aspect of delivering the finite project execution and alignment. Strategy Area: Strategically alignment of the successful project execution has been helpful for achieving the deployment of the effective implication model for the project of website and mobile application development of I-Crop Project. Social Area: The social area is responsible for the inclusion of the operations and aligning the utilization of the social platform for the effective process modification. Better- The implication of the website and mobile application for I-Crop would be helpful for improving the operations aligned with the development. 2|W a s i f N u m a n - 1 1 6 4 0 4 2 6
ITC505-Assignment 3 Faster- The faster operation development can be achieved with the improvement of the effective website and mobile application Cheaper- The overall cost of the operations of I-Crop would be decreased with the inclusion of the website and mobile application. Do more- The installation of website and mobile application would help in easing the communication management for the operations for I-Crop. RankImpactMetricsTimeframe (in months) 1FinancialProfit Margin3 2CustomerFeedbacks and Orders4 3OperationalProcessing Time2 4StrategyEffective Implication1 5SocialFeedbacks on social media web5 3|W a s i f N u m a n - 1 1 6 4 0 4 2 6
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
ITC505-Assignment 3 2. Part Two:Define Scope and produce a Scope Management Plan Define the scope:The project scope involves the simplification management and integration of the successive and improved operations for I-Crop. The project scope definition would be implied for identifying the alignment of the operations and execution. The scope definition would be implied for easing the significant formation and development. The alignment would be helpfulforintegratingthesuccessfulformationoftheimprovedwebsiteandmobile development. The information development would support the formation of the improved functional development and improvements. The project scope would include the functions of developing the website and mobile design, developing the website and mobile, implementation plan, and closure documents. Provide a list of Resources: People:Analyst,Documenter,Planner,ProjectManager,WebsiteDesigner,Application Designer, Engineer, Website Developer, Programmer, and Application Developer. Technology: Website Development, Mobile Application Development, Design Development, Mobile Application UI Development, and Testing technology. Facilities: Testing and UI simulation environment facility would be required for the completion of the project. 4|W a s i f N u m a n - 1 1 6 4 0 4 2 6
ITC505-Assignment 3 Screenshot of Project Resource List: IDResource NameTypeMax. UnitsStd. RateOvt. Rate 1AnalystWork100%$50.00/hr$0.00/hr 2DocumenterWork100%$55.00/hr$0.00/hr 3PlannerWork100%$60.00/hr$0.00/hr 4Project ManagerWork100%$125.00/hr$0.00/hr 5Website DesignerWork100%$90.00/hr$0.00/hr 6Application DesignerWork100%$90.00/hr$0.00/hr 7EngineerWork100%$120.00/hr$0.00/hr 8Website DeveloperWork100%$100.00/hr$0.00/hr 9ProgrammerWork100%$110.00/hr$0.00/hr 10Application DeveloperWork100%$100.00/hr$0.00/hr 11DocumentsMaterial$150.00 12Design ToolsMaterial$1,200.00 13Domain CostMaterial$750.00 Scope Management Plan:The project of website and mobile application development of I-Crop Project would be executed for developing the innovative technology for mobile and website development in integrating the alignment of the innovative operation development. 5|W a s i f N u m a n - 1 1 6 4 0 4 2 6
ITC505-Assignment 3 Requirements:The analysis of the factors of development can be implied for easing the design and development of the website and mobile application. The integration management would be helpful for ensuring the completion of the project. In scope-out scope items:The project plan, developing the website and mobile design, developing the website and mobile, implementation plan, and closure documents are the in scope items where as the transportation requirements, communication, and change management are the out of scope items of the project. Deliverables:The deliverables for the website and mobile application development of I-Crop Projectwouldincludeprojectplan,design,development,testingresults,andclosure documentation. Acceptance Criteria: Feasible Project Plan is made Simulation of the design provides positive outcomes Developed website and mobile application meets the requirement criteria Testing results are as per the expectation 3. Part Three: WBS 6|W a s i f N u m a n - 1 1 6 4 0 4 2 6
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
ITC505-Assignment 3 Milestones WBSMilestone NameDurationStartFinish 1.5Signing off0 daysMon 11/12/18Mon 11/12/18 2.5Approving Complete Plan0 daysWed 11/21/18Wed 11/21/18 3.1.5Approving Website0 daysFri 11/30/18Fri 11/30/18 3.2.5Approving Mobile Application0 daysTue 12/11/18Tue 12/11/18 5.5Closure0 daysFri 1/25/19Fri 1/25/19 Activities / Tasks WBSTask Name 0I-Crop Website and Mobile Application Development Project 1Initialization Phase 1.1Analyzing requirements 1.2Making Project Charter Documents 1.3Making Project Initiation Documents 1.4Submitting documents 1.5Signing off 2Plan Development Phase 2.1Selecting Plan Methodology 2.2Making Plan Outline 2.3Reviewing Plan Outline 7|W a s i f N u m a n - 1 1 6 4 0 4 2 6
ITC505-Assignment 3 2.4Making Complete Plan 2.5Approving Complete Plan 3Design Development Phase 3.1Design of Website 3.1.1Selecting Design Platform 3.1.2Making Website Outline 3.1.3Reviewing Website Outline 3.1.4Making Complete Website 3.1.5Approving Website 3.2Design of Mobile Application 3.2.1Selecting Design Platform 3.2.2Making Mobile Application Outline 3.2.3Reviewing Mobile Application Outline 3.2.4Making Complete Mobile Application 3.2.5Approving Mobile Application 4Development Phase 4.1Development of Website 4.1.1Buying Website Domain 4.1.2Developing Website Interface 4.1.3Aligning Functions of Website 4.1.4Making Programs for Website 4.1.5Checking Mobile Compatibility 8|W a s i f N u m a n - 1 1 6 4 0 4 2 6
ITC505-Assignment 3 4.1.6Completion of Website Development 4.2Development of Mobile Application 4.2.1Developing Application Interface 4.2.2Making Programs for Mobile Application 4.2.3Integrating Mobile Applications 4.2.4Completion of Mobile Application Development 5Closing Phase 5.1Making Closure Reports 5.2Making Evaluation Checklist 5.3Submitting Report Documents 5.4Signing off 5.5Closure 9|W a s i f N u m a n - 1 1 6 4 0 4 2 6
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
ITC505-Assignment 3 Resource Assignments IDResource NameWork 1Analyst8 hrs 2Documenter64 hrs 3Planner48 hrs 4Project Manager32 hrs 5Website Designer48 hrs 6Application Designer48 hrs 7Engineer40 hrs 8Website Developer72 hrs 9Programmer56 hrs 10Application Developer64 hrs 11Documents3 12Design Tools4 13Domain Cost1 Details Work Work Work Work Work Work Work Work Work Work Work Work Work MSSFTWTM Oct 21, '18Nov 18, '18Dec 16, '18Jan 13, '19Feb 10, '19 8h 40h16h8h 24h24h 8h24h 48h 48h 8h16h8h8h 8h56h8h 16h40h 16h48h 21 22 1 10|W a s i f N u m a n - 1 1 6 4 0 4 2 6
ITC505-Assignment 3 11|W a s i f N u m a n - 1 1 6 4 0 4 2 6
ITC505-Assignment 3 Estimates for Each Activity / Task WBSTask NameResource NamesCost 1.1Analyzing requirementsAnalyst$400.00 1.2Making Project Charter DocumentsDocumenter, Documents[1]$1,030.00 1.3Making Project Initiation DocumentsDocumenter, Documents[1]$1,030.00 1.4Submitting documentsDocumenter$440.00 1.5Signing off$0.00 2.1Selecting Plan MethodologyPlanner$480.00 2.2Making Plan OutlinePlanner$960.00 2.3Reviewing Plan OutlineProject Manager$1,000.00 2.4Making Complete PlanPlanner$1,440.00 2.5Approving Complete Plan$0.00 3.1.1Selecting Design PlatformWebsite Designer, Design Tools[1]$1,920.00 3.1.2Making Website OutlineWebsite Designer$1,440.00 3.1.3Reviewing Website OutlineEngineer$960.00 3.1.4Making Complete WebsiteWebsite Designer, Design Tools[1]$3,360.00 3.1.5Approving Website$0.00 3.2.1Selecting Design PlatformApplication Designer, Design Tools[1]$1,920.00 12|W a s i f N u m a n - 1 1 6 4 0 4 2 6
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
ITC505-Assignment 3 3.2.2Making Mobile Application OutlineApplication Designer$1,440.00 3.2.3Reviewing Mobile Application OutlineEngineer$960.00 3.2.4Making Complete Mobile ApplicationApplication Designer, Design Tools[1]$3,360.00 3.2.5Approving Mobile Application$0.00 4.1.1Buying Website DomainEngineer, Domain Cost[1]$1,710.00 4.1.2Developing Website InterfaceWebsite Developer$2,400.00 4.1.3Aligning Functions of WebsiteWebsite Developer$1,600.00 4.1.4Making Programs for WebsiteProgrammer$1,760.00 4.1.5Checking Mobile CompatibilityWebsite Developer$800.00 4.1.6Completion of Website DevelopmentWebsite Developer$2,400.00 4.2.1Developing Application InterfaceApplication Developer$1,600.00 4.2.2Making Programs for Mobile ApplicationProgrammer$4,400.00 4.2.3Integrating Mobile ApplicationsEngineer$1,920.00 4.2.4Completion of Mobile Application DevelopmentApplication Developer$4,800.00 5.1Making Closure ReportsDocumenter, Documents[1]$1,030.00 5.2Making Evaluation ChecklistProject Manager$2,000.00 5.3Submitting Report DocumentsDocumenter$440.00 5.4Signing offProject Manager$1,000.00 5.5Closure$0.00 13|W a s i f N u m a n - 1 1 6 4 0 4 2 6
ITC505-Assignment 3 Project Budget Resource NameWorkStandard RateCost Analyst8 hrs$50.00/hr$400.00 Documenter64 hrs$55.00/hr$3,520.00 Planner48 hrs$60.00/hr$2,880.00 Project Manager32 hrs$125.00/hr$4,000.00 Website Designer48 hrs$90.00/hr$4,320.00 Application Designer48 hrs$90.00/hr$4,320.00 Engineer40 hrs$120.00/hr$4,800.00 Website Developer72 hrs$100.00/hr$7,200.00 Programmer56 hrs$110.00/hr$6,160.00 Application Developer64 hrs$100.00/hr$6,400.00 Documents3$150.00$450.00 Design Tools4$1,200.00$4,800.00 Domain Cost1$750.00$750.00 Total Budget$50,000.00 14|W a s i f N u m a n - 1 1 6 4 0 4 2 6
ITC505-Assignment 3 4. Part Four: Project Risk Analysis and Plan Assumptions:Thefollowingaretheassumptionsoftheprojectofwebsiteandmobile application development of I-Crop Project, a)Feasible Project Plan is made b)Simulation of the design provides positive outcomes c)Developed website and mobile application meets the requirement criteria d)Testing results are as per the expectation Risk Identification:The possible risk factors for the project of website and mobile application development of I-Crop Project are delay in completion, shortage of resources, design flaws, functional errors, and human mistakes. Risk Analysis: Risk FactorDescriptionMember Involved 15|W a s i f N u m a n - 1 1 6 4 0 4 2 6
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
ITC505-Assignment 3 Delayin completion The delay in completion of the project would result in forming major problems in execution of the operations. Project Manager Shortageof resources The shortage of resources is another major factor for reducing the pace of operations and hindering the completion of the project. HR Manager Design flawsThe flaws in design would result in harming the operations and delaying the completion of the project. Designer Functional errors The functional errors would tend to cause the major problems for defining the issues in completion of the project. Engineer Human mistakes The mistakes by the human in project operations would also form the delay in completion of the project. Team Members 5. Part Five: Quality Management Plan Quality Statement:The project of website and mobile application development of I-Crop Project would be executed for developing the innovative technology for mobile and website development in integrating the alignment of the innovative operation development. The analysis of the factors of development can be implied for easing the design and development of the website and mobile application. The integration management would be helpful for ensuring the completion of the project. A set of verification activities:The testing methods and inclusion of the simulation would be required for ensuring the completion of the project activities. A set of validation activities:The project plan validation would be developed using the project checklist and assumption criteria analysis. 16|W a s i f N u m a n - 1 1 6 4 0 4 2 6
ITC505-Assignment 3 6. Part Six: Closure and Evaluation Annotated Bibliography: FirstArticle:Exploringthevalueofprojectmanagement:linkingprojectmanagement performance and project success According to Mir and Pinnington (2014), the project management consideration would be implied for the easing the management of the successful project integration and development of refinedmanagementfordevelopingsuccessfulintegrationmanagement.Theutilization management would be effectively deployed for qualifying the involved management process. The integration of the successive management can be helpful for aligning the usefulness of the activities and implying the management process. The execution of the project activities would be effectively implied for easing the integration management. The analysis of the factors of development can be implied for easing the design and development of the website and mobile application. The integration management would be helpful for ensuring the completion of the project.Thecompletionoftheprojectmanagementinstallationwouldbeimpliedfor successfully management of the activities. The integration has been aligned for easing the management process. Second Article: Information technology project management According to Marchewka (2014), the information technology project management has been helpful for assigning the utilization management for developing the integration management for easing the successfully management of the proposition. The project management would be 17|W a s i f N u m a n - 1 1 6 4 0 4 2 6
ITC505-Assignment 3 effectively deployed for qualifying the involved management process. The project integration of the successive management can be helpful for aligning the usefulness of the activities and implying the management process. The execution of the project activities would be effectively impliedforeasingtheprojectintegrationmanagement.Theanalysisofthefactorsof development can be implied for easing the design and development of the website and mobile application. The project integration management would be helpful for ensuring the completion of the project. The completion of the project management installation would be implied for successfully management of the activities. The project integration has been aligned for easing the management process. Third Article: Project management: a systems approach to planning, scheduling, and controlling According to Kerzner and Kerzner (2017), the completion planning development would be effectively deployed for qualifying the involved planning development process. The integration of the successive planning development can be helpful for aligning the usefulness of the activities and implying the planning development process. The execution of the project activities would be effectively implied for easing the integration planning development. The analysis of the factors of development can be implied for easing the design and development of the website and mobile application. The integration planning development would be helpful for ensuring the completion of the project. The completion of the project planning development installation would be implied for successfully planning development of the activities. Checklist for the project 18|W a s i f N u m a n - 1 1 6 4 0 4 2 6
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
ITC505-Assignment 3 QuestionCheck Is required information for the project valid and trustable? Is the project plan sustainable for completion? Is design of website and mobile application feasible? Arethefunctionaloperationsofthewebsiteandmobileapplication appropriate? Evaluation Criteria Feasible Project Plan is made Simulation of the design provides positive outcomes Developed website and mobile application meets the requirement criteria Testing results are as per the expectation 19|W a s i f N u m a n - 1 1 6 4 0 4 2 6
ITC505-Assignment 3 MS PROJECT FILE Please click below to access the Microsoft project file, where the entire documentation has been made. 20|W a s i f N u m a n - 1 1 6 4 0 4 2 6
ITC505-Assignment 3 Bibliography Binder, J. (2016).Global project management: communication, collaboration and management across borders. Routledge. Eskerod, P., & Jepsen, A. L. (2016).Project stakeholder management. Routledge. Harris, E. (2017).Strategic project risk appraisal and management. Routledge. Heagney, J. (2016).Fundamentals of project management. Amacom. Heldman, K. (2018).PMP: project management professional exam study guide. John Wiley & Sons. Kerzner, H., & Kerzner, H. R. (2017).Project management: a systems approach to planning, scheduling, and controlling. John Wiley & Sons. Larson, E. W., Gray, C. F., Danlin, U., Honig, B., & Bacarini, D. (2014).Project management: The managerial process(Vol. 6). Grandview Heights, OH: McGraw-Hill Education. Leach, L. P. (2014).Critical chain project management. Artech House. Lock, D. (2017).The essentials of project management. Routledge. Marchewka, J. T. (2014).Information technology project management. John Wiley & Sons. Martens, M. L., & Carvalho, M. M. (2017). Key factors of sustainability in project management context: A survey exploring the project managers' perspective.International Journal of Project Management,35(6), 1084-1102. 21|W a s i f N u m a n - 1 1 6 4 0 4 2 6
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
ITC505-Assignment 3 Mir, F. A., & Pinnington, A. H. (2014). Exploring the value of project management: linking project management performance and project success.International journal of project management,32(2), 202-217. Schwalbe, K. (2015).Information technology project management. Cengage Learning. Verzuh, E. (2015).The fast forward MBA in project management. John Wiley & Sons. Walker, A. (2015).Project management in construction. John Wiley & Sons. 22|W a s i f N u m a n - 1 1 6 4 0 4 2 6