Project Final Report for Website and Application Development for I-Crop
VerifiedAdded on 2023/06/07
|15
|2690
|419
AI Summary
This report outlines the measurable organizational value, scope management plan, project schedule, budget, and risk analysis for the website and application development project for I-Crop.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.
Running head: PROJECT FINAL REPORT
Project Final Report
Website and Application Development for I-Crop
Name of the Student:
Student ID:
Name of the Students:
Author’s note:
Project Final Report
Website and Application Development for I-Crop
Name of the Student:
Student ID:
Name of the Students:
Author’s note:
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
1PROJECT FINAL REPORT
1. Part One: MOV - Measurable Organisational Value
Financial Area: Economically the project has to be feasible for the clients and it has the
highest priority in terms of important factors.
Customer Area: Customer Approval is another major factor for alignment of the project
activities and lower priority management.
Operational Area: The operations of the project can be efficiently implied for the
alignment of the successive management.
Strategy Area: The strategy area can be implied for the alignment of the successive
implication of the operations and it has a specific area of importance for the project.
Social Area: The social area is responsible for making sure that the activities can be
implied successfully for operating in the reasonable formation model.
Better- Improved customer experience with website (even accessible from mobile) and
mobile application
Faster- Increase the pace of operations for the formation of the efficient customer support
and formation
Cheaper- Cost and Expenses of the activities can be decreased and hence it would result
in more profit generation
Do more- Provide scope for the communication and implication of the activities
successfully
1. Part One: MOV - Measurable Organisational Value
Financial Area: Economically the project has to be feasible for the clients and it has the
highest priority in terms of important factors.
Customer Area: Customer Approval is another major factor for alignment of the project
activities and lower priority management.
Operational Area: The operations of the project can be efficiently implied for the
alignment of the successive management.
Strategy Area: The strategy area can be implied for the alignment of the successive
implication of the operations and it has a specific area of importance for the project.
Social Area: The social area is responsible for making sure that the activities can be
implied successfully for operating in the reasonable formation model.
Better- Improved customer experience with website (even accessible from mobile) and
mobile application
Faster- Increase the pace of operations for the formation of the efficient customer support
and formation
Cheaper- Cost and Expenses of the activities can be decreased and hence it would result
in more profit generation
Do more- Provide scope for the communication and implication of the activities
successfully
2PROJECT FINAL REPORT
Rank Impact Metrics Timeframe (in months)
1 Financial NPV and Profit Calculation 2
2 Customer Customer feedback and Suggestions 4
3 Operational Management Plan 5
4 Strategy Strategic Analysis Matrix 6
5 Social Social Sites Review 2
2. Part Two: Define Scope and produce a Scope Management Plan
Define the scope: Scope can be defined as the involved functions and deliverable for the project
of website and mobile application formation project of I-Crop.
Requirements: The inclusion of the principles of project management with the website and
mobile formation technology are the requirements of the project.
In scope-out scope items: The initiation documents, project plan, website and mobile
application design, website and mobile application, and final closure report are the in scope items
Rank Impact Metrics Timeframe (in months)
1 Financial NPV and Profit Calculation 2
2 Customer Customer feedback and Suggestions 4
3 Operational Management Plan 5
4 Strategy Strategic Analysis Matrix 6
5 Social Social Sites Review 2
2. Part Two: Define Scope and produce a Scope Management Plan
Define the scope: Scope can be defined as the involved functions and deliverable for the project
of website and mobile application formation project of I-Crop.
Requirements: The inclusion of the principles of project management with the website and
mobile formation technology are the requirements of the project.
In scope-out scope items: The initiation documents, project plan, website and mobile
application design, website and mobile application, and final closure report are the in scope items
3PROJECT FINAL REPORT
of the project of website and mobile application formation project of I-Crop. The transportation
requirements and the communication plan are the out of scope items of the project of website and
mobile application formation project of I-Crop.
Deliverables: Project initiation documents, project plan, website and mobile application design,
website and mobile application, and final closure report
Acceptance Criteria: The acceptance criteria for the project of website and mobile application
formation project of I-Crop is,
All documents are made properly
Design and Plan has been pre-approved
All testing results are positive and as expected
Feasible Cost Analysis has been executed
Provide a list of Resources:
People: Analyst, Documenter, Planner, Project Manager, Website Designer, Application
Designer, Engineer, Website Developer, Programmer, and Application Developer
Technology: Website Designing and Developing Tools, Mobile Application Designing and
Developing Tools
Facilities: Testing facilities and Project meeting rooms
3. Part Three: Project Schedule
Milestones
of the project of website and mobile application formation project of I-Crop. The transportation
requirements and the communication plan are the out of scope items of the project of website and
mobile application formation project of I-Crop.
Deliverables: Project initiation documents, project plan, website and mobile application design,
website and mobile application, and final closure report
Acceptance Criteria: The acceptance criteria for the project of website and mobile application
formation project of I-Crop is,
All documents are made properly
Design and Plan has been pre-approved
All testing results are positive and as expected
Feasible Cost Analysis has been executed
Provide a list of Resources:
People: Analyst, Documenter, Planner, Project Manager, Website Designer, Application
Designer, Engineer, Website Developer, Programmer, and Application Developer
Technology: Website Designing and Developing Tools, Mobile Application Designing and
Developing Tools
Facilities: Testing facilities and Project meeting rooms
3. Part Three: Project Schedule
Milestones
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
4PROJECT FINAL REPORT
WBS Milestone Name Duration Start Finish
1.5 Sign off 0 days Fri 10/12/18 Fri 10/12/18
2.5 Plan Approval 0 days Mon 10/29/18 Mon 10/29/18
3.1.5 Design Approval 0 days Tue 11/13/18 Tue 11/13/18
3.2.5 Design Approval 0 days Wed 11/28/18 Wed 11/28/18
5.5 Closed 0 days Fri 2/8/19 Fri 2/8/19
Activities / Tasks
WBS Task Name
1.1 Requirement Analysis
1.2 Charter Documentation
1.3 Initiation Document
1.4 Document Submission
2.1 Selection of Plan Methodology
2.2 Outline of plan
2.3 Plan Review
2.4 Complete Plan
3.1.1 Design Platform selection
3.1.2 Outline of Website
3.1.3 Review of Website
3.1.4 Complete Website Design
3.2.1 Design Platform selection
3.2.2 Outline of Application
3.2.3 Review of Application Design
WBS Milestone Name Duration Start Finish
1.5 Sign off 0 days Fri 10/12/18 Fri 10/12/18
2.5 Plan Approval 0 days Mon 10/29/18 Mon 10/29/18
3.1.5 Design Approval 0 days Tue 11/13/18 Tue 11/13/18
3.2.5 Design Approval 0 days Wed 11/28/18 Wed 11/28/18
5.5 Closed 0 days Fri 2/8/19 Fri 2/8/19
Activities / Tasks
WBS Task Name
1.1 Requirement Analysis
1.2 Charter Documentation
1.3 Initiation Document
1.4 Document Submission
2.1 Selection of Plan Methodology
2.2 Outline of plan
2.3 Plan Review
2.4 Complete Plan
3.1.1 Design Platform selection
3.1.2 Outline of Website
3.1.3 Review of Website
3.1.4 Complete Website Design
3.2.1 Design Platform selection
3.2.2 Outline of Application
3.2.3 Review of Application Design
5PROJECT FINAL REPORT
3.2.4 Complete Application Design
4.1.1 Buy Website Domain
4.1.2 Develop Website Interface
4.1.3 Functions are aligned
4.1.4 Programming the website functions
4.1.5 Checking Mobile Compatibility
4.1.6 Complete Website is developed
4.2.1 Application Interface is developed
4.2.2 Programming of the application functions
4.2.3 Application Integration
4.2.4 Complete Application Development
5.1 Developing Final Reports
5.2 Checklist Development
5.3 Submission of documents
5.4 Sign off
3.2.4 Complete Application Design
4.1.1 Buy Website Domain
4.1.2 Develop Website Interface
4.1.3 Functions are aligned
4.1.4 Programming the website functions
4.1.5 Checking Mobile Compatibility
4.1.6 Complete Website is developed
4.2.1 Application Interface is developed
4.2.2 Programming of the application functions
4.2.3 Application Integration
4.2.4 Complete Application Development
5.1 Developing Final Reports
5.2 Checklist Development
5.3 Submission of documents
5.4 Sign off
6PROJECT FINAL REPORT
Resource Assignments
ID Resource Name Work
1 Analyst 16 hrs
2 Documenter 96 hrs
3 Planner 72 hrs
4 Project Manager 40 hrs
5 Website Designer 72 hrs
6 Application Designer 72 hrs
7 Engineer 64 hrs
8 Website Developer 120 hrs
9 Programmer 96 hrs
10 Application Developer 112 hrs
11 Documents 3
12 Design Tools 4
13 Domain Cost 1
Details
Work
Work
Work
Work
Work
Work
Work
Work
Work
Work
Work
Work
Work
T W T M S S F T W T M S
Sep 23, '18 Oct 21, '18 Nov 18, '18 Dec 16, '18 Jan 13, '19 Feb 10, '19
16h
40h 24h 16h 16h
32h 40h
16h 24h
32h 40h
24h 48h
16h 24h 24h
8h 48h 64h
24h 8h 40h 24h
32h 24h 56h
1.67 0.33 0.67 0.33
1 2 1
1
Resource Assignments
ID Resource Name Work
1 Analyst 16 hrs
2 Documenter 96 hrs
3 Planner 72 hrs
4 Project Manager 40 hrs
5 Website Designer 72 hrs
6 Application Designer 72 hrs
7 Engineer 64 hrs
8 Website Developer 120 hrs
9 Programmer 96 hrs
10 Application Developer 112 hrs
11 Documents 3
12 Design Tools 4
13 Domain Cost 1
Details
Work
Work
Work
Work
Work
Work
Work
Work
Work
Work
Work
Work
Work
T W T M S S F T W T M S
Sep 23, '18 Oct 21, '18 Nov 18, '18 Dec 16, '18 Jan 13, '19 Feb 10, '19
16h
40h 24h 16h 16h
32h 40h
16h 24h
32h 40h
24h 48h
16h 24h 24h
8h 48h 64h
24h 8h 40h 24h
32h 24h 56h
1.67 0.33 0.67 0.33
1 2 1
1
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
7PROJECT FINAL REPORT
Estimates for Each Activity / Task
ID Task
Mode
WBS Task Name Duration Start Finish Predecessors
0 0 Website and Application
Development for I-Crop
95 days Mon 10/1/18 Fri 2/8/19
1 1 Initial Phase 10 days Mon 10/1/18 Fri 10/12/18
2 1.1 Requirement Analysis 2 days Mon 10/1/18 Tue 10/2/18
3 1.2 Charter Documentation 3 days Wed 10/3/18 Fri 10/5/18 2
4 1.3 Initiation Document 3 days Mon 10/8/18 Wed 10/10/18 3
5 1.4 Document Submission 2 days Thu 10/11/18 Fri 10/12/18 4
6 1.5 Sign off 0 days Fri 10/12/18 Fri 10/12/18 5
7 2 Planning Phase 11 days Mon 10/15/18 Mon 10/29/18
8 2.1 Selection of Plan Methodology 1 day Mon 10/15/18 Mon 10/15/18 6
9 2.2 Outline of plan 3 days Tue 10/16/18 Thu 10/18/18 8
10 2.3 Plan Review 2 days Fri 10/19/18 Mon 10/22/18 9
11 2.4 Complete Plan 5 days Tue 10/23/18 Mon 10/29/18 10
12 2.5 Plan Approval 0 days Mon 10/29/18 Mon 10/29/18 11
13 3 Design Phase 22 days Tue 10/30/18 Wed 11/28/18
14 3.1 Website Design 11 days Tue 10/30/18 Tue 11/13/18
15 3.1.1 Design Platform selection 1 day Tue 10/30/18 Tue 10/30/18 12
16 3.1.2 Outline of Website 3 days Wed 10/31/18 Fri 11/2/18 15
17 3.1.3 Review of Website 2 days Mon 11/5/18 Tue 11/6/18 16
18 3.1.4 Complete Website Design 5 days Wed 11/7/18 Tue 11/13/18 17
19 3.1.5 Design Approval 0 days Tue 11/13/18 Tue 11/13/18 18
20 3.2 Application Design 11 days Wed 11/14/18 Wed 11/28/18
21 3.2.1 Design Platform selection 1 day Wed 11/14/18 Wed 11/14/18 19
22 3.2.2 Outline of Application 3 days Thu 11/15/18 Mon 11/19/18 21
23 3.2.3 Review of Application Design2 days Tue 11/20/18 Wed 11/21/18 22
24 3.2.4 Complete Application Design 5 days Thu 11/22/18 Wed 11/28/18 23
25 3.2.5 Design Approval 0 days Wed 11/28/18 Wed 11/28/18 24
26 4 Development Phase 45 days Thu 11/29/18 Wed 1/30/19
27 4.1 Website Development 20 days Thu 11/29/18 Wed 12/26/18
28 4.1.1 Buy Website Domain 1 day Thu 11/29/18 Thu 11/29/18 25
29 4.1.2 Develop Website Interface 5 days Fri 11/30/18 Thu 12/6/18 28
30 4.1.3 Functions are aligned 2 days Fri 12/7/18 Mon 12/10/18 29
31 4.1.4 Programming the website functions4 days Tue 12/11/18 Fri 12/14/18 30
32 4.1.5 Checking Mobile Compatibility3 days Mon 12/17/18 Wed 12/19/18 31
33 4.1.6 Complete Website is developed5 days Thu 12/20/18 Wed 12/26/18 32
34 4.2 Mobile Application Development25 days Thu 12/27/18 Wed 1/30/19
35 4.2.1 Application Interface is developed4 days Thu 12/27/18 Tue 1/1/19 33
36 4.2.2 Programming of the
application functions
8 days Wed 1/2/19 Fri 1/11/19 35
37 4.2.3 Application Integration 3 days Mon 1/14/19 Wed 1/16/19 36
38 4.2.4 Complete Application Development10 days Thu 1/17/19 Wed 1/30/19 37
39 5 Closure 7 days Thu 1/31/19 Fri 2/8/19
40 5.1 Developing Final Reports 3 days Thu 1/31/19 Mon 2/4/19 38
41 5.2 Checklist Development 2 days Tue 2/5/19 Wed 2/6/19 40
42 5.3 Submission of documents 1 day Thu 2/7/19 Thu 2/7/19 41
43 5.4 Sign off 1 day Fri 2/8/19 Fri 2/8/19 42
44 5.5 Closed 0 days Fri 2/8/19 Fri 2/8/19 43
F
Aug 12, '18
Estimates for Each Activity / Task
ID Task
Mode
WBS Task Name Duration Start Finish Predecessors
0 0 Website and Application
Development for I-Crop
95 days Mon 10/1/18 Fri 2/8/19
1 1 Initial Phase 10 days Mon 10/1/18 Fri 10/12/18
2 1.1 Requirement Analysis 2 days Mon 10/1/18 Tue 10/2/18
3 1.2 Charter Documentation 3 days Wed 10/3/18 Fri 10/5/18 2
4 1.3 Initiation Document 3 days Mon 10/8/18 Wed 10/10/18 3
5 1.4 Document Submission 2 days Thu 10/11/18 Fri 10/12/18 4
6 1.5 Sign off 0 days Fri 10/12/18 Fri 10/12/18 5
7 2 Planning Phase 11 days Mon 10/15/18 Mon 10/29/18
8 2.1 Selection of Plan Methodology 1 day Mon 10/15/18 Mon 10/15/18 6
9 2.2 Outline of plan 3 days Tue 10/16/18 Thu 10/18/18 8
10 2.3 Plan Review 2 days Fri 10/19/18 Mon 10/22/18 9
11 2.4 Complete Plan 5 days Tue 10/23/18 Mon 10/29/18 10
12 2.5 Plan Approval 0 days Mon 10/29/18 Mon 10/29/18 11
13 3 Design Phase 22 days Tue 10/30/18 Wed 11/28/18
14 3.1 Website Design 11 days Tue 10/30/18 Tue 11/13/18
15 3.1.1 Design Platform selection 1 day Tue 10/30/18 Tue 10/30/18 12
16 3.1.2 Outline of Website 3 days Wed 10/31/18 Fri 11/2/18 15
17 3.1.3 Review of Website 2 days Mon 11/5/18 Tue 11/6/18 16
18 3.1.4 Complete Website Design 5 days Wed 11/7/18 Tue 11/13/18 17
19 3.1.5 Design Approval 0 days Tue 11/13/18 Tue 11/13/18 18
20 3.2 Application Design 11 days Wed 11/14/18 Wed 11/28/18
21 3.2.1 Design Platform selection 1 day Wed 11/14/18 Wed 11/14/18 19
22 3.2.2 Outline of Application 3 days Thu 11/15/18 Mon 11/19/18 21
23 3.2.3 Review of Application Design2 days Tue 11/20/18 Wed 11/21/18 22
24 3.2.4 Complete Application Design 5 days Thu 11/22/18 Wed 11/28/18 23
25 3.2.5 Design Approval 0 days Wed 11/28/18 Wed 11/28/18 24
26 4 Development Phase 45 days Thu 11/29/18 Wed 1/30/19
27 4.1 Website Development 20 days Thu 11/29/18 Wed 12/26/18
28 4.1.1 Buy Website Domain 1 day Thu 11/29/18 Thu 11/29/18 25
29 4.1.2 Develop Website Interface 5 days Fri 11/30/18 Thu 12/6/18 28
30 4.1.3 Functions are aligned 2 days Fri 12/7/18 Mon 12/10/18 29
31 4.1.4 Programming the website functions4 days Tue 12/11/18 Fri 12/14/18 30
32 4.1.5 Checking Mobile Compatibility3 days Mon 12/17/18 Wed 12/19/18 31
33 4.1.6 Complete Website is developed5 days Thu 12/20/18 Wed 12/26/18 32
34 4.2 Mobile Application Development25 days Thu 12/27/18 Wed 1/30/19
35 4.2.1 Application Interface is developed4 days Thu 12/27/18 Tue 1/1/19 33
36 4.2.2 Programming of the
application functions
8 days Wed 1/2/19 Fri 1/11/19 35
37 4.2.3 Application Integration 3 days Mon 1/14/19 Wed 1/16/19 36
38 4.2.4 Complete Application Development10 days Thu 1/17/19 Wed 1/30/19 37
39 5 Closure 7 days Thu 1/31/19 Fri 2/8/19
40 5.1 Developing Final Reports 3 days Thu 1/31/19 Mon 2/4/19 38
41 5.2 Checklist Development 2 days Tue 2/5/19 Wed 2/6/19 40
42 5.3 Submission of documents 1 day Thu 2/7/19 Thu 2/7/19 41
43 5.4 Sign off 1 day Fri 2/8/19 Fri 2/8/19 42
44 5.5 Closed 0 days Fri 2/8/19 Fri 2/8/19 43
F
Aug 12, '18
8PROJECT FINAL REPORT
Project Budget
The time phased budget showing the complete budget of the project is shown below,
4. Part Four: Project Risk Analysis and Plan
Ref no RF000901 RF000902 RF000903 RF000904 RF000905
Risk Name Website and
Application
Development
Issues
Design Flaws Over budget Human
Errors
Delay in
Completion
Description Functions of
the website and
application
might not work
properly
Design made
for website
and mobile
application
would not be
feasible
The project
can go over
budget by
exhausting
more
resources than
planned
Human
mistakes in
executing the
activities of
project is
another
major risk
Overall delay
in completion
of the project
Category Technical Technical Financial Human Operational
Triggers Equipment or
device failures
Lack of
Design
Principles
Shortage of
Resources
General
Mistakes by
human
Minute issues
in the project
Potential
Response
Prior Testing
methods
SDLC
approach
should be
used
Provisional
budget should
be developed
Training of
the members
Contingency
Planning
should be
done
Project Budget
The time phased budget showing the complete budget of the project is shown below,
4. Part Four: Project Risk Analysis and Plan
Ref no RF000901 RF000902 RF000903 RF000904 RF000905
Risk Name Website and
Application
Development
Issues
Design Flaws Over budget Human
Errors
Delay in
Completion
Description Functions of
the website and
application
might not work
properly
Design made
for website
and mobile
application
would not be
feasible
The project
can go over
budget by
exhausting
more
resources than
planned
Human
mistakes in
executing the
activities of
project is
another
major risk
Overall delay
in completion
of the project
Category Technical Technical Financial Human Operational
Triggers Equipment or
device failures
Lack of
Design
Principles
Shortage of
Resources
General
Mistakes by
human
Minute issues
in the project
Potential
Response
Prior Testing
methods
SDLC
approach
should be
used
Provisional
budget should
be developed
Training of
the members
Contingency
Planning
should be
done
9PROJECT FINAL REPORT
Risk
Owner
Developer Designer Budgeter Project
Manager
Planner
Probability Likely Possible Possible Unlikely Likely
Impact Very High High Medium High Low
Ranking 1 2 3 4 5
5. Part Five: Quality Management Plan
Quality management plan deals with the analysis of the factors of quality involved for the project
and develop some methods of dealing with the execution of the project. The quality management
activities ensure that the outputs of the project are of standard quality and acceptable by the
client. For this project, the testing of the go live function can be done for ensuring the completion
of the project
A set of verification activities: Various testing methods like alpha testing, simulation, mobile
platform acceptability, UI testing, and performance testing
A set of validation activities: Quality analysis and control using 7QC, checklist verification,
and proper documentation
Risk
Owner
Developer Designer Budgeter Project
Manager
Planner
Probability Likely Possible Possible Unlikely Likely
Impact Very High High Medium High Low
Ranking 1 2 3 4 5
5. Part Five: Quality Management Plan
Quality management plan deals with the analysis of the factors of quality involved for the project
and develop some methods of dealing with the execution of the project. The quality management
activities ensure that the outputs of the project are of standard quality and acceptable by the
client. For this project, the testing of the go live function can be done for ensuring the completion
of the project
A set of verification activities: Various testing methods like alpha testing, simulation, mobile
platform acceptability, UI testing, and performance testing
A set of validation activities: Quality analysis and control using 7QC, checklist verification,
and proper documentation
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
10PROJECT FINAL REPORT
Bibliography
Braglia, M., &Frosolini, M. (2014).An integrated approach to implement project management
information systems within the extended enterprise.International Journal of Project
Management, 32(1), 18-29.
Coronel, C., & Morris, S. (2016). Database systems: design, implementation, & management.
Cengage Learning.
Galliers, R. D., &Leidner, D. E. (2014). Strategic information management: challenges and
strategies in managing information systems. Routledge.
Garton, C., & McCulloch, E. (2012). Fundamentals of Technology Project Management. MC
Press, LLC.
Goetsch, D. L., & Davis, S. B. (2014). Quality management for organizational
excellence.pearson.
Kendrick, T. (2015). Identifying and managing project risk: essential tools for failure-proofing
your project. AMACOM Div American Mgmt Assn.
Nanda, V. (2016). Quality management system handbook for product development
companies.CRC Press.
Pritchard, C. L., & PMP, P. R. (2014). Risk management: concepts and guidance. CRC Press.
Schwalbe, K. (2015). Information technology project management.Cengage Learning.
Stark, J. (2015). Product lifecycle management.In Product Lifecycle Management (pp. 1-
29).Springer International Publishing.
Bibliography
Braglia, M., &Frosolini, M. (2014).An integrated approach to implement project management
information systems within the extended enterprise.International Journal of Project
Management, 32(1), 18-29.
Coronel, C., & Morris, S. (2016). Database systems: design, implementation, & management.
Cengage Learning.
Galliers, R. D., &Leidner, D. E. (2014). Strategic information management: challenges and
strategies in managing information systems. Routledge.
Garton, C., & McCulloch, E. (2012). Fundamentals of Technology Project Management. MC
Press, LLC.
Goetsch, D. L., & Davis, S. B. (2014). Quality management for organizational
excellence.pearson.
Kendrick, T. (2015). Identifying and managing project risk: essential tools for failure-proofing
your project. AMACOM Div American Mgmt Assn.
Nanda, V. (2016). Quality management system handbook for product development
companies.CRC Press.
Pritchard, C. L., & PMP, P. R. (2014). Risk management: concepts and guidance. CRC Press.
Schwalbe, K. (2015). Information technology project management.Cengage Learning.
Stark, J. (2015). Product lifecycle management.In Product Lifecycle Management (pp. 1-
29).Springer International Publishing.
11PROJECT FINAL REPORT
Verburg, R. M., Bosch-Sijtsema, P., &Vartiainen, M. (2013).Getting it done: Critical success
factors for project managers in virtual work settings.International Journal of Project
Management, 31(1), 68-79.
Verzuh, E. (2015). The fast forward MBA in project management.John Wiley & Sons.
Verburg, R. M., Bosch-Sijtsema, P., &Vartiainen, M. (2013).Getting it done: Critical success
factors for project managers in virtual work settings.International Journal of Project
Management, 31(1), 68-79.
Verzuh, E. (2015). The fast forward MBA in project management.John Wiley & Sons.
12PROJECT FINAL REPORT
Appendix: 6. Part Six: Closure and Evaluation
Annotated Bibliography:
First Artcile: Quality management system handbook for product formation companies
According to Nanda (2016), the project management concept deals with the implication of the
efficient methodology for analysing the efficient innovation and operations for listing the
modification of the activities and aligning the formation of successive management process. The
project management methodology can be helpful for easing the involvement of the efficient
formation and improvements. The management of the project activities can be implied for
aligning the formation of the successful implication of activities. The using of the proper project
management methodologies can be helpful in easing the process of utilizing the smart formation
model. The alignment can be formed for easing the simplification of the successful execution
and using. The alignment would also be helpful for listing the execution activities of the project
successfully. The management of the project activities would support the implication of the
methodology for implying the successful execution of the project activities. The implying of
project management factors would align with the accessibility of the improved project operations
and formation. The using of the efficient management can be helpful for executing the formation
of the activities and developing project schedule.
Second Article: The fast forward MBA in project management
On the other hand Verzuh (2015), have provided the in depth review of the project operations
and it criticizes the implication of the successful management. The project management
principles can be implied for aligning the operational formation and using appropriate
Appendix: 6. Part Six: Closure and Evaluation
Annotated Bibliography:
First Artcile: Quality management system handbook for product formation companies
According to Nanda (2016), the project management concept deals with the implication of the
efficient methodology for analysing the efficient innovation and operations for listing the
modification of the activities and aligning the formation of successive management process. The
project management methodology can be helpful for easing the involvement of the efficient
formation and improvements. The management of the project activities can be implied for
aligning the formation of the successful implication of activities. The using of the proper project
management methodologies can be helpful in easing the process of utilizing the smart formation
model. The alignment can be formed for easing the simplification of the successful execution
and using. The alignment would also be helpful for listing the execution activities of the project
successfully. The management of the project activities would support the implication of the
methodology for implying the successful execution of the project activities. The implying of
project management factors would align with the accessibility of the improved project operations
and formation. The using of the efficient management can be helpful for executing the formation
of the activities and developing project schedule.
Second Article: The fast forward MBA in project management
On the other hand Verzuh (2015), have provided the in depth review of the project operations
and it criticizes the implication of the successful management. The project management
principles can be implied for aligning the operational formation and using appropriate
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.
13PROJECT FINAL REPORT
configuration. The usefulness of the probable project management principles can be implied for
easing the formation of the improved functional management. The implication of the operations
can be implied for listing the evaluation of the successive management operations. The various
principles of project management had been successful for implying the formation of the
successive information management and execution. The implication of successive principle
management can be attained for using the formation of the activities and aligning the implication
of the operations and easing the formation formation. The alignment of the project activities can
be developed for easing the using of the improved project management operations.
Third Article: Identifying and managing project risk: essential tools for failure-proofing your
project
On the contrary Kendrick (2015), have focused on the execution of the project activities by
implying risk management strategies. The risk management strategies are helpful for evaluating
the prospects of project execution and alignment of the improved operation formation. The
project operation alignment can be successful for easing the implication and management of the
activities for easing the using of the proper project formation. The risk management can be
employed for analysing the situations and identifying the possible risk factors for execution of
the project. The analysis would also be helpful for executing the project budget formation. The
impact of risk factors on cost can be evaluated and some contingency planning can be developed.
The time, budget, and quality contingency can be developed for forming the execution of the
cohesive project plan execution. Risk identification, prioritisation, evaluation, mitigation, and
documentation are the activities of the project risk management plan.
Checklist for the project
configuration. The usefulness of the probable project management principles can be implied for
easing the formation of the improved functional management. The implication of the operations
can be implied for listing the evaluation of the successive management operations. The various
principles of project management had been successful for implying the formation of the
successive information management and execution. The implication of successive principle
management can be attained for using the formation of the activities and aligning the implication
of the operations and easing the formation formation. The alignment of the project activities can
be developed for easing the using of the improved project management operations.
Third Article: Identifying and managing project risk: essential tools for failure-proofing your
project
On the contrary Kendrick (2015), have focused on the execution of the project activities by
implying risk management strategies. The risk management strategies are helpful for evaluating
the prospects of project execution and alignment of the improved operation formation. The
project operation alignment can be successful for easing the implication and management of the
activities for easing the using of the proper project formation. The risk management can be
employed for analysing the situations and identifying the possible risk factors for execution of
the project. The analysis would also be helpful for executing the project budget formation. The
impact of risk factors on cost can be evaluated and some contingency planning can be developed.
The time, budget, and quality contingency can be developed for forming the execution of the
cohesive project plan execution. Risk identification, prioritisation, evaluation, mitigation, and
documentation are the activities of the project risk management plan.
Checklist for the project
14PROJECT FINAL REPORT
Evaluation Criteria
The evaluation criteria for checking whether the successful execution of the activities of the
project are achieved is given below,
All documents are made properly
Design and Plan has been pre-approved
All testing results are positive and as expected
Feasible Cost Analysis has been executed
Evaluation Criteria
The evaluation criteria for checking whether the successful execution of the activities of the
project are achieved is given below,
All documents are made properly
Design and Plan has been pre-approved
All testing results are positive and as expected
Feasible Cost Analysis has been executed
1 out of 15
Related Documents
Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
© 2024 | Zucol Services PVT LTD | All rights reserved.