Resource Allocation Problem in Workhouse Australia Case Study
Added on 2023-06-04
9 Pages1179 Words130 Views
Workhouse Australia Case Description
Name of the Student
Name of the University
Author’s Note
Name of the Student
Name of the University
Author’s Note
Table of Contents
Part A question 2.........................................................................................................................3
a) Explanation of the steps that are required for resolving resource allocation problem........3
b) Comparison between mpp files...........................................................................................3
c) Difference between the mpp files........................................................................................3
d) Problems associated with Ms project after the process of resource levelling.....................3
Part A question 3.........................................................................................................................3
Part A question 4.........................................................................................................................5
a) Explanation for the selection of resource............................................................................5
b) Comparison between mpp files...........................................................................................5
c) Explanation..........................................................................................................................5
Part A question 5.........................................................................................................................5
a) Project risks..........................................................................................................................5
b) Incorporating activities in WBS..........................................................................................6
Part A question 6.........................................................................................................................6
Part B: Revising the plan.................................................................................................................6
Part B question 1..........................................................................................................................6
Part B question 2..........................................................................................................................7
Part A question 2.........................................................................................................................3
a) Explanation of the steps that are required for resolving resource allocation problem........3
b) Comparison between mpp files...........................................................................................3
c) Difference between the mpp files........................................................................................3
d) Problems associated with Ms project after the process of resource levelling.....................3
Part A question 3.........................................................................................................................3
Part A question 4.........................................................................................................................5
a) Explanation for the selection of resource............................................................................5
b) Comparison between mpp files...........................................................................................5
c) Explanation..........................................................................................................................5
Part A question 5.........................................................................................................................5
a) Project risks..........................................................................................................................5
b) Incorporating activities in WBS..........................................................................................6
Part A question 6.........................................................................................................................6
Part B: Revising the plan.................................................................................................................6
Part B question 1..........................................................................................................................6
Part B question 2..........................................................................................................................7
Part A: Development of project schedule
Part A question 1
Part A question 2
a) Explanation of the steps that are required for resolving resource allocation problem
The issue in the resource allocation has been currently available in the schedule which is
to be developed in the warehouse construction project. It has been found that the use of resource
have been maintained for over location with the help of resource levelling. The resource
levelling process is undertaken in the tasks for project initiatives have not been adjusted and nit
reflected in the separate assignments. Proper analysis of the resource levelling f the project help
in reflecting the project duration for increasing the cost with different activities to be formed in
the project.
b) Comparison between mpp files
WHA_PartAQ1.mpp WHA_PartAQ2.mpp
Total duration Total cost Total duration Total cost
177 days $657,120.00 301days $657,120.00
c) Difference between the mpp files
The table shows that the total time taken for the project in PartAQ1.mpp is 177 days
whereas the total time that is needed as per the WHA_PartAQ2.mpp is around 301 days. There
has been variation in the project duration and levelling of resources has been over allocated.
Part A question 1
Part A question 2
a) Explanation of the steps that are required for resolving resource allocation problem
The issue in the resource allocation has been currently available in the schedule which is
to be developed in the warehouse construction project. It has been found that the use of resource
have been maintained for over location with the help of resource levelling. The resource
levelling process is undertaken in the tasks for project initiatives have not been adjusted and nit
reflected in the separate assignments. Proper analysis of the resource levelling f the project help
in reflecting the project duration for increasing the cost with different activities to be formed in
the project.
b) Comparison between mpp files
WHA_PartAQ1.mpp WHA_PartAQ2.mpp
Total duration Total cost Total duration Total cost
177 days $657,120.00 301days $657,120.00
c) Difference between the mpp files
The table shows that the total time taken for the project in PartAQ1.mpp is 177 days
whereas the total time that is needed as per the WHA_PartAQ2.mpp is around 301 days. There
has been variation in the project duration and levelling of resources has been over allocated.
End of preview
Want to access all the pages? Upload your documents or become a member.
Related Documents
Project Management: Workhouse Australia Case Descriptionlg...
|9
|1245
|466
Project Management: Workhouse Australia Case Descriptionlg...
|9
|1261
|390
WorkHouse Australia Project Planning and Managementlg...
|7
|1774
|399
Project Management: Bike Share Australialg...
|8
|1207
|59
Project Management for Bike Share Australialg...
|9
|1360
|110
Bike Sharing in Australia Assignment PDFlg...
|6
|719
|185