This project draft report details the initial schedule for the Apex Area Medical Centre (AAMC) project. It includes a network diagram, a schedule based on time relationships, resource loading, and cash flow analysis. The report refines the Work Breakdown Structure (WBS) and elemental estimates, incorporating phases such as planning, design, basement and floor works, concrete works, and electrical works. Key activities and their durations are outlined in a precedence table, which informs the project's critical path and Gantt chart. The report also addresses resource allocation and provides cash flow projections for the project's initial and final stages. The project leverages construction project management principles for effective management and integration of activities, with a focus on quality assessment and inspections throughout the construction process. Desklib provides access to similar solved assignments and project resources for students.

Running head: PROJECT DRAFT REPORT
Project Draft Report
Apex Area Medical Centre Project (AAMC)
Name of the Student:
Student ID:
Name of the University:
Author’s note:
Project Draft Report
Apex Area Medical Centre Project (AAMC)
Name of the Student:
Student ID:
Name of the University:
Author’s note:
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

1PROJECT DRAFT REPORT
Table of Contents
Introduction......................................................................................................................................2
1. Unconstrained Schedule..............................................................................................................2
1.1 Precedence Table...................................................................................................................2
1.2 Project Schedule Description.................................................................................................7
1.3 Network Diagram..................................................................................................................9
1.4 Project Critical Path Diagram..............................................................................................10
1.5 Project Gantt Chart..............................................................................................................11
1.6 Earned value analysis..........................................................................................................12
1.8 Cash Flow in terms of resources..........................................................................................13
1.9 Cash Flow for First 25%......................................................................................................15
1.10 Cash flow for Last 25%.....................................................................................................16
Conclusion.....................................................................................................................................21
Bibliography..................................................................................................................................22
Table of Contents
Introduction......................................................................................................................................2
1. Unconstrained Schedule..............................................................................................................2
1.1 Precedence Table...................................................................................................................2
1.2 Project Schedule Description.................................................................................................7
1.3 Network Diagram..................................................................................................................9
1.4 Project Critical Path Diagram..............................................................................................10
1.5 Project Gantt Chart..............................................................................................................11
1.6 Earned value analysis..........................................................................................................12
1.8 Cash Flow in terms of resources..........................................................................................13
1.9 Cash Flow for First 25%......................................................................................................15
1.10 Cash flow for Last 25%.....................................................................................................16
Conclusion.....................................................................................................................................21
Bibliography..................................................................................................................................22

2PROJECT DRAFT REPORT
Introduction
The following assignment has been made for the development of the improved analysis
and project management for the utilization of the effective management of the work and aligning
the functional management of activities. The following report would involve the completeness of
the work and cohesive management of activities.
1. Unconstrained Schedule
1.1 Precedence Table
Task Name Predecessors Duratio
n Start Successors Finish
Identify mission and
Objectives, Create Project
Charter
7 days Mon
10/8/18 4, 5 Tue
10/16/18
Create Business Plan and
Issue 3 5 days Wed
10/17/18 7 Tue
10/23/18
Create Project Initiation
Document and Issue 3 12 days Wed
10/24/18
Fri
11/9/18
Soil Investigation 4 3 days Wed
10/24/18 8, 9 Fri
10/26/18
Architectural 7 60 days Mon
10/29/18 Fri 2/1/19
Structural 7 15 days Mon
10/29/18 10 Fri
11/16/18
Mechanical 9 10 days Mon
11/19/18 11 Fri
11/30/18
Electrical 10 15 days Mon
12/3/18 14, 17 Fri
12/21/18
Survey 11 5 days Mon
12/24/18 15 Fri
12/28/18
Excavation 14 10 days Mon Fri
Introduction
The following assignment has been made for the development of the improved analysis
and project management for the utilization of the effective management of the work and aligning
the functional management of activities. The following report would involve the completeness of
the work and cohesive management of activities.
1. Unconstrained Schedule
1.1 Precedence Table
Task Name Predecessors Duratio
n Start Successors Finish
Identify mission and
Objectives, Create Project
Charter
7 days Mon
10/8/18 4, 5 Tue
10/16/18
Create Business Plan and
Issue 3 5 days Wed
10/17/18 7 Tue
10/23/18
Create Project Initiation
Document and Issue 3 12 days Wed
10/24/18
Fri
11/9/18
Soil Investigation 4 3 days Wed
10/24/18 8, 9 Fri
10/26/18
Architectural 7 60 days Mon
10/29/18 Fri 2/1/19
Structural 7 15 days Mon
10/29/18 10 Fri
11/16/18
Mechanical 9 10 days Mon
11/19/18 11 Fri
11/30/18
Electrical 10 15 days Mon
12/3/18 14, 17 Fri
12/21/18
Survey 11 5 days Mon
12/24/18 15 Fri
12/28/18
Excavation 14 10 days Mon Fri
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

3PROJECT DRAFT REPORT
12/31/18 1/11/19
Grading 11 5 days Mon
12/24/18 18, 19 Fri
12/28/18
Water Control 17 29 days Mon
12/31/18 20 Thu
2/7/19
Erosion control 17 29 days Mon
12/31/18 20 Thu
2/7/19
Underground utilities 18, 19 10 days Fri 2/8/19 23 Thu
2/21/19
Piles (Precast) 20 14 days Fri
2/22/19 25, 26, 49 Wed
3/13/19
Columns (Basement -
Floor 2) 23 28 days Thu
3/14/19 32 Tue
4/30/19
Columns (Floor 3 - 4) 23 10 days Thu
3/14/19 28 Wed
3/27/19
Columns (Floor 5 - 6) 28 20 days Thu
4/11/19 30 Tue
5/14/19
Columns (Floor 7 - 9) 26 10 days Thu
3/28/19 27 Wed
4/10/19
Slab -Beams
(Basement - Floor 2) 27 12 days Wed
5/15/19 31 Thu
5/30/19
Slab-Beams (Floor 3-
4) 30 8 days Fri
5/31/19 32 Tue
6/11/19
Slab-Beams (Floor 5 -
6) 25, 31 8 days Wed
6/12/19 33 Fri
6/21/19
Slab-Beams (Floor 7 -
9) 32 8 days Mon
6/24/19 35 Wed
7/3/19
Roofing Trusses 33 5 days Thu
7/4/19 36 Wed
7/10/19
Roofing Cover 35 3 days Wed
8/28/19 72, 73, 74 Fri
8/30/19
Columns (Basement -
Floor 2) 21 5 days Mon
9/2/19 40 Fri 9/6/19
Columns Floor( 3 - 4) 39 5 days Mon 41, 44, 45 Fri
12/31/18 1/11/19
Grading 11 5 days Mon
12/24/18 18, 19 Fri
12/28/18
Water Control 17 29 days Mon
12/31/18 20 Thu
2/7/19
Erosion control 17 29 days Mon
12/31/18 20 Thu
2/7/19
Underground utilities 18, 19 10 days Fri 2/8/19 23 Thu
2/21/19
Piles (Precast) 20 14 days Fri
2/22/19 25, 26, 49 Wed
3/13/19
Columns (Basement -
Floor 2) 23 28 days Thu
3/14/19 32 Tue
4/30/19
Columns (Floor 3 - 4) 23 10 days Thu
3/14/19 28 Wed
3/27/19
Columns (Floor 5 - 6) 28 20 days Thu
4/11/19 30 Tue
5/14/19
Columns (Floor 7 - 9) 26 10 days Thu
3/28/19 27 Wed
4/10/19
Slab -Beams
(Basement - Floor 2) 27 12 days Wed
5/15/19 31 Thu
5/30/19
Slab-Beams (Floor 3-
4) 30 8 days Fri
5/31/19 32 Tue
6/11/19
Slab-Beams (Floor 5 -
6) 25, 31 8 days Wed
6/12/19 33 Fri
6/21/19
Slab-Beams (Floor 7 -
9) 32 8 days Mon
6/24/19 35 Wed
7/3/19
Roofing Trusses 33 5 days Thu
7/4/19 36 Wed
7/10/19
Roofing Cover 35 3 days Wed
8/28/19 72, 73, 74 Fri
8/30/19
Columns (Basement -
Floor 2) 21 5 days Mon
9/2/19 40 Fri 9/6/19
Columns Floor( 3 - 4) 39 5 days Mon 41, 44, 45 Fri
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

4PROJECT DRAFT REPORT
9/9/19 9/13/19
Columns Floor( 5 - 6) 40 5 days Mon
9/16/19 42 Fri
9/20/19
Columns Floor( 7 - 9) 41 5 days Mon
9/23/19 46 Fri
9/27/19
Slab-Beams (Basement -
Floor 2) 40 4 days Mon
9/16/19
Thu
9/19/19
Slab-Beams Floor( 3 - 4) 40 4 days Mon
9/16/19
Thu
9/19/19
Slab-Beams Floor( 5 - 6) 42 4 days Mon
9/30/19 47 Thu
10/3/19
Slab-Beams Floor( 7 - 8) 46 4 days Fri
10/4/19
Wed
10/9/19
Stairway (Basement -
Floor 2) 23 2 days Thu
3/14/19 50, 52, 56 Fri
3/15/19
Stairway Floor(3 - 4) 49 2 days Mon
3/18/19 51 Tue
3/19/19
Stairway Floor( 5 -6) 50 4 days Wed
3/20/19
Mon
3/25/19
Stairway Floor( 7 - 8) 49 4 days Mon
3/18/19 53 Thu
3/21/19
Patios 52 1 day Fri
3/22/19
Fri
3/22/19
Internal wall 49 30 days Mon
3/18/19 57, 58 Fri
4/26/19
External wall 56 45 days Mon
4/29/19 69 Fri
6/28/19
Screeding 56 90 days Mon
4/29/19 60 Fri
8/30/19
Partitions 57 55 days Mon
7/1/19 60 Fri
9/13/19
Dry wall 58, 69 45 days Mon
9/16/19 62, 63, 65, 66 Fri
11/15/19
Interior doors 60 20 days Mon 64 Fri
9/9/19 9/13/19
Columns Floor( 5 - 6) 40 5 days Mon
9/16/19 42 Fri
9/20/19
Columns Floor( 7 - 9) 41 5 days Mon
9/23/19 46 Fri
9/27/19
Slab-Beams (Basement -
Floor 2) 40 4 days Mon
9/16/19
Thu
9/19/19
Slab-Beams Floor( 3 - 4) 40 4 days Mon
9/16/19
Thu
9/19/19
Slab-Beams Floor( 5 - 6) 42 4 days Mon
9/30/19 47 Thu
10/3/19
Slab-Beams Floor( 7 - 8) 46 4 days Fri
10/4/19
Wed
10/9/19
Stairway (Basement -
Floor 2) 23 2 days Thu
3/14/19 50, 52, 56 Fri
3/15/19
Stairway Floor(3 - 4) 49 2 days Mon
3/18/19 51 Tue
3/19/19
Stairway Floor( 5 -6) 50 4 days Wed
3/20/19
Mon
3/25/19
Stairway Floor( 7 - 8) 49 4 days Mon
3/18/19 53 Thu
3/21/19
Patios 52 1 day Fri
3/22/19
Fri
3/22/19
Internal wall 49 30 days Mon
3/18/19 57, 58 Fri
4/26/19
External wall 56 45 days Mon
4/29/19 69 Fri
6/28/19
Screeding 56 90 days Mon
4/29/19 60 Fri
8/30/19
Partitions 57 55 days Mon
7/1/19 60 Fri
9/13/19
Dry wall 58, 69 45 days Mon
9/16/19 62, 63, 65, 66 Fri
11/15/19
Interior doors 60 20 days Mon 64 Fri

5PROJECT DRAFT REPORT
11/18/19 12/13/19
Windows 60 30 days Mon
11/18/19
Fri
12/27/19
Security doors 62 20 days Mon
12/16/19 67 Fri
1/10/20
Tiles 60 90 days Mon
11/18/19 84 Fri
3/20/20
Glazing works 60 40 days Mon
11/18/19 67 Fri
1/10/20
Decoration 66, 64 30 days Mon
1/13/20 68 Fri
2/21/20
Carpeting 67 50 days Mon
2/24/20 85 Fri 5/1/20
Plumbing systems (Main
Line) 36 15 days Mon
9/2/19 75 Fri
9/20/19
Plumbing systems
(Floor. 1-2) 36 10 days Mon
10/21/19 74 Fri
11/1/19
Plumbing systems
(Floor. 3-4) 36, 73 10 days Mon
11/4/19 81 Fri
11/15/19
Plumbing systems
(Floor. 4-6) 72 10 days Mon
9/23/19 76 Fri
10/4/19
Plumbing systems
(Floor. 7-9) 75 10 days Mon
10/7/19 78 Fri
10/18/19
Electrical Fixtures
(Distribution) 76 5 days Mon
10/21/19 79 Fri
10/25/19
Electrical Fixtures (Floor.
1-2) 78 10 days Mon
10/28/19 80 Fri
11/8/19
Electrical Fixtures (Floor.
3-4) 79 10 days Mon
11/11/19 81 Fri
11/22/19
Electrical Fixtures (Floor.
5-6) 74, 80 10 days Mon
11/25/19 82 Fri
12/6/19
Electrical Fixtures (Floor.
7-9) 81 10 days Mon
12/9/19 84 Fri
12/20/19
Systems Controls 65, 82 10 days Mon 85 Fri 4/3/20
11/18/19 12/13/19
Windows 60 30 days Mon
11/18/19
Fri
12/27/19
Security doors 62 20 days Mon
12/16/19 67 Fri
1/10/20
Tiles 60 90 days Mon
11/18/19 84 Fri
3/20/20
Glazing works 60 40 days Mon
11/18/19 67 Fri
1/10/20
Decoration 66, 64 30 days Mon
1/13/20 68 Fri
2/21/20
Carpeting 67 50 days Mon
2/24/20 85 Fri 5/1/20
Plumbing systems (Main
Line) 36 15 days Mon
9/2/19 75 Fri
9/20/19
Plumbing systems
(Floor. 1-2) 36 10 days Mon
10/21/19 74 Fri
11/1/19
Plumbing systems
(Floor. 3-4) 36, 73 10 days Mon
11/4/19 81 Fri
11/15/19
Plumbing systems
(Floor. 4-6) 72 10 days Mon
9/23/19 76 Fri
10/4/19
Plumbing systems
(Floor. 7-9) 75 10 days Mon
10/7/19 78 Fri
10/18/19
Electrical Fixtures
(Distribution) 76 5 days Mon
10/21/19 79 Fri
10/25/19
Electrical Fixtures (Floor.
1-2) 78 10 days Mon
10/28/19 80 Fri
11/8/19
Electrical Fixtures (Floor.
3-4) 79 10 days Mon
11/11/19 81 Fri
11/22/19
Electrical Fixtures (Floor.
5-6) 74, 80 10 days Mon
11/25/19 82 Fri
12/6/19
Electrical Fixtures (Floor.
7-9) 81 10 days Mon
12/9/19 84 Fri
12/20/19
Systems Controls 65, 82 10 days Mon 85 Fri 4/3/20
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

6PROJECT DRAFT REPORT
3/23/20
Fire alarms 84, 68 10 days Mon
5/4/20 87, 91 Fri
5/15/20
Mechanical Fixtures
(Elevators etc) 85 15 days Mon
5/18/20 88 Fri 6/5/20
Mechanical Fixtures (Floor
1- 4) 87 30 days Mon
6/8/20 89 Fri
7/17/20
Mechanical Fixtures (Floor
5- 9) 88 30 days Mon
7/20/20
Fri
8/28/20
Access roads 85 14 days Mon
5/18/20 92, 93 Thu
6/4/20
Signages 91 5 days Fri 6/5/20 96 Thu
6/11/20
Parking lot 91 14 days Fri 6/5/20 96 Wed
6/24/20
Testing 1 92, 93 2 days Thu
6/25/20
97, 98, 99, 100,
101, 102, 103, 104,
105
Fri
6/26/20
Testing 2 96 2 days Mon
6/29/20 107 Tue
6/30/20
Testing 3 96 2 days Wed
7/1/20 108 Thu
7/2/20
Testing 4 96 2 days Fri 7/3/20 109 Mon
7/6/20
Testing 5 96 2 days Tue
7/7/20
Wed
7/8/20
Testing 6 96 2 days Thu
7/9/20
Fri
7/10/20
Testing 7 96 2 days Mon
7/13/20
Tue
7/14/20
Testing 8 96 2 days Wed
7/15/20
Thu
7/16/20
Testing 9 96 2 days Fri
7/17/20
Mon
7/20/20
3/23/20
Fire alarms 84, 68 10 days Mon
5/4/20 87, 91 Fri
5/15/20
Mechanical Fixtures
(Elevators etc) 85 15 days Mon
5/18/20 88 Fri 6/5/20
Mechanical Fixtures (Floor
1- 4) 87 30 days Mon
6/8/20 89 Fri
7/17/20
Mechanical Fixtures (Floor
5- 9) 88 30 days Mon
7/20/20
Fri
8/28/20
Access roads 85 14 days Mon
5/18/20 92, 93 Thu
6/4/20
Signages 91 5 days Fri 6/5/20 96 Thu
6/11/20
Parking lot 91 14 days Fri 6/5/20 96 Wed
6/24/20
Testing 1 92, 93 2 days Thu
6/25/20
97, 98, 99, 100,
101, 102, 103, 104,
105
Fri
6/26/20
Testing 2 96 2 days Mon
6/29/20 107 Tue
6/30/20
Testing 3 96 2 days Wed
7/1/20 108 Thu
7/2/20
Testing 4 96 2 days Fri 7/3/20 109 Mon
7/6/20
Testing 5 96 2 days Tue
7/7/20
Wed
7/8/20
Testing 6 96 2 days Thu
7/9/20
Fri
7/10/20
Testing 7 96 2 days Mon
7/13/20
Tue
7/14/20
Testing 8 96 2 days Wed
7/15/20
Thu
7/16/20
Testing 9 96 2 days Fri
7/17/20
Mon
7/20/20
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

7PROJECT DRAFT REPORT
Testing 10 96 2 days Tue
7/21/20
Wed
7/22/20
Inspections 1 97 1 day Wed
7/1/20 110 Wed
7/1/20
Inspections 2 98 1 day Fri 7/3/20 111 Fri 7/3/20
Inspections 3 99 1 day Tue
7/7/20 112 Tue
7/7/20
Inspections 4 107 1 day Thu
7/2/20 113 Thu
7/2/20
Inspections 5 108 1 day Mon
7/6/20 114 Mon
7/6/20
Inspections 6 109 1 day Wed
7/8/20 115 Wed
7/8/20
Inspections 7 110 1 day Fri 7/3/20 116 Fri 7/3/20
Inspections 8 111 1 day Tue
7/7/20 116 Tue
7/7/20
Inspections 9 112 1 day Thu
7/9/20 116 Thu
7/9/20
Inspections 10 113, 114,
115 1 day Fri
7/10/20
Fri
7/10/20
1.2 Project Schedule Description
The project had been considered for the constructing the flat complex and the utilization
of the construction project management principles for the alignment of the effective and
improved management process. The project has been divided into phases of planning, basement
and floor works, concrete works, electrical works, quality assessment, and inspections. The
construction works would be required for making sure that works can be integrated with the
alignment of the successful and effective management of construction works. The duration of the
projects include the following phases,
Testing 10 96 2 days Tue
7/21/20
Wed
7/22/20
Inspections 1 97 1 day Wed
7/1/20 110 Wed
7/1/20
Inspections 2 98 1 day Fri 7/3/20 111 Fri 7/3/20
Inspections 3 99 1 day Tue
7/7/20 112 Tue
7/7/20
Inspections 4 107 1 day Thu
7/2/20 113 Thu
7/2/20
Inspections 5 108 1 day Mon
7/6/20 114 Mon
7/6/20
Inspections 6 109 1 day Wed
7/8/20 115 Wed
7/8/20
Inspections 7 110 1 day Fri 7/3/20 116 Fri 7/3/20
Inspections 8 111 1 day Tue
7/7/20 116 Tue
7/7/20
Inspections 9 112 1 day Thu
7/9/20 116 Thu
7/9/20
Inspections 10 113, 114,
115 1 day Fri
7/10/20
Fri
7/10/20
1.2 Project Schedule Description
The project had been considered for the constructing the flat complex and the utilization
of the construction project management principles for the alignment of the effective and
improved management process. The project has been divided into phases of planning, basement
and floor works, concrete works, electrical works, quality assessment, and inspections. The
construction works would be required for making sure that works can be integrated with the
alignment of the successful and effective management of construction works. The duration of the
projects include the following phases,

8PROJECT DRAFT REPORT
Planning: the activities included in this phase are identify mission and objectives, create
project charter, create business plan and issue, and create project initiation document and issue.
Design: the design phase would include the activities of the soil investigation,
architectural, structural, mechanical, and electrical.
Basement and Floors 1 – 9: The work required in basement and flooring include
earthworks, survey, excavation, ground works, grading, water control, erosion control,
underground utilities, structures, reinforcements, piles (precast), columns, columns (basement -
floor 2), columns (floor 3 - 4), columns (floor 5 - 6), columns (floor 7 - 9), slab-beams, slab -
beams (basement - floor 2), slab-beams (floor 3- 4), slab-beams (floor 5 - 6), slab-beams (floor 7
- 9), roofing, roofing trusses, roofing cover, concrete,
Columns: the columns of the flooring would be done by involving the following sub
projects columns (basement - floor 2), columns floor (3 - 4), columns floor (5 - 6), columns floor
(7 - 9).
Slab-Beams: the slam beams would include the slab-beams (basement - floor 2), slab-
beams floor (3 - 4), slab-beams floor (5 - 6), slab-beams floor (7 - 8).
Stairway: Stairway construction would be sub sectioned into stairway (basement - floor
2), stairway floor (3 - 4), stairway floor (5 -6), and stairway floor (7 - 8).
Other works: some other construction works include patios, block wall-masonry, block
wall, internal wall, external wall, screeding, interior –finishes, partitions, dry wall, insulation,
interior doors, windows, security doors, tiles, glazing works, decoration, carpeting, mep systems
Planning: the activities included in this phase are identify mission and objectives, create
project charter, create business plan and issue, and create project initiation document and issue.
Design: the design phase would include the activities of the soil investigation,
architectural, structural, mechanical, and electrical.
Basement and Floors 1 – 9: The work required in basement and flooring include
earthworks, survey, excavation, ground works, grading, water control, erosion control,
underground utilities, structures, reinforcements, piles (precast), columns, columns (basement -
floor 2), columns (floor 3 - 4), columns (floor 5 - 6), columns (floor 7 - 9), slab-beams, slab -
beams (basement - floor 2), slab-beams (floor 3- 4), slab-beams (floor 5 - 6), slab-beams (floor 7
- 9), roofing, roofing trusses, roofing cover, concrete,
Columns: the columns of the flooring would be done by involving the following sub
projects columns (basement - floor 2), columns floor (3 - 4), columns floor (5 - 6), columns floor
(7 - 9).
Slab-Beams: the slam beams would include the slab-beams (basement - floor 2), slab-
beams floor (3 - 4), slab-beams floor (5 - 6), slab-beams floor (7 - 8).
Stairway: Stairway construction would be sub sectioned into stairway (basement - floor
2), stairway floor (3 - 4), stairway floor (5 -6), and stairway floor (7 - 8).
Other works: some other construction works include patios, block wall-masonry, block
wall, internal wall, external wall, screeding, interior –finishes, partitions, dry wall, insulation,
interior doors, windows, security doors, tiles, glazing works, decoration, carpeting, mep systems
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

9PROJECT DRAFT REPORT
Plumbing: the plumbing works include plumbing systems (main line), plumbing systems
(floor. 1-2), plumbing systems (floor. 3-4), plumbing systems (floor. 4-6), plumbing systems
(floor. 7-9).
Electrical: the electrical works include electrical fixtures (distribution), electrical fixtures
(floor. 1-2), electrical fixtures (floor. 3-4), electrical fixtures (floor. 5-6), electrical fixtures
(floor. 7-9), sprinkler, systems controls, fire alarms, mechanical systems, mechanical fixtures
(elevators etc), mechanical fixtures (floor 1- 4), mechanical fixtures (floor 5- 9).
1.3 Network Diagram
7 8
10 14 15
18 20 23 25
26
28 30 31
32 35
39 40 41
44
45
46
49 50 51
52
56 60 62
63
64
65
66
79
85 87
91 92
98
99
100
101
102
103
104
105
107
108
109
110
111
112
113
114
115
3 4
19
5
69
53
57
58
6867
27
74
78
42 47
119
73
17 3633 72 7675
96
84
116
93
97
82 81 80
89
88
Plumbing: the plumbing works include plumbing systems (main line), plumbing systems
(floor. 1-2), plumbing systems (floor. 3-4), plumbing systems (floor. 4-6), plumbing systems
(floor. 7-9).
Electrical: the electrical works include electrical fixtures (distribution), electrical fixtures
(floor. 1-2), electrical fixtures (floor. 3-4), electrical fixtures (floor. 5-6), electrical fixtures
(floor. 7-9), sprinkler, systems controls, fire alarms, mechanical systems, mechanical fixtures
(elevators etc), mechanical fixtures (floor 1- 4), mechanical fixtures (floor 5- 9).
1.3 Network Diagram
7 8
10 14 15
18 20 23 25
26
28 30 31
32 35
39 40 41
44
45
46
49 50 51
52
56 60 62
63
64
65
66
79
85 87
91 92
98
99
100
101
102
103
104
105
107
108
109
110
111
112
113
114
115
3 4
19
5
69
53
57
58
6867
27
74
78
42 47
119
73
17 3633 72 7675
96
84
116
93
97
82 81 80
89
88
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

10PROJECT DRAFT REPORT
1.4 Project Critical Path Diagram
ID Task
Mode
WBS Task Name
3 1.1.1 1.1.1 Identify mission and
Objectives, Create Project
Charter
4 1.1.2 1.1.2 Create Business Plan
and Issue
7 1.1 1.2.1 Soil Investigation
9 1.2.3 1.2.3 Structural
10 1.2.4 1.2.4 Mechanical
11 1.2.5 1.2.5 Electrical
17 2.1.3.1 2.1.3.1 Grading
18 2.1.3.2 2.1.3.2 Water Control
19 2.1.3.3 2.1.3.3 Erosion control
20 2.1.3.4 2.1.3.4 Underground utilities
23 2.2.1.1 2.2.1.1 Piles (Precast)
49 2.3.3.1 2.4.1 Stairway (Basement -
Floor 2)
56 2.4.1.1 2.6.1.1 Internal wall
57 2.4.1.2 2.6.1.2 External wall
69 2.5..5 2.7.4 Partitions
60 2.5.1 2.7.1 Dry wall
62 2.5.2.1 2.7.2.1 Interior doors
64 2.5.2.3 2.7.2.3 Security doors
66 2.5.2.5 2.7.2.5 Glazing works
67 2.5.2.6 2.7.2.6 Decoration
68 2.5.4 2.7.3 Carpeting
85 2.6.3.2 2.10.2 Fire alarms
87 2.6.4.1 2.11.1 Mechanical Fixtures
(Elevators etc)
88 2.6.4.2 2.11.2 Mechanical Fixtures
(Floor 1- 4)
89 2.6.4.3 2.11.3 Mechanical Fixtures
(Floor 5- 9)
Team IbMo
Team IbMo
Geotechnical Engineer[20%],Soil Lab technician[20%],Soil investigation Engineer[20%]
AutoCAD drafts man[50%],Estimator-Compiler,Snr Stuctural Engineer
Mechanical systems designer,AutoCAD drafts man[20%],Estimator-Compiler[20%]
Electrical systems designer,AutoCAD drafts man,Estimator-Compiler
Leveller,Helper[200%],Grader operator
Pump operator (certified),Pump Operator,Helper[200%]
Erosion control specialist,Sediment control specialist,Labourer[200%]
Utility line locator,Utility line assessor,Utility line technician
Auger cast superintendent,Concrete technicians[200%],PM Deep foundations,Concrete mixer technician[200%]
Concrete form setter[600%],Concrete batch maker[200%],Concrete mixer driver[200%],Concrete technicians[500%]
Curtain wall installer[300%],Carpenter[200%],Brick layer[200%],Brick leveller[200%]
Curtain wall installer[300%],Carpenter[200%],Brick layer[200%],Brick leveller[300%]
Partition wall installer[200%],Partition wall technician[200%],metal stud framer
Dry wall finisher[200%],Dry wall installer[200%],Carpenter Foreman
Door assembler[200%],Door installer[200%],Door finisher
Door assembler[200%],Door installer[200%],Door finisher
Glass/ Glazing installer[200%],painter glazing technician[200%],Project Manager Glazing
Painter[200%],Decorator,Paint technician
Carpet Installer[200%],Flooring Installation Helper[200%],Labourer[200%]
Fire alarm technician,Fire alarm supervisor,Fire alarm aassistance/ appprentice[200%]
HVAC Engineer,Commissioning engineer,HVAC technician,HVAC apprentice/assistant[200%],Hel
HVAC Engineer,Commissioning engineer,HVAC technician,HVAC apprentice/ assistant[200%]
HVAC Engineer,Commissioning engineer,HVAC technician,HVAC apprentice/assistant[2
Sep Nov Jan Mar May Jul Sep Nov Jan Mar May Jul Sep Nov Jan Mar May Jul Sep Nov Jan Mar
Qtr 3, 2018 Qtr 1, 2019 Qtr 3, 2019 Qtr 1, 2020 Qtr 3, 2020 Qtr 1, 2021 Qtr 3, 2021 Qtr 1, 2022
1.4 Project Critical Path Diagram
ID Task
Mode
WBS Task Name
3 1.1.1 1.1.1 Identify mission and
Objectives, Create Project
Charter
4 1.1.2 1.1.2 Create Business Plan
and Issue
7 1.1 1.2.1 Soil Investigation
9 1.2.3 1.2.3 Structural
10 1.2.4 1.2.4 Mechanical
11 1.2.5 1.2.5 Electrical
17 2.1.3.1 2.1.3.1 Grading
18 2.1.3.2 2.1.3.2 Water Control
19 2.1.3.3 2.1.3.3 Erosion control
20 2.1.3.4 2.1.3.4 Underground utilities
23 2.2.1.1 2.2.1.1 Piles (Precast)
49 2.3.3.1 2.4.1 Stairway (Basement -
Floor 2)
56 2.4.1.1 2.6.1.1 Internal wall
57 2.4.1.2 2.6.1.2 External wall
69 2.5..5 2.7.4 Partitions
60 2.5.1 2.7.1 Dry wall
62 2.5.2.1 2.7.2.1 Interior doors
64 2.5.2.3 2.7.2.3 Security doors
66 2.5.2.5 2.7.2.5 Glazing works
67 2.5.2.6 2.7.2.6 Decoration
68 2.5.4 2.7.3 Carpeting
85 2.6.3.2 2.10.2 Fire alarms
87 2.6.4.1 2.11.1 Mechanical Fixtures
(Elevators etc)
88 2.6.4.2 2.11.2 Mechanical Fixtures
(Floor 1- 4)
89 2.6.4.3 2.11.3 Mechanical Fixtures
(Floor 5- 9)
Team IbMo
Team IbMo
Geotechnical Engineer[20%],Soil Lab technician[20%],Soil investigation Engineer[20%]
AutoCAD drafts man[50%],Estimator-Compiler,Snr Stuctural Engineer
Mechanical systems designer,AutoCAD drafts man[20%],Estimator-Compiler[20%]
Electrical systems designer,AutoCAD drafts man,Estimator-Compiler
Leveller,Helper[200%],Grader operator
Pump operator (certified),Pump Operator,Helper[200%]
Erosion control specialist,Sediment control specialist,Labourer[200%]
Utility line locator,Utility line assessor,Utility line technician
Auger cast superintendent,Concrete technicians[200%],PM Deep foundations,Concrete mixer technician[200%]
Concrete form setter[600%],Concrete batch maker[200%],Concrete mixer driver[200%],Concrete technicians[500%]
Curtain wall installer[300%],Carpenter[200%],Brick layer[200%],Brick leveller[200%]
Curtain wall installer[300%],Carpenter[200%],Brick layer[200%],Brick leveller[300%]
Partition wall installer[200%],Partition wall technician[200%],metal stud framer
Dry wall finisher[200%],Dry wall installer[200%],Carpenter Foreman
Door assembler[200%],Door installer[200%],Door finisher
Door assembler[200%],Door installer[200%],Door finisher
Glass/ Glazing installer[200%],painter glazing technician[200%],Project Manager Glazing
Painter[200%],Decorator,Paint technician
Carpet Installer[200%],Flooring Installation Helper[200%],Labourer[200%]
Fire alarm technician,Fire alarm supervisor,Fire alarm aassistance/ appprentice[200%]
HVAC Engineer,Commissioning engineer,HVAC technician,HVAC apprentice/assistant[200%],Hel
HVAC Engineer,Commissioning engineer,HVAC technician,HVAC apprentice/ assistant[200%]
HVAC Engineer,Commissioning engineer,HVAC technician,HVAC apprentice/assistant[2
Sep Nov Jan Mar May Jul Sep Nov Jan Mar May Jul Sep Nov Jan Mar May Jul Sep Nov Jan Mar
Qtr 3, 2018 Qtr 1, 2019 Qtr 3, 2019 Qtr 1, 2020 Qtr 3, 2020 Qtr 1, 2021 Qtr 3, 2021 Qtr 1, 2022

11PROJECT DRAFT REPORT
1.5 Project Gantt Chart
ID Task
Mode
WBS Task Name
3 1.1.1 1.1.1 Identify mission and
Objectives, Create Project
Charter
4 1.1.2 1.1.2 Create Business Plan
and Issue
5 1.1.3 1.1.3 Create Project Initiation
Document and Issue
7 1.1 1.2.1 Soil Investigation
8 1.2 1.2.2 Architectural
9 1.2.3 1.2.3 Structural
10 1.2.4 1.2.4 Mechanical
11 1.2.5 1.2.5 Electrical
14 2.1.1 2.1.1 Survey
15 2.1.2 2.1.2 Excavation
17 2.1.3.1 2.1.3.1 Grading
18 2.1.3.2 2.1.3.2 Water Control
19 2.1.3.3 2.1.3.3 Erosion control
20 2.1.3.4 2.1.3.4 Underground utilities
23 2.2.1.1 2.2.1.1 Piles (Precast)
25 2.2.1.2.1 2.2.1.2.1 Columns
(Basement - Floor 2)
26 2.2.1.2.2 2.2.1.2.2 Columns (Floor 3 - 4)
27 2.2.1.2.3 2.2.1.2.3 Columns (Floor 5 - 6)
28 2.2.1.2.4 2.2.1.2.4 Columns (Floor 7 - 9)
30 2.2.1.3.1 2.2.1.3.1 Slab -Beams
(Basement - Floor 2)
31 2.2.1.3.2 2.2.1.3.2 Slab-Beams
(Floor 3- 4)
32 2.2.1.3.3 2.2.1.3.3 Slab-Beams
(Floor 5 - 6)
33 2.2.1.3.4 2.2.1.3.4 Slab-Beams
(Floor 7 - 9)
35 2.2.1.4.1 2.2.1.4.1 Roofing Trusses
36 2.2.1.4.2 2.2.1.4.2 Roofing Cover
39 2.3.1.1 2.3.1.1 Columns
(Basement - Floor 2)
40 2.3.1.2 2.3.1.2 Columns Floor( 3 - 4)
41 2.3.1.3 2.3.1.3 Columns Floor( 5 - 6)
42 2.3.1.4 2.3.1.4 Columns Floor( 7 - 9)
44 2.3.2.1 2.3.2.1 Slab-Beams
(Basement - Floor 2)
45 2.3.2.2 2.3.2.2 Slab-Beams Floor( 3 - 4)
46 2.3.2.3 2.3.2.3 Slab-Beams Floor( 5 - 6)
47 2.3.2.4 2.3.2.4 Slab-Beams Floor( 7 - 8)
49 2.3.3.1 2.4.1 Stairway (Basement -
Floor 2)
50 2.3.3.2 2.4.2 Stairway Floor(3 - 4)
51 2.3.3.3 2.4.3 Stairway Floor( 5 -6)
52 2.3.3.4 2.4.4 Stairway Floor( 7 - 8)
53 2.3.4 2.5 Patios
56 2.4.1.1 2.6.1.1 Internal wall
57 2.4.1.2 2.6.1.2 External wall
58 2.4.1.3 2.6.1.3 Screeding
69 2.5..5 2.7.4 Partitions
60 2.5.1 2.7.1 Dry wall
62 2.5.2.1 2.7.2.1 Interior doors
63 2.5.2.2 2.7.2.2 Windows
64 2.5.2.3 2.7.2.3 Security doors
65 2.5.2.4 2.7.2.4 Tiles
66 2.5.2.5 2.7.2.5 Glazing works
67 2.5.2.6 2.7.2.6 Decoration
68 2.5.4 2.7.3 Carpeting
72 2.6.1.1 2.8.1.1 Plumbing systems
(Main Line)
73 2.6.1.2 2.8.1.2 Plumbing systems
(Floor. 1-2)
74 2.6.1.3 2.8.1.3 Plumbing systems
(Floor. 3-4)
75 2.6.1.4 2.8.1.4 Plumbing systems
(Floor. 4-6)
76 2.6.1.5 2.8.1.5 Plumbing systems
(Floor. 7-9)
78 2.6.2.1 2.9.1 Electrical Fixtures
(Distribution)
79 2.6.2.2 2.9.2 Electrical Fixtures (Floor. 1-2)
80 2.6.2.3 2.9.3 Electrical Fixtures (Floor. 3-4)
81 2.6.2.4 2.9.4 Electrical Fixtures (Floor. 5-6)
82 2.6.2.5 2.9.5 Electrical Fixtures (Floor. 7-9)
84 2.6.3.1 2.10.1 Systems Controls
85 2.6.3.2 2.10.2 Fire alarms
87 2.6.4.1 2.11.1 Mechanical Fixtures
(Elevators etc)
88 2.6.4.2 2.11.2 Mechanical Fixtures
(Floor 1- 4)
89 2.6.4.3 2.11.3 Mechanical Fixtures
(Floor 5- 9)
91 3.1 3.1 Access roads
92 3.2 3.2 Signages
93 3.3 3.3 Parking lot
96 4.1 4.1.1 Testing 1
97 4.1 4.1.2 Testing 2
98 4.1 4.1.3 Testing 3
99 4.1 4.1.4 Testing 4
100 4.1 4.1.5 Testing 5
101 4.1 4.1.6 Testing 6
102 4.1 4.1.7 Testing 7
103 4.1 4.1.8 Testing 8
104 4.1 4.1.9 Testing 9
105 4.1 4.1.10 Testing 10
107 4.2 4.2.1 Inspections 1
108 4.2 4.2.2 Inspections 2
109 4.2 4.2.3 Inspections 3
110 4.2 4.2.4 Inspections 4
111 4.2 4.2.5 Inspections 5
112 4.2 4.2.6 Inspections 6
113 4.2 4.2.7 Inspections 7
114 4.2 4.2.8 Inspections 8
115 4.2 4.2.9 Inspections 9
116 4.2 4.2.10 Inspections 10
Team IbMo
Team IbMo
Team IbMo,Test Technicians[0%]
Geotechnical Engineer[20%],Soil Lab technician[20%],Soil investigation Engineer[20%]
Senior architect,AutoCAD drafts man[20%],Estimator-Compiler[20%]
AutoCAD drafts man[50%],Estimator-Compiler,Snr Stuctural Engineer
Mechanical systems designer,AutoCAD drafts man[20%],Estimator-Compiler[20%]
Electrical systems designer,AutoCAD drafts man,Estimator-Compiler
Geodectic Engineer,Surveyor assistant,Geodectic technician
Excavator operator,Dump operator,Helper
Leveller,Helper[200%],Grader operator
Pump operator (certified),Pump Operator,Helper[200%]
Erosion control specialist,Sediment control specialist,Labourer[200%]
Utility line locator,Utility line assessor,Utility line technician
Auger cast superintendent,Concrete technicians[200%],PM Deep foundations,Concrete mixer technician[200%]
Rebar Installer[400%],Rebar detailing co-ordinator[200%],Rebar Detailer[200%],Rebar Bender[400%]
Rebar Bender[400%],Rebar Detailer[200%],Rebar detailing co-ordinator[200%],Rebar Installer[400%]
Rebar Bender[400%],Rebar Detailer[200%],Rebar Installer[400%],Rebar detailing co-ordinator[200%]
Rebar Bender[400%],Rebar Detailer[200%],Rebar Installer[400%],Rebar detailing co-ordinator[200%]
Rebar Bender[400%],Rebar Installer[400%],Rebar detailing co-ordinator[200%],Rebar Detailer[200%]
Rebar Bender[400%],Rebar Installer[400%],Rebar detailing co-ordinator[200%],Rebar Detailer[200%]
Rebar Bender[400%],Rebar Installer[400%],Rebar detailing co-ordinator[200%],Rebar Detailer[200%]
Rebar Bender[400%],Rebar Detailer[200%],Rebar detailing co-ordinator[200%],Rebar Installer[400%]
Truss assembler[400%],Framer[200%],Helper[600%]
Roof helper[400%],Roofer[400%],Labourer[400%]
Concrete form setter[600%],Concrete batch maker[200%],Concrete mixer driver[200%],Labourer[500%]
Concrete batch maker[200%],Concrete form setter[600%],Concrete mixer driver[200%],Labourer[500%]
Concrete form setter[600%],Concrete batch maker[200%],Concrete mixer driver[200%],Labourer[500%]
Concrete batch maker[200%],Concrete form setter[600%],Concrete technicians[500%],Concrete mixer driv
Concrete batch maker,Concrete mixer driver,Concrete form setter,Concrete technicians
Concrete batch maker,Concrete form setter,Concrete technicians,Concrete mixer driver
Concrete batch maker,Concrete form setter,Concrete mixer driver,Concrete technicians
Concrete batch maker,Concrete mixer driver,Concrete technicians,Concrete form setter
Concrete form setter[600%],Concrete batch maker[200%],Concrete mixer driver[200%],Concrete technicians[500%]
Concrete batch maker[200%],Concrete form setter[600%],Concrete mixer driver[200%],Concrete technicians[500%]
Concrete batch maker[200%],Concrete mixer driver[200%],Concrete technicians[500%],Concrete form setter[600%]
Concrete batch maker[200%],Concrete mixer driver[200%],Concrete technicians[500%],Concrete form setter[600%]
Concrete batch maker[200%],Concrete form setter[500%],Concrete mixer driver[200%]
Curtain wall installer[300%],Carpenter[200%],Brick layer[200%],Brick leveller[200%]
Curtain wall installer[300%],Carpenter[200%],Brick layer[200%],Brick leveller[300%]
Screed operator[200%],Concrete finishers[200%],Labourers[300%]
Partition wall installer[200%],Partition wall technician[200%],metal stud framer
Dry wall finisher[200%],Dry wall installer[200%],Carpenter Foreman
Door assembler[200%],Door installer[200%],Door finisher
Window installer[200%],Assistant installer[200%],Installer helper
Door assembler[200%],Door installer[200%],Door finisher
Grout & Tile technician,Tile setter,Tile cutting machine operator
Glass/Glazing installer[200%],painter glazing technician[200%],Project Manager Glazing
Painter[200%],Decorator,Paint technician
Carpet Installer[200%],Flooring Installation Helper[200%],Labourer[200%]
Plumber,Journeyman plumber,Plumbing supervisor
Plumber,Journeyman plumber,Plumbing supervisor
Plumber,J ourneyman plumber,Plumbing supervisor
Plumber,Journeyman plumber,Plumbing supervisor
Plumber,Journeyman plumber,Plumbing supervisor
Licensed electrician,Commissioning specialist - electrical,Electrician,Assistant/Apprentice[200%]
Licensed electrician,Commissioning specialist - electrical,Electrician,Assistant/Apprentice[200%]
Licensed electrician,Commissioning specialist - electrical,Electrician,Assistant/Apprentice[200%]
Licensed electrician,Commissioning specialist - electrical,Electrician,Assistant/Apprentice[200%]
Licensed electrician,Commissioning specialist - electrical,Electrician,Assistant/Apprentice[200%]
Power systems controller,Sytems Engineer,Controls system specialist,Sprinkler fitter,F
Fire alarm technician,Fire alarm supervisor,Fire alarm aassistance/ appprentice[2
HVAC Engineer,Commissioning engineer,HVAC technician,HVAC apprentice/as
HVAC Engineer,Commissioning engineer,HVAC technician,HVAC apprentic
HVAC Engineer,Commissioning engineer,HVAC technician,HVAC appr
Highway construction crew,Crew members for asphalt paving,Asphalt roller
Signage installer,Signage designer
Highway construction crew,Asphalt roller,Crew members for asphalt paving
Test Technicians,Tester (Intern),Construction materials field testing technici
Test Technicians,Tester (Intern),Construction materials field testing technici
Test Technicians,Tester (Intern),Construction materials field testing technic
Test Technicians,Tester (Intern),Construction materials field testing technic
Test Technicians,Tester (Intern),Construction materials field testing technic
Test Technicians,Tester (Intern),Construction materials field testing techni
Test Technicians,Tester (Intern),Construction materials field testing techni
Test Technicians,Tester (Intern),Construction materials field testing techni
Test Technicians,Tester (Intern),Construction materials field testing techn
Test Technicians,Tester (Intern),Construction materials field testing techn
MeP Inspector[10%],Construction inspector[10%],Inspector (Buildings)[10%]
MeP Inspector[10%],Construction inspector[10%],Inspector (Buildings)[10%
MeP Inspector[10%],Construction inspector[10%],Inspector (Buildings)[10%
MeP Inspector[10%],Construction inspector[10%],Inspector (Buildings)[10%]
MeP Inspector[10%],Construction inspector[10%],Inspector (Buildings)[10%
MeP Inspector[10%],Construction inspector[10%],Inspector (Buildings)[10%
MeP Inspector[10%],Construction inspector[10%],Inspector (Buildings)[10%
MeP Inspector[10%],Construction inspector[10%],Inspector (Buildings)[10%
MeP Inspector[10%],Construction inspector[10%],Inspector (Buildings)[10%
MeP Inspector[10%],Construction inspector[10%],Inspector (Buildings)[10%
Sep Nov Jan Mar May Jul Sep Nov Jan Mar May Jul Sep Nov Jan Mar May Jul Sep Nov Jan Mar
Qtr 3, 2018 Qtr 1, 2019 Qtr 3, 2019 Qtr 1, 2020 Qtr 3, 2020 Qtr 1, 2021 Qtr 3, 2021 Qtr 1, 2022
1.5 Project Gantt Chart
ID Task
Mode
WBS Task Name
3 1.1.1 1.1.1 Identify mission and
Objectives, Create Project
Charter
4 1.1.2 1.1.2 Create Business Plan
and Issue
5 1.1.3 1.1.3 Create Project Initiation
Document and Issue
7 1.1 1.2.1 Soil Investigation
8 1.2 1.2.2 Architectural
9 1.2.3 1.2.3 Structural
10 1.2.4 1.2.4 Mechanical
11 1.2.5 1.2.5 Electrical
14 2.1.1 2.1.1 Survey
15 2.1.2 2.1.2 Excavation
17 2.1.3.1 2.1.3.1 Grading
18 2.1.3.2 2.1.3.2 Water Control
19 2.1.3.3 2.1.3.3 Erosion control
20 2.1.3.4 2.1.3.4 Underground utilities
23 2.2.1.1 2.2.1.1 Piles (Precast)
25 2.2.1.2.1 2.2.1.2.1 Columns
(Basement - Floor 2)
26 2.2.1.2.2 2.2.1.2.2 Columns (Floor 3 - 4)
27 2.2.1.2.3 2.2.1.2.3 Columns (Floor 5 - 6)
28 2.2.1.2.4 2.2.1.2.4 Columns (Floor 7 - 9)
30 2.2.1.3.1 2.2.1.3.1 Slab -Beams
(Basement - Floor 2)
31 2.2.1.3.2 2.2.1.3.2 Slab-Beams
(Floor 3- 4)
32 2.2.1.3.3 2.2.1.3.3 Slab-Beams
(Floor 5 - 6)
33 2.2.1.3.4 2.2.1.3.4 Slab-Beams
(Floor 7 - 9)
35 2.2.1.4.1 2.2.1.4.1 Roofing Trusses
36 2.2.1.4.2 2.2.1.4.2 Roofing Cover
39 2.3.1.1 2.3.1.1 Columns
(Basement - Floor 2)
40 2.3.1.2 2.3.1.2 Columns Floor( 3 - 4)
41 2.3.1.3 2.3.1.3 Columns Floor( 5 - 6)
42 2.3.1.4 2.3.1.4 Columns Floor( 7 - 9)
44 2.3.2.1 2.3.2.1 Slab-Beams
(Basement - Floor 2)
45 2.3.2.2 2.3.2.2 Slab-Beams Floor( 3 - 4)
46 2.3.2.3 2.3.2.3 Slab-Beams Floor( 5 - 6)
47 2.3.2.4 2.3.2.4 Slab-Beams Floor( 7 - 8)
49 2.3.3.1 2.4.1 Stairway (Basement -
Floor 2)
50 2.3.3.2 2.4.2 Stairway Floor(3 - 4)
51 2.3.3.3 2.4.3 Stairway Floor( 5 -6)
52 2.3.3.4 2.4.4 Stairway Floor( 7 - 8)
53 2.3.4 2.5 Patios
56 2.4.1.1 2.6.1.1 Internal wall
57 2.4.1.2 2.6.1.2 External wall
58 2.4.1.3 2.6.1.3 Screeding
69 2.5..5 2.7.4 Partitions
60 2.5.1 2.7.1 Dry wall
62 2.5.2.1 2.7.2.1 Interior doors
63 2.5.2.2 2.7.2.2 Windows
64 2.5.2.3 2.7.2.3 Security doors
65 2.5.2.4 2.7.2.4 Tiles
66 2.5.2.5 2.7.2.5 Glazing works
67 2.5.2.6 2.7.2.6 Decoration
68 2.5.4 2.7.3 Carpeting
72 2.6.1.1 2.8.1.1 Plumbing systems
(Main Line)
73 2.6.1.2 2.8.1.2 Plumbing systems
(Floor. 1-2)
74 2.6.1.3 2.8.1.3 Plumbing systems
(Floor. 3-4)
75 2.6.1.4 2.8.1.4 Plumbing systems
(Floor. 4-6)
76 2.6.1.5 2.8.1.5 Plumbing systems
(Floor. 7-9)
78 2.6.2.1 2.9.1 Electrical Fixtures
(Distribution)
79 2.6.2.2 2.9.2 Electrical Fixtures (Floor. 1-2)
80 2.6.2.3 2.9.3 Electrical Fixtures (Floor. 3-4)
81 2.6.2.4 2.9.4 Electrical Fixtures (Floor. 5-6)
82 2.6.2.5 2.9.5 Electrical Fixtures (Floor. 7-9)
84 2.6.3.1 2.10.1 Systems Controls
85 2.6.3.2 2.10.2 Fire alarms
87 2.6.4.1 2.11.1 Mechanical Fixtures
(Elevators etc)
88 2.6.4.2 2.11.2 Mechanical Fixtures
(Floor 1- 4)
89 2.6.4.3 2.11.3 Mechanical Fixtures
(Floor 5- 9)
91 3.1 3.1 Access roads
92 3.2 3.2 Signages
93 3.3 3.3 Parking lot
96 4.1 4.1.1 Testing 1
97 4.1 4.1.2 Testing 2
98 4.1 4.1.3 Testing 3
99 4.1 4.1.4 Testing 4
100 4.1 4.1.5 Testing 5
101 4.1 4.1.6 Testing 6
102 4.1 4.1.7 Testing 7
103 4.1 4.1.8 Testing 8
104 4.1 4.1.9 Testing 9
105 4.1 4.1.10 Testing 10
107 4.2 4.2.1 Inspections 1
108 4.2 4.2.2 Inspections 2
109 4.2 4.2.3 Inspections 3
110 4.2 4.2.4 Inspections 4
111 4.2 4.2.5 Inspections 5
112 4.2 4.2.6 Inspections 6
113 4.2 4.2.7 Inspections 7
114 4.2 4.2.8 Inspections 8
115 4.2 4.2.9 Inspections 9
116 4.2 4.2.10 Inspections 10
Team IbMo
Team IbMo
Team IbMo,Test Technicians[0%]
Geotechnical Engineer[20%],Soil Lab technician[20%],Soil investigation Engineer[20%]
Senior architect,AutoCAD drafts man[20%],Estimator-Compiler[20%]
AutoCAD drafts man[50%],Estimator-Compiler,Snr Stuctural Engineer
Mechanical systems designer,AutoCAD drafts man[20%],Estimator-Compiler[20%]
Electrical systems designer,AutoCAD drafts man,Estimator-Compiler
Geodectic Engineer,Surveyor assistant,Geodectic technician
Excavator operator,Dump operator,Helper
Leveller,Helper[200%],Grader operator
Pump operator (certified),Pump Operator,Helper[200%]
Erosion control specialist,Sediment control specialist,Labourer[200%]
Utility line locator,Utility line assessor,Utility line technician
Auger cast superintendent,Concrete technicians[200%],PM Deep foundations,Concrete mixer technician[200%]
Rebar Installer[400%],Rebar detailing co-ordinator[200%],Rebar Detailer[200%],Rebar Bender[400%]
Rebar Bender[400%],Rebar Detailer[200%],Rebar detailing co-ordinator[200%],Rebar Installer[400%]
Rebar Bender[400%],Rebar Detailer[200%],Rebar Installer[400%],Rebar detailing co-ordinator[200%]
Rebar Bender[400%],Rebar Detailer[200%],Rebar Installer[400%],Rebar detailing co-ordinator[200%]
Rebar Bender[400%],Rebar Installer[400%],Rebar detailing co-ordinator[200%],Rebar Detailer[200%]
Rebar Bender[400%],Rebar Installer[400%],Rebar detailing co-ordinator[200%],Rebar Detailer[200%]
Rebar Bender[400%],Rebar Installer[400%],Rebar detailing co-ordinator[200%],Rebar Detailer[200%]
Rebar Bender[400%],Rebar Detailer[200%],Rebar detailing co-ordinator[200%],Rebar Installer[400%]
Truss assembler[400%],Framer[200%],Helper[600%]
Roof helper[400%],Roofer[400%],Labourer[400%]
Concrete form setter[600%],Concrete batch maker[200%],Concrete mixer driver[200%],Labourer[500%]
Concrete batch maker[200%],Concrete form setter[600%],Concrete mixer driver[200%],Labourer[500%]
Concrete form setter[600%],Concrete batch maker[200%],Concrete mixer driver[200%],Labourer[500%]
Concrete batch maker[200%],Concrete form setter[600%],Concrete technicians[500%],Concrete mixer driv
Concrete batch maker,Concrete mixer driver,Concrete form setter,Concrete technicians
Concrete batch maker,Concrete form setter,Concrete technicians,Concrete mixer driver
Concrete batch maker,Concrete form setter,Concrete mixer driver,Concrete technicians
Concrete batch maker,Concrete mixer driver,Concrete technicians,Concrete form setter
Concrete form setter[600%],Concrete batch maker[200%],Concrete mixer driver[200%],Concrete technicians[500%]
Concrete batch maker[200%],Concrete form setter[600%],Concrete mixer driver[200%],Concrete technicians[500%]
Concrete batch maker[200%],Concrete mixer driver[200%],Concrete technicians[500%],Concrete form setter[600%]
Concrete batch maker[200%],Concrete mixer driver[200%],Concrete technicians[500%],Concrete form setter[600%]
Concrete batch maker[200%],Concrete form setter[500%],Concrete mixer driver[200%]
Curtain wall installer[300%],Carpenter[200%],Brick layer[200%],Brick leveller[200%]
Curtain wall installer[300%],Carpenter[200%],Brick layer[200%],Brick leveller[300%]
Screed operator[200%],Concrete finishers[200%],Labourers[300%]
Partition wall installer[200%],Partition wall technician[200%],metal stud framer
Dry wall finisher[200%],Dry wall installer[200%],Carpenter Foreman
Door assembler[200%],Door installer[200%],Door finisher
Window installer[200%],Assistant installer[200%],Installer helper
Door assembler[200%],Door installer[200%],Door finisher
Grout & Tile technician,Tile setter,Tile cutting machine operator
Glass/Glazing installer[200%],painter glazing technician[200%],Project Manager Glazing
Painter[200%],Decorator,Paint technician
Carpet Installer[200%],Flooring Installation Helper[200%],Labourer[200%]
Plumber,Journeyman plumber,Plumbing supervisor
Plumber,Journeyman plumber,Plumbing supervisor
Plumber,J ourneyman plumber,Plumbing supervisor
Plumber,Journeyman plumber,Plumbing supervisor
Plumber,Journeyman plumber,Plumbing supervisor
Licensed electrician,Commissioning specialist - electrical,Electrician,Assistant/Apprentice[200%]
Licensed electrician,Commissioning specialist - electrical,Electrician,Assistant/Apprentice[200%]
Licensed electrician,Commissioning specialist - electrical,Electrician,Assistant/Apprentice[200%]
Licensed electrician,Commissioning specialist - electrical,Electrician,Assistant/Apprentice[200%]
Licensed electrician,Commissioning specialist - electrical,Electrician,Assistant/Apprentice[200%]
Power systems controller,Sytems Engineer,Controls system specialist,Sprinkler fitter,F
Fire alarm technician,Fire alarm supervisor,Fire alarm aassistance/ appprentice[2
HVAC Engineer,Commissioning engineer,HVAC technician,HVAC apprentice/as
HVAC Engineer,Commissioning engineer,HVAC technician,HVAC apprentic
HVAC Engineer,Commissioning engineer,HVAC technician,HVAC appr
Highway construction crew,Crew members for asphalt paving,Asphalt roller
Signage installer,Signage designer
Highway construction crew,Asphalt roller,Crew members for asphalt paving
Test Technicians,Tester (Intern),Construction materials field testing technici
Test Technicians,Tester (Intern),Construction materials field testing technici
Test Technicians,Tester (Intern),Construction materials field testing technic
Test Technicians,Tester (Intern),Construction materials field testing technic
Test Technicians,Tester (Intern),Construction materials field testing technic
Test Technicians,Tester (Intern),Construction materials field testing techni
Test Technicians,Tester (Intern),Construction materials field testing techni
Test Technicians,Tester (Intern),Construction materials field testing techni
Test Technicians,Tester (Intern),Construction materials field testing techn
Test Technicians,Tester (Intern),Construction materials field testing techn
MeP Inspector[10%],Construction inspector[10%],Inspector (Buildings)[10%]
MeP Inspector[10%],Construction inspector[10%],Inspector (Buildings)[10%
MeP Inspector[10%],Construction inspector[10%],Inspector (Buildings)[10%
MeP Inspector[10%],Construction inspector[10%],Inspector (Buildings)[10%]
MeP Inspector[10%],Construction inspector[10%],Inspector (Buildings)[10%
MeP Inspector[10%],Construction inspector[10%],Inspector (Buildings)[10%
MeP Inspector[10%],Construction inspector[10%],Inspector (Buildings)[10%
MeP Inspector[10%],Construction inspector[10%],Inspector (Buildings)[10%
MeP Inspector[10%],Construction inspector[10%],Inspector (Buildings)[10%
MeP Inspector[10%],Construction inspector[10%],Inspector (Buildings)[10%
Sep Nov Jan Mar May Jul Sep Nov Jan Mar May Jul Sep Nov Jan Mar May Jul Sep Nov Jan Mar
Qtr 3, 2018 Qtr 1, 2019 Qtr 3, 2019 Qtr 1, 2020 Qtr 3, 2020 Qtr 1, 2021 Qtr 3, 2021 Qtr 1, 2022
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide
1 out of 23
Related Documents

Your All-in-One AI-Powered Toolkit for Academic Success.
 +13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
Copyright © 2020–2025 A2Z Services. All Rights Reserved. Developed and managed by ZUCOL.