System Analysis and Design Project: Allhomes and iTech Case Study

Verified

Added on  2021/05/31

|6
|433
|70
Project
AI Summary
This project analyzes two case studies, Allhomes and iTech, focusing on system analysis and design principles. The Allhomes case study includes a work breakdown structure, task durations, and a Gantt chart illustrating the critical path for the project. The iTech case study also presents a work breakdown structure and Gantt chart, detailing task durations and dependencies. The project utilizes project management methodologies to demonstrate the planning, scheduling, and execution of tasks. The assignment includes visual representations such as diagrams and Gantt charts to illustrate project timelines and task relationships. The project also highlights the application of project management tools and techniques, providing insights into the practical aspects of system analysis and design in real-world scenarios. The project is supported by a bibliography that cites relevant sources in the field of project management.
Document Page
Running Head: SYSTEM ANALYSIS AND DESIGN
System Analysis and Design: Portfolio 1
Name of the Student
Name of the University
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
1SYSTEM ANALYSIS AND DESIGN
Question 1: Allhomes Company Case Study
Task 1
The work breakdown structure for the project is shown in the following diagram.
Figure 1: Work Breakdown Structure of the Project
(Source: Created by Author)
The tasks, durations and predecessors are shown in the following table.
Task Name Duration Start Finish Predecessors
Allhomes Company 16 days Thu 5/10/18 Thu 5/31/18
Phase 1 8 days Thu 5/10/18 Mon 5/21/18
Document Page
2SYSTEM ANALYSIS AND DESIGN
Review of All Applications 2 days Thu 5/10/18 Fri 5/11/18
Notify IT Team 1 day Mon 5/14/18 Mon 5/14/18 2
Set Up Interview Schedule 5 days Tue 5/15/18 Mon 5/21/18 3
Phase 2 7 days Tue 5/22/18 Wed 5/30/18
Prepare Set of Interview
Questions
2 days Tue 5/22/18 Wed 5/23/18 4
Conduct Interviews 5 days Thu 5/24/18 Wed 5/30/18 6
Phase 3 1 day Thu 5/31/18 Thu 5/31/18
Selection of Candidate 1 day Thu 5/31/18 Thu 5/31/18 7
Task 2
The start and finish dates of each task is shown in the following diagram along with the
critical path marked in red within the Gantt chart.
Document Page
3SYSTEM ANALYSIS AND DESIGN
Figure 2: Critical Path and Task Start-Finish Dates
(Source: Created by Author)
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
4SYSTEM ANALYSIS AND DESIGN
Question 2: iTech Company Case Study
Task 1
The work breakdown structure is as follows.
iTech Company
Introduction Tour for Kim
Meet with Human
Resources
Tour Company
Offices
Meet with Users
Work on Necessary
Paperwork
Meet Team for
Introduction
Figure 3: Work Breakdown Structure
(Source: Created by Author)
The tasks, durations and the predecessors are as follows.
Task Name Duration Start Finish Predecessors
iTech Company 1 day Thu 5/10/18 Thu 5/10/18
Introduction Tour for Kim 1 day Thu 5/10/18 Thu 5/10/18
Document Page
5SYSTEM ANALYSIS AND DESIGN
Meet with Human
Resources
3 hrs Thu 5/10/18 Thu 5/10/18
Tour Company Offices 4 hrs Thu 5/10/18 Thu 5/10/18 2
Meet with Users 3 hrs Thu 5/10/18 Thu 5/10/18 2
Work on Necessary
Paperwork
2 hrs Thu 5/10/18 Thu 5/10/18 2
Meet Team for
Introduction
1 hr Thu 5/10/18 Thu 5/10/18 3,4,5
Task 2
The start and finish dates of each task is shown in the following diagram along with the
critical path marked in red within the Gantt chart.
ID Task
Mode
Task Name Duration Start Finish
0 iTech Company 1 day Thu 5/10/18Thu 5/10/18
1 Introduction
Tour for Kim
1 day Thu
5/10/18
Thu
5/10/18
2 Meet with
Human
Resources
3 hrs Thu
5/10/18
Thu
5/10/18
3 Tour Company Offi ces4 hrs Thu 5/10/18Thu 5/10/18
4 Meet with Users3 hrs Thu 5/10/18Thu 5/10/18
5 Work on
Necessary
Paperwork
2 hrs Thu
5/10/18
Thu
5/10/18
6 Meet Team
for
Introduction
1 hr Thu
5/10/18
Thu
5/10/18
8 AM 10 AM 12 PM 2 PM 4 PM 6 PM 8 PM 10 PM 12 AM 2 AM 4 AM 6 AM 8 AM 10 AM 12 PM 2 PM 4 PM 6 PM
Thu May 10 Fri May 11
Figure 4: Critical Path and Task Start-Finish Dates
(Source: Created by Author)
chevron_up_icon
1 out of 6
circle_padding
hide_on_mobile
zoom_out_icon
[object Object]