OHS Risk Management Report: Demolition Project, Campbell
VerifiedAdded on  2023/06/04
|17
|3772
|248
Report
AI Summary
This report, prepared by a Project Manager from Arcadis Australia Pvt Ltd, details the demolition management plan for a single-storey building in Campbell, Australia, for Defence Housing Australia (DHA). The report emphasizes safety guidelines from Safework Australia, outlining the roles and responsibilities of the principal contractor, demolition contractors, asbestos assessors, and other involved parties. It addresses environmental hazards, including air and water quality, waste management, asbestos dust, and traffic control, while minimizing impacts on adjacent infrastructures and residents. The report covers risk management strategies, including managing underground services, operating machinery, and mitigating potential hazards from the demolition of the existing building and surrounding structures. It also discusses the importance of air quality control, asbestos dust management, and tree management, ensuring a safe and environmentally responsible demolition process. The report concludes with a focus on monitoring requirements and provides references to relevant standards and guidelines.

Running Head: Demolition 0
Principal of OHS Risk Management
Demolition
Student details
10/18/2018
Principal of OHS Risk Management
Demolition
Student details
10/18/2018
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Demolition 1
Executive Summary
This report is prepared by me, Project Manager of the Arcadis Australia Pvt Ltd, to carry out
demolition of a single-storey building in Campbell for construction of block of four units by
Minter Ellison as per appointed by Defence Housing Australia (DHA). Report will discuss
the management plan required to carry out the demolition work at the site with proper safety
measurements. Safety guidelines provided by Safework Australia will be followed for the
demolition of the building and this plan is prepared by following the guidelines by Safework.
Report will give the details of the principal contractors, demolition contractors, workers,
environmental consultants, asbestos assessors/removalist and other workers and contractors
needed for the completion of project. Guidelines needed for the safety of the environmental
hazards due to the demolition work like air quality, water quality, waste management, and
tree management, asbestos dust management will be discussed in the report. Effects of
demolition work on the adjacent infrastructures and how these effects can be minimised will
be given in the report. Rules for managing the traffic near the work site will be discussed so
residents in the work area would not face any problem due to the project and hazards and
risks associated with the demolition can be minimised on the health and safety of working
personnel and residents near the site.
Executive Summary
This report is prepared by me, Project Manager of the Arcadis Australia Pvt Ltd, to carry out
demolition of a single-storey building in Campbell for construction of block of four units by
Minter Ellison as per appointed by Defence Housing Australia (DHA). Report will discuss
the management plan required to carry out the demolition work at the site with proper safety
measurements. Safety guidelines provided by Safework Australia will be followed for the
demolition of the building and this plan is prepared by following the guidelines by Safework.
Report will give the details of the principal contractors, demolition contractors, workers,
environmental consultants, asbestos assessors/removalist and other workers and contractors
needed for the completion of project. Guidelines needed for the safety of the environmental
hazards due to the demolition work like air quality, water quality, waste management, and
tree management, asbestos dust management will be discussed in the report. Effects of
demolition work on the adjacent infrastructures and how these effects can be minimised will
be given in the report. Rules for managing the traffic near the work site will be discussed so
residents in the work area would not face any problem due to the project and hazards and
risks associated with the demolition can be minimised on the health and safety of working
personnel and residents near the site.

Demolition 2
Contents
Executive Summary...................................................................................................................1
Introduction................................................................................................................................4
1. Project Information.........................................................................................................4
Management and overview:...............................................................................................4
Principal Contractor Details:..................................................................................................5
Details of persons at workplace with OHS Responsibilities:.................................................5
Demolition Contractors:.....................................................................................................5
Asbestos Assessor:.............................................................................................................5
Asbestos Removalist:.........................................................................................................6
Scope of Work:......................................................................................................................6
Roles and Responsibilities.........................................................................................................6
Principal Contractor:..............................................................................................................6
Contractors:............................................................................................................................6
Workers:.................................................................................................................................7
People with specific OHS roles and responsibilities:............................................................7
Australian standards, Codes of Practice and other guidance (Worksafe)..............................7
Risk Management.......................................................................................................................8
Air quality..............................................................................................................................9
Asbestos Dust.......................................................................................................................10
Sediments/ Surface water.....................................................................................................10
Contents
Executive Summary...................................................................................................................1
Introduction................................................................................................................................4
1. Project Information.........................................................................................................4
Management and overview:...............................................................................................4
Principal Contractor Details:..................................................................................................5
Details of persons at workplace with OHS Responsibilities:.................................................5
Demolition Contractors:.....................................................................................................5
Asbestos Assessor:.............................................................................................................5
Asbestos Removalist:.........................................................................................................6
Scope of Work:......................................................................................................................6
Roles and Responsibilities.........................................................................................................6
Principal Contractor:..............................................................................................................6
Contractors:............................................................................................................................6
Workers:.................................................................................................................................7
People with specific OHS roles and responsibilities:............................................................7
Australian standards, Codes of Practice and other guidance (Worksafe)..............................7
Risk Management.......................................................................................................................8
Air quality..............................................................................................................................9
Asbestos Dust.......................................................................................................................10
Sediments/ Surface water.....................................................................................................10
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

Demolition 3
Tree Management.................................................................................................................10
Waste Management..............................................................................................................11
Vibration..............................................................................................................................11
Traffic Management.............................................................................................................12
Monitoring Requirements........................................................................................................12
Conclusion................................................................................................................................13
Reference..................................................................................................................................14
Tree Management.................................................................................................................10
Waste Management..............................................................................................................11
Vibration..............................................................................................................................11
Traffic Management.............................................................................................................12
Monitoring Requirements........................................................................................................12
Conclusion................................................................................................................................13
Reference..................................................................................................................................14
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Demolition 4
Introduction
I as a Project Manager for the demolition work under Arcadis Australia am responsible for
the entire work related to the demolition. In this report I am presenting the company details,
details of other workers and contractors required to carry out the demolition work. This report
will also discuss about the safety guidelines for the demolition work given by Safework
Australia for eliminating health and safety risks or hazards.
Project Information
Management and overview: Arcadis Australia Pacific Pvt Ltd has been given a task of
preparing a demolition management plan (DMP) of an existing single storey building on the
site located in Campbell, by the Defence Housing Australia (DHA). The Principal Contractor
will be responsible for the implementation of the DMP prepared by the Arcadis Australia
Pacific Pvt Ltd. The objective of the DMP should be focused on the measures to ensure that
the entire demolition work is carried out without any adverse effect on the environment and
the surroundings around the site. Its main aim is to complete the work without any hazards in
the vicinity of the work area.
The existing building is located in the Campbell. It is a single storey building built in 1930s
and later extended in the late 1950s with cement sheeting. A garage and shed were also built
with cement. It also has a concrete drive, two old oil drums, which are now empty and a
strong oily smell is all over in the area.
Introduction
I as a Project Manager for the demolition work under Arcadis Australia am responsible for
the entire work related to the demolition. In this report I am presenting the company details,
details of other workers and contractors required to carry out the demolition work. This report
will also discuss about the safety guidelines for the demolition work given by Safework
Australia for eliminating health and safety risks or hazards.
Project Information
Management and overview: Arcadis Australia Pacific Pvt Ltd has been given a task of
preparing a demolition management plan (DMP) of an existing single storey building on the
site located in Campbell, by the Defence Housing Australia (DHA). The Principal Contractor
will be responsible for the implementation of the DMP prepared by the Arcadis Australia
Pacific Pvt Ltd. The objective of the DMP should be focused on the measures to ensure that
the entire demolition work is carried out without any adverse effect on the environment and
the surroundings around the site. Its main aim is to complete the work without any hazards in
the vicinity of the work area.
The existing building is located in the Campbell. It is a single storey building built in 1930s
and later extended in the late 1950s with cement sheeting. A garage and shed were also built
with cement. It also has a concrete drive, two old oil drums, which are now empty and a
strong oily smell is all over in the area.

Demolition 5
Demolition of House
Principal Contractor Details: Principal contractor has control over the construction
phase of the project (HealthandSafetyExecutive, 2014). Here Minter Ellison Pvt Ltd is
appointed as principal contractor for the demolition of the existing building and the
construction of a four block unit in the suburban area by Defence Housing Australia (DHA).
Minter elision is providing engineering services for the construction of the infrastructures in
Australia. The company was established in 1995 and its head office is located in Sydney,
Australia.
Details of persons at workplace with OHS Responsibilities:
Demolition Contractors: Arcadis Australia Pacific Pvt Ltd is given the responsibility of
demolition of the existing building by the DHA. Arcadis Australia is a professionally
managed organization. It was established in 2000, and has been providing services related to
the infrastructure, mining and construction since then. Arcadis offers implosion and
demolition of all structures and buildings of residence, commercial and industrial.
Asbestos Assessor: SESA stands for Safety & Environmental Services Australia are
appointed for the asbestos assessor for demolition work. It is a team of management
Demolition of House
Principal Contractor Details: Principal contractor has control over the construction
phase of the project (HealthandSafetyExecutive, 2014). Here Minter Ellison Pvt Ltd is
appointed as principal contractor for the demolition of the existing building and the
construction of a four block unit in the suburban area by Defence Housing Australia (DHA).
Minter elision is providing engineering services for the construction of the infrastructures in
Australia. The company was established in 1995 and its head office is located in Sydney,
Australia.
Details of persons at workplace with OHS Responsibilities:
Demolition Contractors: Arcadis Australia Pacific Pvt Ltd is given the responsibility of
demolition of the existing building by the DHA. Arcadis Australia is a professionally
managed organization. It was established in 2000, and has been providing services related to
the infrastructure, mining and construction since then. Arcadis offers implosion and
demolition of all structures and buildings of residence, commercial and industrial.
Asbestos Assessor: SESA stands for Safety & Environmental Services Australia are
appointed for the asbestos assessor for demolition work. It is a team of management
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

Demolition 6
environmental consultants, scientists, OHS consultants, engineers, occupational hygienists
and inspectors. The team is specialised in workplace health and safety (WHS), property
safety, risk management and occupational hygiene. It is based in Sydney but providing
services in all over Australia (SESA, 2018).
Asbestos Removalist: For the removal of asbestos ‘Asbestos Removals Australia (ARA)
are hired. It is a Queensland-based company that provides services of asbestos removals
throughout the Australia. It has extensive experience in removing asbestos safely and
effectively. It also has license to transport the asbestos waste (ARA, 2018).
Scope of Work: The objective of this assessment is to providing a safe workplace to the
workers, ensuring proper health conditions of the site workers and elimination of risks to the
neighbouring residence. This assessment will provide guidelines for the implementation of
demolition work at any site and ensuring safety of the people in the vicinity of the work area
and effectively manage and reduce the potential impact on the environment.
Roles and Responsibilities
Principal Contractor: This DMP will be implemented by the principal contractor. The
roles of the principal contractor includes the watching performance of the work in accordance
to administrative requirements, all the documentation related to the demolition plan,
monitoring and reporting operation and post demolition requirements (HSE, 2015).
Contractors: Demolition Contractors implement relevant components needed for the task
to carry out. Their job is to report all the environmental risks, hazards and misses to the
principal contractor immediately and also providing safety measures in association with
environmental incidents (Safeworkaustralia, 2012).
environmental consultants, scientists, OHS consultants, engineers, occupational hygienists
and inspectors. The team is specialised in workplace health and safety (WHS), property
safety, risk management and occupational hygiene. It is based in Sydney but providing
services in all over Australia (SESA, 2018).
Asbestos Removalist: For the removal of asbestos ‘Asbestos Removals Australia (ARA)
are hired. It is a Queensland-based company that provides services of asbestos removals
throughout the Australia. It has extensive experience in removing asbestos safely and
effectively. It also has license to transport the asbestos waste (ARA, 2018).
Scope of Work: The objective of this assessment is to providing a safe workplace to the
workers, ensuring proper health conditions of the site workers and elimination of risks to the
neighbouring residence. This assessment will provide guidelines for the implementation of
demolition work at any site and ensuring safety of the people in the vicinity of the work area
and effectively manage and reduce the potential impact on the environment.
Roles and Responsibilities
Principal Contractor: This DMP will be implemented by the principal contractor. The
roles of the principal contractor includes the watching performance of the work in accordance
to administrative requirements, all the documentation related to the demolition plan,
monitoring and reporting operation and post demolition requirements (HSE, 2015).
Contractors: Demolition Contractors implement relevant components needed for the task
to carry out. Their job is to report all the environmental risks, hazards and misses to the
principal contractor immediately and also providing safety measures in association with
environmental incidents (Safeworkaustralia, 2012).
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Demolition 7
Workers: Duties of workers is to take care of their own safety and health. It is also their job
to take care of health and safety of other workers and persons in the vicinity of work.
Workers need to follow all the rules, instructions provided them regarding safe work and
must cooperate with procedures and policies related to the safety at the workplace (Victoria,
2015).
People with specific OHS roles and responsibilities:
Roles of environmental consultant in accordance with this DMP includes providing
information to the principal contractor related to environmental issues linked with the work,
management of all the environmental impacts linked with the project, identify risks and
issues with the work and implementation of corrective measures for the environmental
incidents (Ahrens, 2018).
Asbestos assessor and removalist job is to providing sufficient advices to the principal
contractor about the hazard materials and asbestos present in the work area (SESA, 2018).
They monitor the asbestos fibres when the elimination for them is on-going. And after the
clearance of asbestos, they conduct an inspection of the site to ensure all the corrective
measures and issue a clearance certificate (ARA, 2018).
Australian standards, Codes of Practice and other guidance (Worksafe)
Work health and safety Act proposed code of practise for regulation of safety and health risk
related with demolition work under section 274. The code of practice was developed by Safe
Work Australia under the council of government of Australia. This code provides guidance to
manage the safety and health risks while conducting the demolition work. This code is
applicable to all the types of demolition work (Safeworkaustralia, 2012). The code of practise
provides guidance for demolition contractors as well as to the principal contractors.
Workers: Duties of workers is to take care of their own safety and health. It is also their job
to take care of health and safety of other workers and persons in the vicinity of work.
Workers need to follow all the rules, instructions provided them regarding safe work and
must cooperate with procedures and policies related to the safety at the workplace (Victoria,
2015).
People with specific OHS roles and responsibilities:
Roles of environmental consultant in accordance with this DMP includes providing
information to the principal contractor related to environmental issues linked with the work,
management of all the environmental impacts linked with the project, identify risks and
issues with the work and implementation of corrective measures for the environmental
incidents (Ahrens, 2018).
Asbestos assessor and removalist job is to providing sufficient advices to the principal
contractor about the hazard materials and asbestos present in the work area (SESA, 2018).
They monitor the asbestos fibres when the elimination for them is on-going. And after the
clearance of asbestos, they conduct an inspection of the site to ensure all the corrective
measures and issue a clearance certificate (ARA, 2018).
Australian standards, Codes of Practice and other guidance (Worksafe)
Work health and safety Act proposed code of practise for regulation of safety and health risk
related with demolition work under section 274. The code of practice was developed by Safe
Work Australia under the council of government of Australia. This code provides guidance to
manage the safety and health risks while conducting the demolition work. This code is
applicable to all the types of demolition work (Safeworkaustralia, 2012). The code of practise
provides guidance for demolition contractors as well as to the principal contractors.

Demolition 8
Risk Management
Services included at the work site where demolition is to be done are electricity, gas,
telephone and water. These could be hazardous to the health and safety of workers and the
people working in the vicinity of work site. As a project manager, it will be my first priority
to ensure the health and safety of people working at the work site. These services are come
into underground services. Safe work code of practice has provided guidelines for managing
underground services (Worksafe, 2016). It is the responsibility of Arcadis contractor to
minimise the risk associated with excavation near services. Information about the buried
services from service owner will be obtained. Further, to trace the underground services, pipe
locating devices will be used in conjunction with information of cable plans. After that
digging process will be started by using safe digging practice. Before any excavation is
carried out, trial holes are essential by hand excavation. Hand digging will be done till all the
services have been found. For hand digging proper hand tools will be used like spades and
shovels, picks, pins or forks and so on (DepartmentofLabour, 2002). Once underground
services will be uncovered, these will be identified correctly by using the techniques of
colours for pipes, duct and cables and variety of materials. Gas pipes, telecommunication
cables, water pipes and electricity cables may be of black colour. Any black pipe or cable is
assumed to be live electricity line or gas pipe until proved it is not
(HealthandSafetyExecutive, 2014).
Operating Machinery used for the demolition work includes 20 tonne excavator, skid steer
loader and semi tipper. Personnel working in the vicinity of heavy equipment may have risk
of physical injuries. Hence, proper guidelines will be needed to the personnel working near
heavy equipment. Personnel must be aware about their position in relation to operating
machinery. Without the knowledge of the operator, no one should walk behind or to the side
of operating machinery (OfficeofIndustrialrelations, 2015). It should be not assumed that the
Risk Management
Services included at the work site where demolition is to be done are electricity, gas,
telephone and water. These could be hazardous to the health and safety of workers and the
people working in the vicinity of work site. As a project manager, it will be my first priority
to ensure the health and safety of people working at the work site. These services are come
into underground services. Safe work code of practice has provided guidelines for managing
underground services (Worksafe, 2016). It is the responsibility of Arcadis contractor to
minimise the risk associated with excavation near services. Information about the buried
services from service owner will be obtained. Further, to trace the underground services, pipe
locating devices will be used in conjunction with information of cable plans. After that
digging process will be started by using safe digging practice. Before any excavation is
carried out, trial holes are essential by hand excavation. Hand digging will be done till all the
services have been found. For hand digging proper hand tools will be used like spades and
shovels, picks, pins or forks and so on (DepartmentofLabour, 2002). Once underground
services will be uncovered, these will be identified correctly by using the techniques of
colours for pipes, duct and cables and variety of materials. Gas pipes, telecommunication
cables, water pipes and electricity cables may be of black colour. Any black pipe or cable is
assumed to be live electricity line or gas pipe until proved it is not
(HealthandSafetyExecutive, 2014).
Operating Machinery used for the demolition work includes 20 tonne excavator, skid steer
loader and semi tipper. Personnel working in the vicinity of heavy equipment may have risk
of physical injuries. Hence, proper guidelines will be needed to the personnel working near
heavy equipment. Personnel must be aware about their position in relation to operating
machinery. Without the knowledge of the operator, no one should walk behind or to the side
of operating machinery (OfficeofIndustrialrelations, 2015). It should be not assumed that the
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

Demolition 9
operator knows about their position. Minimum distance of two meter should be maintained
from the operating machinery. Heavy operating machinery may produce high noise which is
not likely for long term. Hence, use of earplugs and earmuffs should be considered in high
noise situation (OfficeofIndustrialrelations, 2015).
Here, demolition of a single storey building that was built in 1930s and was extended in late
150s with cement sheeting needs to done. There is also a garage and shed of the material is
present which is also needed to be demolished. On one side of the site is a childcare centre, at
the rear side of the site there is a primary school oval and on the other side of the site there is
two-storey residence. The fence along this boundary is very dilapidated and looks ready to
fall. On the front side there is a fire hydrant and two large trees. And the opposite side of the
street is a milk bar with parking of five cars. Hence, a plan needed for the demolition will
consider these conditions. Potential impact of demolition on air quality, surface water,
asbestos dust, sediments and tree management all will be considered in the demolition plan
(NCA, 2017).
Air quality
Emissions from asbestos dust, soils, plant and equipment and dust produced during
demolition work will impact the air quality. As there are two oil drums which are now empty
but the stains of oil are on the ground and there is strong oily smell in the area. Therefore,
under the supervision of principal contractor and the environmental consultant, odour
suppressant will be managed. The objective of this management is to eliminate and minimise
the effects of the odours and the dust on the environment, health of workers in the vicinity of
the site and the residents around the site (Gunton, 2017). Actions that will be taken in this
process include use of sealed cabins, materials containing asbestos remain moist, covering of
stock piles, residents in the vicinity of the work must be informed in prior of potential dust
operator knows about their position. Minimum distance of two meter should be maintained
from the operating machinery. Heavy operating machinery may produce high noise which is
not likely for long term. Hence, use of earplugs and earmuffs should be considered in high
noise situation (OfficeofIndustrialrelations, 2015).
Here, demolition of a single storey building that was built in 1930s and was extended in late
150s with cement sheeting needs to done. There is also a garage and shed of the material is
present which is also needed to be demolished. On one side of the site is a childcare centre, at
the rear side of the site there is a primary school oval and on the other side of the site there is
two-storey residence. The fence along this boundary is very dilapidated and looks ready to
fall. On the front side there is a fire hydrant and two large trees. And the opposite side of the
street is a milk bar with parking of five cars. Hence, a plan needed for the demolition will
consider these conditions. Potential impact of demolition on air quality, surface water,
asbestos dust, sediments and tree management all will be considered in the demolition plan
(NCA, 2017).
Air quality
Emissions from asbestos dust, soils, plant and equipment and dust produced during
demolition work will impact the air quality. As there are two oil drums which are now empty
but the stains of oil are on the ground and there is strong oily smell in the area. Therefore,
under the supervision of principal contractor and the environmental consultant, odour
suppressant will be managed. The objective of this management is to eliminate and minimise
the effects of the odours and the dust on the environment, health of workers in the vicinity of
the site and the residents around the site (Gunton, 2017). Actions that will be taken in this
process include use of sealed cabins, materials containing asbestos remain moist, covering of
stock piles, residents in the vicinity of the work must be informed in prior of potential dust
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Demolition 10
impacts. It would be make sure that there should be no complaints from neighbouring
residents and surrounding businesses. As a project manager I will evaluate the air quality
myself.
Asbestos Dust
Mechanical removal of building materials, earth disturbance due to vehicle movement and
demolition over asbestos impacted soil generates asbestos dust. This generation of the
asbestos dust should be prevented and its impact should be minimised. The action plan for
this management plan is use of water spray for dust suppressant, after finishing of earthworks
the area should be covered with plastic sheeting, use of sealed cabins on truck entering and
excavation equipment (Queenslandgovernment, 2018). I will evaluate the air quality along
with environmental consultant.
Sediments/ Surface water
As the demolition work is to be carried out in the residential area where surface water is
present, so the impact from sediments. Main objective of this management is to avoid impact
on the water quality in drains and surface waters, minimise soil migration to surface waters
and drains. Management plan for sediment control includes use of sediment control structure
before commencement of works (EPA, 2017). It is will be the responsibility of site
contractors to check the increase in the sediment and as a project manager I will be
responsible for ensuring that the trained and qualified staffs are monitoring the program.
Tree Management
As there are two trees at the front side of the site, hence a tree management plan is needed as
per the tree management plan 2011. The objective of this plan is to avoid the damage to the
regulated trees, minimising soil damage and avoiding impact to ecological habitats. The tree
management plan includes the fencing around the regulated trees will be installed. Site
impacts. It would be make sure that there should be no complaints from neighbouring
residents and surrounding businesses. As a project manager I will evaluate the air quality
myself.
Asbestos Dust
Mechanical removal of building materials, earth disturbance due to vehicle movement and
demolition over asbestos impacted soil generates asbestos dust. This generation of the
asbestos dust should be prevented and its impact should be minimised. The action plan for
this management plan is use of water spray for dust suppressant, after finishing of earthworks
the area should be covered with plastic sheeting, use of sealed cabins on truck entering and
excavation equipment (Queenslandgovernment, 2018). I will evaluate the air quality along
with environmental consultant.
Sediments/ Surface water
As the demolition work is to be carried out in the residential area where surface water is
present, so the impact from sediments. Main objective of this management is to avoid impact
on the water quality in drains and surface waters, minimise soil migration to surface waters
and drains. Management plan for sediment control includes use of sediment control structure
before commencement of works (EPA, 2017). It is will be the responsibility of site
contractors to check the increase in the sediment and as a project manager I will be
responsible for ensuring that the trained and qualified staffs are monitoring the program.
Tree Management
As there are two trees at the front side of the site, hence a tree management plan is needed as
per the tree management plan 2011. The objective of this plan is to avoid the damage to the
regulated trees, minimising soil damage and avoiding impact to ecological habitats. The tree
management plan includes the fencing around the regulated trees will be installed. Site

Demolition 11
contractors will watch any damage to the regulated trees (OxfordBrookesUniversity, 2014).
And as a project manager I will be responsible for the monitoring program for the tree
management.
Waste Management
Waste generated during the demolition work needs to be managed properly. Appropriate
disposal of waste is to be ensured. Objective of waste management is to minimise its impact
on the environment. Health risk is associated with dust generation and contaminated soil
exposure, hence waste management plan is must. Action plan that needs to be implemented
for the waste management include a spill clean-up kit should be there where bulk fuel is
being transferred; transport of soil is to be done with trucks fitted with cover tarpaulins
(NCA, 2017). Regular observations will be made by me and the principal contractor will
ensure the proper implementation of the monitoring program.
Vibration
As the work site is surrounded by infrastructures of a childcare centre at one side, a primary
school oval on the rear side and a two-storey residence on the other side and the fence along
this side looks ready to fall, hence because of the close proximity of the structures, it is the
responsibility of the principal contractor to consider a structural integrity assessment by a
specialised consultant or a qualified engineer of the buildings within proximity of the work
area. Its objective is to minimise the effects on the adjacent buildings due to the project
(Designingbuildingswiki, 2018). Action need to be taken for the prevention of adjacent
structures will include an inspection to access the potential damage to the surrounded
structures associated with vibration impacts. Therefore, to minimise the vibration effects
appropriate size machinery and equipment will be used. Machinery used is such that over-
revving and over-loading would be prevented and also reduce vibration generation. As a
contractors will watch any damage to the regulated trees (OxfordBrookesUniversity, 2014).
And as a project manager I will be responsible for the monitoring program for the tree
management.
Waste Management
Waste generated during the demolition work needs to be managed properly. Appropriate
disposal of waste is to be ensured. Objective of waste management is to minimise its impact
on the environment. Health risk is associated with dust generation and contaminated soil
exposure, hence waste management plan is must. Action plan that needs to be implemented
for the waste management include a spill clean-up kit should be there where bulk fuel is
being transferred; transport of soil is to be done with trucks fitted with cover tarpaulins
(NCA, 2017). Regular observations will be made by me and the principal contractor will
ensure the proper implementation of the monitoring program.
Vibration
As the work site is surrounded by infrastructures of a childcare centre at one side, a primary
school oval on the rear side and a two-storey residence on the other side and the fence along
this side looks ready to fall, hence because of the close proximity of the structures, it is the
responsibility of the principal contractor to consider a structural integrity assessment by a
specialised consultant or a qualified engineer of the buildings within proximity of the work
area. Its objective is to minimise the effects on the adjacent buildings due to the project
(Designingbuildingswiki, 2018). Action need to be taken for the prevention of adjacent
structures will include an inspection to access the potential damage to the surrounded
structures associated with vibration impacts. Therefore, to minimise the vibration effects
appropriate size machinery and equipment will be used. Machinery used is such that over-
revving and over-loading would be prevented and also reduce vibration generation. As a
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide
1 out of 17
Related Documents

Your All-in-One AI-Powered Toolkit for Academic Success.
 +13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
Copyright © 2020–2025 A2Z Services. All Rights Reserved. Developed and managed by ZUCOL.