International Project Management: ATA Solar Project Risk Analysis
VerifiedAdded on 2019/10/30
|9
|1476
|329
Report
AI Summary
This report presents a comprehensive risk management plan for the ATA's East Timor solar project. It begins with an overview of the project, its scope, and the identified risks and challenges, including issues related to information gathering, transportation, communication, division of roles, relationships with local and external organizations, labor skills, language barriers, local suppliers, and health and safety. The report outlines a detailed risk management cycle, encompassing risk identification, assessment, resource management, and monitoring. A risk mitigation and priority action plan is provided, addressing each identified risk with specific strategies. Stakeholder considerations and the project approval process are also discussed, alongside a list of references. The report aims to provide Google, the project sponsor, with a robust framework for managing project risks and ensuring successful project completion.

International Project Management
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

International Project Management
Contents
1. Vision of the case study:................................................................................................................2
2. Overview:......................................................................................................................................2
3. Scope of the project:.....................................................................................................................2
4. Project risks and challenges:..........................................................................................................2
5. Risks Management plan:................................................................................................................3
6. Risk Mitigation and Priority action Plan:........................................................................................5
7. Stakeholders:.................................................................................................................................7
8. Project Approval:...........................................................................................................................7
9. Sign Off:.........................................................................................................................................7
10. References:................................................................................................................................7
1
Contents
1. Vision of the case study:................................................................................................................2
2. Overview:......................................................................................................................................2
3. Scope of the project:.....................................................................................................................2
4. Project risks and challenges:..........................................................................................................2
5. Risks Management plan:................................................................................................................3
6. Risk Mitigation and Priority action Plan:........................................................................................5
7. Stakeholders:.................................................................................................................................7
8. Project Approval:...........................................................................................................................7
9. Sign Off:.........................................................................................................................................7
10. References:................................................................................................................................7
1

International Project Management
1. Vision of the case study:
The fund is raised by the Google to give support to the development of the ATA’s east Timor
solar project. The risks management plan is the initial requirement of the Google to sponsor
the project of ATA. The company is looking forward to design risk identification and
mitigation plan to fulfil the demand of the Google. The interview was arranged with the
owner of the project to focus on the current scenario.
2. Overview:
The sustainable technologies will be used for deploying the ATA’s east Timor solar project.
The synchronization between the activities, resources, skills, and availability of the material
should be managed to accomplish the project within the allocated time and budget.
3. Scope of the project:
The development of the risks identification and mitigation plan is the core concern of the
project. The cause of potential delay should be analysed in the starting phase of the project
development life cycle to provide fruitful result in the end of the project completion. The
logical and fact based assumption should be used for carrying over the project activities.
4. Project risks and challenges:
ATA’s east Timor solar project is equipped with some risks which should be given
consideration for developing proactive action plan or risks mitigation strategies.
Information gathering: “The data collected should be relevant and accurate for laying
down the business activities” (Ma, 2011). The improper use of research
methodologies tools can affect the working of the project.
Problem associated with the transportation of the goods: Lots of crucial time is wasted
in the transportation of the equipment. “The non-availability of the relevant
equipment on time can affect the working of the processes” (Moser, 2017).
Communication platform: The inefficiency in the communication platform and
integration of the employees can affect the on-time completion of the project.
2
1. Vision of the case study:
The fund is raised by the Google to give support to the development of the ATA’s east Timor
solar project. The risks management plan is the initial requirement of the Google to sponsor
the project of ATA. The company is looking forward to design risk identification and
mitigation plan to fulfil the demand of the Google. The interview was arranged with the
owner of the project to focus on the current scenario.
2. Overview:
The sustainable technologies will be used for deploying the ATA’s east Timor solar project.
The synchronization between the activities, resources, skills, and availability of the material
should be managed to accomplish the project within the allocated time and budget.
3. Scope of the project:
The development of the risks identification and mitigation plan is the core concern of the
project. The cause of potential delay should be analysed in the starting phase of the project
development life cycle to provide fruitful result in the end of the project completion. The
logical and fact based assumption should be used for carrying over the project activities.
4. Project risks and challenges:
ATA’s east Timor solar project is equipped with some risks which should be given
consideration for developing proactive action plan or risks mitigation strategies.
Information gathering: “The data collected should be relevant and accurate for laying
down the business activities” (Ma, 2011). The improper use of research
methodologies tools can affect the working of the project.
Problem associated with the transportation of the goods: Lots of crucial time is wasted
in the transportation of the equipment. “The non-availability of the relevant
equipment on time can affect the working of the processes” (Moser, 2017).
Communication platform: The inefficiency in the communication platform and
integration of the employees can affect the on-time completion of the project.
2
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

International Project Management
Division of roles and responsibilities: The inappropriate division of the responsibility
can raises the level of frustration in th working employees. The skills should be
measured for providing responsibility.
Relationship with local organization: The cultural difference is the core concern for
the enterprise which should be resolved to overcome the problem of conflicts.
External organization: The relationship with the external organization can affect the
sponsorship program of the project. The money and funds is the basic need for
completing the project on time.
Labour skills: The availability of the unskilled labour can affect the project
completion within the time limit.
Barrier of language: The language is the tool used for communication. The difference
in language can affect the working condition of the project which can leads to project
failure.
Local Supplier: “The local suppliers are not providing the raw material and other
resources required for the completion of the project” (Owens, 2010).
Health and safety issues: The working capability of the employees decreases with the
unhealthy and security issues associated with the working environment.
5. Risks Management plan:
We have discussed above the risks associated with the ATA’s east Timor solar project. The
focus should be given on managing risks, developing the risks mitigation plan, and setting out
priorities associated with the risks identified.
Stages of the Risk management cycle Activities
Phase of risks identification Analysis of the physical site associated with
the ATA’s east Timor solar project.
Identification of risks associated with the
transportation, communication, language,
local supplier, external organization, and
others
Assessment of risks “The identification of risks leads to setting
the priority to the risks identified” (Muller,
2015). The priority should be set according to
3
Division of roles and responsibilities: The inappropriate division of the responsibility
can raises the level of frustration in th working employees. The skills should be
measured for providing responsibility.
Relationship with local organization: The cultural difference is the core concern for
the enterprise which should be resolved to overcome the problem of conflicts.
External organization: The relationship with the external organization can affect the
sponsorship program of the project. The money and funds is the basic need for
completing the project on time.
Labour skills: The availability of the unskilled labour can affect the project
completion within the time limit.
Barrier of language: The language is the tool used for communication. The difference
in language can affect the working condition of the project which can leads to project
failure.
Local Supplier: “The local suppliers are not providing the raw material and other
resources required for the completion of the project” (Owens, 2010).
Health and safety issues: The working capability of the employees decreases with the
unhealthy and security issues associated with the working environment.
5. Risks Management plan:
We have discussed above the risks associated with the ATA’s east Timor solar project. The
focus should be given on managing risks, developing the risks mitigation plan, and setting out
priorities associated with the risks identified.
Stages of the Risk management cycle Activities
Phase of risks identification Analysis of the physical site associated with
the ATA’s east Timor solar project.
Identification of risks associated with the
transportation, communication, language,
local supplier, external organization, and
others
Assessment of risks “The identification of risks leads to setting
the priority to the risks identified” (Muller,
2015). The priority should be set according to
3
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

International Project Management
the magnitude of effect on the working
condition of the project. “The handling of the
risks with ease helps in improving decision
making proficiency of the manager”
(Kamane, 2014).
Resource management and development of
the plan
The on-time delivery of the resources helps
in resolving risks. “The proactive plans
should be developed to resolve the identified
risks in advanced” (Cabral, 2012).
Monitoring and controlling of the process The monitoring and control helps in
completing the project on-time with
minimum number of risks associated with it.
The following diagram shows the risks management cycle plan which helps in completing the
project within allocated time and budget.
The procedure of handling the risks and processes associated with the completion of the is
depicted in the figure below:
4
ATA solar
Project risks
management
plan
Risks
Identiication
Seeting of
priority to
risks
Division of
risks
Risks
analysis
plan
Creation of
responses
and
strategies
Risks mitigation
action plan
Risks
Monitoring
the magnitude of effect on the working
condition of the project. “The handling of the
risks with ease helps in improving decision
making proficiency of the manager”
(Kamane, 2014).
Resource management and development of
the plan
The on-time delivery of the resources helps
in resolving risks. “The proactive plans
should be developed to resolve the identified
risks in advanced” (Cabral, 2012).
Monitoring and controlling of the process The monitoring and control helps in
completing the project on-time with
minimum number of risks associated with it.
The following diagram shows the risks management cycle plan which helps in completing the
project within allocated time and budget.
The procedure of handling the risks and processes associated with the completion of the is
depicted in the figure below:
4
ATA solar
Project risks
management
plan
Risks
Identiication
Seeting of
priority to
risks
Division of
risks
Risks
analysis
plan
Creation of
responses
and
strategies
Risks mitigation
action plan
Risks
Monitoring

International Project Management
6. Risk Mitigation and Priority action Plan:
Identification
of risks
Identification
of
Probability
Identification
of Frequency
Setting
of
Priority
Risk Mitigation action plan
Good
Transportation
Low Weekly High The goods and resources
required for the project should
be made available by the local
organization and suppliers
Managing the
Communication
platform
High Periodic High Formal and informal
communication
Use of interpreter
Giving values to the culture of
the working people
Division of role High Monthly or Low The roles and responsibilities
5
6. Risk Mitigation and Priority action Plan:
Identification
of risks
Identification
of
Probability
Identification
of Frequency
Setting
of
Priority
Risk Mitigation action plan
Good
Transportation
Low Weekly High The goods and resources
required for the project should
be made available by the local
organization and suppliers
Managing the
Communication
platform
High Periodic High Formal and informal
communication
Use of interpreter
Giving values to the culture of
the working people
Division of role High Monthly or Low The roles and responsibilities
5
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

International Project Management
and
responsibilities
according to
requirement
should be provided according
to the skills of the employees.
“The responsibilities should be
changed periodically according
to the requirement of the
project” (Reddy, 2017). The
proper distribution helps in
overcoming the problem of
chaos and conflicts
Local Supplier Medium Periodic Low “They should be motivated to
provide the material on
demand” (Rao, 2014). The
demand should be raised in
advance to the local supplier
External
organization
Low Once Low “The collection of funds can be
raised by developing good and
health relationship with
external agencies and
organization” (Tooley, 2012)
Barrier of
language
Medium Daily Low The problem of language
barrier can be resolved with the
use of an Interpreter for
translation and to carry healthy
communication between the
two participating units.
Health and
safety of the
employees
High Periodic Mediu
m
The health and safety standards
should be developed for
resolving the health and safety
issues. The follow up of the
action plan should be
organized periodically.
6
and
responsibilities
according to
requirement
should be provided according
to the skills of the employees.
“The responsibilities should be
changed periodically according
to the requirement of the
project” (Reddy, 2017). The
proper distribution helps in
overcoming the problem of
chaos and conflicts
Local Supplier Medium Periodic Low “They should be motivated to
provide the material on
demand” (Rao, 2014). The
demand should be raised in
advance to the local supplier
External
organization
Low Once Low “The collection of funds can be
raised by developing good and
health relationship with
external agencies and
organization” (Tooley, 2012)
Barrier of
language
Medium Daily Low The problem of language
barrier can be resolved with the
use of an Interpreter for
translation and to carry healthy
communication between the
two participating units.
Health and
safety of the
employees
High Periodic Mediu
m
The health and safety standards
should be developed for
resolving the health and safety
issues. The follow up of the
action plan should be
organized periodically.
6
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

International Project Management
7. Stakeholders:
The consideration should be given on the participating stakeholders because the active
stakeholders helps in achieving fruitful result at the end of the project and helps in satisfying
their requirement. The key performance indicators should be used in the working culture to
measure the performance of the employees and motivate them with rewards. The solar project
should be completed within the period of 18 months by increasing the efficiency of the
stakeholders.
8. Project Approval:
o Approved
o Not approved
o Under consideration
9. Sign Off:
The project should be approved with the sign of the project sponsors.
10. References:
Cabral R. (2012). A Review of risk management in construction. Retrieved from
https://file.scirp.org/pdf/ME_2014041514072361.pdf
Kamane, S. (2014). Risk management in construction industry. Retrieved from
http://www.iosrjournals.org/iosr-jmce/papers/sicete(civil)-volume2/25.pdf
Ma, T. (2011). Project risks analysis of solar energy project delays in India. Retrieved from
http://search.ror.unisa.edu.au/media/researcharchive/open/9915909479901831/53108
456620001831
Moser, D. (2017). Best practice guidelines for risk identification, assessment, and mitigation.
Retrieved from
https://www.tuv.com/content-media-files/master-content/services/industrial-services/
pdf/tuv-rheinland-solar-bankability-final-report.pdf
Muller, G. (2015). Risks management and resolution strategies for establishing small
hydropower market. Retrieved from
7
7. Stakeholders:
The consideration should be given on the participating stakeholders because the active
stakeholders helps in achieving fruitful result at the end of the project and helps in satisfying
their requirement. The key performance indicators should be used in the working culture to
measure the performance of the employees and motivate them with rewards. The solar project
should be completed within the period of 18 months by increasing the efficiency of the
stakeholders.
8. Project Approval:
o Approved
o Not approved
o Under consideration
9. Sign Off:
The project should be approved with the sign of the project sponsors.
10. References:
Cabral R. (2012). A Review of risk management in construction. Retrieved from
https://file.scirp.org/pdf/ME_2014041514072361.pdf
Kamane, S. (2014). Risk management in construction industry. Retrieved from
http://www.iosrjournals.org/iosr-jmce/papers/sicete(civil)-volume2/25.pdf
Ma, T. (2011). Project risks analysis of solar energy project delays in India. Retrieved from
http://search.ror.unisa.edu.au/media/researcharchive/open/9915909479901831/53108
456620001831
Moser, D. (2017). Best practice guidelines for risk identification, assessment, and mitigation.
Retrieved from
https://www.tuv.com/content-media-files/master-content/services/industrial-services/
pdf/tuv-rheinland-solar-bankability-final-report.pdf
Muller, G. (2015). Risks management and resolution strategies for establishing small
hydropower market. Retrieved from
7

International Project Management
http://search.ror.unisa.edu.au/media/researcharchive/open/9915909479901831/53108
456620001831
Owens, J. (2010). Risk management. Retrieved from
http://agile.csc.ncsu.edu/SEMaterials/RiskManagement.pdf
Rao, R. (2014). A systematic framework of schedule risks management for power grid
engineering project. Retrieved from http://www.google.co.in/url?
sa=t&rct=j&q=Research%20paper%20odf%20on%20Risks%20management
%20cycle%20plan%20for%20the%20solar
%20project&source=web&cd=1&cad=rja&uact=8&ved=0ahUKEwibgJKN8J7WAh
WIpI8KHbdfAqkQFggoMAA&url=http://www.mdpi.com/2071-1050/6/10/6872/
pdf&usg=AFQjCNFJKRZJRZlIx_GLIYpelN_fnxwDAQ
Reddy, V. (2017). Risk management cycle or procedure. Retrieved from
https://www.simplilearn.com/risk-management-cycle-article
Tooley, W. (2012). Risk management hand book. Retrieved from
http://www.adelaide.edu.au/legalandrisk/docs/resources/Risk_Management_Handboo
k.pdf
8
http://search.ror.unisa.edu.au/media/researcharchive/open/9915909479901831/53108
456620001831
Owens, J. (2010). Risk management. Retrieved from
http://agile.csc.ncsu.edu/SEMaterials/RiskManagement.pdf
Rao, R. (2014). A systematic framework of schedule risks management for power grid
engineering project. Retrieved from http://www.google.co.in/url?
sa=t&rct=j&q=Research%20paper%20odf%20on%20Risks%20management
%20cycle%20plan%20for%20the%20solar
%20project&source=web&cd=1&cad=rja&uact=8&ved=0ahUKEwibgJKN8J7WAh
WIpI8KHbdfAqkQFggoMAA&url=http://www.mdpi.com/2071-1050/6/10/6872/
pdf&usg=AFQjCNFJKRZJRZlIx_GLIYpelN_fnxwDAQ
Reddy, V. (2017). Risk management cycle or procedure. Retrieved from
https://www.simplilearn.com/risk-management-cycle-article
Tooley, W. (2012). Risk management hand book. Retrieved from
http://www.adelaide.edu.au/legalandrisk/docs/resources/Risk_Management_Handboo
k.pdf
8
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide
1 out of 9
Related Documents
Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
Copyright © 2020–2026 A2Z Services. All Rights Reserved. Developed and managed by ZUCOL.