This project management assignment details the implementation of a website for Auzi Security Services, a company providing security services. The project aims to meet increasing demand through an online platform, with a budget of approximately $47,040 and a timeline of 80 days. The paper includes an executive summary, business case, project plan, and benefit review plan. It utilizes Work Breakdown Structure (WBS) to simplify complex tasks and project schedules to maintain timelines and resource allocation. Stakeholders include designers, developers, and a project manager who assigns responsibilities. The assignment identifies potential risks like budget estimation errors and improper management, proposing mitigation strategies. The project also includes a detailed cost breakdown, timescale, deliverables, and a Gantt chart. The ethical considerations and project quality maintenance are also discussed.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.

Running head: PROJECT MANAGEMENT
Project: Implementation of website for the Auzi security services company
Name of the Student
Name of the University
Author’s Note
Project: Implementation of website for the Auzi security services company
Name of the Student
Name of the University
Author’s Note
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.

1
PROJECT MANAGEMENT
Executive Summary
The paper mainly focuses on the implementation of a website for the Auzi security services. It is
identified that the company generally provides bodyguard security services to different
commercial buildings, providers as well as retail business. However, due to present economic as
well as political condition, there is an upswing in the requirement of services. In order to fulfil
the enhancing demand, the organization wants to implement a website. The company requires
minimum 80 days with the budget of around $47,040 in order to complete the implementation of
the project successfully.
It is identified that with the implementation of the website the organization can easily reach the
customers and can be able to meet their expectations as well as demands. Similarly, the
customers can book for the bodyguard services online whenever they need (Adeusi et al., 2014).
Thus, the implementation of the website for the Auzi security services is useful for both the
customers as well as for the organization.
The paper utilizes WBS as well as project schedule in order to reflect the project deliverables
costs as well as time that are needed for successfully executing the project. It is analyzed that
WBS is mainly utilized in the project in order to minimize various complicated activities of the
project as it generally breaks activities in simpler form (Badewi, 2016). WBS is found to be
quite useful for the project managers as they can be able to oversee tasks of the project more
effectively than the complex activities of the project. On the other hand, project schedule is
generally utilized in this project in order to keep the entire project on track by setting realistic
timeframe and by assigning resources appropriately.
The stakeholders who are involved in the project include designer, developer, project manager as
well as project planner. It is identified that the project manager allocates project responsibilities
PROJECT MANAGEMENT
Executive Summary
The paper mainly focuses on the implementation of a website for the Auzi security services. It is
identified that the company generally provides bodyguard security services to different
commercial buildings, providers as well as retail business. However, due to present economic as
well as political condition, there is an upswing in the requirement of services. In order to fulfil
the enhancing demand, the organization wants to implement a website. The company requires
minimum 80 days with the budget of around $47,040 in order to complete the implementation of
the project successfully.
It is identified that with the implementation of the website the organization can easily reach the
customers and can be able to meet their expectations as well as demands. Similarly, the
customers can book for the bodyguard services online whenever they need (Adeusi et al., 2014).
Thus, the implementation of the website for the Auzi security services is useful for both the
customers as well as for the organization.
The paper utilizes WBS as well as project schedule in order to reflect the project deliverables
costs as well as time that are needed for successfully executing the project. It is analyzed that
WBS is mainly utilized in the project in order to minimize various complicated activities of the
project as it generally breaks activities in simpler form (Badewi, 2016). WBS is found to be
quite useful for the project managers as they can be able to oversee tasks of the project more
effectively than the complex activities of the project. On the other hand, project schedule is
generally utilized in this project in order to keep the entire project on track by setting realistic
timeframe and by assigning resources appropriately.
The stakeholders who are involved in the project include designer, developer, project manager as
well as project planner. It is identified that the project manager allocates project responsibilities

2
PROJECT MANAGEMENT
to different stakeholders of the project so that they can engage in the project as per their expertise
and can be able successfully complete the project within the estimated budget as well as time
(Chih & Zwikael, 2015). The paper also illustrates the risks that are mainly associated with the
project.
The risks that are identified during the progress of the project mainly include improper budget
estimation, inappropriate management as well as difficulty in identifying required resources of
the project. It is analyzed that proper risk management strategies must be utilized in the project
in order to resolve the risks that are mainly associated with the project (Conforto et al., 2014).
The project manager implements number of risk mitigation strategies that are useful in resolving
or mitigating the risks as well as challenges that are generally associated with the project.
It is identified that the project manager suggests to analyze the market for getting idea about the
costs of various resources that are generally needed for completing the project. Proper market
analysis assists in estimating the proper budget for the project (Bromiley, McShane, Nair &
Rustambekov, 2015). In addition to this, it is analyzed that proper experienced project managers
must be hired within the project who will be able to execute the objectives as well as goals of the
project quite successfully as compared to inexperienced project managers.
In addition to this, it is analyzed that maintenance of project quality is very much important in
order to provide quality customer service to the clients. In order to maintain project quality it is
necessary to monitor the project on a regular basis (Chance & Brooks 2015). Weekly tracking of
project schedule not only executes the entire project within the estimated budget as well as time
but also assists analyzing any quality related risks so that the risks can be mitigated in the initial
stage without creating any negative impact on the project.
PROJECT MANAGEMENT
to different stakeholders of the project so that they can engage in the project as per their expertise
and can be able successfully complete the project within the estimated budget as well as time
(Chih & Zwikael, 2015). The paper also illustrates the risks that are mainly associated with the
project.
The risks that are identified during the progress of the project mainly include improper budget
estimation, inappropriate management as well as difficulty in identifying required resources of
the project. It is analyzed that proper risk management strategies must be utilized in the project
in order to resolve the risks that are mainly associated with the project (Conforto et al., 2014).
The project manager implements number of risk mitigation strategies that are useful in resolving
or mitigating the risks as well as challenges that are generally associated with the project.
It is identified that the project manager suggests to analyze the market for getting idea about the
costs of various resources that are generally needed for completing the project. Proper market
analysis assists in estimating the proper budget for the project (Bromiley, McShane, Nair &
Rustambekov, 2015). In addition to this, it is analyzed that proper experienced project managers
must be hired within the project who will be able to execute the objectives as well as goals of the
project quite successfully as compared to inexperienced project managers.
In addition to this, it is analyzed that maintenance of project quality is very much important in
order to provide quality customer service to the clients. In order to maintain project quality it is
necessary to monitor the project on a regular basis (Chance & Brooks 2015). Weekly tracking of
project schedule not only executes the entire project within the estimated budget as well as time
but also assists analyzing any quality related risks so that the risks can be mitigated in the initial
stage without creating any negative impact on the project.

3
PROJECT MANAGEMENT
Table of Contents
1. Business case...............................................................................................................................4
1.1 Description and rationale.......................................................................................................4
1.2 Expected benefits...................................................................................................................4
1.3 Costs, timescales....................................................................................................................4
1.4 Potential risks.........................................................................................................................8
1.5 Ethical issues.......................................................................................................................11
2. Project Plan................................................................................................................................12
2.1 Duration of the project.........................................................................................................12
2.2 Cost associated with project................................................................................................14
2.3 Deliverables and milestones of the project..........................................................................16
2.4 Delivery time of the millstones............................................................................................17
2.5 People and resources to meet the plan.................................................................................17
2.6 Control exerted within the project.......................................................................................18
2.7 Maintenance of quality........................................................................................................19
2.8 Risks in approach taken.......................................................................................................20
2.9 WBS.....................................................................................................................................21
2.10 Cash Flow..........................................................................................................................21
2.11 Resource allocation............................................................................................................22
2.12 Gantt chart.........................................................................................................................23
PROJECT MANAGEMENT
Table of Contents
1. Business case...............................................................................................................................4
1.1 Description and rationale.......................................................................................................4
1.2 Expected benefits...................................................................................................................4
1.3 Costs, timescales....................................................................................................................4
1.4 Potential risks.........................................................................................................................8
1.5 Ethical issues.......................................................................................................................11
2. Project Plan................................................................................................................................12
2.1 Duration of the project.........................................................................................................12
2.2 Cost associated with project................................................................................................14
2.3 Deliverables and milestones of the project..........................................................................16
2.4 Delivery time of the millstones............................................................................................17
2.5 People and resources to meet the plan.................................................................................17
2.6 Control exerted within the project.......................................................................................18
2.7 Maintenance of quality........................................................................................................19
2.8 Risks in approach taken.......................................................................................................20
2.9 WBS.....................................................................................................................................21
2.10 Cash Flow..........................................................................................................................21
2.11 Resource allocation............................................................................................................22
2.12 Gantt chart.........................................................................................................................23
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.

4
PROJECT MANAGEMENT
3. Benefit review plan....................................................................................................................24
3.1 Identification of benefits......................................................................................................24
Bibliography..................................................................................................................................26
PROJECT MANAGEMENT
3. Benefit review plan....................................................................................................................24
3.1 Identification of benefits......................................................................................................24
Bibliography..................................................................................................................................26

5
PROJECT MANAGEMENT
1. Business case
1.1 Description and rationale
The project mainly focuses on the “Auzi Security Services” company that was mainly
founded by Muhammad Shahzad Anjum. It is identified that the company mainly engages in
providing security guard services as well as referrals to various providers, retails business,
commercial buildings as well as for special event venues. Due to the current economic as well as
political condition, there is an upswing in general as well as outsources services. In order to meet
the growing demand, the company wants to implement a website.
1.2 Expected benefits
It is identified that implementation of a website for Auzi Security services is quite
beneficial. With the help of the website, the company can be able to expand its business by
providing proper services of body guards to the customers. The implementation of website
assists in generating more customers as it generally provides a global community. In addition to
this, 24*7 service is provided by the ecommerce website which assists in boosting the demand
for the services of the company as the customers can order for the services whenever they want.
1.3 Costs, timescales
Project cost
WBS Task Name Duration Cost
0
Implementation of website for Auzi
Security services company
86 days $49,680.00
1 Project planning phase 11 days $5,520.00
PROJECT MANAGEMENT
1. Business case
1.1 Description and rationale
The project mainly focuses on the “Auzi Security Services” company that was mainly
founded by Muhammad Shahzad Anjum. It is identified that the company mainly engages in
providing security guard services as well as referrals to various providers, retails business,
commercial buildings as well as for special event venues. Due to the current economic as well as
political condition, there is an upswing in general as well as outsources services. In order to meet
the growing demand, the company wants to implement a website.
1.2 Expected benefits
It is identified that implementation of a website for Auzi Security services is quite
beneficial. With the help of the website, the company can be able to expand its business by
providing proper services of body guards to the customers. The implementation of website
assists in generating more customers as it generally provides a global community. In addition to
this, 24*7 service is provided by the ecommerce website which assists in boosting the demand
for the services of the company as the customers can order for the services whenever they want.
1.3 Costs, timescales
Project cost
WBS Task Name Duration Cost
0
Implementation of website for Auzi
Security services company
86 days $49,680.00
1 Project planning phase 11 days $5,520.00

6
PROJECT MANAGEMENT
1.1
Conversation with project team
members
3 days $1,200.00
1.2 Development of project proposal 2 days $640.00
1.3 Creating agreement for project 3 days $2,160.00
1.4 Identifying stakeholders of the project 2 days $800.00
1.5 Approval of project plan 1 day $720.00
2 Web application design 25 days $11,800.00
2.1 Gathering ideas for initial stage 4 days $1,280.00
2.2 Client review 3 days $1,200.00
2.3 Revising the design of the project 5 days $3,000.00
2.4 Undertaking feasibility study 3 days $720.00
2.5 Analysing budget for the project 5 days $1,200.00
2.6 Undertaking meeting for project kick-off 4 days $4,000.00
2.7 Approval for final design 1 day $400.00
3 Coding 17 days $13,160.00
3.1 Prototype construction 3 days $3,480.00
3.2 Development of database 5 days $3,000.00
3.3 Validation of code 4 days $3,520.00
3.4 Cross-browser testing 3 days $840.00
3.5 Optimization 2 days $2,320.00
4 Web content build 2 days $1,760.00
4.1 Navigation structure 1 day $880.00
PROJECT MANAGEMENT
1.1
Conversation with project team
members
3 days $1,200.00
1.2 Development of project proposal 2 days $640.00
1.3 Creating agreement for project 3 days $2,160.00
1.4 Identifying stakeholders of the project 2 days $800.00
1.5 Approval of project plan 1 day $720.00
2 Web application design 25 days $11,800.00
2.1 Gathering ideas for initial stage 4 days $1,280.00
2.2 Client review 3 days $1,200.00
2.3 Revising the design of the project 5 days $3,000.00
2.4 Undertaking feasibility study 3 days $720.00
2.5 Analysing budget for the project 5 days $1,200.00
2.6 Undertaking meeting for project kick-off 4 days $4,000.00
2.7 Approval for final design 1 day $400.00
3 Coding 17 days $13,160.00
3.1 Prototype construction 3 days $3,480.00
3.2 Development of database 5 days $3,000.00
3.3 Validation of code 4 days $3,520.00
3.4 Cross-browser testing 3 days $840.00
3.5 Optimization 2 days $2,320.00
4 Web content build 2 days $1,760.00
4.1 Navigation structure 1 day $880.00
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

7
PROJECT MANAGEMENT
4.2 Site content pages 1 day $880.00
5 User experience 8 days $6,920.00
5.1 Updating details for website login 2 days $1,760.00
5.2 Updating project details 3 days $1,680.00
5.3 Presentation display for program 3 days $3,480.00
6 Project requirement 10 days $6,840.00
6.1 Accessing web application 3 days $2,640.00
6.2
Estimation of software as well as
hardware needs
4 days $2,400.00
6.3 Review 3 days $1,800.00
7 Testing phase 6 days $1,680.00
7.1 Unit testing 2 days $560.00
7.2 System testing 2 days $560.00
7.3 User acceptance testing 2 days $560.00
8 Project closure phase 7 days $2,000.00
8.1 Assessment of risk 3 days $840.00
8.2 Quality management 3 days $840.00
8.3 Final review 1 day $320.00
Timescale
Task Name Duration Start Finish
PROJECT MANAGEMENT
4.2 Site content pages 1 day $880.00
5 User experience 8 days $6,920.00
5.1 Updating details for website login 2 days $1,760.00
5.2 Updating project details 3 days $1,680.00
5.3 Presentation display for program 3 days $3,480.00
6 Project requirement 10 days $6,840.00
6.1 Accessing web application 3 days $2,640.00
6.2
Estimation of software as well as
hardware needs
4 days $2,400.00
6.3 Review 3 days $1,800.00
7 Testing phase 6 days $1,680.00
7.1 Unit testing 2 days $560.00
7.2 System testing 2 days $560.00
7.3 User acceptance testing 2 days $560.00
8 Project closure phase 7 days $2,000.00
8.1 Assessment of risk 3 days $840.00
8.2 Quality management 3 days $840.00
8.3 Final review 1 day $320.00
Timescale
Task Name Duration Start Finish

8
PROJECT MANAGEMENT
Implementation of website for Auzi Security
services company
86 days Fri 23-03-18 Fri 20-07-18
Project planning phase 11 days Fri 23-03-18 Fri 06-04-18
Conversation with project team members 3 days Fri 23-03-18 Tue 27-03-18
Development of project proposal 2 days Wed 28-03-18 Thu 29-03-18
Creating agreement for project 3 days Fri 30-03-18 Tue 03-04-18
Identifying stakeholders of the project 2 days Wed 04-04-18 Thu 05-04-18
Approval of project plan 1 day Fri 06-04-18 Fri 06-04-18
Web application design 25 days Mon 09-04-18 Fri 11-05-18
Gathering ideas for initial stage 4 days Mon 09-04-18 Thu 12-04-18
Client review 3 days Fri 13-04-18 Tue 17-04-18
Revising the design of the project 5 days Wed 18-04-18 Tue 24-04-18
Undertaking feasibility study 3 days Wed 25-04-18 Fri 27-04-18
Analysing budget for the project 5 days Mon 30-04-18 Fri 04-05-18
Undertaking meeting for project kick-off 4 days Mon 07-05-18 Thu 10-05-18
Approval for final design 1 day Fri 11-05-18 Fri 11-05-18
Coding 17 days Mon 14-05-18 Tue 05-06-18
Prototype construction 3 days Mon 14-05-18 Wed 16-05-18
Development of database 5 days Thu 17-05-18 Wed 23-05-18
Validation of code 4 days Thu 24-05-18 Tue 29-05-18
Cross-browser testing 3 days Wed 30-05-18 Fri 01-06-18
Optimization 2 days Mon 04-06-18 Tue 05-06-18
Web content build 2 days Wed 06-06-18 Thu 07-06-18
PROJECT MANAGEMENT
Implementation of website for Auzi Security
services company
86 days Fri 23-03-18 Fri 20-07-18
Project planning phase 11 days Fri 23-03-18 Fri 06-04-18
Conversation with project team members 3 days Fri 23-03-18 Tue 27-03-18
Development of project proposal 2 days Wed 28-03-18 Thu 29-03-18
Creating agreement for project 3 days Fri 30-03-18 Tue 03-04-18
Identifying stakeholders of the project 2 days Wed 04-04-18 Thu 05-04-18
Approval of project plan 1 day Fri 06-04-18 Fri 06-04-18
Web application design 25 days Mon 09-04-18 Fri 11-05-18
Gathering ideas for initial stage 4 days Mon 09-04-18 Thu 12-04-18
Client review 3 days Fri 13-04-18 Tue 17-04-18
Revising the design of the project 5 days Wed 18-04-18 Tue 24-04-18
Undertaking feasibility study 3 days Wed 25-04-18 Fri 27-04-18
Analysing budget for the project 5 days Mon 30-04-18 Fri 04-05-18
Undertaking meeting for project kick-off 4 days Mon 07-05-18 Thu 10-05-18
Approval for final design 1 day Fri 11-05-18 Fri 11-05-18
Coding 17 days Mon 14-05-18 Tue 05-06-18
Prototype construction 3 days Mon 14-05-18 Wed 16-05-18
Development of database 5 days Thu 17-05-18 Wed 23-05-18
Validation of code 4 days Thu 24-05-18 Tue 29-05-18
Cross-browser testing 3 days Wed 30-05-18 Fri 01-06-18
Optimization 2 days Mon 04-06-18 Tue 05-06-18
Web content build 2 days Wed 06-06-18 Thu 07-06-18

9
PROJECT MANAGEMENT
Navigation structure 1 day Wed 06-06-18 Wed 06-06-18
Site content pages 1 day Thu 07-06-18 Thu 07-06-18
User experience 8 days Fri 08-06-18 Tue 19-06-18
Updating details for website login 2 days Fri 08-06-18 Mon 11-06-18
Updating project details 3 days Tue 12-06-18 Thu 14-06-18
Presentation display for program 3 days Fri 15-06-18 Tue 19-06-18
Project requirement 10 days Wed 20-06-18 Tue 03-07-18
Accessing web application 3 days Wed 20-06-18 Fri 22-06-18
Estimation of software as well as hardware needs 4 days Mon 25-06-18 Thu 28-06-18
Review 3 days Fri 29-06-18 Tue 03-07-18
Testing phase 6 days Wed 04-07-18 Wed 11-07-18
Unit testing 2 days Wed 04-07-18 Thu 05-07-18
System testing 2 days Fri 06-07-18 Mon 09-07-18
User acceptance testing 2 days Tue 10-07-18 Wed 11-07-18
Project closure phase 7 days Thu 12-07-18 Fri 20-07-18
Assessment of risk 3 days Thu 12-07-18 Mon 16-07-18
Quality management 3 days Tue 17-07-18 Thu 19-07-18
Final review 1 day Fri 20-07-18 Fri 20-07-18
1.4 Potential risks
Risk Description Likelihood Consequences Mitigation Cost
PROJECT MANAGEMENT
Navigation structure 1 day Wed 06-06-18 Wed 06-06-18
Site content pages 1 day Thu 07-06-18 Thu 07-06-18
User experience 8 days Fri 08-06-18 Tue 19-06-18
Updating details for website login 2 days Fri 08-06-18 Mon 11-06-18
Updating project details 3 days Tue 12-06-18 Thu 14-06-18
Presentation display for program 3 days Fri 15-06-18 Tue 19-06-18
Project requirement 10 days Wed 20-06-18 Tue 03-07-18
Accessing web application 3 days Wed 20-06-18 Fri 22-06-18
Estimation of software as well as hardware needs 4 days Mon 25-06-18 Thu 28-06-18
Review 3 days Fri 29-06-18 Tue 03-07-18
Testing phase 6 days Wed 04-07-18 Wed 11-07-18
Unit testing 2 days Wed 04-07-18 Thu 05-07-18
System testing 2 days Fri 06-07-18 Mon 09-07-18
User acceptance testing 2 days Tue 10-07-18 Wed 11-07-18
Project closure phase 7 days Thu 12-07-18 Fri 20-07-18
Assessment of risk 3 days Thu 12-07-18 Mon 16-07-18
Quality management 3 days Tue 17-07-18 Thu 19-07-18
Final review 1 day Fri 20-07-18 Fri 20-07-18
1.4 Potential risks
Risk Description Likelihood Consequences Mitigation Cost
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.

10
PROJECT MANAGEMENT
strategies
Improper
budget
estimation
Due to
improper
budget
estimation,
the project
manager can
face
difficulty in
completing
the entire
successfully
on time
(Adeusi et
al., 2014)
Likely Major Proper budget
estimation must
be done by
analyzing the
market costs of
various
resources that
are required for
implementation
of the project.
The cost for
proper
market
analysis is
around
$5,000
Difficulty in
estimating
hardware
and software
requirements
If the
software and
hardware
requirements
of the
project are
not properly
estimated
Unlikely Major It is very much
important to
estimate both
software as well
as hardware
needs of the
project before
the execution
The budget
that is
needed is
around
$3,000.
PROJECT MANAGEMENT
strategies
Improper
budget
estimation
Due to
improper
budget
estimation,
the project
manager can
face
difficulty in
completing
the entire
successfully
on time
(Adeusi et
al., 2014)
Likely Major Proper budget
estimation must
be done by
analyzing the
market costs of
various
resources that
are required for
implementation
of the project.
The cost for
proper
market
analysis is
around
$5,000
Difficulty in
estimating
hardware
and software
requirements
If the
software and
hardware
requirements
of the
project are
not properly
estimated
Unlikely Major It is very much
important to
estimate both
software as well
as hardware
needs of the
project before
the execution
The budget
that is
needed is
around
$3,000.

11
PROJECT MANAGEMENT
then it will
be quite
difficult to
implement
the website.
phase by a
technical expert
who have
proper
knowledge in
the field of
website
implementation.
Maintenance
issues
If the
website is
not
maintained
properly
from time to
time then the
operations
of the
organization
will get
affected.
Almost
certain
Moderate It is very much
necessary to
maintain the
website from
time to time in
order to avoid
maintenance
related issues
(Badewi, 2016).
$7,000
must be
spend on the
maintenance
of the
website.
Improper
management
If the
project
manager
Almost
certain
Major It is very much
necessary to
hire
$800 must
be spend on
recruiting
PROJECT MANAGEMENT
then it will
be quite
difficult to
implement
the website.
phase by a
technical expert
who have
proper
knowledge in
the field of
website
implementation.
Maintenance
issues
If the
website is
not
maintained
properly
from time to
time then the
operations
of the
organization
will get
affected.
Almost
certain
Moderate It is very much
necessary to
maintain the
website from
time to time in
order to avoid
maintenance
related issues
(Badewi, 2016).
$7,000
must be
spend on the
maintenance
of the
website.
Improper
management
If the
project
manager
Almost
certain
Major It is very much
necessary to
hire
$800 must
be spend on
recruiting

12
PROJECT MANAGEMENT
does not
manage the
project
properly
then project
may face
number of
issues as
well as
challenges
(Chance &
Brooks,
2015).
experienced
project manager
who will be
able to manage
the project
successfully.
experienced
project
managers
for the
project.
Likelihood Consequences
Insignificant Minor Moderate Major Catastrophic
Almost
certain
Maintenance
issues
Improper
management
Likely Improper
budget
estimation
Moderate
Unlikely Difficulty in
PROJECT MANAGEMENT
does not
manage the
project
properly
then project
may face
number of
issues as
well as
challenges
(Chance &
Brooks,
2015).
experienced
project manager
who will be
able to manage
the project
successfully.
experienced
project
managers
for the
project.
Likelihood Consequences
Insignificant Minor Moderate Major Catastrophic
Almost
certain
Maintenance
issues
Improper
management
Likely Improper
budget
estimation
Moderate
Unlikely Difficulty in
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

13
PROJECT MANAGEMENT
estimating
hardware
and software
requirement
s
Rare
1.5 Ethical issues
Yes, the solution that is proposed for the project is abide by the law as all the strategies
that are made in order to resolve this issues are proper as well as ethical for the clients as well as
for the company.
Yes, the project activities as well as processes are generally aligned with the PMI code of
ethics as well as professional conduct in order to avoid ethical issues within the project.
It is identified that the proposed solutions for the various risks as well as challenges
generally aligned with both employers as well as code of ethics in order to avoid any type of
ethical issue within the project (Conforto et al., 2014). The solution generally agree with the
employers code of ethics in order to avoid the possible copyright issues, content collection issues
, software issues as well as potential privacy issues within the project.
Possible copyright issues: The project does not used online materials assuming that the
perquisites for copyright protection issues are generally met. The project does not copies
someone else work and thus it is free from copyright infringement.
Content collection issues:The information as well as data that is related with Auzi
security services is generally collected as well as gathered with the permission of the
PROJECT MANAGEMENT
estimating
hardware
and software
requirement
s
Rare
1.5 Ethical issues
Yes, the solution that is proposed for the project is abide by the law as all the strategies
that are made in order to resolve this issues are proper as well as ethical for the clients as well as
for the company.
Yes, the project activities as well as processes are generally aligned with the PMI code of
ethics as well as professional conduct in order to avoid ethical issues within the project.
It is identified that the proposed solutions for the various risks as well as challenges
generally aligned with both employers as well as code of ethics in order to avoid any type of
ethical issue within the project (Conforto et al., 2014). The solution generally agree with the
employers code of ethics in order to avoid the possible copyright issues, content collection issues
, software issues as well as potential privacy issues within the project.
Possible copyright issues: The project does not used online materials assuming that the
perquisites for copyright protection issues are generally met. The project does not copies
someone else work and thus it is free from copyright infringement.
Content collection issues:The information as well as data that is related with Auzi
security services is generally collected as well as gathered with the permission of the

14
PROJECT MANAGEMENT
organization and further the information that is gathered will not be misused and thus no
possibility of content collection issue is present.
Software issues: The software that is used in the project is free from various types of
troubleshooting issues and it will be properly utilized in the project in order to create the website
for the Auzi security services.
Potential privacy issues: The information as well as data that is utilized in the project
does not create any privacy issues within the organization and it will generally utilize
information by maintaining the privacy protection laws.
Conflict of interest issues: The project is mainly created by taking ideas as well as
views from various stakeholders of the organization therefore no issues related with the conflict
of interest occurs within the organization.
2.1 Duration of the project
The time that is needed for completing the implementation of the website successfully for
Auzi security services is around 80 days. The time that is required for completing each of the
project activities are provided in the table below:
WBS Task Name Duration
0
Implementation of website for Auzi Security services
company
86 days
1 Project planning phase 11 days
1.1 Conversation with project team members 3 days
1.2 Development of project proposal 2 days
1.3 Creating agreement for project 3 days
1.4 Identifying stakeholders of the project 2 days
PROJECT MANAGEMENT
organization and further the information that is gathered will not be misused and thus no
possibility of content collection issue is present.
Software issues: The software that is used in the project is free from various types of
troubleshooting issues and it will be properly utilized in the project in order to create the website
for the Auzi security services.
Potential privacy issues: The information as well as data that is utilized in the project
does not create any privacy issues within the organization and it will generally utilize
information by maintaining the privacy protection laws.
Conflict of interest issues: The project is mainly created by taking ideas as well as
views from various stakeholders of the organization therefore no issues related with the conflict
of interest occurs within the organization.
2.1 Duration of the project
The time that is needed for completing the implementation of the website successfully for
Auzi security services is around 80 days. The time that is required for completing each of the
project activities are provided in the table below:
WBS Task Name Duration
0
Implementation of website for Auzi Security services
company
86 days
1 Project planning phase 11 days
1.1 Conversation with project team members 3 days
1.2 Development of project proposal 2 days
1.3 Creating agreement for project 3 days
1.4 Identifying stakeholders of the project 2 days

15
PROJECT MANAGEMENT
1.5 Approval of project plan 1 day
2 Web application design 25 days
2.1 Gathering ideas for initial stage 4 days
2.2 Client review 3 days
2.3 Revising the design of the project 5 days
2.4 Undertaking feasibility study 3 days
2.5 Analysing budget for the project 5 days
2.6 Undertaking meeting for project kick-off 4 days
2.7 Approval for final design 1 day
3 Coding 17 days
3.1 Prototype construction 3 days
3.2 Development of database 5 days
3.3 Validation of code 4 days
3.4 Cross-browser testing 3 days
3.5 Optimization 2 days
4 Web content build 2 days
4.1 Navigation structure 1 day
4.2 Site content pages 1 day
5 User experience 8 days
5.1 Updating details for website login 2 days
5.2 Updating project details 3 days
PROJECT MANAGEMENT
1.5 Approval of project plan 1 day
2 Web application design 25 days
2.1 Gathering ideas for initial stage 4 days
2.2 Client review 3 days
2.3 Revising the design of the project 5 days
2.4 Undertaking feasibility study 3 days
2.5 Analysing budget for the project 5 days
2.6 Undertaking meeting for project kick-off 4 days
2.7 Approval for final design 1 day
3 Coding 17 days
3.1 Prototype construction 3 days
3.2 Development of database 5 days
3.3 Validation of code 4 days
3.4 Cross-browser testing 3 days
3.5 Optimization 2 days
4 Web content build 2 days
4.1 Navigation structure 1 day
4.2 Site content pages 1 day
5 User experience 8 days
5.1 Updating details for website login 2 days
5.2 Updating project details 3 days
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.

16
PROJECT MANAGEMENT
5.3 Presentation display for program 3 days
6 Project requirement 10 days
6.1 Accessing web application 3 days
6.2 Estimation of software as well as hardware needs 4 days
6.3 Review 3 days
7 Testing phase 6 days
7.1 Unit testing 2 days
7.2 System testing 2 days
7.3 User acceptance testing 2 days
8 Project closure phase 7 days
8.1 Assessment of risk 3 days
8.2 Quality management 3 days
8.3 Final review 1 day
2.2 Cost associated with project
In order to complete the project of website implementation, it is identified that budget of
around $47,040 is generally required.
WBS Task Name Cost
0
Implementation of website for Auzi Security
services company
$49,680.00
1 Project planning phase $5,520.00
1.1 Conversation with project team members $1,200.00
1.2 Development of project proposal $640.00
PROJECT MANAGEMENT
5.3 Presentation display for program 3 days
6 Project requirement 10 days
6.1 Accessing web application 3 days
6.2 Estimation of software as well as hardware needs 4 days
6.3 Review 3 days
7 Testing phase 6 days
7.1 Unit testing 2 days
7.2 System testing 2 days
7.3 User acceptance testing 2 days
8 Project closure phase 7 days
8.1 Assessment of risk 3 days
8.2 Quality management 3 days
8.3 Final review 1 day
2.2 Cost associated with project
In order to complete the project of website implementation, it is identified that budget of
around $47,040 is generally required.
WBS Task Name Cost
0
Implementation of website for Auzi Security
services company
$49,680.00
1 Project planning phase $5,520.00
1.1 Conversation with project team members $1,200.00
1.2 Development of project proposal $640.00

17
PROJECT MANAGEMENT
1.3 Creating agreement for project $2,160.00
1.4 Identifying stakeholders of the project $800.00
1.5 Approval of project plan $720.00
2 Web application design $11,800.00
2.1 Gathering ideas for initial stage $1,280.00
2.2 Client review $1,200.00
2.3 Revising the design of the project $3,000.00
2.4 Undertaking feasibility study $720.00
2.5 Analysing budget for the project $1,200.00
2.6 Undertaking meeting for project kick-off $4,000.00
2.7 Approval for final design $400.00
3 Coding $13,160.00
3.1 Prototype construction $3,480.00
3.2 Development of database $3,000.00
3.3 Validation of code $3,520.00
3.4 Cross-browser testing $840.00
3.5 Optimization $2,320.00
4 Web content build $1,760.00
4.1 Navigation structure $880.00
4.2 Site content pages $880.00
5 User experience $6,920.00
5.1 Updating details for website login $1,760.00
PROJECT MANAGEMENT
1.3 Creating agreement for project $2,160.00
1.4 Identifying stakeholders of the project $800.00
1.5 Approval of project plan $720.00
2 Web application design $11,800.00
2.1 Gathering ideas for initial stage $1,280.00
2.2 Client review $1,200.00
2.3 Revising the design of the project $3,000.00
2.4 Undertaking feasibility study $720.00
2.5 Analysing budget for the project $1,200.00
2.6 Undertaking meeting for project kick-off $4,000.00
2.7 Approval for final design $400.00
3 Coding $13,160.00
3.1 Prototype construction $3,480.00
3.2 Development of database $3,000.00
3.3 Validation of code $3,520.00
3.4 Cross-browser testing $840.00
3.5 Optimization $2,320.00
4 Web content build $1,760.00
4.1 Navigation structure $880.00
4.2 Site content pages $880.00
5 User experience $6,920.00
5.1 Updating details for website login $1,760.00

18
PROJECT MANAGEMENT
5.2 Updating project details $1,680.00
5.3 Presentation display for program $3,480.00
6 Project requirement $6,840.00
6.1 Accessing web application $2,640.00
6.2 Estimation of software as well as hardware needs $2,400.00
6.3 Review $1,800.00
7 Testing phase $1,680.00
7.1 Unit testing $560.00
7.2 System testing $560.00
7.3 User acceptance testing $560.00
8 Project closure phase $2,000.00
8.1 Assessment of risk $840.00
8.2 Quality management $840.00
8.3 Final review $320.00
PROJECT MANAGEMENT
5.2 Updating project details $1,680.00
5.3 Presentation display for program $3,480.00
6 Project requirement $6,840.00
6.1 Accessing web application $2,640.00
6.2 Estimation of software as well as hardware needs $2,400.00
6.3 Review $1,800.00
7 Testing phase $1,680.00
7.1 Unit testing $560.00
7.2 System testing $560.00
7.3 User acceptance testing $560.00
8 Project closure phase $2,000.00
8.1 Assessment of risk $840.00
8.2 Quality management $840.00
8.3 Final review $320.00
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

19
PROJECT MANAGEMENT
2.3 Deliverables and milestones of the project
Milestone Deliverable
Milestone 1: Completion of project planning phase Planning document
Milestone 2: Completion of web application design Prototype of the application
Milestone 3: Completion of coding Report of coding completion
Milestone 4: Completion of web content build The web content document
Milestone 5: Completion of user experience testing Testing report
Milestone 6: Completion of project requirement Project Documentation
Milestone 7: Completion of closure phase Complete application
2.4 Delivery time of the millstones
Milestone Completion date
Milestone 1: Completion of project planning phase Fri 06-04-18
Milestone 2: Completion of web application design Fri 11-05-18
Milestone 3: Completion of coding Tue 05-06-18
Milestone 4: Completion of web content build Thu 07-06-18
Milestone 5: Completion of user experience testing Tue 19-06-18
Milestone 6: Completion of project requirement Tue 03-07-18
Milestone 7: Completion of closure phase Thu 12-07-18
PROJECT MANAGEMENT
2.3 Deliverables and milestones of the project
Milestone Deliverable
Milestone 1: Completion of project planning phase Planning document
Milestone 2: Completion of web application design Prototype of the application
Milestone 3: Completion of coding Report of coding completion
Milestone 4: Completion of web content build The web content document
Milestone 5: Completion of user experience testing Testing report
Milestone 6: Completion of project requirement Project Documentation
Milestone 7: Completion of closure phase Complete application
2.4 Delivery time of the millstones
Milestone Completion date
Milestone 1: Completion of project planning phase Fri 06-04-18
Milestone 2: Completion of web application design Fri 11-05-18
Milestone 3: Completion of coding Tue 05-06-18
Milestone 4: Completion of web content build Thu 07-06-18
Milestone 5: Completion of user experience testing Tue 19-06-18
Milestone 6: Completion of project requirement Tue 03-07-18
Milestone 7: Completion of closure phase Thu 12-07-18

20
PROJECT MANAGEMENT
2.5 People and resources to meet the plan
Human resource: The people who are involved in the project are provided in the table
below:
Resource
Name
Type
Materia
l Label
Initial
s
Grou
p
Max.
Units
Std.
Rate
Ovt.
Rate
Cost/
Use
Accrue
At
Base
Calenda
r
Project
manager
Wor
k
P
100
%
$50.00/
hr
$0.00/
hr
$0.00
Prorate
d
Standard
Project
planner
Wor
k
P
100
%
$40.00/
hr
$0.00/
hr
$0.00
Prorate
d
Standard
Application
manager
Wor
k
A
100
%
$40.00/
hr
$0.00/
hr
$0.00
Prorate
d
Standard
Developer
Wor
k
D
100
%
$35.00/
hr
$0.00/
hr
$0.00
Prorate
d
Standard
Database
administrato
r
Wor
k
D
100
%
$35.00/
hr
$0.00/
hr
$0.00
Prorate
d
Standard
Coder
Wor
k
C
100
%
$35.00/
hr
$0.00/
hr
$0.00
Prorate
d
Standard
Tester
Wor
k
T
100
%
$35.00/
hr
$0.00/
hr
$0.00
Prorate
d
Standard
PROJECT MANAGEMENT
2.5 People and resources to meet the plan
Human resource: The people who are involved in the project are provided in the table
below:
Resource
Name
Type
Materia
l Label
Initial
s
Grou
p
Max.
Units
Std.
Rate
Ovt.
Rate
Cost/
Use
Accrue
At
Base
Calenda
r
Project
manager
Wor
k
P
100
%
$50.00/
hr
$0.00/
hr
$0.00
Prorate
d
Standard
Project
planner
Wor
k
P
100
%
$40.00/
hr
$0.00/
hr
$0.00
Prorate
d
Standard
Application
manager
Wor
k
A
100
%
$40.00/
hr
$0.00/
hr
$0.00
Prorate
d
Standard
Developer
Wor
k
D
100
%
$35.00/
hr
$0.00/
hr
$0.00
Prorate
d
Standard
Database
administrato
r
Wor
k
D
100
%
$35.00/
hr
$0.00/
hr
$0.00
Prorate
d
Standard
Coder
Wor
k
C
100
%
$35.00/
hr
$0.00/
hr
$0.00
Prorate
d
Standard
Tester
Wor
k
T
100
%
$35.00/
hr
$0.00/
hr
$0.00
Prorate
d
Standard

21
PROJECT MANAGEMENT
Quality
analyst
Wor
k
100
%
$35.00/
hr
$0.00/
hr
$0.00
Prorate
d
Standard
Financial
manager
Wor
k
F
100
%
$30.00/
hr
$0.00/
hr
$0.00
Prorate
d
Standard
Financial resources: The financial resource that is generally needed in order to
complete the project is around $47,040.
Software and hardware requirements: Server, computer, database, PHP, JavaScript,
HTML, CSS, JQuery, MySQL and BootStrap
2.6 Control exerted within the project
The project can be controlled by utilizing steps that are as follows:
Holding meetings:Proper meetings must be conducted from timely basis in order to track
the project so that the objectives as well as goals of the project can be easily met.
Performing quality control:Proper quality control must be performed in order to make
sure that the quality of the project is proper (De Carvalho et al., 2015). It generally aims to make
sure that the activities as well as tasks at any stage of the project lifecycle must signed off in
order to continue project development.
Tracking work progress:It is very much necessary to track the work progresses of the
project by properly measuring, monitoring as well controlling the progress of the project
(Kerzner, 2017). The project manager must track the work progress at any given stage in order to
ensure that the project is progressing in the right direction.
PROJECT MANAGEMENT
Quality
analyst
Wor
k
100
%
$35.00/
hr
$0.00/
hr
$0.00
Prorate
d
Standard
Financial
manager
Wor
k
F
100
%
$30.00/
hr
$0.00/
hr
$0.00
Prorate
d
Standard
Financial resources: The financial resource that is generally needed in order to
complete the project is around $47,040.
Software and hardware requirements: Server, computer, database, PHP, JavaScript,
HTML, CSS, JQuery, MySQL and BootStrap
2.6 Control exerted within the project
The project can be controlled by utilizing steps that are as follows:
Holding meetings:Proper meetings must be conducted from timely basis in order to track
the project so that the objectives as well as goals of the project can be easily met.
Performing quality control:Proper quality control must be performed in order to make
sure that the quality of the project is proper (De Carvalho et al., 2015). It generally aims to make
sure that the activities as well as tasks at any stage of the project lifecycle must signed off in
order to continue project development.
Tracking work progress:It is very much necessary to track the work progresses of the
project by properly measuring, monitoring as well controlling the progress of the project
(Kerzner, 2017). The project manager must track the work progress at any given stage in order to
ensure that the project is progressing in the right direction.
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.

22
PROJECT MANAGEMENT
Respond to change: It is identified that by responding to the various project changes, the
project manager is able to make sure that the cost, schedule as well as scope of the project
remain relevant to the current situation.
2.7 Maintenance of quality
The steps that are required to be performed in order to maintain the quality of the project
are elaborated below:
Appropriate communication: Despite of proper planning and scheduling, it is very
much necessary to utilize proper communication with the stakeholders as well as project team
members (Snyder, 2014). Excellent communication assists in encouraging formal and informal
discussion about expectation, innovation as well as progress of project.
Manage stakeholders: In order to manage the stakeholders, it is very much necessary to
analyze their concerns and needs for preparing proper strategy that would be helpful in providing
proper amount of opportunities as well as information to the stakeholders for involvement.
Good measurement
Constant review: It is necessary to review progress of the budget, schedule as well as
quality elements of the project (Sun et al., 2015). Proper review helps in allowing early
identification of problems so that they can be corrected easily for keeping the project on track.
2.8 Risks in approach taken
The risks that are taken in approach are reflected with the help of risk matrix, which is
provided below:
Likelihood Consequences
Insignificant Minor Moderate Major Catastrophic
PROJECT MANAGEMENT
Respond to change: It is identified that by responding to the various project changes, the
project manager is able to make sure that the cost, schedule as well as scope of the project
remain relevant to the current situation.
2.7 Maintenance of quality
The steps that are required to be performed in order to maintain the quality of the project
are elaborated below:
Appropriate communication: Despite of proper planning and scheduling, it is very
much necessary to utilize proper communication with the stakeholders as well as project team
members (Snyder, 2014). Excellent communication assists in encouraging formal and informal
discussion about expectation, innovation as well as progress of project.
Manage stakeholders: In order to manage the stakeholders, it is very much necessary to
analyze their concerns and needs for preparing proper strategy that would be helpful in providing
proper amount of opportunities as well as information to the stakeholders for involvement.
Good measurement
Constant review: It is necessary to review progress of the budget, schedule as well as
quality elements of the project (Sun et al., 2015). Proper review helps in allowing early
identification of problems so that they can be corrected easily for keeping the project on track.
2.8 Risks in approach taken
The risks that are taken in approach are reflected with the help of risk matrix, which is
provided below:
Likelihood Consequences
Insignificant Minor Moderate Major Catastrophic

23
PROJECT MANAGEMENT
Almost
certain
Maintenance
issues
Improper
management
Likely Improper
budget
estimation
Moderate
Unlikely Difficulty in
estimating
hardware
and software
requirement
s
Rare
2.9 WBS
WBS Task Name
0 Implementation of website for Auzi Security services company
1 Project planning phase
1.1 Conversation with project team members
1.2 Development of project proposal
1.3 Creating agreement for project
1.4 Identifying stakeholders of the project
PROJECT MANAGEMENT
Almost
certain
Maintenance
issues
Improper
management
Likely Improper
budget
estimation
Moderate
Unlikely Difficulty in
estimating
hardware
and software
requirement
s
Rare
2.9 WBS
WBS Task Name
0 Implementation of website for Auzi Security services company
1 Project planning phase
1.1 Conversation with project team members
1.2 Development of project proposal
1.3 Creating agreement for project
1.4 Identifying stakeholders of the project

24
PROJECT MANAGEMENT
1.5 Approval of project plan
2 Web application design
2.1 Gathering ideas for initial stage
2.2 Client review
2.3 Revising the design of the project
2.4 Undertaking feasibility study
2.5 Analysing budget for the project
2.6 Undertaking meeting for project kick-off
2.7 Approval for final design
3 Coding
3.1 Prototype construction
3.2 Development of database
3.3 Validation of code
3.4 Cross-browser testing
3.5 Optimization
4 Web content build
4.1 Navigation structure
4.2 Site content pages
5 User experience
5.1 Updating details for website login
5.2 Updating project details
5.3 Presentation display for program
PROJECT MANAGEMENT
1.5 Approval of project plan
2 Web application design
2.1 Gathering ideas for initial stage
2.2 Client review
2.3 Revising the design of the project
2.4 Undertaking feasibility study
2.5 Analysing budget for the project
2.6 Undertaking meeting for project kick-off
2.7 Approval for final design
3 Coding
3.1 Prototype construction
3.2 Development of database
3.3 Validation of code
3.4 Cross-browser testing
3.5 Optimization
4 Web content build
4.1 Navigation structure
4.2 Site content pages
5 User experience
5.1 Updating details for website login
5.2 Updating project details
5.3 Presentation display for program
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

25
PROJECT MANAGEMENT
6 Project requirement
6.1 Accessing web application
6.2 Estimation of software as well as hardware needs
6.3 Review
7 Testing phase
7.1 Unit testing
7.2 System testing
7.3 User acceptance testing
8 Project closure phase
8.1 Assessment of risk
8.2 Quality management
8.3 Final review
2.10 Cash Flow
Company: Retail company in Cambodia
Operating activities Month 1 Month 2 Month 3
Net income 20,6
99.00
20,4
56.00
15,8
68.00
Depreciation 3,5
78.00
4,7
85.00
4,8
96.00
Accounts receivable
- - -
Inventories
- - -
Accounts payable
- - -
Amortization
PROJECT MANAGEMENT
6 Project requirement
6.1 Accessing web application
6.2 Estimation of software as well as hardware needs
6.3 Review
7 Testing phase
7.1 Unit testing
7.2 System testing
7.3 User acceptance testing
8 Project closure phase
8.1 Assessment of risk
8.2 Quality management
8.3 Final review
2.10 Cash Flow
Company: Retail company in Cambodia
Operating activities Month 1 Month 2 Month 3
Net income 20,6
99.00
20,4
56.00
15,8
68.00
Depreciation 3,5
78.00
4,7
85.00
4,8
96.00
Accounts receivable
- - -
Inventories
- - -
Accounts payable
- - -
Amortization

26
PROJECT MANAGEMENT
- - -
Other liabilities
- - -
Other operating cash flow
items - - -
Total operating activities 24,2
77.00
25,2
41.00
20,7
64.00
Investing activities Year 1 Year 2 Year 3 Total
Capital expenditures
- - - -
Acquisition of business
- - -
Sale of fixed assets
- -
-
1,000.00
-
1,000.00
Other investing cash flow
items - - - -
Total investing activities
- -
-
1,000.00
-
1,000.00
Financing activities Month1 Month 2 Month 3 Month 4
Long-term debt/financing 9,6
85.00
7,7
89.00
8,9
86.00
2,4
56.00
Preferred stock
- - - -
Total cash dividends paid
- - - -
Common stock
- - - -
Other financing cash flow
items - - - -
Total financing activities 9,6
85.00
7,7
89.00
8,9
86.00
26,4
60.00
Cumulative cash flow 33,9
62.00
33,0
30.00
28,7
50.00
95,7
42.00
Beginning cash balance 50,0
00.00
83,9
62.00
116,9
92.00
PROJECT MANAGEMENT
- - -
Other liabilities
- - -
Other operating cash flow
items - - -
Total operating activities 24,2
77.00
25,2
41.00
20,7
64.00
Investing activities Year 1 Year 2 Year 3 Total
Capital expenditures
- - - -
Acquisition of business
- - -
Sale of fixed assets
- -
-
1,000.00
-
1,000.00
Other investing cash flow
items - - - -
Total investing activities
- -
-
1,000.00
-
1,000.00
Financing activities Month1 Month 2 Month 3 Month 4
Long-term debt/financing 9,6
85.00
7,7
89.00
8,9
86.00
2,4
56.00
Preferred stock
- - - -
Total cash dividends paid
- - - -
Common stock
- - - -
Other financing cash flow
items - - - -
Total financing activities 9,6
85.00
7,7
89.00
8,9
86.00
26,4
60.00
Cumulative cash flow 33,9
62.00
33,0
30.00
28,7
50.00
95,7
42.00
Beginning cash balance 50,0
00.00
83,9
62.00
116,9
92.00

27
PROJECT MANAGEMENT
Ending cash balance 83,9
62.00
116,9
92.00
145,7
42.00
2.11 Resource allocation
Project manager
Project planner
Application manager
Developer
Database administrator
Coder
Tester
Qulaity analyst
Finanacial manager
0 hrs
50 hrs
100 hrs
150 hrs
200 hrs
250 hrs
300 hrs
350 hrs
Actual Work Remaining Work Baseline Work
Figure 1: Resource allocation
(Source: Created by Author)
PROJECT MANAGEMENT
Ending cash balance 83,9
62.00
116,9
92.00
145,7
42.00
2.11 Resource allocation
Project manager
Project planner
Application manager
Developer
Database administrator
Coder
Tester
Qulaity analyst
Finanacial manager
0 hrs
50 hrs
100 hrs
150 hrs
200 hrs
250 hrs
300 hrs
350 hrs
Actual Work Remaining Work Baseline Work
Figure 1: Resource allocation
(Source: Created by Author)
1 out of 28
Related Documents

Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
© 2024 | Zucol Services PVT LTD | All rights reserved.