FIN5003: Project Management Report on Batmobile Production Project
VerifiedAdded on 2023/04/21
|16
|848
|296
Report
AI Summary
This report delves into the project management aspects of producing a modified Batmobile, stemming from the success of a recent Batman movie. It includes an AON (Activity On Node) diagram illustrating early and late start/finish times, activity durations, and predecessors. The report identifies the critical path (A>D>E>G) and explores crashing strategies to reduce the project completion time. By calculating crash costs and times for each activity, the analysis determines that the project can be completed in 16 weeks (7 weeks earlier than scheduled) with an additional cost of $1,163,000. The report concludes that while the project duration can be significantly reduced, the critical path remains unchanged. It uses project management principles discussed in cited academic papers to provide a framework for the recommendations.
1 out of 16