Project Development: Strategic Management Beauty Soap in the UK

Verified

Added on  2023/04/22

|13
|589
|130
Project
AI Summary
This project details the development of a new beauty soap in the UK, outlining objectives, cost estimations (£100,000), and a four-month timescale. It includes activities from idea generation to commercialization, visualized through a Gantt chart and network diagram. The critical path analysis reveals a 75-day total duration. The project monitors progress through schedule adherence, cost management, and resource utilization. Outcomes show effective project performance, though resource allocation requires attention. The actual project cost was £94,080, resulting in a positive variance of £5920. Recommendations include specifying activity start/finish times, recruiting experienced personnel, adopting activity-based costing, and utilizing quality management techniques. The project successfully develops a new Premium Allure beauty soap product, achieving its objectives within the given constraints.
Document Page
Project Development for Strategic
Management
Task 5.2
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
INTRODUCTION
Introduction:
The current project is based on development of new beauty product in UK.
Project has chosen soap as a beauty product.
Project will focus on different activities and aspects which are required to
manage by project manager at the time of developing a new beauty soap for
customers.
Project objectives: Developing a beauty product for customer is the
major objective of this project.
Cost estimation: £100000.
Time estimation: 4 months
Document Page
Timescale for the project plan
Activities (in days) 3 14 27 43 5 14 21
Idea generation
Idea screening
Development of concept
Business analysis
Marketing testing
Technical implementation
Commercialization
Document Page
Implementation of the project plan:
Gantt chart
Network diagram
Project summery
Critical path analysis
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Gantt chart:
Document Page
PERT (Network Diagram):
Document Page
Critical path analysis
Critical path Calculation of total duration Total duration for completing
the project
3-4-6-7-8-9-10-11-13-14-15-
16-17-21-23-26-27-28-29-34
2+1+5+5+3+2+2+2+2+2+1
0+7+6+2+10+5+2+5+3+4+
2
75 days
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Measures to monitor and
evaluate progress and outcomes
Running on schedule
Running within planned costs
Proper use of resources
Document Page
Outcomes of the project
Gantt chart, Network diagram and Critical path analysis have reflected
that project has completed on planned time.
Every activity has accomplished as per the estimated duration.
Overall, it has reflected that project performance is very effective.
But, allocation of the resources has reflected that most of the resources
are over allocated.
As per the above WBS project manager can effectively develop new
Premium Allure beauty Soap product using all these activities.
These activities have helped in attaining project objectives in effective
manner.
Document Page
Cont…..
As per the above discussion project manager has estimated
cost for this project was £100000.
Implementation of the project plan has reflected that actual
cost of this project is £94080.
It has reflected that actual cost of project is low as compare to
planned cost. So, positive variance of cost is $5920.
It has reflected that project manager has allocated financial
resources in effective manner.
Therefore, the whole project plan has under controlled and
completed within the given constraints.
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Recommedations
Project manager should decide specified the start and finish time of
every activity to decrease the issue relate to increase completion of
plan.
Organization should recruit those people who are having the high
experience and already done the similar work in new product
development.
Manager should adopt the activity based costing method for managing
the funds at every level of project plan.
Manager of project should use the different quality management
techniques such as TQM, control charts, Six Sigma etc.
Document Page
References
Greasley, A., 2007. Operations Management. SAGE.
Hobbs, P., 2009. Project Management. Dorling Kindersley Limited.
Kathy, O. R. and Deborah, R. P., 2007. Integrating self‐managed work
teams into project management. Journal of Facilities Management. 5(1).
Pp.22 - 36.
Kloppenborg, T., 2011. Contemporary Project Management. 2nd ed.
Cengage Learning
Knapp, A. and et.al., 2010. A Project Manager's Guide to Passing the
Project Management (Pmp) Exam. www.pmexam.com.
Document Page
Thank You
chevron_up_icon
1 out of 13
circle_padding
hide_on_mobile
zoom_out_icon
logo.png

Your All-in-One AI-Powered Toolkit for Academic Success.

Available 24*7 on WhatsApp / Email

[object Object]