Big Data Implementation in German Telecom: A Project Report
VerifiedAdded on 2025/05/03
|22
|3027
|294
AI Summary
Desklib offers solved assignments and past papers to help students succeed.

PROJECT MANAGEMENT
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Contents
Executive summary...............................................................................................................................4
Introduction...........................................................................................................................................5
A clear outlined of project.....................................................................................................................6
Gather functional and non-functional requirement..............................................................................6
The envisaged project team member....................................................................................................7
Develop a project plan...........................................................................................................................8
Determine Project Scope...................................................................................................................8
Estimate time for the project............................................................................................................8
Determine resource required for project..........................................................................................8
Gantt chart & network diagram.........................................................................................................9
Estimated Cost for the project.........................................................................................................10
Plan quality of the project...............................................................................................................11
Stakeholder analysis for project......................................................................................................12
Communication Plan.......................................................................................................................13
Plan project risk management.........................................................................................................14
Plan project deployment.................................................................................................................15
Project sign- off page...........................................................................................................................16
Post review project & recommendations............................................................................................17
Conclusion...........................................................................................................................................18
References...........................................................................................................................................19
Appendix.............................................................................................................................................20
Executive summary...............................................................................................................................4
Introduction...........................................................................................................................................5
A clear outlined of project.....................................................................................................................6
Gather functional and non-functional requirement..............................................................................6
The envisaged project team member....................................................................................................7
Develop a project plan...........................................................................................................................8
Determine Project Scope...................................................................................................................8
Estimate time for the project............................................................................................................8
Determine resource required for project..........................................................................................8
Gantt chart & network diagram.........................................................................................................9
Estimated Cost for the project.........................................................................................................10
Plan quality of the project...............................................................................................................11
Stakeholder analysis for project......................................................................................................12
Communication Plan.......................................................................................................................13
Plan project risk management.........................................................................................................14
Plan project deployment.................................................................................................................15
Project sign- off page...........................................................................................................................16
Post review project & recommendations............................................................................................17
Conclusion...........................................................................................................................................18
References...........................................................................................................................................19
Appendix.............................................................................................................................................20

List of tables
Table 1: Title table.................................................................................................................................5
Table 2: Skills of stakeholder.................................................................................................................6
Table 3: Time table................................................................................................................................7
Table 4: resource table..........................................................................................................................7
Table 5: Cost table.................................................................................................................................9
Table 6: Phase of the project.................................................................................................................9
Table 7: Stakeholder table...................................................................................................................11
Table 8: Communication table.............................................................................................................12
Table 9: risk matrix..............................................................................................................................13
Table 10: post review project table.....................................................................................................16
List of figures
Figure 1: WBS........................................................................................................................................9
Figure 2: Gantt chart............................................................................................................................11
Figure 3: Network diagram..................................................................................................................12
Figure 4: appendix...............................................................................................................................22
Table 1: Title table.................................................................................................................................5
Table 2: Skills of stakeholder.................................................................................................................6
Table 3: Time table................................................................................................................................7
Table 4: resource table..........................................................................................................................7
Table 5: Cost table.................................................................................................................................9
Table 6: Phase of the project.................................................................................................................9
Table 7: Stakeholder table...................................................................................................................11
Table 8: Communication table.............................................................................................................12
Table 9: risk matrix..............................................................................................................................13
Table 10: post review project table.....................................................................................................16
List of figures
Figure 1: WBS........................................................................................................................................9
Figure 2: Gantt chart............................................................................................................................11
Figure 3: Network diagram..................................................................................................................12
Figure 4: appendix...............................................................................................................................22
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

Executive summary
A Company of German telecom wants to implement the big data to provide the customer with faster
& simple services through the medium of digital. Its objective is to understand the requirement of
customer & develop a good relation with customer & also expand the marketing and sales platform.
So, to implement big data first clear the objective, start & end date & gather the functional & non-
functional requirement of the project. Then identify the stakeholder & their skills, develop the plan
of the project to estimate the cost & time, project scope, plan quality, analysis of stakeholder,
communication plan, risk & deployment plan, at the last of the project sign-off & the post-project
review & the recommendation.
A Company of German telecom wants to implement the big data to provide the customer with faster
& simple services through the medium of digital. Its objective is to understand the requirement of
customer & develop a good relation with customer & also expand the marketing and sales platform.
So, to implement big data first clear the objective, start & end date & gather the functional & non-
functional requirement of the project. Then identify the stakeholder & their skills, develop the plan
of the project to estimate the cost & time, project scope, plan quality, analysis of stakeholder,
communication plan, risk & deployment plan, at the last of the project sign-off & the post-project
review & the recommendation.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Introduction
The German Company of telecom implements big data, by introducing the digital technologies &
approaches that have a large impact on the industry of telecom & the delivered services to the
customer with more alterations. As customer want to have faster delivery by the digital medium,
this will improve the understanding & retention of the customer. This report outlined the project
title, objectives, start & end date, functional & non-functional requirements, team members of
project, project involve (Work breakdown structure, estimated time, cost, Gantt chart, stakeholder
analysis, resource need, communication plan, risk of plan project & deployment of plan project),
project sign off page & project review & recommendation.
The German Company of telecom implements big data, by introducing the digital technologies &
approaches that have a large impact on the industry of telecom & the delivered services to the
customer with more alterations. As customer want to have faster delivery by the digital medium,
this will improve the understanding & retention of the customer. This report outlined the project
title, objectives, start & end date, functional & non-functional requirements, team members of
project, project involve (Work breakdown structure, estimated time, cost, Gantt chart, stakeholder
analysis, resource need, communication plan, risk of plan project & deployment of plan project),
project sign off page & project review & recommendation.

A clear outlined of project
Table 1: Title table
Title Implementation of big data in
telecommunication company of German.
Start date 1 May 2019
End date 4 December 2019
Goal Implementing the big data in telecom Company
to increase the productivity, develop the
relationship among platforms as with end
customers. By using digital technologies it will
serve the customer in a better way.
Gather functional and non-functional requirement
Non-functional requirement
Performance-This will allow the system to execute the task for the instant of time.
Reusability- It is considering for capacity to function continuously for the conditions that are
defined previously.
Maintainability- System ability to alter subsistence.
Usability- It is necessary to be distant with several other attributes as the customer may see
how flexible attribute of the system will work.
Testability- System will execute test cases as per the defined criteria.
Functional requirement
Data processing- it will involve the gathering & organization of primary data will provide
meaning. It contains stages like modeling, data mining, file exporting & sources of the data
file.
Predictive applications- it contains identify management that deals with the process of
organization for commanding access to the individual data & fraud analytics will involve the
detection functionalities.
Analytics-It is the tool of big data that will offer the various packages & modules to provide
customer options.
Reporting- It contains dashboards, insight location based & reporting for real time.
Table 1: Title table
Title Implementation of big data in
telecommunication company of German.
Start date 1 May 2019
End date 4 December 2019
Goal Implementing the big data in telecom Company
to increase the productivity, develop the
relationship among platforms as with end
customers. By using digital technologies it will
serve the customer in a better way.
Gather functional and non-functional requirement
Non-functional requirement
Performance-This will allow the system to execute the task for the instant of time.
Reusability- It is considering for capacity to function continuously for the conditions that are
defined previously.
Maintainability- System ability to alter subsistence.
Usability- It is necessary to be distant with several other attributes as the customer may see
how flexible attribute of the system will work.
Testability- System will execute test cases as per the defined criteria.
Functional requirement
Data processing- it will involve the gathering & organization of primary data will provide
meaning. It contains stages like modeling, data mining, file exporting & sources of the data
file.
Predictive applications- it contains identify management that deals with the process of
organization for commanding access to the individual data & fraud analytics will involve the
detection functionalities.
Analytics-It is the tool of big data that will offer the various packages & modules to provide
customer options.
Reporting- It contains dashboards, insight location based & reporting for real time.
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

Security- It will offer the tools to make sure for safety & security. Involves, data encryption
& single sign- on.
Technology support- It has distributed file system, map reduces, YARN & Hadoop common
(Ahmed, Abdulsamad, & Potrus, 2015).
The envisaged project team member
Table 2: Skills of stakeholder
Title skills
CEO CEO will understand the necessity of the clear &
concise communication that is brevity,
transparency, approachability, collaboration &
transformative.
Director of IT Honest & integrity, decision making, targeting
the goals, communication, organizing & strategic
thinking, effective hiring.
Strategic Partners Develop clear objectives, understanding the
uniqueness of the business, do research & keep
on communicating.
Customers Problem-solving skills, patience, positive
attitude, listening skills & clear communication.
Manager of the project Risk management, team management,
leadership, communication & negotiation.
Resource Provider Communication, publishing resources.
Staff member The ability for teamwork, communication skills,
management of time, problem-solving, &
intelligence & competency.
Data analyst It has the ability to model, analyze & interpret
the data, accuracy & attention.
Database Analyst It will understand the objectives, documentation,
technical skills, good at managing the time &
ability to manage & update the knowledge of IT.
Software engineer Object-oriented design (OOD), testing &
& single sign- on.
Technology support- It has distributed file system, map reduces, YARN & Hadoop common
(Ahmed, Abdulsamad, & Potrus, 2015).
The envisaged project team member
Table 2: Skills of stakeholder
Title skills
CEO CEO will understand the necessity of the clear &
concise communication that is brevity,
transparency, approachability, collaboration &
transformative.
Director of IT Honest & integrity, decision making, targeting
the goals, communication, organizing & strategic
thinking, effective hiring.
Strategic Partners Develop clear objectives, understanding the
uniqueness of the business, do research & keep
on communicating.
Customers Problem-solving skills, patience, positive
attitude, listening skills & clear communication.
Manager of the project Risk management, team management,
leadership, communication & negotiation.
Resource Provider Communication, publishing resources.
Staff member The ability for teamwork, communication skills,
management of time, problem-solving, &
intelligence & competency.
Data analyst It has the ability to model, analyze & interpret
the data, accuracy & attention.
Database Analyst It will understand the objectives, documentation,
technical skills, good at managing the time &
ability to manage & update the knowledge of IT.
Software engineer Object-oriented design (OOD), testing &
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

debugging of software, excellent
communication, software development, logical
thinking & problem-solving.
QA Technical skills, creative & critical,
communication & eager in learning (Mikalef,
Giannakos, Pappas, & Krogstie, 2018).
Develop a project plan
Determine Project Scope
The company of telecom in German, scope to utilize the digital technologies that serve the
improvement of understanding of customers & are being used increasingly to develop the relations
with end users and with the platform that provided for sales & marketing activities. It will enable for
creating new services & product in the manner of cost-effective &retention that will increase the
competition in the market & will contribute to rapidly altering the needs of the customer.
communication, software development, logical
thinking & problem-solving.
QA Technical skills, creative & critical,
communication & eager in learning (Mikalef,
Giannakos, Pappas, & Krogstie, 2018).
Develop a project plan
Determine Project Scope
The company of telecom in German, scope to utilize the digital technologies that serve the
improvement of understanding of customers & are being used increasingly to develop the relations
with end users and with the platform that provided for sales & marketing activities. It will enable for
creating new services & product in the manner of cost-effective &retention that will increase the
competition in the market & will contribute to rapidly altering the needs of the customer.

Figure 1: WBS
Estimate time for the project
Table 3: Time table
Specialist Number of devices Months required
Software engineer four 6
Database analyst four 1
Project manager (Big
data)
one 6
Data analyst two 6
QA engineer one 6
Director of IT four 6
Estimate time for the project
Table 3: Time table
Specialist Number of devices Months required
Software engineer four 6
Database analyst four 1
Project manager (Big
data)
one 6
Data analyst two 6
QA engineer one 6
Director of IT four 6
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

Determine resource required for project
Table 4: resource table
Resource description
Labour Labour utilized for the
task for implementation
of big data in telecom.
Materials & supplies It is not produced in
exact length. It will
generate waste.
Tools & techniques It include the resource
calendar, & estimation
techniques etc.
Gantt chart & network diagram
Gantt chart
Table 4: resource table
Resource description
Labour Labour utilized for the
task for implementation
of big data in telecom.
Materials & supplies It is not produced in
exact length. It will
generate waste.
Tools & techniques It include the resource
calendar, & estimation
techniques etc.
Gantt chart & network diagram
Gantt chart
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

ID Task
Mode
Task Name Duration Start Finish Predecessors Resource Names Cost
0 German
telecommunication
156 days Wed
01-05-19
Wed
04-12-19
€355.20
1 1. Analysis 38 days Wed
01-05-19
Fri 21-06-19 €79.68
2 1.1 Meetings
on-site
12 days Wed
01-05-19
Thu
16-05-19
Software
engineer
€19.20
3 1.2 Discussion
with
stakeholders
14 days Fri 17-05-19 Wed
05-06-19
2 Data Analyst €44.80
4 1.3 Current
document
8 days Thu
06-06-19
Mon
17-06-19
3 IT Director €10.88
5 1.4 Analysis
finished
4 days Tue
18-06-19
Fri 21-06-19 4 Manager of
project
€4.80
6 2. Designing of
architechture
43 days Mon
24-06-19
Wed
21-08-19
€65.60
7 2.1 Designing
of database
10 days Mon
24-06-19
Fri 05-07-19 5 Manager of
project
€12.00
8 2.2 Designing
of software
10 days Mon
08-07-19
Fri 19-07-19 7 Software
engineer
€16.00
9 2.3 Designing
of interface
12 days Mon
22-07-19
Tue
06-08-19
8 Database
analyst,Software
engineer
€28.80
10 2.4 Develop
the design
specification
6 days Wed
07-08-19
Wed
14-08-19
9 Database
analyst
€4.80
11 2.5 Design
finished
5 days Thu
15-08-19
Wed
21-08-19
10 Database
analyst
€4.00
12 3. System
integration &
development
48 days Thu
22-08-19
Mon
28-10-19
€160.96
13 3.1 Develop
the model of
system
12 days Thu
22-08-19
Fri 06-09-19 11 Manager of
project,Software
engineer,Data
Analyst ,IT
€97.92
14 3.2 Integrate
the model of
system
11 days Mon
09-09-19
Mon
23-09-19
13 QA engineer €11.44
15 3.3 Execute
the intial
testing
14 days Tue
24-09-19
Fri 11-10-19 14 IT Director €19.04
16 3.4
Development
finished
11 days Mon
14-10-19
Mon
28-10-19
15 IT Director
,Software
engineer
€32.56
17 4. Testing and
launch
27 days Tue
29-10-19
Wed
04-12-19
€48.96
18 4.1 Perform
the testing of
system
14 days Tue
29-10-19
Fri 15-11-19 16 Software
engineer
€22.40
19 4.2 Detect
document
issues
7 days Mon
18-11-19
Tue
26-11-19
18 Data Analyst €22.40
20 4.3 Detect the
correct issues
4 days Wed
27-11-19
Mon
02-12-19
19 QA engineer €4.16
21 4.4 Testing
finished
2 days Tue
03-12-19
Wed
04-12-19
20 €0.00
Software engineer
Data Analyst
IT Director
Manager of project
Manager of project
Software engineer
Database analyst,Software engineer
Database analyst
Database analyst
Manager of project,Software engineer,Data Analyst ,IT
QA engineer
IT Director
IT Director ,Software engineer
Software engineer
Data Analyst
QA engineer
A M J J A S O N D J F M
Half 1, 2019 Half 2, 2019 Half 1, 2020
Figure 2: Gantt chart
Network Diagram
Figure 3: Network diagram
Mode
Task Name Duration Start Finish Predecessors Resource Names Cost
0 German
telecommunication
156 days Wed
01-05-19
Wed
04-12-19
€355.20
1 1. Analysis 38 days Wed
01-05-19
Fri 21-06-19 €79.68
2 1.1 Meetings
on-site
12 days Wed
01-05-19
Thu
16-05-19
Software
engineer
€19.20
3 1.2 Discussion
with
stakeholders
14 days Fri 17-05-19 Wed
05-06-19
2 Data Analyst €44.80
4 1.3 Current
document
8 days Thu
06-06-19
Mon
17-06-19
3 IT Director €10.88
5 1.4 Analysis
finished
4 days Tue
18-06-19
Fri 21-06-19 4 Manager of
project
€4.80
6 2. Designing of
architechture
43 days Mon
24-06-19
Wed
21-08-19
€65.60
7 2.1 Designing
of database
10 days Mon
24-06-19
Fri 05-07-19 5 Manager of
project
€12.00
8 2.2 Designing
of software
10 days Mon
08-07-19
Fri 19-07-19 7 Software
engineer
€16.00
9 2.3 Designing
of interface
12 days Mon
22-07-19
Tue
06-08-19
8 Database
analyst,Software
engineer
€28.80
10 2.4 Develop
the design
specification
6 days Wed
07-08-19
Wed
14-08-19
9 Database
analyst
€4.80
11 2.5 Design
finished
5 days Thu
15-08-19
Wed
21-08-19
10 Database
analyst
€4.00
12 3. System
integration &
development
48 days Thu
22-08-19
Mon
28-10-19
€160.96
13 3.1 Develop
the model of
system
12 days Thu
22-08-19
Fri 06-09-19 11 Manager of
project,Software
engineer,Data
Analyst ,IT
€97.92
14 3.2 Integrate
the model of
system
11 days Mon
09-09-19
Mon
23-09-19
13 QA engineer €11.44
15 3.3 Execute
the intial
testing
14 days Tue
24-09-19
Fri 11-10-19 14 IT Director €19.04
16 3.4
Development
finished
11 days Mon
14-10-19
Mon
28-10-19
15 IT Director
,Software
engineer
€32.56
17 4. Testing and
launch
27 days Tue
29-10-19
Wed
04-12-19
€48.96
18 4.1 Perform
the testing of
system
14 days Tue
29-10-19
Fri 15-11-19 16 Software
engineer
€22.40
19 4.2 Detect
document
issues
7 days Mon
18-11-19
Tue
26-11-19
18 Data Analyst €22.40
20 4.3 Detect the
correct issues
4 days Wed
27-11-19
Mon
02-12-19
19 QA engineer €4.16
21 4.4 Testing
finished
2 days Tue
03-12-19
Wed
04-12-19
20 €0.00
Software engineer
Data Analyst
IT Director
Manager of project
Manager of project
Software engineer
Database analyst,Software engineer
Database analyst
Database analyst
Manager of project,Software engineer,Data Analyst ,IT
QA engineer
IT Director
IT Director ,Software engineer
Software engineer
Data Analyst
QA engineer
A M J J A S O N D J F M
Half 1, 2019 Half 2, 2019 Half 1, 2020
Figure 2: Gantt chart
Network Diagram
Figure 3: Network diagram

Estimated Cost for the project
Table 5: Cost table
Specialist Number of
devices
Cost/ hour
Software engineer four £ 71.70
Database analyst four £ 80.66
Project manager one £ 89.62
Data analyst two £ 58.25
QA engineer one £ 62.73
Director of IT four £376.38
Table 6: Phase of the project
Project Phases Software
engineer
Data
analyst
Database
analyst
Director
of IT
Big
data
PM
Designing of
architecture
2% 5% 3%
Software &
hardware
configuration
1% 5% 2%
System
integration &
development
22% 10% 3% 10%
Testing &
launch
12% 2% 1% 4%
Maintenance 10% 1% 3% 5% 3%
Total 42% 13% 10% 15% 20%
One director of IT working cost for six months is £62.77/ hour.
Four, a software engineer working cost for six months is £ 71.70/ hour.
Two, a data analyst working for four months is £ 80.66/ hour.
Table 5: Cost table
Specialist Number of
devices
Cost/ hour
Software engineer four £ 71.70
Database analyst four £ 80.66
Project manager one £ 89.62
Data analyst two £ 58.25
QA engineer one £ 62.73
Director of IT four £376.38
Table 6: Phase of the project
Project Phases Software
engineer
Data
analyst
Database
analyst
Director
of IT
Big
data
PM
Designing of
architecture
2% 5% 3%
Software &
hardware
configuration
1% 5% 2%
System
integration &
development
22% 10% 3% 10%
Testing &
launch
12% 2% 1% 4%
Maintenance 10% 1% 3% 5% 3%
Total 42% 13% 10% 15% 20%
One director of IT working cost for six months is £62.77/ hour.
Four, a software engineer working cost for six months is £ 71.70/ hour.
Two, a data analyst working for four months is £ 80.66/ hour.
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide
1 out of 22
Related Documents

Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
Copyright © 2020–2025 A2Z Services. All Rights Reserved. Developed and managed by ZUCOL.