This report presents a detailed project plan for the development of a Fitness App by App World Ink. The plan includes an executive summary, introduction, and project charter, along with a Gantt chart illustrating the project's timeline and work breakdown structure. A network diagram visualizes task dependencies, and the report defines key milestones using the SMART criteria. Resource allocation, including human and material resources, is outlined in a resources table, and the project budget is meticulously estimated across various phases. A RACI table clarifies responsibilities, and potential risks are identified and assessed via a probability impact matrix. The project aims to provide fitness tips and in-app purchases for fitness products. The project plan provides a detailed overview of the project's schedule, budget, and potential risks.

Running head: BISY2004
Bisy2004: Fitness APP
Name of Student
Name of University
Author Note
Bisy2004: Fitness APP
Name of Student
Name of University
Author Note
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

1
BISY2004
Executive Summary
The report aims in preparation of a project plan related to the development of a Fitness App by
the company App world Ink. The company is known to create all types of smartphone
application to satisfy the needs of the customers. The current project that is undertaken by App
world Ink, is based on development of a Fitness application. The application aims to provide all
the necessary fitness tips and will incorporate in app purchases for the fitness products as well.
The details of the schedule, budget and the risks are discussed in the plan that is developed.
BISY2004
Executive Summary
The report aims in preparation of a project plan related to the development of a Fitness App by
the company App world Ink. The company is known to create all types of smartphone
application to satisfy the needs of the customers. The current project that is undertaken by App
world Ink, is based on development of a Fitness application. The application aims to provide all
the necessary fitness tips and will incorporate in app purchases for the fitness products as well.
The details of the schedule, budget and the risks are discussed in the plan that is developed.

2
BISY2004
Table of Contents
Introduction..........................................................................................................................3
Background and Rationale...............................................................................................3
Project Charter.................................................................................................................3
1. Gantt chart.......................................................................................................................4
2. Network Diagram............................................................................................................5
3. Milestone.........................................................................................................................9
4. Resources Table.............................................................................................................11
5. Project Budget...............................................................................................................12
6. RACI Table....................................................................................................................16
7. Potential Risks...............................................................................................................18
8. Probability Impact Matrix..............................................................................................21
Conclusion.........................................................................................................................21
BISY2004
Table of Contents
Introduction..........................................................................................................................3
Background and Rationale...............................................................................................3
Project Charter.................................................................................................................3
1. Gantt chart.......................................................................................................................4
2. Network Diagram............................................................................................................5
3. Milestone.........................................................................................................................9
4. Resources Table.............................................................................................................11
5. Project Budget...............................................................................................................12
6. RACI Table....................................................................................................................16
7. Potential Risks...............................................................................................................18
8. Probability Impact Matrix..............................................................................................21
Conclusion.........................................................................................................................21
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

3
BISY2004
Introduction
Background and Rationale
The project plan aims in providing the readers with a detailed information regarding the
scheduling needs of development of a Fitness application. The report provide the details of the
network diagram, milestone and the resources assigned. It is quite crucial to understand
requirement of the project to set up the budget of the project in an accurate manner. The major
milestone of the project. The potential project risks and significant issues are discussed in an
effective manner. Development of the project plan aims in overseeing of all the critical tasks and
the milestone of this project. The plan provides the detail of the time estimated for finishing the
project, along with the effort needed to execute the project in a set time. The project plan further
provides an idea of the Gantt chart and the network diagram prepared for project. The probability
impact matric that is prepared as a part of the project plan provides a description of the risks that
are required to be addressed in the project.
Project Charter
Project Title: Fitness App
Date of Approval: 26th December 2018
Starting Date: 26th December 2018
Completion Date: 26th April 2019
Key Schedule Milestone: Completion of Plan by 15th January 2019, Completion of model
development by 26th February, Finalization of Model Design by 14th March and Completion of
the Project by 26th April.
BISY2004
Introduction
Background and Rationale
The project plan aims in providing the readers with a detailed information regarding the
scheduling needs of development of a Fitness application. The report provide the details of the
network diagram, milestone and the resources assigned. It is quite crucial to understand
requirement of the project to set up the budget of the project in an accurate manner. The major
milestone of the project. The potential project risks and significant issues are discussed in an
effective manner. Development of the project plan aims in overseeing of all the critical tasks and
the milestone of this project. The plan provides the detail of the time estimated for finishing the
project, along with the effort needed to execute the project in a set time. The project plan further
provides an idea of the Gantt chart and the network diagram prepared for project. The probability
impact matric that is prepared as a part of the project plan provides a description of the risks that
are required to be addressed in the project.
Project Charter
Project Title: Fitness App
Date of Approval: 26th December 2018
Starting Date: 26th December 2018
Completion Date: 26th April 2019
Key Schedule Milestone: Completion of Plan by 15th January 2019, Completion of model
development by 26th February, Finalization of Model Design by 14th March and Completion of
the Project by 26th April.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

4
BISY2004
Total Budget: $358,120.00, with $2, 50,000 for Marketing
Project Manager: Ramandeep Kaur Kaul
1. Gantt chart
The figure 1 depicts the Gantt chart of the undertaken project. The figure provides the
detailed work breakdown structure as well. The column named “WBS” indicate the work
breakdown structure and the “Task Name” indicate the task to be executed for completion of the
project on a scheduled time (Kerzner and Kerzner 2017). The Gantt chart corresponding to the
development of a fitness application are as follows-
Figure 1: The Gantt chart corresponding to development of a Fitness Application
BISY2004
Total Budget: $358,120.00, with $2, 50,000 for Marketing
Project Manager: Ramandeep Kaur Kaul
1. Gantt chart
The figure 1 depicts the Gantt chart of the undertaken project. The figure provides the
detailed work breakdown structure as well. The column named “WBS” indicate the work
breakdown structure and the “Task Name” indicate the task to be executed for completion of the
project on a scheduled time (Kerzner and Kerzner 2017). The Gantt chart corresponding to the
development of a fitness application are as follows-
Figure 1: The Gantt chart corresponding to development of a Fitness Application

5
BISY2004
The tasks which are to be executed as a part of the project is indicated in the Gantt chart.
It is observed that the entire project of development of the fitness application will take four
months. Figure 1 indicates that there are 7 major phases that are needed to be completed for
successful execution of the project. It is observed that a maximum time is allocated for the
development phase. The project will be successfully completed only if all the tasks are
completed within the scheduled deadline. The column “milestone” indicate whether a particular
activity is a milestone or not (Meredith et al., 2017). The Gantt chart indicate that the project has
7 major milestone including the last milestone, which is the “Project End”. The critical tasks of
the project are indicated in red. All the tasks marked in red indicate the project’s critical task.
2. Network Diagram
The figure 2, indicates the network diagram of the fitness application development
project. The network diagram is prepared, provide a critical view of the tasks which are to be
executed as a part of project execution phase. The network diagram of the Fitness app
development project, is depicted as follows-
BISY2004
The tasks which are to be executed as a part of the project is indicated in the Gantt chart.
It is observed that the entire project of development of the fitness application will take four
months. Figure 1 indicates that there are 7 major phases that are needed to be completed for
successful execution of the project. It is observed that a maximum time is allocated for the
development phase. The project will be successfully completed only if all the tasks are
completed within the scheduled deadline. The column “milestone” indicate whether a particular
activity is a milestone or not (Meredith et al., 2017). The Gantt chart indicate that the project has
7 major milestone including the last milestone, which is the “Project End”. The critical tasks of
the project are indicated in red. All the tasks marked in red indicate the project’s critical task.
2. Network Diagram
The figure 2, indicates the network diagram of the fitness application development
project. The network diagram is prepared, provide a critical view of the tasks which are to be
executed as a part of project execution phase. The network diagram of the Fitness app
development project, is depicted as follows-
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

6
BISY2004
BISY2004
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

7
BISY2004
BISY2004

8
BISY2004
BISY2004
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

9
BISY2004
Figure 2: Representing the Network Diagram
3. Milestone
Milestone of a project generally signifies the critical tasks that are to be executed as a part
of project implementation. The milestone for this fitness development project is identifies on
basis of SMART criteria. With the help of the SMART criteria, the key events of the
development of the fitness app project is identified on basis of the criteria, which include,
specific, measurable, attainable and relevant to the project (Fleming and Koppelman 2016). The
milestone that are indicated in the table below are specific to the project undertaken, it is
attainable, measurable and is definitely relevant to the project undertaken. The project milestone
are shown as follows-
BISY2004
Figure 2: Representing the Network Diagram
3. Milestone
Milestone of a project generally signifies the critical tasks that are to be executed as a part
of project implementation. The milestone for this fitness development project is identifies on
basis of SMART criteria. With the help of the SMART criteria, the key events of the
development of the fitness app project is identified on basis of the criteria, which include,
specific, measurable, attainable and relevant to the project (Fleming and Koppelman 2016). The
milestone that are indicated in the table below are specific to the project undertaken, it is
attainable, measurable and is definitely relevant to the project undertaken. The project milestone
are shown as follows-
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

10
BISY2004
Milestone Date Status Responsible Comment
M1: Approval of
Project Plan
Tue 15-01-19 Completed Project Manager The Plan was
approved
M2: Sending the
model product
for Approval
Mon 25-02-19 Completed Application
Designer
The Model was
ready within the
expected time
M3: Finalization
of Model Design
and
Specification
Thu 14-03-19 Completed Application
Designer
All Good
M4: The Fitness
App is Ready to
Launch
Tue 09-04-19 Completed Application
Designer
The application
launch was one
schedule
M5: Application
Launch
Thu 11-04-19 Completed Project Manager All Good
M6: Completion
of Training
Tue 23-04-19 Completed Trainer The training was
needed
BISY2004
Milestone Date Status Responsible Comment
M1: Approval of
Project Plan
Tue 15-01-19 Completed Project Manager The Plan was
approved
M2: Sending the
model product
for Approval
Mon 25-02-19 Completed Application
Designer
The Model was
ready within the
expected time
M3: Finalization
of Model Design
and
Specification
Thu 14-03-19 Completed Application
Designer
All Good
M4: The Fitness
App is Ready to
Launch
Tue 09-04-19 Completed Application
Designer
The application
launch was one
schedule
M5: Application
Launch
Thu 11-04-19 Completed Project Manager All Good
M6: Completion
of Training
Tue 23-04-19 Completed Trainer The training was
needed

11
BISY2004
M7: The Project
Ends
Fri 26-04-19 Completed Project Manager All good
The table above indicates the most significant milestone of the project considered. Since
the project has been already completed, it is observed that all the milestone are achieved within
the set date. The above indicated seven milestone was quite critical to ascertain that the Fitness
app development project has been finished in a successful manner. The table further indicates the
date of achievement of the milestone and the person who was responsible for achieving the
milestone.
4. Resources Table
Appropriate estimate and calculation of the resources needed for the project was
necessary in order to ensure that the fitness app development project is executed accordingly. For
ensuring that the fitness application is developed in effective way, the most essential resources
needed for the project is estimated and is allocated to each of the task (Heagney 2016). The
project cost is analyzed on basis of the resources and the cost of each resources. The resources
considered for this firness development project are indicated in the table below-
Resource
Name Type Materia
l Label Initials Grou
p
Max.
Units Std. Rate Ovt.
Rate Cost/Use Accrue
At
Base
Calendar Overallocated
Project
Manager Work P 100% $90.00/hr $0.00/
hr $0.00 Prorated Standard No
Business
Analyst Work B 100% $50.00/hr $0.00/
hr $0.00 Prorated Standard No
Resource
Manager Work R 100% $60.00/hr $0.00/
hr $0.00 Prorated Standard No
Marketing
Manager Work M 100% $75.00/hr $0.00/
hr $0.00 Prorated Standard No
BISY2004
M7: The Project
Ends
Fri 26-04-19 Completed Project Manager All good
The table above indicates the most significant milestone of the project considered. Since
the project has been already completed, it is observed that all the milestone are achieved within
the set date. The above indicated seven milestone was quite critical to ascertain that the Fitness
app development project has been finished in a successful manner. The table further indicates the
date of achievement of the milestone and the person who was responsible for achieving the
milestone.
4. Resources Table
Appropriate estimate and calculation of the resources needed for the project was
necessary in order to ensure that the fitness app development project is executed accordingly. For
ensuring that the fitness application is developed in effective way, the most essential resources
needed for the project is estimated and is allocated to each of the task (Heagney 2016). The
project cost is analyzed on basis of the resources and the cost of each resources. The resources
considered for this firness development project are indicated in the table below-
Resource
Name Type Materia
l Label Initials Grou
p
Max.
Units Std. Rate Ovt.
Rate Cost/Use Accrue
At
Base
Calendar Overallocated
Project
Manager Work P 100% $90.00/hr $0.00/
hr $0.00 Prorated Standard No
Business
Analyst Work B 100% $50.00/hr $0.00/
hr $0.00 Prorated Standard No
Resource
Manager Work R 100% $60.00/hr $0.00/
hr $0.00 Prorated Standard No
Marketing
Manager Work M 100% $75.00/hr $0.00/
hr $0.00 Prorated Standard No
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide
1 out of 23
Related Documents
Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
Copyright © 2020–2025 A2Z Services. All Rights Reserved. Developed and managed by ZUCOL.