Detailed Change Control Report: PROJ6003 Blue Spider Project Analysis
VerifiedAdded on 2022/08/12
|12
|2077
|32
Report
AI Summary
This report provides a comprehensive analysis of the change control process within the Blue Spider project. It begins by identifying crucial changes needed, such as revisions to the project plan, communication strategies, and resource allocation, highlighting their impact on project scope, time, cost, and quality. The report details the process of submitting change requests, emphasizing the importance of prioritization and communication. It then outlines options for satisfying each change, along with associated risks, and presents a complete change request form. The analysis covers changes in design material, project plans, communication strategies, and resource allocation, along with the associated risks and mitigation strategies. The report concludes by summarizing the key changes and the importance of change management in ensuring the project's success, offering valuable insights into effective project execution and control.

Running head: BUSINESS PROJECT MANAGEMENT
Business Project Management Part B: Change Control
Name of Student
Name of University
Author Note
Business Project Management Part B: Change Control
Name of Student
Name of University
Author Note
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

1BUSINESS PROJECT MANAGEMENT
Table of Contents
Introduction..........................................................................................................................2
1. Identification of the Changes Required...........................................................................2
2. Process of Submitting a Change Request........................................................................5
3. Options to satisfy each change and Risks........................................................................6
4. Change Request Form......................................................................................................8
Conclusion...........................................................................................................................9
Bibliography......................................................................................................................10
Table of Contents
Introduction..........................................................................................................................2
1. Identification of the Changes Required...........................................................................2
2. Process of Submitting a Change Request........................................................................5
3. Options to satisfy each change and Risks........................................................................6
4. Change Request Form......................................................................................................8
Conclusion...........................................................................................................................9
Bibliography......................................................................................................................10

2BUSINESS PROJECT MANAGEMENT
Introduction
Change is an inevitable part of any project and proper management of changes in a
project is necessary to ensure that a project is proceeding as per plan (Heldman, 2018). Effective
project management is associated with proper change control and change management so that at
the end of the project, the key project specifications are met (Stackpole, 2013). A number of
problems were identified for the blue spider project that needed effective management to ensure
that the project is a success. In the following paragraphs the changes that were needed in the blue
spider project were identified followed by discussing the process of submitting a change. The
report further discusses the options of satisfying each change and the key risks associated with
the option of change. The report provides the evidence of a complete change request form
associated with the chosen project.
1. Identification of the Changes Required
The case study Blue Spider needed significant changes that could have eliminated or
significantly reduced the chances of project failure.
The analysis of the case indicated that there were certain issues with the project plan that
lead to the project going over budget. The key change that is needed in the blue spider project is
redesign and develop the project plan that will ensure that the key specification of the project are
met.
Another change that is essential for the project include change in the communication
process of the project. There were issues with the communication within the team as the team
lacked effective communication. To formulate this change and incorporate the same in the
project it is essential to properly identify the key communication needs in the project.
Introduction
Change is an inevitable part of any project and proper management of changes in a
project is necessary to ensure that a project is proceeding as per plan (Heldman, 2018). Effective
project management is associated with proper change control and change management so that at
the end of the project, the key project specifications are met (Stackpole, 2013). A number of
problems were identified for the blue spider project that needed effective management to ensure
that the project is a success. In the following paragraphs the changes that were needed in the blue
spider project were identified followed by discussing the process of submitting a change. The
report further discusses the options of satisfying each change and the key risks associated with
the option of change. The report provides the evidence of a complete change request form
associated with the chosen project.
1. Identification of the Changes Required
The case study Blue Spider needed significant changes that could have eliminated or
significantly reduced the chances of project failure.
The analysis of the case indicated that there were certain issues with the project plan that
lead to the project going over budget. The key change that is needed in the blue spider project is
redesign and develop the project plan that will ensure that the key specification of the project are
met.
Another change that is essential for the project include change in the communication
process of the project. There were issues with the communication within the team as the team
lacked effective communication. To formulate this change and incorporate the same in the
project it is essential to properly identify the key communication needs in the project.
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

3BUSINESS PROJECT MANAGEMENT
Another change that is required in the blue spider project is related to management of the
human resources. The analysis of the case study indicate that there are certain issues that were
faced with the management of the human resources. The changes were needed in terms of
allocation of the human resources throughout the entire duration of the blue spider project.
The identified changes in the project will have certain impact on scope, time, cost and
quality of a project. The impact of the said changes and the technique of managing the impact of
the changes on scope, time, cost and quality of the project are indicated in the following table-
Changes Needed Impact on Scope, Time,
Cost and Quality
Techniques to Manage the
Impact
Changes in Project Plan Time: The project might
require additional time for
completion (Hornstein,
2015)
Cost: Changes in Project plan
while the project is in its
execution stage might incur
additional cost to complete
the project
The impact on the time and
cost can be managed by the
technique of project crashing.
Project crashing can
accelerate the project
schedule and can help in
completion of the project on
time. Crashing some
unimportant tasks will help in
releasing the cost associated
with those tasks, thus helping
in managing the project
scope.
Changes in Communication Scope: The change in the The change in the scope of
Another change that is required in the blue spider project is related to management of the
human resources. The analysis of the case study indicate that there are certain issues that were
faced with the management of the human resources. The changes were needed in terms of
allocation of the human resources throughout the entire duration of the blue spider project.
The identified changes in the project will have certain impact on scope, time, cost and
quality of a project. The impact of the said changes and the technique of managing the impact of
the changes on scope, time, cost and quality of the project are indicated in the following table-
Changes Needed Impact on Scope, Time,
Cost and Quality
Techniques to Manage the
Impact
Changes in Project Plan Time: The project might
require additional time for
completion (Hornstein,
2015)
Cost: Changes in Project plan
while the project is in its
execution stage might incur
additional cost to complete
the project
The impact on the time and
cost can be managed by the
technique of project crashing.
Project crashing can
accelerate the project
schedule and can help in
completion of the project on
time. Crashing some
unimportant tasks will help in
releasing the cost associated
with those tasks, thus helping
in managing the project
scope.
Changes in Communication Scope: The change in the The change in the scope of
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

4BUSINESS PROJECT MANAGEMENT
Plan communication process can
significantly impact the scope
of the project. There is a
probability enhancement of
project scope (Heagney,
2016).
the project is needed to be
accepted since there is a
probability of scope
enhancement in the blue
spider project. After changing
the communication plan, the
scope of the project is needed
to be controlled (Yap, Abdul-
Rahman & Chen, 2017)
Changes Resource
Management and Resource
Allocation
Cost: Any change in the
resource needs of a project
can significantly affect the
cost of the project leading to
an increase in the project cost
(Hayes, 2018).
The impact on the cost due to
change in resource
management and allocation
can be managed by ensuring
that none of the project tasks
are delayed. Any delay in the
project can result in
requirement of resources for a
longer time, thus increasing
the overall project cost.
Changes in design material Cost: This change will have a
significant impact on the
project cost.
This change is necessary or
else the project will not be
able to meet the initial
specification. The impact of
Plan communication process can
significantly impact the scope
of the project. There is a
probability enhancement of
project scope (Heagney,
2016).
the project is needed to be
accepted since there is a
probability of scope
enhancement in the blue
spider project. After changing
the communication plan, the
scope of the project is needed
to be controlled (Yap, Abdul-
Rahman & Chen, 2017)
Changes Resource
Management and Resource
Allocation
Cost: Any change in the
resource needs of a project
can significantly affect the
cost of the project leading to
an increase in the project cost
(Hayes, 2018).
The impact on the cost due to
change in resource
management and allocation
can be managed by ensuring
that none of the project tasks
are delayed. Any delay in the
project can result in
requirement of resources for a
longer time, thus increasing
the overall project cost.
Changes in design material Cost: This change will have a
significant impact on the
project cost.
This change is necessary or
else the project will not be
able to meet the initial
specification. The impact of

5BUSINESS PROJECT MANAGEMENT
the change can be only be
managed by asking additional
time from the client to
implement this particular
change on the project.
2. Process of Submitting a Change Request
The process of submission of a change request plays a significant role in incorporation of
the key changes in the project. There are certain essential steps that are needed to be followed for
managing the changes in the project (Dawson, 2019). The process of change request that is to be
followed for the blue spider project are indicated as follows-
1. Identification of the necessary and required changes in the project.
2. Determining whether a particular change is within the scope of the project or out of the
scope
3. Assessing the priority of the proposed changes and deciding the course of action
4. Drafting the request for the required changes in the project (Cameron & Green, 2019)
On analysis of the case study, it is observed that certain changes are required in the
project plan, communication plan and in management of the resources needed for the project. On
assessment of the changes needed, it is observed that the change in the project plan and the
communication plan is needed to be prioritized. Therefore, the project team should work
on/implement these changes on the project to reduce the chances of project failure.
the change can be only be
managed by asking additional
time from the client to
implement this particular
change on the project.
2. Process of Submitting a Change Request
The process of submission of a change request plays a significant role in incorporation of
the key changes in the project. There are certain essential steps that are needed to be followed for
managing the changes in the project (Dawson, 2019). The process of change request that is to be
followed for the blue spider project are indicated as follows-
1. Identification of the necessary and required changes in the project.
2. Determining whether a particular change is within the scope of the project or out of the
scope
3. Assessing the priority of the proposed changes and deciding the course of action
4. Drafting the request for the required changes in the project (Cameron & Green, 2019)
On analysis of the case study, it is observed that certain changes are required in the
project plan, communication plan and in management of the resources needed for the project. On
assessment of the changes needed, it is observed that the change in the project plan and the
communication plan is needed to be prioritized. Therefore, the project team should work
on/implement these changes on the project to reduce the chances of project failure.
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

6BUSINESS PROJECT MANAGEMENT
The process of submitting a change request involves communication of the key changes
needed in the project along with communicating the changes so that the project team remains
prepared for the changes that will be incorporated. The course of action of going forward with
the change is required to the communicated to the team to ascertain successful implementation of
the changes in the project. On acceptance and acknowledgement of the changes needed in the
project by all the team members, a change request is successfully submitted.
3. Options to satisfy each change and Risks
The analysis of the Blue Spider project case has indicated four major changes that are
needed to be incorporated in the project to ascertain that the initial specification and the
requirements of the project are met. The options to satisfy each change and the risk associated
with the options of implementation of the change are indicated in the following table-
Changes Needed Option to satisfy the
Change Request
Risks Associated with
change request
Need of changing the
preliminary design material
This change is needed to be
incorporated in the project to
ensure that the initial project
criteria are met. This change
request can be executed
successfully by
communicating the issue to
the client and buying some
time from the client
The key risk associated with
the option is that there are
high probability of client
getting dissatisfied or client
refusing to make any
additional payment for the
same.
The process of submitting a change request involves communication of the key changes
needed in the project along with communicating the changes so that the project team remains
prepared for the changes that will be incorporated. The course of action of going forward with
the change is required to the communicated to the team to ascertain successful implementation of
the changes in the project. On acceptance and acknowledgement of the changes needed in the
project by all the team members, a change request is successfully submitted.
3. Options to satisfy each change and Risks
The analysis of the Blue Spider project case has indicated four major changes that are
needed to be incorporated in the project to ascertain that the initial specification and the
requirements of the project are met. The options to satisfy each change and the risk associated
with the options of implementation of the change are indicated in the following table-
Changes Needed Option to satisfy the
Change Request
Risks Associated with
change request
Need of changing the
preliminary design material
This change is needed to be
incorporated in the project to
ensure that the initial project
criteria are met. This change
request can be executed
successfully by
communicating the issue to
the client and buying some
time from the client
The key risk associated with
the option is that there are
high probability of client
getting dissatisfied or client
refusing to make any
additional payment for the
same.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

7BUSINESS PROJECT MANAGEMENT
Need of changing the plan
prepared for the project
Certain management
problems are identified in the
project and for that change in
the project plan is needed.
The option is to identify the
key issues and modifying the
plan accordingly to ensure
that the initial specifications
of the project are met.
The key risk associated with
brining in a change in the
project plan is that there is a
high probability of the project
facing a delay (Hillson,
2017).
Need of bringing in changes
in the existing
communication plan
The communication needs of
the team members are to be
identified and accordingly the
existing communication plan
is to be modified
The key risk associated with
the option is that changing the
communication plan while
the project is in the execution
stage might impact the time
required for completion of a
particular activity (Carvalho
& Rabechini Junior,2015).
Need of bringing in changes
in the process of resource
allocation and resource
management
The changes in the resource
allocation can be managed by
assessing the main resource
needs of the project and
allocating each resource to a
particular task
Addition of new resources in
the project can increase the
risk of cost overrun.
Need of changing the plan
prepared for the project
Certain management
problems are identified in the
project and for that change in
the project plan is needed.
The option is to identify the
key issues and modifying the
plan accordingly to ensure
that the initial specifications
of the project are met.
The key risk associated with
brining in a change in the
project plan is that there is a
high probability of the project
facing a delay (Hillson,
2017).
Need of bringing in changes
in the existing
communication plan
The communication needs of
the team members are to be
identified and accordingly the
existing communication plan
is to be modified
The key risk associated with
the option is that changing the
communication plan while
the project is in the execution
stage might impact the time
required for completion of a
particular activity (Carvalho
& Rabechini Junior,2015).
Need of bringing in changes
in the process of resource
allocation and resource
management
The changes in the resource
allocation can be managed by
assessing the main resource
needs of the project and
allocating each resource to a
particular task
Addition of new resources in
the project can increase the
risk of cost overrun.

8BUSINESS PROJECT MANAGEMENT
4. Change Request Form
Project name: The Blue Spider Project
Requested By: Project Manager
Change Description: Change in Design Material
Change Reason: The materials failed to meet the initial specification
Impact of Change: Increase in project cost and time
Proposed Action: Change in design material is inevitable
Status: In progress
Approved by: Project Client
Project name: The Blue Spider Project
Requested By: Project Manager
Change Description: Change in Project Plan and communication plan and resource plan
Change Reason: Issues with Project Management is faced
Impact of Change: Impact on project Cost
Proposed Action: Changes to be incorporated to manage the project effectively. The entire
plan is to be modified in consideration to the issues faced.
Status: Approved
Approved by: Project Client
Conclusion
4. Change Request Form
Project name: The Blue Spider Project
Requested By: Project Manager
Change Description: Change in Design Material
Change Reason: The materials failed to meet the initial specification
Impact of Change: Increase in project cost and time
Proposed Action: Change in design material is inevitable
Status: In progress
Approved by: Project Client
Project name: The Blue Spider Project
Requested By: Project Manager
Change Description: Change in Project Plan and communication plan and resource plan
Change Reason: Issues with Project Management is faced
Impact of Change: Impact on project Cost
Proposed Action: Changes to be incorporated to manage the project effectively. The entire
plan is to be modified in consideration to the issues faced.
Status: Approved
Approved by: Project Client
Conclusion
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

9BUSINESS PROJECT MANAGEMENT
The report provides an idea of the key changes that are needed in the blue spider project.
The need of changing the design material, project plan, communication plan and the resource
plan is discussed in the report. The process of incorporation of the change is documented in the
report and risk associated with the change are discussed in the report. A change request form for
the key change needed in the project is drafted.
The report provides an idea of the key changes that are needed in the blue spider project.
The need of changing the design material, project plan, communication plan and the resource
plan is discussed in the report. The process of incorporation of the change is documented in the
report and risk associated with the change are discussed in the report. A change request form for
the key change needed in the project is drafted.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

10BUSINESS PROJECT MANAGEMENT
Bibliography
Abrell-Vogel, C., & Rowold, J. (2014). Leaders’ commitment to change and their effectiveness
in change–a multilevel investigation. Journal of organizational change management.
Cameron, E., & Green, M. (2019). Making sense of change management: A complete guide to
the models, tools and techniques of organizational change. Kogan Page Publishers.
Carvalho, M. M. D., & Rabechini Junior, R. (2015). Impact of risk management on project
performance: the importance of soft skills. International Journal of Production
Research, 53(2), 321-340.
Dawson, P. (2019). Reshaping change: A processual perspective. Routledge.
Hayes, J. (2018). The theory and practice of change management. Palgrave.
Heagney, J. (2016). Fundamentals of project management. Amacom.
Heldman, K. (2018). PMP: project management professional exam study guide. John Wiley &
Sons.
Hillson, D. (2017). Managing risk in projects. Routledge.
Hornstein, H. A. (2015). The integration of project management and organizational change
management is now a necessity. International Journal of Project Management, 33(2),
291-298.
Jayatilleke, S., & Lai, R. (2018). A systematic review of requirements change
management. Information and Software Technology, 93, 163-185.
Bibliography
Abrell-Vogel, C., & Rowold, J. (2014). Leaders’ commitment to change and their effectiveness
in change–a multilevel investigation. Journal of organizational change management.
Cameron, E., & Green, M. (2019). Making sense of change management: A complete guide to
the models, tools and techniques of organizational change. Kogan Page Publishers.
Carvalho, M. M. D., & Rabechini Junior, R. (2015). Impact of risk management on project
performance: the importance of soft skills. International Journal of Production
Research, 53(2), 321-340.
Dawson, P. (2019). Reshaping change: A processual perspective. Routledge.
Hayes, J. (2018). The theory and practice of change management. Palgrave.
Heagney, J. (2016). Fundamentals of project management. Amacom.
Heldman, K. (2018). PMP: project management professional exam study guide. John Wiley &
Sons.
Hillson, D. (2017). Managing risk in projects. Routledge.
Hornstein, H. A. (2015). The integration of project management and organizational change
management is now a necessity. International Journal of Project Management, 33(2),
291-298.
Jayatilleke, S., & Lai, R. (2018). A systematic review of requirements change
management. Information and Software Technology, 93, 163-185.

11BUSINESS PROJECT MANAGEMENT
Stackpole, C. S. (2013). A project manager's book of forms: A companion to the PMBOK guide.
John Wiley & Sons.
Yap, J. B. H., Abdul-Rahman, H., & Chen, W. (2017). Collaborative model: Managing design
changes with reusable project experiences through project learning and effective
communication. International Journal of Project Management, 35(7), 1253-1271.
Stackpole, C. S. (2013). A project manager's book of forms: A companion to the PMBOK guide.
John Wiley & Sons.
Yap, J. B. H., Abdul-Rahman, H., & Chen, W. (2017). Collaborative model: Managing design
changes with reusable project experiences through project learning and effective
communication. International Journal of Project Management, 35(7), 1253-1271.
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide
1 out of 12
Related Documents

Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
Copyright © 2020–2025 A2Z Services. All Rights Reserved. Developed and managed by ZUCOL.