This project scoping report details the plan to modify and upgrade ABC Pvt. Ltd.'s website, a consultancy and software solutions provider. The report includes a project scope outlining website modifications, new feature additions, and overall website upgrades. It identifies stakeholders such as the sponsor, project leader, supervisor, and website developer, detailing their involvement. The report addresses potential issues like security risks and system complexity, along with assumptions regarding budget and timelines. It also presents a risk management plan addressing cyber security threats and development complications. The report proposes initial timelines, task allocations, and relationships with other projects. Additionally, it provides a detailed budget, resource requirements, and quality assurance measures, along with the impact of relevant legislation. Finally, the report concludes with recommendations to ensure the project's success, emphasizing timely completion, promotion, and online security.
Document Page
Running Head: PROJECT MANAGEMENT
Project Management
Name of the Student
Name of the University
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
1PROJECT MANAGEMENT
1. Introduction
ABC Pvt. Ltd. is a private business organization that provides consultancy services and
software solutions to a wide range of clients from small and medium sized organizations to large
business organizations. The company has an official website but it only has limited features and
meant for information display only. The company now wants to update the website and add more
functions that will benefit the business of the company.
2. Project Scoping Report
i. Project Scope
The scope of the project includes the following.
Modification of the company website
Addition of new features in the website
Upgradation of the complete website
ii. Stakeholder Identification
The stakeholders are identified as follows.
Stakeholder Name Designation Extent of Involvement
Mr. B. Banner Sponsor High
Mr. A. Hughes Project Leader Very High
Mr. C. Charles Project Supervisor High
Mr. D. Andrews Chief Website Developer Medium
Document Page
2PROJECT MANAGEMENT
iii. Identification of Issues
Some of possible issues and constraints are as follows.
The website update may bring about some unnecessary issues like chances of
external attacks, breach of security of the internal server of company and others.
The website update may become very complicated and the existing staffs may not
be able to control the functionalities of the website.
The company may face problems in the near future for system and server
maintenance.
iv. Assumptions
The following assumptions have been made in the project.
The decided budget is sufficient for the project.
The projected timeline of 3 months is sufficient for the project.
This project will fulfill the company’s requirement for a business portal.
The business portal will have all the features required by the company without
any technical issues or problems.
v. Risks Associated
Some of the risks associated and the management solutions are as follows.
Risk Management Plan
Cyber security risk may occur due to malware,
unauthorized access, hacking, injection of
malicious files and others
Installation of firewalls and anti-virus software
The addition of new features in the website may Following a standard development model along
Document Page
3PROJECT MANAGEMENT
result in creation of many bugs and complications with phase by phase implementation of the features
Budget overshoot may occur due to overspending
and lack of clear scope definition
Define scope and develop appropriate spending
plan for the project
vi. Initial Timelines
Proposed project timeline Time Required
Project lifespan: include dates or total time required for
completion
3 Months
Phase 1: Scoping and feasibility 0.5 Months
Phase 2: Planning 0.5 Months
Phase 3: Implementation 2 Months
Phase 4: Evaluation 1 Month
vii. Representation of Task Allocations
The management and supervision duties will be allocated to the project leader and the
supervisor. The supervisor will preside over the project execution and report to the project leader
who will then review the project progress on weekly basis. The Chief Website Developer will be
responsible for the website update and can appoint his team of developers and testers to complete
all the activities.
viii. Relationship with Other Projects
This project will help the company to handle future projects much more efficiently as the
new business portal will allow the company to automate data processing, handling and
management. Moreover, client involvement with the future projects will also increase with the
development of the online business portal.
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
4PROJECT MANAGEMENT
ix. Costs, Resources and Quality Assurance
Proposed budget
Hardware $ 2500
Software Platform $ 1000
Software Tool $ 1000
Software Development Program $ 2000
Other Costs including Conveyances $ 500
Total of proposed budget $ 7000
As seen from the budget estimation, it is seen that the main resource requirements for the
project include necessary hardware and software needed for updating the company website.
Quality assurance includes fulfilling all the requirements of the project including the new
features of the website, development of the business portal, content update and others. The final
product must not have any bugs and any security loopholes that may compromise the personal
information of the clients.
x. Impact of Relevant Legislation
For this project, the most relevant legislation is the Canadian Information and
Technology Law that provides guidelines on IT implementation and maintenance. During
planning of the project, the relevant legislations must be considered so that the company does not
get associated with any legal complications. Furthermore, the company must also ensure all the
software purchased are licensed versions and purchased from non-piracy websites / online
vendors.
Document Page
5PROJECT MANAGEMENT
xi. Measurement of Degree of Success
Degree of success is generally measured by the extent of benefits received from a project.
In this project, the degree of success will be measured by the quality of the new business portal
and the benefits received from the business portal for the business operations of the company.
3. Conclusion and Recommendations
Finally, it can be concluded that the company can go ahead with the plan for upgradation
of the website within the estimated budget but needs to ensure that the benefits will be achieved
within a very short time. The customers will be able to open their own profiles in the business
portal and conduct business through the portal only.
Some recommendations to the company for project are as follows.
The company must ensure the entire project is completed within the specified
time period and within the specified budget.
The company must promote the business portal among the customers.
The company must ensure the online security of the business portal for preventing
compromise of the personal information of the clients.
Document Page
6PROJECT MANAGEMENT
Bibliography
Kerzner, Harold, and Harold R. Kerzner. Project management: a systems approach to planning,
scheduling, and controlling. John Wiley & Sons, 2017.
Fleming, Quentin W., and Joel M. Koppelman. "Earned value project management." Project
Management Institute, 2016.
Heagney, Joseph. Fundamentals of project management. Amacom, 2016.
Harrison, Frederick, and Dennis Lock. Advanced project management: a structured approach.
Routledge, 2017.