CPCCBC5003A: On-site Construction Planning and Supervision Report
VerifiedAdded on 2022/12/27
|11
|1750
|88
Report
AI Summary
This report provides a detailed review of the planning and supervision of on-site medium-rise building construction. It covers several key aspects, including the availability and suitability of subcontractors, material procurement and authorized purchases, site access and accommodation, and maintaining contact with relevant statutory authorities. The report emphasizes the importance of a Gantt chart for tracking critical events, milestones, labor and material supply, and equipment availability. It also addresses issues related to cost-benefit analysis and schedule maintenance. The methodology involves establishing clear communication channels, defining subcontractor responsibilities, and ensuring quality control. The report includes a review of regulatory requirements, contract requirements, and site safety protocols. The conclusion highlights the importance of safety in both demolition and construction phases and provides a list of relevant references.

SUPERVISE THE PLANNING OF ON-SITE MEDIUM RISE BUILDING OR
CONSTRUCTION WORK
By Name
Course
Instructor
Institution
Location
Date
CONSTRUCTION WORK
By Name
Course
Instructor
Institution
Location
Date
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Assessment task.
Section C – Instructions to students
Task instructions:
Following on from assessment task 2 and 3,
Availability of subcontractors and their suitability to meet job requirements is reviewed.
Availability of materials and conditions of purchase and authorised purchases are reviewed.
Access to the site is established within requirements and on-site accommodation is located in an appropriate location.
Contact is established and maintained with relevant statutory authorities controlling construction work.
Gantt Chart Using the template provided.
critical events and milestones
labour supply and availability information
materials supply and availability information
plant and equipment availability information
services provision
Issues related to conducting a cost benefit analysis
How will the schedule be maintained and monitored?
Section C – Instructions to students
Task instructions:
Following on from assessment task 2 and 3,
Availability of subcontractors and their suitability to meet job requirements is reviewed.
Availability of materials and conditions of purchase and authorised purchases are reviewed.
Access to the site is established within requirements and on-site accommodation is located in an appropriate location.
Contact is established and maintained with relevant statutory authorities controlling construction work.
Gantt Chart Using the template provided.
critical events and milestones
labour supply and availability information
materials supply and availability information
plant and equipment availability information
services provision
Issues related to conducting a cost benefit analysis
How will the schedule be maintained and monitored?

Introduction
Aim
i. To review the Availability of subcontractors and their suitability to meet job
requirements.
ii. To review the Availability of materials and conditions of purchase and authorised
purchases are.
iii. To Access that the site is established within requirements and on-site accommodation is
located in an appropriate location.
iv. To explore that the contact is established and maintained with relevant statutory
authorities controlling construction work.
v. To review that the Gantt Chart is made in accordance with provided details such as
a) critical events and milestones
b) labour supply and availability information
c) materials supply and availability information
d) plant and equipment availability information
e) services provision
vi. to investigate the Issues related to conducting a cost benefit analysis
vii. to outline how the schedules will be maintained and monitored
Purpose
The purpose of this review is to highlight the relationship between the contractors and the
subcontractor in the subversion of the planning of on-site medium rise building and the various
Aim
i. To review the Availability of subcontractors and their suitability to meet job
requirements.
ii. To review the Availability of materials and conditions of purchase and authorised
purchases are.
iii. To Access that the site is established within requirements and on-site accommodation is
located in an appropriate location.
iv. To explore that the contact is established and maintained with relevant statutory
authorities controlling construction work.
v. To review that the Gantt Chart is made in accordance with provided details such as
a) critical events and milestones
b) labour supply and availability information
c) materials supply and availability information
d) plant and equipment availability information
e) services provision
vi. to investigate the Issues related to conducting a cost benefit analysis
vii. to outline how the schedules will be maintained and monitored
Purpose
The purpose of this review is to highlight the relationship between the contractors and the
subcontractor in the subversion of the planning of on-site medium rise building and the various
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

mechanisms in which the prime contractor will ascertain that the deliverables are of quality from
the subcontractors as well as the establishments of long term business relationship
Scope
The document will be applicable to all the sections of the project. The contractor as well
as all the subcontractors will adhere to the regulations and rules as highlighted in the document.
Methodology
I. The below guiding principles will be applied in managing all the subcontractors.
II. An establishment of a project office for effective support to the needs and concerns of the
subcontractors.
III. There will be clear and well defined and established communication channels
IV. A team will be jointly constituted who together with the team of the subcontractors so
that the areas of responsibility are clearly defined.
V. For each subcontractor, the delivers bales will be identified and the content required be
clearly highlighted in the statement of work
VI. All the difficulties for the contractor will be identified in a clear manner and detailed in
the statement of work
VII. Each of the subcontractors will have their duties clearly identified in a statement of work
as well as the constrains such as the required contents
VIII. The requirements of quality for each subcontractor will be required and clearly identified
in a statement of work as well as the necessities in order to enable for independent quality
assurance and process.
the subcontractors as well as the establishments of long term business relationship
Scope
The document will be applicable to all the sections of the project. The contractor as well
as all the subcontractors will adhere to the regulations and rules as highlighted in the document.
Methodology
I. The below guiding principles will be applied in managing all the subcontractors.
II. An establishment of a project office for effective support to the needs and concerns of the
subcontractors.
III. There will be clear and well defined and established communication channels
IV. A team will be jointly constituted who together with the team of the subcontractors so
that the areas of responsibility are clearly defined.
V. For each subcontractor, the delivers bales will be identified and the content required be
clearly highlighted in the statement of work
VI. All the difficulties for the contractor will be identified in a clear manner and detailed in
the statement of work
VII. Each of the subcontractors will have their duties clearly identified in a statement of work
as well as the constrains such as the required contents
VIII. The requirements of quality for each subcontractor will be required and clearly identified
in a statement of work as well as the necessities in order to enable for independent quality
assurance and process.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

IX. The services and products which are offered by the subcontractors will be with regards to
the acceptance from the contractors.
X. Appropriate terms and conditions will be specified for each of the subcontract.
XI. Facilities will be provided in adequacy so as to meet the needs of the subcontractors.
XII. The chief contractor will be able to offers support to the subcontractors in services such
as processing of payments, invoices, in reference to the materials which will be delivered
to the contractor in an acceptable form for consignment to the contractor. The contractor
thus will generate a format requirements for the invoices.
Background
This review concerns the tender was for the construction four stories having a floor of 1200
square meters. There is some key regulatory requirement for the construction of the above-
chosen building. Basically, these requirements are the ones which govern the whole process of
the construction of buildings and it is not limited to the selected housing
CONTRACT
REQUIREMENTS
No/yes Contractor’s
Comments
Principal’s
Verification
1. A site safety plan has been developed
from hazard identification and risk
assessment data, and is revised as
necessary.
2. Supervision ensures that the contractor’s
work methods on site conform to the site
safety plan requirements.
3. All relevant specifications, drawings and
work plans are available on site.
4. The Contractor has obtained all relevant
permits, licences and approvals and
copies are available on site.
5. The Contractor has up to date copies of
all correspondence, instructions and
directives relevant to health and safety.
the acceptance from the contractors.
X. Appropriate terms and conditions will be specified for each of the subcontract.
XI. Facilities will be provided in adequacy so as to meet the needs of the subcontractors.
XII. The chief contractor will be able to offers support to the subcontractors in services such
as processing of payments, invoices, in reference to the materials which will be delivered
to the contractor in an acceptable form for consignment to the contractor. The contractor
thus will generate a format requirements for the invoices.
Background
This review concerns the tender was for the construction four stories having a floor of 1200
square meters. There is some key regulatory requirement for the construction of the above-
chosen building. Basically, these requirements are the ones which govern the whole process of
the construction of buildings and it is not limited to the selected housing
CONTRACT
REQUIREMENTS
No/yes Contractor’s
Comments
Principal’s
Verification
1. A site safety plan has been developed
from hazard identification and risk
assessment data, and is revised as
necessary.
2. Supervision ensures that the contractor’s
work methods on site conform to the site
safety plan requirements.
3. All relevant specifications, drawings and
work plans are available on site.
4. The Contractor has obtained all relevant
permits, licences and approvals and
copies are available on site.
5. The Contractor has up to date copies of
all correspondence, instructions and
directives relevant to health and safety.

CONTRACT
REQUIREMENTS
No/yes Contractor’s
Comments
Principal’s
Verification
6. The Contractor conducts regular site
safety inspections and records of the
inspections are available.
7. The Contractor has copies of Material
Safety Data Sheets for all substances
used on site.
8. Copies of relevant legislation, standards
and codes of practice are available on
site.
9. The Contractor has nominated a person
on site with overall responsibility for
health & safety matters.
10. Work site boundaries have been defined
and access restrictions are enforced to
prevent unauthorised entry.
11. The Contractor maintains a site visitor’s
book which is kept up to date.
12. Safe means of access and egress to the
site are maintained.
13. The Contractor has implemented a site
safety induction program and records are
maintained.
14. Safety / Warning signs are in place and
maintained in good order.
15. Permit to work procedures are operating
for confined space entry, hot work etc.
16. Isolation / Tagging systems are used for
unsafe or defective equipment.
17. Site emergency response plans have
been developed and are regularly
practiced.
18. An up to date Accident / Incident report
book is maintained and WorkCover is
notified of incidents where required by
legislation.
19. All Accident / Incident investigations are
up to date and completed satisfactorily.
20. First aid facilities and trained personnel
are available on site.
21. A site safety committee has been formed
and meets regularly.
22. Minutes of the site safety committee
meetings are maintained and published.
REQUIREMENTS
No/yes Contractor’s
Comments
Principal’s
Verification
6. The Contractor conducts regular site
safety inspections and records of the
inspections are available.
7. The Contractor has copies of Material
Safety Data Sheets for all substances
used on site.
8. Copies of relevant legislation, standards
and codes of practice are available on
site.
9. The Contractor has nominated a person
on site with overall responsibility for
health & safety matters.
10. Work site boundaries have been defined
and access restrictions are enforced to
prevent unauthorised entry.
11. The Contractor maintains a site visitor’s
book which is kept up to date.
12. Safe means of access and egress to the
site are maintained.
13. The Contractor has implemented a site
safety induction program and records are
maintained.
14. Safety / Warning signs are in place and
maintained in good order.
15. Permit to work procedures are operating
for confined space entry, hot work etc.
16. Isolation / Tagging systems are used for
unsafe or defective equipment.
17. Site emergency response plans have
been developed and are regularly
practiced.
18. An up to date Accident / Incident report
book is maintained and WorkCover is
notified of incidents where required by
legislation.
19. All Accident / Incident investigations are
up to date and completed satisfactorily.
20. First aid facilities and trained personnel
are available on site.
21. A site safety committee has been formed
and meets regularly.
22. Minutes of the site safety committee
meetings are maintained and published.
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

CONTRACT
REQUIREMENTS
No/yes Contractor’s
Comments
Principal’s
Verification
23. Health and safety issues have been
resolved in a timely manner.
24. Any outstanding prohibition or
improvement notices from WorkCover
inspections are being addressed.
25. The Contractor monitors the safety
performance of all subcontractors on site
and records are available.
26. Hazard identifications and risk
assessments are available for the plant
and equipment used on site.
27. Inspection, maintenance and service
records are available for the plant and
equipment used on site.
28. Fire protection equipment is available on
site and maintained in good working
order.
29. Personal protective equipment is
available and maintained in good
working order.
30. Flammable materials, gas cylinders and
other hazardous substances are stored
safely on site.
31. Facilities, amenities and the standard of
general housekeeping on site are
satisfactory.
Contractor’s Representative:
Principal’s Representative:
Signature:
Signature:
Conclusion
The study focused on a review on various aspects of the construction after demolition of a
structure. Although the two terminologies have been used concurrently in the built
environment, the procedures are actually different. Safety requirements were found to be
useful in either process of the demolition or construction.
REFERENCES
REQUIREMENTS
No/yes Contractor’s
Comments
Principal’s
Verification
23. Health and safety issues have been
resolved in a timely manner.
24. Any outstanding prohibition or
improvement notices from WorkCover
inspections are being addressed.
25. The Contractor monitors the safety
performance of all subcontractors on site
and records are available.
26. Hazard identifications and risk
assessments are available for the plant
and equipment used on site.
27. Inspection, maintenance and service
records are available for the plant and
equipment used on site.
28. Fire protection equipment is available on
site and maintained in good working
order.
29. Personal protective equipment is
available and maintained in good
working order.
30. Flammable materials, gas cylinders and
other hazardous substances are stored
safely on site.
31. Facilities, amenities and the standard of
general housekeeping on site are
satisfactory.
Contractor’s Representative:
Principal’s Representative:
Signature:
Signature:
Conclusion
The study focused on a review on various aspects of the construction after demolition of a
structure. Although the two terminologies have been used concurrently in the built
environment, the procedures are actually different. Safety requirements were found to be
useful in either process of the demolition or construction.
REFERENCES
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Al-Hammadi, Y.A., 2013, October. Towards Efficient Workover Cost and Time Saving: Hoist
Applications Reveal The Advantages Over Conventional Rigs: 1st Case Study in UAE Fields.
In SPE/IADC Middle East Drilling Technology Conference & Exhibition. Society of Petroleum
Engineers.
De Marco, A., Cusati, V., Trifari, V., Ruocco, M., Nicolosi, F. and Della Vecchia, P., A Java
Toolchain of Programs for Aircraft Design(2015).
Langlo, F., 2014. Application of a reliability centered maintenence on a drilling system (Master's
thesis, University of Stavanger, Norway).
Li, H., Lu, M., Hsu, S.C., Gray, M. and Huang, T., 2015. Proactive behavior-based safety
management for construction safety improvement. Safety science, 75, pp.107-117.
Merry, R.E., 2015. Exploring the economic limits of pumping for sugarcane irrigation. System.
Muizu, W.O.Z. and Putri, A.D., 2018. Analisis Kebutuhan Ground Support Equipment (Gse)
Training Approve Sebagai Upaya Terhadap Peningkatan Kompetensi Operator di PT. GMF
Aeroasia. Media Mahardhika, 16(2), pp.115-123.
Neubauer, D.M., 2016. Safety ladder and work platform for helicopter and aircraft maintenence.
U.S. Patent Application 14/338,741.
Ning, X., Qi, J. and Wu, C., 2018. A quantitative safety risk assessment model for construction
site layout planning. Safety science, 104, pp.246-259.
Výtisk, T. and Janalík, R., 2015, May. Experimental determination of technical parameters in
order to optimize the operation of a generator achieving electrical output. In Electric Power
Engineering (EPE), 2015 16th International Scientific Conference on (pp. 572-574). IEEE.
Applications Reveal The Advantages Over Conventional Rigs: 1st Case Study in UAE Fields.
In SPE/IADC Middle East Drilling Technology Conference & Exhibition. Society of Petroleum
Engineers.
De Marco, A., Cusati, V., Trifari, V., Ruocco, M., Nicolosi, F. and Della Vecchia, P., A Java
Toolchain of Programs for Aircraft Design(2015).
Langlo, F., 2014. Application of a reliability centered maintenence on a drilling system (Master's
thesis, University of Stavanger, Norway).
Li, H., Lu, M., Hsu, S.C., Gray, M. and Huang, T., 2015. Proactive behavior-based safety
management for construction safety improvement. Safety science, 75, pp.107-117.
Merry, R.E., 2015. Exploring the economic limits of pumping for sugarcane irrigation. System.
Muizu, W.O.Z. and Putri, A.D., 2018. Analisis Kebutuhan Ground Support Equipment (Gse)
Training Approve Sebagai Upaya Terhadap Peningkatan Kompetensi Operator di PT. GMF
Aeroasia. Media Mahardhika, 16(2), pp.115-123.
Neubauer, D.M., 2016. Safety ladder and work platform for helicopter and aircraft maintenence.
U.S. Patent Application 14/338,741.
Ning, X., Qi, J. and Wu, C., 2018. A quantitative safety risk assessment model for construction
site layout planning. Safety science, 104, pp.246-259.
Výtisk, T. and Janalík, R., 2015, May. Experimental determination of technical parameters in
order to optimize the operation of a generator achieving electrical output. In Electric Power
Engineering (EPE), 2015 16th International Scientific Conference on (pp. 572-574). IEEE.

Wiseman, P.E., O'Herrin, K., Hauer, R., Orrick, B., Ries, P. and Sivyer, D., 2017, July. Careers
paths in urban forestry and arboriculture: linking higher education and professional
advancement. In 2017 ISA Annual International Conference and Trade Show.
Zhang, S., Boukamp, F. and Teizer, J., 2015. Ontology-based semantic modeling of construction
safety knowledge: Towards automated safety planning for job hazard analysis
(JHA). Automation in Construction, 52, pp.29-41.
paths in urban forestry and arboriculture: linking higher education and professional
advancement. In 2017 ISA Annual International Conference and Trade Show.
Zhang, S., Boukamp, F. and Teizer, J., 2015. Ontology-based semantic modeling of construction
safety knowledge: Towards automated safety planning for job hazard analysis
(JHA). Automation in Construction, 52, pp.29-41.
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

Review of the gantt chart
March
2019
Apri
l
2019
August
2019
December
2019
February
2020
April
2019
August
2019
Environmental
Assessment
Demolition phase
Removal of
materials
Site clearance
CONSTRUCTION
PHASE
Post –
Construction
Stage
March
2019
Apri
l
2019
August
2019
December
2019
February
2020
April
2019
August
2019
Environmental
Assessment
Demolition phase
Removal of
materials
Site clearance
CONSTRUCTION
PHASE
Post –
Construction
Stage
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Building
Commissioning
Occupancy By the
Owner
Closure
Commissioning
Occupancy By the
Owner
Closure
1 out of 11
Related Documents

Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
Copyright © 2020–2025 A2Z Services. All Rights Reserved. Developed and managed by ZUCOL.