This project details the setup and planning for developing an e-commerce website for Navy Bush Spices Australia (NBSA). Established in 2010, NBSA aims to expand its brand awareness, increase sales, and venture into overseas markets like Singapore, Hong Kong, and Japan. The project focuses on enhancing the existing website to incorporate e-commerce functionalities, enabling online product sales and meeting consumer demands. Key objectives include a 25% increase in daily sales and network traffic, improved customer recommendations, and a substantial revenue boost. The project plan covers various phases, including initiation, planning, execution, monitoring, and closure, with specific tasks, timelines, resource allocation, and risk management strategies. The staffing includes roles such as project manager, supervisor, business analyst, and web developers, with a clear communication strategy to keep stakeholders informed. Milestones are defined at the end of each phase to track progress and ensure successful project deployment. Desklib is a valuable platform providing students access to solved assignments and study tools.
tabler-icon-diamond-filled.svg

Contribute Materials

Your contribution can guide someone’s learning journey. Share your documents today.
Document Page
ASSESSMENT TASK 2: PROJECT SETUP
ASSESSMENT TASK 2: PROJECT SETUP
Australian Navy Bush Spices Australia
Name of the Student
Name of the University
Author Note
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
1
ASSESSMENT TASK 2: PROJECT SETUP
Project Scope
To be completed all projects
To enhance the existing website to be more attractive and informative. This would be
with 7000 dollars funding of the proposed website enhancement.
Background
The business objectives for the organization is to create a brand awareness and
increase sales, expand in the overseas market including Singapore, Hong Kong, and Japan
and to develop the broader product range. The purpose of the new transformation will be
made within the existing website for the incorporation of functions that can be helpful in
enabling the product selling using the website. This attempt will be helpful in meeting the
demands and requirements of the consumers and the organization in developing the strategies
those could alternatively enhance the expansion and the overall revenue.
Business needs/business Drivers
To increase the company sales
To create brand awareness
To develop a broader product range
Expanding the business to overseas market such as Singapore, Jong Kong, Japan
Value to Native Bush Spices Australia
It will eventually increase the sale of Bush Spices Australia
It will also make the organization more profitable
Attracting more customers to buy Bush Spices Australia
It will more informative and attractive attributes on products will be labelled which
will
eventually make the customer be more informative towards the product they purchase
Document Page
2
ASSESSMENT TASK 2: PROJECT SETUP
Criteria for success
Make plan with the team
Once the plan is done the its time for CEO to approve the plan
Then to expedite the plan
And to maintain
Cost and Cost and schedule-Options to be considered
Cost Area Details
Consultation Fee for Web 5 hours
Designer 6 Hours
Meeting the PR 4 hours
Dependencies
The website redesign is based on the approval of the CEO of the management.
Hiring correct candidates to work for redesigning the website
Adequate funds or budget
Constraint
Time limitation
Hard to find the suitable web designer
Sudden plan change
Team member resigning job
Assumptions
The project must be done on time which is 4 weeks
The Budget is approved and need to be expedite on time
The website should be real, informative and attractive for the customer
Document Page
3
ASSESSMENT TASK 2: PROJECT SETUP
Preliminary risk assessment
A sudden resignation of staff
Finding a suitable web designer
A designer which is within our budget
Project staffing
Operation Manager
Customer service officer
Marketing manager
Project Management Plan
Title
Development of E-Commerce Website for Navy Bush Spices Australia (NBSA)
Background/Context
NBSA was established in 2010 in manner to cater for the needs and demands of the
Australian Native food products with an organic certification. The company has not been
widely spread among Australia and thus, the business revenue is not very good as per the
case study. The simple website being developed is capable of spreading the information about
the organization however, there is very wide scope for enhancing the overall scope for the
organization through modifying the existing website. The business objectives for the
organization is to create a brand awareness and increase sales, expand in the overseas market
including Singapore, Hong Kong, and Japan and to develop the broader product range. The
purpose of the new transformation will be made within the existing website for the
incorporation of functions that can be helpful in enabling the product selling using the
website. This attempt will be helpful in meeting the demands and requirements of the
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
4
ASSESSMENT TASK 2: PROJECT SETUP
consumers and the organization in developing the strategies those could alternatively enhance
the expansion and the overall revenue.
Target Outcome
To allow users to purchase products from the website
Contribute in creating the brand awareness through spreading the information
using the internet
To increase the overall revenue of the organization
To cover the overseas market including Singapore, Hong Kong, and Japan
How will the success of the project be measured?
The daily sales should be increased by 25% in its initial stage.
The network traffic should be increased by 50%.
There should be 4:1 customer recommendation means among four customers,
there should be one who recommends the website to others.
The revenue should be increased by 25% during its initial stage and should
reach to 200% when the project is finally deployed.
The user account or the loyal customer should be increased by 25% through
registering in the website.
Outputs
The number of the consumers will be increased in rapid manner as the traffic and
interaction between the consumers can be made easily over the website.
Large number of customers can reach to the organization via the medium of new online
website
Increase in revenue
Development of brand awareness
Document Page
5
ASSESSMENT TASK 2: PROJECT SETUP
Increase the brand range
Project Staffing
Role Responsibility Skills Required Staffs
require
d
Start
date
Required
time
Project
Team
Project
Manager
Report status,
manage
stakeholders
Project
Management
1 21/09/18 Six months
Core
Team
Quality assurance,
Deliverables review
Project
Management
3 23/09/18 Four
months
Content
Develope
r
Develop the report
for the web
development
Technical writing
and
1 20/09/18 Four
months
Web
Designer
Development of the
web-based
evaluation
management tool
Technical writing
skills, Web
designing
1 30/09/18 Three
months
Web
Develope
r
Building the web-
based performance
management tool
Web
development
1 30/09/18 Two months
Review
Team
Evaluation of the
deliverables and
project review
Project
Management
20 29/09/18 Two months
Project Organization Chart
Document Page
6
ASSESSMENT TASK 2: PROJECT SETUP
Reporting Requirements
The weekly report will be generated that will be consisting of brief email
summarising the outcomes of the project growth and development
Every stakeholder will have the responsibility to participate in the meeting
The senior manager will be receiving the regular updates on the project on weekly
basis
Resources
Following is the list of the human resources required for the development and successful
deployment of the project:
Project Manager
Supervisor
Business Analyst
Resource Manager
Market Analyst
Human Resource Manager
Contractors
Sponsors
Project heads
Software engineer
System Analyst
IT professionals
Stakeholder and communication strategy
Sl.
No
Stakeholder Roles Responsibilities
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
7
ASSESSMENT TASK 2: PROJECT SETUP
.
1.
Project
Manager
Deliver the project constraints
in an efficient and effective
manner and manage the roles
and responsibilities of the
stakeholders involved in the
project
Manage the project constraints and
keep the internal stakeholders
concentric and motivated towards
the accomplishment of the necessary
project deliveries
2.
Supervisor
Manage the staffs under his
authority and manage the
necessary daily operations in
an appropriate and effective
manner
Develop a good relationship with the
staffs and members at lower post
and keep them busy in delivering the
necessary deliverables of the project
3.
Business
Analyst
Analyse the business scenario
and propose the better
strategies regarding the
business strategies on how to
fulfil the needs and
requirements of the
consumers
Develop the best suitable strategies
those could allow the organization in
fulfilling the need and requirements
of the consumers and satisfying
them through offering best strategies
4.
Resource
Manager
Manage the resources of the
project in an efficient and
effective manner and allow
the successful deployment of
the project
Manage the resources and make sure
that the deliveries being managed is
capable of delivering the necessary
daily operations
5. Market Analyse the market and Make sure that the proposed
Document Page
8
ASSESSMENT TASK 2: PROJECT SETUP
Analyst
propose the strategies that can
help in targeting consumers
and assuring the enhancement
in the production
strategies allow the organization to
be ahead of the competitors and
deliver the necessary project
deliverables
6.
Human
Resource
Manager
Manage the human resources
in an efficient and effective
manner
Make sure that the human resources
are utilizing the comforts and the
facilities introduced by the
organization
7.
Project heads
Take the decisions those are
crucial and emphasizing on
the entire project
Make sure that the decision taken is
in the favour of every stakeholder
8.
Software
engineer
Develop the sophisticated e-
commerce website for the
organization
Make sure that the website is easily
accessible and understood to the
consumers
Project Activities and Milestones
WBS Task Name Duration Start Finish
Pre
dece
ssor
s
1 Improving Website for Native bush 242 days Mon 24-09-18 Tue 27-08-19
1.1 Phase 1: Initiation 42 days Mon 24-09-18 Tue 20-11-18
1.1.1 Analysing the business goals 7 days Mon 24-09-18 Tue 02-10-18
1.1.2 Analysing the problems 6 days Wed 03-10-18 Wed 10-10-18 3
1.1.3 Developing Objectives 7 days Thu 11-10-18 Fri 19-10-18 4
1.1.4 Developing Scopes 5 days Mon 22-10-18 Fri 26-10-18 5
1.1.5 Identification of Resources 4 days Mon 29-10-18 Thu 01-11-18 6
Document Page
9
ASSESSMENT TASK 2: PROJECT SETUP
1.1.6 Proposal to the Project Heads 6 days Fri 02-11-18 Fri 09-11-18 7
1.1.7 Approval of the projects 7 days Mon 12-11-18 Tue 20-11-18 8
1.1.8 Milestone 1: Phase 1 completed 0 days Tue 20-11-18 Tue 20-11-18 9
1.2 Phase 2: Planning 45 days Wed 21-11-18 Tue 22-01-19
1.2.1 Timeline estimation 4 days Wed 21-11-18 Mon 26-11-18 10
1.2.2 Budget estimation 6 days Tue 27-11-18 Tue 04-12-18 12
1.2.3 resource identification 7 days Wed 05-12-18 Thu 13-12-18 13
1.2.4 Allocation of resources 5 days Fri 14-12-18 Thu 20-12-18 14
1.2.5 stakeholder allotment 6 days Fri 21-12-18 Fri 28-12-18 15
1.2.6 Communication Plan 4 days Mon 31-12-18 Thu 03-01-19 16
1.2.7 Project Staffing 6 days Fri 04-01-19 Fri 11-01-19 17
1.2.8 Risk Management 7 days Mon 14-01-19 Tue 22-01-19 18
1.2.9 Milestone 2: Phase 2 completed 0 days Tue 22-01-19 Tue 22-01-19 19
1.3 Phase 3: Execution 47 days Wed 23-01-19 Thu 28-03-19
1.3.1 Analysis of previous website 5 days Wed 23-01-19 Tue 29-01-19 20
1.3.2 User interface development 7 days Wed 30-01-19 Thu 07-02-19 22
1.3.3 RSS development 4 days Fri 08-02-19 Wed 13-02-19 23
1.3.4 Instalment of necessary options 8 days Thu 14-02-19 Mon 25-02-19 24
1.3.5 Embedding e-commerce 4 days Tue 26-02-19 Fri 01-03-19 25
1.3.6 Payment service incorporation 4 days Mon 04-03-19 Thu 07-03-19 26
1.3.7 Advertisements 6 days Fri 08-03-19 Fri 15-03-19 27
1.3.8 Communication with the consumers 4 days Mon 18-03-19 Thu 21-03-19 28
1.3.9
Enhancing customers' awareness
through providing necessary
information
5 days Fri 22-03-19 Thu 28-03-19 29
1.3.10 Milestone 3: Phase 3: Completed 0 days Thu 28-03-19 Thu 28-03-19 30
1.4 Phase 4: Monitoring and controlling 56 days Fri 29-03-19 Fri 14-06-19
1.4.1 Regular Project documentation 7 days Fri 29-03-19 Mon 08-04-19 31
1.4.2 Brainstorming 6 days Tue 09-04-19 Tue 16-04-19 33
1.4.3 Analysing the growth and
development of project 8 days Wed 17-04-19 Fri 26-04-19 34
1.4.4 Preparing project checklist 4 days Mon 29-04-19 Thu 02-05-19 35
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
10
ASSESSMENT TASK 2: PROJECT SETUP
1.4.5 Comparing the scope and objectives 5 days Fri 03-05-19 Thu 09-05-19 36
1.4.6 Identifying bugs and glitches 8 days Fri 10-05-19 Tue 21-05-19 37
1.4.7 Real world testing 5 days Wed 22-05-19 Tue 28-05-19 38
1.4.8 Gathering Feedback 8 days Wed 29-05-19 Fri 07-06-19 39
1.4.9 Implementing necessary
modifications 5 days Mon 10-06-19 Fri 14-06-19 40
1.4.10 Milestone 4: Phase 4 completed 0 days Fri 14-06-19 Fri 14-06-19 41
1.5 Phase 5: Project Closure 52 days Mon 17-06-19 Tue 27-08-19
1.5.1 Training to the employees 7 days Mon 17-06-19 Tue 25-06-19 42
1.5.2 Analysing growth 8 days Wed 26-06-19 Fri 05-07-19 44
1.5.3 Deployment of Website 5 days Mon 08-07-19 Fri 12-07-19 45
1.5.4 Project documentation 9 days Mon 15-07-19 Thu 25-07-19 46
1.5.5 Staff releasing 5 days Fri 26-07-19 Thu 01-08-19 47
1.5.6 resource releasing 6 days Fri 02-08-19 Fri 09-08-19 48
1.5.7 Learning gathered documentation 7 days Mon 12-08-19 Tue 20-08-19 49
1.5.8 Project Celebration 5 days Wed 21-08-19 Tue 27-08-19 50
1.5.9 Milestone 5: Phase 5 completed 0 days Tue 27-08-19 Tue 27-08-19 51
Project Communication
Communication
Type
Description Who Schedule
start
Schedule
Finish
Verbal All the stakeholders can
combine under one roof and
everyone should be allowed
for expressing their views on
the project and propose their
valuable thoughts on the
progress, issues and the
strategies through which the
All internal
stakeholder
s
Mon 24-
09-18
And every
next week
Mon 24-
09-18
And every
next week
Document Page
11
ASSESSMENT TASK 2: PROJECT SETUP
progress can be deployed
E-mail The decision-making and the
approvals can be
communicated over the mail
Project
heads and
the
Governmen
t
Mon 24-
09-18
Whenever
necessary
for certain
approvals
Video
conferencing
It can allow to communicate
with the individuals who are
no longer at the project site
or within the region of the
project
Heads,
CEO, and
sponsors
Mon 24-
09-18
Whenever
necessary
for certain
approvals
Meeting hall,
verbally
The project manager can
communicate with the
internal team members and
the internal stakeholders on
the response of the current
growth and development of
the project
Project
manager
Every
week
Every
week
Market related The market needs to be
discussed while transforming
the existing system of the
organization in manner to
develop the strategies those
Project
manager,
Business
analyst,
software
Mon 24-
09-18
Fri 19-10-
18
Document Page
12
ASSESSMENT TASK 2: PROJECT SETUP
could be adopted for the
successful delivery of the
project
engineer,
market
analyst
Business related The business strategies need
to be developed based on the
survey and the research in
manner to assure that the
objectives being developed Is
capable of meeting final
outcome of the project
Project
manager,
Business
analyst,
software
engineer,
market
analyst
Mon 24-
09-18
Fri 19-10-
18
Risk Management Strategy
Risk Likelihood Severity Treatment methods
Budget
escalation
Medium Very
High
Proper and effective planning considering every
phase and activity of the project, regular audit,
quality assurance adoption
Time
escalation
Medium Very
High
Proper and effective planning considering every
phase and activity of the project, regular audit,
quality assurance adoption
Less effective
user interface
High High Development of the RSS documentation before
executing the project or deploying the
manipulation in the existing website
Less user
acceptance
Low Medium Use should be introduced about the features and
the benefits being introduced with this
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
13
ASSESSMENT TASK 2: PROJECT SETUP
transformation.
Resource
deficiency
Very Low High Proper and effective resource management
should be managed considering the daily
facilities and requirements of the project
Power source Very low Very
Low
The facility manager should be sure about the
availability of the secondary power source
before deploying the project
Less effective
communication
Medium Very
High
Following the communication plan developed in
strict manner in manner to make sure that the
project being developed is efficient and effective
enough for the management of the
communication between the stakeholders
Less effective
leadership and
management
attributes
Low Very
High
The appointed leader should be capable of
managing the complexities and the required
decision-making for the successful and efficient
management of other stakeholders and assuring
that every stakeholder contributes 100% for the
deployment of the project.
Project management policy and procedure
Purpose
Native Bush Spice Australia adopts a standard approach to project management to
ensure the consistent use of project management procedures and templates. This policy and
procedure are designed to specify the requirements for managing projects to ensure that
Document Page
14
ASSESSMENT TASK 2: PROJECT SETUP
project scope is articulated, stakeholders are involved, risks are managed and project benefits
are maximized. This policy and procedure apply to all projects.
Types of project
Generally, there are three types of project - small project, medium project and large
project. In each of the above cases the following staff are to be involved.
Large Project:
Project Manager
Project team member
Senior Manager
Project Steering Group
Project staff will vary depending on the type of project.
Project Phases
All projects should progress through the following project phases. Stage one
Stage one of the project management process is triggered when a staff member
identifies the need to solve a problem, improve a process or implement a new service. It
defines what the project will attempt to achieve based on appropriate business justification.
Stage two
The purpose of this phase is to determine how the project will be excecued. This
means developing a project management plan based on the project scope. The Australian
Native Bush Spice project management template should be use. Essentially the preparation of
a detailed model of the work required to achieve the project objectives is required and
Document Page
15
ASSESSMENT TASK 2: PROJECT SETUP
confirmation of the budget and project arrangements suggested in the Business Case. Risks
are also defined and documented in a risk management plan A detailed schedule is also
prepared.
Stage three
The purpose of this phase is to implement the project. Regular reports of the progress
of the project should be provided to relevant staff, as well as regular meetings as outlined in
the project management plan.
Stage four
This is the final phase of the project and is the formal closure of the delivery
component of the project. It has two main outcomes: The handover of project outputs to the
operational areas responsible for ongoing support and maintenance (if applicable to the
project); and
The evaluation of the success of the project
The evaluation of the success of the project is important part of the project. The actual
project outcomes and cost must be compared with the planned outcomes and determine
whether what was achieved by the project was worth the amount invested. Project
recommendations to be included in project evaluation report should include a
recommendation to close project. All project issues arising must be documented in the project
issues register.
Project Communication
It is expected that the project team meet at least weekly depending on the size of the
project. A brief email summarizing outcome of the meeting must be sent to senior
management.
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
16
ASSESSMENT TASK 2: PROJECT SETUP
Weekly reports must also be sent to senior management regarding project progress.
Project record keeping
A project folder is to be established for each project. The overall folder should be the
name of the project e.g. Human Resources Information System Project and sub-folders
should be created including folders for the business case, project management plan, project
reports, minutes and any other relevant folders e.g. briefs to contractors. All documents
should include the version number, date and title of document.
Document Page
17
ASSESSMENT TASK 2: PROJECT SETUP
Bibliography
Apenko, S., 2017. Human Resource Management of Innovative Projects in the Context of
Business Strategy. STRATEGIC MANAGEMENT, 22(1), pp.3-6.
Binder, J., 2016. Global project management: communication, collaboration and
management across borders. Routledge.
Binder, J., 2016. Global project management: communication, collaboration and
management across borders. Routledge.
Cha, J., Newman, M. and Winch, G., 2018. Revisiting the project management knowledge
framework: Rebalancing the framework to include transformation projects. International
Journal of Managing Projects in Business, 11(4), pp.1026-1043.
Fleming, Q.W. and Koppelman, J.M., 2016, December. Earned value project management.
Project Management Institute.
Harrison, F. and Lock, D., 2017. Advanced project management: a structured approach.
Routledge.
Hornstein, H.A., 2015. The integration of project management and organizational change
management is now a necessity. International Journal of Project Management, 33(2),
pp.291-298.
Kerzner, H. and Kerzner, H.R., 2017. Project management: a systems approach to planning,
scheduling, and controlling. John Wiley & Sons.
Lock, D., 2017. The essentials of project management. Routledge.
Marchewka, J.T., 2014. Information technology project management. John Wiley & Sons.
Document Page
18
ASSESSMENT TASK 2: PROJECT SETUP
Nicholas, J.M. and Steyn, H., 2017. Project management for engineering, business and
technology. Routledge.
Pinto, J.K. and Winch, G., 2016. The unsettling of “settled science:” The past and future of
the management of projects. International Journal of Project Management, 34(2), pp.237-
245.
Riol, H. and Thuillier, D., 2015. Project management for academic research projects:
balancing structure and flexibility. International Journal of Project Organisation and
Management, 7(3), pp.251-269.
Svejvig, P. and Andersen, P., 2015. Rethinking project management: A structured literature
review with a critical look at the brave new world. International Journal of Project
Management, 33(2), pp.278-290.
Verzuh, E., 2015. The fast forward MBA in project management. John Wiley & Sons.
Walker, A., 2015. Project management in construction. John Wiley & Sons
chevron_up_icon