This report details a project aimed at developing a Car Data Management System for the Sydney car rental project. The report begins with a project charter outlining the business case, goals, and scope. It then delves into information gathering methods, including questionnaires, surveys, and interviews, along with identified risks and constraints such as delays, cost overruns, and system development issues. A comprehensive project plan is presented, featuring a work breakdown structure, detailed project schedule with start and end dates for each phase, and a project budget with resource allocation and associated costs. The report assigns project roles and responsibilities to team members, and includes a Gantt chart visualizing the project timeline. Additional sections cover quality management and disaster recovery plans. The project is centered around improving the operational efficiency of the car rental company by implementing a software system for managing vehicle data, booking, and pricing.

Running head: PROJECT MANAGEMENT REPORT
Project Management Report: Car Rental Project
Student Name:
Student ID:
University Name:
Author’s note:
Project Management Report: Car Rental Project
Student Name:
Student ID:
University Name:
Author’s note:
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

1PROJECT MANAGEMENT REPORT
Table of Contents
Question 1: Project Charter.............................................................................................................2
Question 2: Information Gathering..................................................................................................6
2.1 Method of Information Gathering.........................................................................................6
2.2 Risks and Constraints of the Project......................................................................................7
Question 3: Project Plan..................................................................................................................8
3.1 Work Breakdown Structure...................................................................................................8
3.2 Project Schedule and Timeline..............................................................................................8
3.3 Project Budget.....................................................................................................................11
Question 4: Project Roles and Responsibilities.............................................................................13
Question 5: Comparison of information........................................................................................15
Question 6: Quality Management Plan..........................................................................................15
Question 7: Disaster Recovery Plan..............................................................................................17
Question 8: Sign off.......................................................................................................................17
Bibliography..................................................................................................................................18
Table of Contents
Question 1: Project Charter.............................................................................................................2
Question 2: Information Gathering..................................................................................................6
2.1 Method of Information Gathering.........................................................................................6
2.2 Risks and Constraints of the Project......................................................................................7
Question 3: Project Plan..................................................................................................................8
3.1 Work Breakdown Structure...................................................................................................8
3.2 Project Schedule and Timeline..............................................................................................8
3.3 Project Budget.....................................................................................................................11
Question 4: Project Roles and Responsibilities.............................................................................13
Question 5: Comparison of information........................................................................................15
Question 6: Quality Management Plan..........................................................................................15
Question 7: Disaster Recovery Plan..............................................................................................17
Question 8: Sign off.......................................................................................................................17
Bibliography..................................................................................................................................18

2PROJECT MANAGEMENT REPORT
Question 1: Project Charter
The project charter for the project of Sydney car rental project for developing Car Data
Management System is given below,
Project Charter
Project Name: Sydney car rental project for developing Car Data
Management System
Date: 03/20/2018
Prepared By: Katherine Jean
Approved By: <<name of the Student>>
Business Case Opportunity Statement
The Sydney Car Rental company had been
facing the issue of delay in operations of
booking system, management issues of
vehicle, and price calculation. All these have
impacted in forming the issues in improved
operations of the organization. The
organization wants to overcome the problems
and implement a new technology for
implementing improved operations.
Implication of new technology
The implementation of the software for
management of the information and data
related to the car parking system. The analysis
had been done for ensuring that the
implementation of the improved operations
would help in developing the successive
information management system for the
organization.
Question 1: Project Charter
The project charter for the project of Sydney car rental project for developing Car Data
Management System is given below,
Project Charter
Project Name: Sydney car rental project for developing Car Data
Management System
Date: 03/20/2018
Prepared By: Katherine Jean
Approved By: <<name of the Student>>
Business Case Opportunity Statement
The Sydney Car Rental company had been
facing the issue of delay in operations of
booking system, management issues of
vehicle, and price calculation. All these have
impacted in forming the issues in improved
operations of the organization. The
organization wants to overcome the problems
and implement a new technology for
implementing improved operations.
Implication of new technology
The implementation of the software for
management of the information and data
related to the car parking system. The analysis
had been done for ensuring that the
implementation of the improved operations
would help in developing the successive
information management system for the
organization.
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

3PROJECT MANAGEMENT REPORT
Goal Statement Project Scope
To develop a software system that would help
in managing the data and information of the
vehicles parked, providing ease of booking,
and faster pricing for the parked vehicles
Process Start Point: Analysis of the
requirements
Process End Point: Implementation of the
software system for managing the information
of the vehicles parked
Expected Benefits: Improved management of
the vehicles, developing a booking system, and
pricing schedule for the car parked.
In Scope:
Out of Scope:
Project Plan
Phase Start Date End Date Actual End
Initiation Phase Tue 5/1/18 Fri 5/18/18 14 days
Plan Development Phase Tue 5/8/18 Tue 5/22/18 11 days
Design Phase
Thu 5/17/18 Wed 6/6/18
15 days
Development Phase Thu 5/17/18 Tue 7/3/18 34 days
Testing Phase Thu 5/24/18 Fri 7/6/18 32 days
Closure Phase Mon 7/16/18 Mon 7/30/18 11 days
Goal Statement Project Scope
To develop a software system that would help
in managing the data and information of the
vehicles parked, providing ease of booking,
and faster pricing for the parked vehicles
Process Start Point: Analysis of the
requirements
Process End Point: Implementation of the
software system for managing the information
of the vehicles parked
Expected Benefits: Improved management of
the vehicles, developing a booking system, and
pricing schedule for the car parked.
In Scope:
Out of Scope:
Project Plan
Phase Start Date End Date Actual End
Initiation Phase Tue 5/1/18 Fri 5/18/18 14 days
Plan Development Phase Tue 5/8/18 Tue 5/22/18 11 days
Design Phase
Thu 5/17/18 Wed 6/6/18
15 days
Development Phase Thu 5/17/18 Tue 7/3/18 34 days
Testing Phase Thu 5/24/18 Fri 7/6/18 32 days
Closure Phase Mon 7/16/18 Mon 7/30/18 11 days
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

4PROJECT MANAGEMENT REPORT
Team
Name Role Commitment (%)
Amelia Kate (Analyst) Analysis of
requirements
80
Katherine Jean (Documenter) Development of PID,
Charter
documentation,
Submission of
documents, Training
Documents are made,
Final reports are
made, and Submission
of reports
90
<<name of the Student>> (Project
Manager)
Management of the
project activities
100
Christie Black (Planner) Developing Project
Schedule Plan
80
Augustus Pan (Budgeter) Making Project
Budget
85
John Lawrence (Risk Analyst) Developing risk
analysis report and
87
Team
Name Role Commitment (%)
Amelia Kate (Analyst) Analysis of
requirements
80
Katherine Jean (Documenter) Development of PID,
Charter
documentation,
Submission of
documents, Training
Documents are made,
Final reports are
made, and Submission
of reports
90
<<name of the Student>> (Project
Manager)
Management of the
project activities
100
Christie Black (Planner) Developing Project
Schedule Plan
80
Augustus Pan (Budgeter) Making Project
Budget
85
John Lawrence (Risk Analyst) Developing risk
analysis report and
87

5PROJECT MANAGEMENT REPORT
forming risk
management plan
Sally Dawn (HR Manager) Implying effective
communication
management process
91
Joseph Jones (Designer) Selection of design
Methodology, Design
requirements analysis,
Outline of design is
formed, and Complete
Design Development
89
Charlie Johnson (Database
Developer)
Review of existing
data, Development of
integrated database,
and Migration of data
to the new database
100
Rey Chan (Software Engineer) Interface
development,
Integration of booking
system, vehicle
management, and
pricing system, and
100
forming risk
management plan
Sally Dawn (HR Manager) Implying effective
communication
management process
91
Joseph Jones (Designer) Selection of design
Methodology, Design
requirements analysis,
Outline of design is
formed, and Complete
Design Development
89
Charlie Johnson (Database
Developer)
Review of existing
data, Development of
integrated database,
and Migration of data
to the new database
100
Rey Chan (Software Engineer) Interface
development,
Integration of booking
system, vehicle
management, and
pricing system, and
100
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

6PROJECT MANAGEMENT REPORT
Complete System
Development
Drake Lay (Programmer) Developing program
for the software
development
100
Amanda Lewis (Tester) Design Simulation,
Database Black box
testing, System
Prototype Testing,
and Program White
Box testing
97
Shannon Beth (Trainer) Providing training to
the employees
80
Question 2: Information Gathering
2.1 Method of Information Gathering
Information collection is helpful for the deployment of the improvement of the operations
and formation of the activities for aligning with the management of the successive management
of the operations. The information gathering for the project of Sydney car rental project for
developing Car Data Management System can be done by using questionnaire, survey, and
interviews. These are the methods of primary data collection for forming the analysis and
Complete System
Development
Drake Lay (Programmer) Developing program
for the software
development
100
Amanda Lewis (Tester) Design Simulation,
Database Black box
testing, System
Prototype Testing,
and Program White
Box testing
97
Shannon Beth (Trainer) Providing training to
the employees
80
Question 2: Information Gathering
2.1 Method of Information Gathering
Information collection is helpful for the deployment of the improvement of the operations
and formation of the activities for aligning with the management of the successive management
of the operations. The information gathering for the project of Sydney car rental project for
developing Car Data Management System can be done by using questionnaire, survey, and
interviews. These are the methods of primary data collection for forming the analysis and
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

7PROJECT MANAGEMENT REPORT
inference of the study. The past records and reports can also be studied for gathering information
for the project.
2.2 Risks and Constraints of the Project
The various risks for the project of Sydney car rental project for developing Car Data
Management System is based on the operations and development factor are,
a. Delay in completion: There are several cases when the project does not meets its
expected deadline due to the delay in completion of the activities and it results in
causing major issue for time driven projects.
b. Cost Overrun: The cost overrun results in causing the loss of the organization in
development of the project and it is caused when the activities of the project
would not be completed in the estimated budget.
c. System Development Issue: The development of system is the final deliverable
for the project and the issues in developing the system would tend to the failure of
the whole project itself.
d. Design Flaws: The design flaws are the major factor that would result in causing
the project to fail as the design is an integral part of the software development
project.
inference of the study. The past records and reports can also be studied for gathering information
for the project.
2.2 Risks and Constraints of the Project
The various risks for the project of Sydney car rental project for developing Car Data
Management System is based on the operations and development factor are,
a. Delay in completion: There are several cases when the project does not meets its
expected deadline due to the delay in completion of the activities and it results in
causing major issue for time driven projects.
b. Cost Overrun: The cost overrun results in causing the loss of the organization in
development of the project and it is caused when the activities of the project
would not be completed in the estimated budget.
c. System Development Issue: The development of system is the final deliverable
for the project and the issues in developing the system would tend to the failure of
the whole project itself.
d. Design Flaws: The design flaws are the major factor that would result in causing
the project to fail as the design is an integral part of the software development
project.

8PROJECT MANAGEMENT REPORT
Question 3: Project Plan
3.1 Work Breakdown Structure
The work breakdown structure for the project of Sydney car rental project for developing Car Data Management System is given below,
Sydney car rental project
for developing Car Data
Management System
Initiation Phase
Analysis of
requirements
Development of PID
Charter
documentation
Submission of
documents
Review and Sign off
Initiation Phase
completed
Plan Development Phase
Scheduling the plan
Cost Budget
Estimation
Risk Management
Planning
Communication Plan
development
Plan Phase
Completed
Software Development
Design phase
Selection of design
Methodology
Design
requirements
analysis
Outline of design is
formed
Complete Design
Development
Design Phase
Completed
Development Phase
Database works
Review of existing
data
Development of
integrated database
Migration of data to
the new database
Database works
completed
Program works
Interface
development
Integration of
booking system,
vehicle
management, and
pricing system
Programming the
functions for the
system
Completion of
program works
Complete System
Development
Testing Phase
Design Simulation
Database Black box
testing
System Prototype
Testing
Program White Box
testing
Testing Phase
Completed
Final Documentation and
Training
Training Documents
are made
Training is given to
employees
Final reports are
made
Submission of
reports
Review and sign off
Project is Closed
Figure 1: Work Breakdown Structure of project
(Source: Created by the author)
3.2 Project Schedule and Timeline
The project schedule for Sydney car rental project for developing Car Data Management System is given below,
WBS Task Name Duration Start Finish
0 Sydney car rental project for developing Car Data Management System 65 days Tue 5/1/18 Mon 7/30/18
1 Initiation Phase 14 days Tue 5/1/18 Fri 5/18/18
1.1 Analysis of requirements 3 days Tue 5/1/18 Thu 5/3/18
1.2 Development of PID 2 days Fri 5/4/18 Mon 5/7/18
1.3 Charter documentation 2 days Tue 5/15/18 Wed 5/16/18
1.4 Submission of documents 1 day Thu 5/17/18 Thu 5/17/18
1.5 Review and Sign off 1 day Fri 5/18/18 Fri 5/18/18
Question 3: Project Plan
3.1 Work Breakdown Structure
The work breakdown structure for the project of Sydney car rental project for developing Car Data Management System is given below,
Sydney car rental project
for developing Car Data
Management System
Initiation Phase
Analysis of
requirements
Development of PID
Charter
documentation
Submission of
documents
Review and Sign off
Initiation Phase
completed
Plan Development Phase
Scheduling the plan
Cost Budget
Estimation
Risk Management
Planning
Communication Plan
development
Plan Phase
Completed
Software Development
Design phase
Selection of design
Methodology
Design
requirements
analysis
Outline of design is
formed
Complete Design
Development
Design Phase
Completed
Development Phase
Database works
Review of existing
data
Development of
integrated database
Migration of data to
the new database
Database works
completed
Program works
Interface
development
Integration of
booking system,
vehicle
management, and
pricing system
Programming the
functions for the
system
Completion of
program works
Complete System
Development
Testing Phase
Design Simulation
Database Black box
testing
System Prototype
Testing
Program White Box
testing
Testing Phase
Completed
Final Documentation and
Training
Training Documents
are made
Training is given to
employees
Final reports are
made
Submission of
reports
Review and sign off
Project is Closed
Figure 1: Work Breakdown Structure of project
(Source: Created by the author)
3.2 Project Schedule and Timeline
The project schedule for Sydney car rental project for developing Car Data Management System is given below,
WBS Task Name Duration Start Finish
0 Sydney car rental project for developing Car Data Management System 65 days Tue 5/1/18 Mon 7/30/18
1 Initiation Phase 14 days Tue 5/1/18 Fri 5/18/18
1.1 Analysis of requirements 3 days Tue 5/1/18 Thu 5/3/18
1.2 Development of PID 2 days Fri 5/4/18 Mon 5/7/18
1.3 Charter documentation 2 days Tue 5/15/18 Wed 5/16/18
1.4 Submission of documents 1 day Thu 5/17/18 Thu 5/17/18
1.5 Review and Sign off 1 day Fri 5/18/18 Fri 5/18/18
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

9PROJECT MANAGEMENT REPORT
M1 Initiation Phase completed 0 days Fri 5/18/18 Fri 5/18/18
2 Plan Development Phase 11 days Tue 5/8/18 Tue 5/22/18
2.1 Scheduling the plan 3 days Tue 5/8/18 Thu 5/10/18
2.2 Cost Budget Estimation 2 days Fri 5/11/18 Mon 5/14/18
2.3 Risk Management Planning 4 days Tue 5/15/18 Fri 5/18/18
2.4 Communication Plan development 3 days Fri 5/18/18 Tue 5/22/18
M2 Plan Phase Completed 0 days Tue 5/22/18 Tue 5/22/18
3 Software Development 42 days Thu 5/17/18 Fri 7/13/18
3.1 Design phase 15 days Thu 5/17/18 Wed 6/6/18
3.1.1 Selection of design Methodology 1 day Thu 5/17/18 Thu 5/17/18
3.1.2 Design requirements analysis 2 days Fri 5/18/18 Mon 5/21/18
3.1.3 Outline of design is formed 2 days Tue 5/22/18 Wed 5/23/18
3.1.4 Complete Design Development 7 days Tue 5/29/18 Wed 6/6/18
M3 Design Phase Completed 0 days Wed 6/6/18 Wed 6/6/18
3.2 Development Phase 34 days Thu 5/17/18 Tue 7/3/18
3.2.1 Database works 13 days Thu 5/17/18 Mon 6/4/18
3.2.1.1 Review of existing data 1 day Thu 5/17/18 Thu 5/17/18
3.2.1.2 Development of integrated database 4 days Fri 5/18/18 Wed 5/23/18
3.2.1.3 Migration of data to the new database 2 days Fri 6/1/18 Mon 6/4/18
M4 Database works completed 0 days Mon 6/4/18 Mon 6/4/18
3.2.2 Program works 21 days Tue 6/5/18 Tue 7/3/18
3.2.2.1 Interface development 5 days Tue 6/5/18 Mon 6/11/18
3.2.2.2 Integration of booking system, vehicle management, and pricing system 3 days Tue 6/12/18 Thu 6/14/18
3.2.2.3 Programming the functions for the system 10 days Fri 6/15/18 Thu 6/28/18
M5 Completion of program works 0 days Tue 7/3/18 Tue 7/3/18
3.3 Complete System Development 5 days Mon 7/9/18 Fri 7/13/18
4 Testing Phase 32 days Thu 5/24/18 Fri 7/6/18
4.1 Design Simulation 3 days Thu 5/24/18 Mon 5/28/18
4.2 Database Black box testing 3 days Tue 5/29/18 Thu 5/31/18
4.3 System Prototype Testing 3 days Wed 7/4/18 Fri 7/6/18
4.4 Program White Box testing 3 days Fri 6/29/18 Tue 7/3/18
M6 Testing Phase Completed 0 days Fri 7/6/18 Fri 7/6/18
5 Final Documentation and Training 11 days Mon 7/16/18 Mon 7/30/18
5.1 Training Documents are made 4 days Mon 7/16/18 Thu 7/19/18
5.2 Training is given to employees 7 days Fri 7/20/18 Mon 7/30/18
5.3 Final reports are made 3 days Fri 7/20/18 Tue 7/24/18
M1 Initiation Phase completed 0 days Fri 5/18/18 Fri 5/18/18
2 Plan Development Phase 11 days Tue 5/8/18 Tue 5/22/18
2.1 Scheduling the plan 3 days Tue 5/8/18 Thu 5/10/18
2.2 Cost Budget Estimation 2 days Fri 5/11/18 Mon 5/14/18
2.3 Risk Management Planning 4 days Tue 5/15/18 Fri 5/18/18
2.4 Communication Plan development 3 days Fri 5/18/18 Tue 5/22/18
M2 Plan Phase Completed 0 days Tue 5/22/18 Tue 5/22/18
3 Software Development 42 days Thu 5/17/18 Fri 7/13/18
3.1 Design phase 15 days Thu 5/17/18 Wed 6/6/18
3.1.1 Selection of design Methodology 1 day Thu 5/17/18 Thu 5/17/18
3.1.2 Design requirements analysis 2 days Fri 5/18/18 Mon 5/21/18
3.1.3 Outline of design is formed 2 days Tue 5/22/18 Wed 5/23/18
3.1.4 Complete Design Development 7 days Tue 5/29/18 Wed 6/6/18
M3 Design Phase Completed 0 days Wed 6/6/18 Wed 6/6/18
3.2 Development Phase 34 days Thu 5/17/18 Tue 7/3/18
3.2.1 Database works 13 days Thu 5/17/18 Mon 6/4/18
3.2.1.1 Review of existing data 1 day Thu 5/17/18 Thu 5/17/18
3.2.1.2 Development of integrated database 4 days Fri 5/18/18 Wed 5/23/18
3.2.1.3 Migration of data to the new database 2 days Fri 6/1/18 Mon 6/4/18
M4 Database works completed 0 days Mon 6/4/18 Mon 6/4/18
3.2.2 Program works 21 days Tue 6/5/18 Tue 7/3/18
3.2.2.1 Interface development 5 days Tue 6/5/18 Mon 6/11/18
3.2.2.2 Integration of booking system, vehicle management, and pricing system 3 days Tue 6/12/18 Thu 6/14/18
3.2.2.3 Programming the functions for the system 10 days Fri 6/15/18 Thu 6/28/18
M5 Completion of program works 0 days Tue 7/3/18 Tue 7/3/18
3.3 Complete System Development 5 days Mon 7/9/18 Fri 7/13/18
4 Testing Phase 32 days Thu 5/24/18 Fri 7/6/18
4.1 Design Simulation 3 days Thu 5/24/18 Mon 5/28/18
4.2 Database Black box testing 3 days Tue 5/29/18 Thu 5/31/18
4.3 System Prototype Testing 3 days Wed 7/4/18 Fri 7/6/18
4.4 Program White Box testing 3 days Fri 6/29/18 Tue 7/3/18
M6 Testing Phase Completed 0 days Fri 7/6/18 Fri 7/6/18
5 Final Documentation and Training 11 days Mon 7/16/18 Mon 7/30/18
5.1 Training Documents are made 4 days Mon 7/16/18 Thu 7/19/18
5.2 Training is given to employees 7 days Fri 7/20/18 Mon 7/30/18
5.3 Final reports are made 3 days Fri 7/20/18 Tue 7/24/18
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

10PROJECT MANAGEMENT REPORT
5.4 Submission of reports 1 day Wed 7/25/18 Wed 7/25/18
5.5 Review and sign off 1 day Thu 7/26/18 Thu 7/26/18
M7 Project is Closed 0 days Thu 7/26/18 Thu 7/26/18
The timeline for the project of Sydney car rental project for developing Car Data Management System is given below,
ID Task
Mode
WBS Task Name Duration Start Finish
0 0 Sydney car rental project for
developing Car Data Management
System
65 days Tue 5/1/18 Mon 7/30/18
1 1 Initiation Phase 14 days Tue 5/1/18 Fri 5/18/18
2 1.1 Analysis of requirements 3 days Tue 5/1/18 Thu 5/3/18
3 1.2 Development of PID 2 days Fri 5/4/18 Mon 5/7/18
4 1.3 Charter documentation 2 days Tue 5/15/18 Wed 5/16/18
5 1.4 Submission of documents 1 day Thu 5/17/18 Thu 5/17/18
6 1.5 Review and Sign off 1 day Fri 5/18/18 Fri 5/18/18
7 M1 Initiation Phase completed 0 days Fri 5/18/18 Fri 5/18/18
8 2 Plan Development Phase 11 days Tue 5/8/18 Tue 5/22/18
9 2.1 Scheduling the plan 3 days Tue 5/8/18 Thu 5/10/18
10 2.2 Cost Budget Estimation 2 days Fri 5/11/18 Mon 5/14/18
11 2.3 Risk Management Planning 4 days Tue 5/15/18 Fri 5/18/18
12 2.4 Communication Plan development 3 days Fri 5/18/18 Tue 5/22/18
13 M2 Plan Phase Completed 0 days Tue 5/22/18 Tue 5/22/18
14 3 Software Development 42 days Thu 5/17/18 Fri 7/13/18
15 3.1 Design phase 15 days Thu 5/17/18 Wed 6/6/18
16 3.1.1 Selection of design Methodology1 day Thu 5/17/18 Thu 5/17/18
17 3.1.2 Design requirements analysis 2 days Fri 5/18/18 Mon 5/21/18
18 3.1.3 Outline of design is formed 2 days Tue 5/22/18 Wed 5/23/18
19 3.1.4 Complete Design Development 7 days Tue 5/29/18 Wed 6/6/18
20 M3 Design Phase Completed 0 days Wed 6/6/18 Wed 6/6/18
21 3.2 Development Phase 34 days Thu 5/17/18 Tue 7/3/18
22 3.2.1 Database works 13 days Thu 5/17/18 Mon 6/4/18
23 3.2.1.1 Review of existing data 1 day Thu 5/17/18 Thu 5/17/18
24 3.2.1.2 Development of integrated database4 days Fri 5/18/18 Wed 5/23/18
25 3.2.1.3 Migration of data to the new
database
2 days Fri 6/1/18 Mon 6/4/18
26 M4 Database works completed 0 days Mon 6/4/18 Mon 6/4/18
27 3.2.2 Program works 21 days Tue 6/5/18 Tue 7/3/18
28 3.2.2.1 Interface development 5 days Tue 6/5/18 Mon 6/11/18
29 3.2.2.2 Integration of booking
system, vehicle management,
and pricing system
3 days Tue 6/12/18 Thu 6/14/18
30 3.2.2.3 Programming the functions
for the system
10 days Fri 6/15/18 Thu 6/28/18
31 M5 Completion of program works0 days Tue 7/3/18 Tue 7/3/18
32 3.3 Complete System Development 5 days Mon 7/9/18 Fri 7/13/18
33 4 Testing Phase 32 days Thu 5/24/18 Fri 7/6/18
34 4.1 Design Simulation 3 days Thu 5/24/18 Mon 5/28/18
35 4.2 Database Black box testing 3 days Tue 5/29/18 Thu 5/31/18
36 4.3 System Prototype Testing 3 days Wed 7/4/18 Fri 7/6/18
37 4.4 Program White Box testing 3 days Fri 6/29/18 Tue 7/3/18
38 M6 Testing Phase Completed 0 days Fri 7/6/18 Fri 7/6/18
39 5 Final Documentation and Training11 days Mon 7/16/18 Mon 7/30/18
40 5.1 Training Documents are made 4 days Mon 7/16/18 Thu 7/19/18
41 5.2 Training is given to employees 7 days Fri 7/20/18 Mon 7/30/18
42 5.3 Final reports are made 3 days Fri 7/20/18 Tue 7/24/18
43 5.4 Submission of reports 1 day Wed 7/25/18 Wed 7/25/18
44 5.5 Review and sign off 1 day Thu 7/26/18 Thu 7/26/18
45 M7 Project is Closed 0 days Thu 7/26/18 Thu 7/26/18
Analyst
Documenter,Documents[1]
Documenter,Documents[1]
Documenter
Project Manager
5/18
Planner
Budgeter
Risk Analyst
HR Manager
5/22
Designer
Designer
Designer,Design Tools[1]
Designer,Design Tools[1]
6/6
Database Developer
Database Developer,Database[1]
Database Developer
6/4
Software Engineer,Interface tools[1]
Software Engineer
Programmer,Programming Tools[1]
7/3
Software Engineer
Tester,Simulator[1]
Tester,Testing Tools[1]
Tester,Prototype[1]
Tester,Testing Tools[1]
7/6
Documenter,Documents[1]
Trainer
Documenter
Documenter
Project Manager
7/26
S W S T M F T S W S T M
Apr 8, '18 May 6, '18 Jun 3, '18 Jul 1, '18 Jul 29, '18 Aug 26, '18
Figure 2: Gantt chart of the project
(Source: Created by the author)
5.4 Submission of reports 1 day Wed 7/25/18 Wed 7/25/18
5.5 Review and sign off 1 day Thu 7/26/18 Thu 7/26/18
M7 Project is Closed 0 days Thu 7/26/18 Thu 7/26/18
The timeline for the project of Sydney car rental project for developing Car Data Management System is given below,
ID Task
Mode
WBS Task Name Duration Start Finish
0 0 Sydney car rental project for
developing Car Data Management
System
65 days Tue 5/1/18 Mon 7/30/18
1 1 Initiation Phase 14 days Tue 5/1/18 Fri 5/18/18
2 1.1 Analysis of requirements 3 days Tue 5/1/18 Thu 5/3/18
3 1.2 Development of PID 2 days Fri 5/4/18 Mon 5/7/18
4 1.3 Charter documentation 2 days Tue 5/15/18 Wed 5/16/18
5 1.4 Submission of documents 1 day Thu 5/17/18 Thu 5/17/18
6 1.5 Review and Sign off 1 day Fri 5/18/18 Fri 5/18/18
7 M1 Initiation Phase completed 0 days Fri 5/18/18 Fri 5/18/18
8 2 Plan Development Phase 11 days Tue 5/8/18 Tue 5/22/18
9 2.1 Scheduling the plan 3 days Tue 5/8/18 Thu 5/10/18
10 2.2 Cost Budget Estimation 2 days Fri 5/11/18 Mon 5/14/18
11 2.3 Risk Management Planning 4 days Tue 5/15/18 Fri 5/18/18
12 2.4 Communication Plan development 3 days Fri 5/18/18 Tue 5/22/18
13 M2 Plan Phase Completed 0 days Tue 5/22/18 Tue 5/22/18
14 3 Software Development 42 days Thu 5/17/18 Fri 7/13/18
15 3.1 Design phase 15 days Thu 5/17/18 Wed 6/6/18
16 3.1.1 Selection of design Methodology1 day Thu 5/17/18 Thu 5/17/18
17 3.1.2 Design requirements analysis 2 days Fri 5/18/18 Mon 5/21/18
18 3.1.3 Outline of design is formed 2 days Tue 5/22/18 Wed 5/23/18
19 3.1.4 Complete Design Development 7 days Tue 5/29/18 Wed 6/6/18
20 M3 Design Phase Completed 0 days Wed 6/6/18 Wed 6/6/18
21 3.2 Development Phase 34 days Thu 5/17/18 Tue 7/3/18
22 3.2.1 Database works 13 days Thu 5/17/18 Mon 6/4/18
23 3.2.1.1 Review of existing data 1 day Thu 5/17/18 Thu 5/17/18
24 3.2.1.2 Development of integrated database4 days Fri 5/18/18 Wed 5/23/18
25 3.2.1.3 Migration of data to the new
database
2 days Fri 6/1/18 Mon 6/4/18
26 M4 Database works completed 0 days Mon 6/4/18 Mon 6/4/18
27 3.2.2 Program works 21 days Tue 6/5/18 Tue 7/3/18
28 3.2.2.1 Interface development 5 days Tue 6/5/18 Mon 6/11/18
29 3.2.2.2 Integration of booking
system, vehicle management,
and pricing system
3 days Tue 6/12/18 Thu 6/14/18
30 3.2.2.3 Programming the functions
for the system
10 days Fri 6/15/18 Thu 6/28/18
31 M5 Completion of program works0 days Tue 7/3/18 Tue 7/3/18
32 3.3 Complete System Development 5 days Mon 7/9/18 Fri 7/13/18
33 4 Testing Phase 32 days Thu 5/24/18 Fri 7/6/18
34 4.1 Design Simulation 3 days Thu 5/24/18 Mon 5/28/18
35 4.2 Database Black box testing 3 days Tue 5/29/18 Thu 5/31/18
36 4.3 System Prototype Testing 3 days Wed 7/4/18 Fri 7/6/18
37 4.4 Program White Box testing 3 days Fri 6/29/18 Tue 7/3/18
38 M6 Testing Phase Completed 0 days Fri 7/6/18 Fri 7/6/18
39 5 Final Documentation and Training11 days Mon 7/16/18 Mon 7/30/18
40 5.1 Training Documents are made 4 days Mon 7/16/18 Thu 7/19/18
41 5.2 Training is given to employees 7 days Fri 7/20/18 Mon 7/30/18
42 5.3 Final reports are made 3 days Fri 7/20/18 Tue 7/24/18
43 5.4 Submission of reports 1 day Wed 7/25/18 Wed 7/25/18
44 5.5 Review and sign off 1 day Thu 7/26/18 Thu 7/26/18
45 M7 Project is Closed 0 days Thu 7/26/18 Thu 7/26/18
Analyst
Documenter,Documents[1]
Documenter,Documents[1]
Documenter
Project Manager
5/18
Planner
Budgeter
Risk Analyst
HR Manager
5/22
Designer
Designer
Designer,Design Tools[1]
Designer,Design Tools[1]
6/6
Database Developer
Database Developer,Database[1]
Database Developer
6/4
Software Engineer,Interface tools[1]
Software Engineer
Programmer,Programming Tools[1]
7/3
Software Engineer
Tester,Simulator[1]
Tester,Testing Tools[1]
Tester,Prototype[1]
Tester,Testing Tools[1]
7/6
Documenter,Documents[1]
Trainer
Documenter
Documenter
Project Manager
7/26
S W S T M F T S W S T M
Apr 8, '18 May 6, '18 Jun 3, '18 Jul 1, '18 Jul 29, '18 Aug 26, '18
Figure 2: Gantt chart of the project
(Source: Created by the author)

11PROJECT MANAGEMENT REPORT
3.3 Project Budget
The project budget for Sydney car rental project for developing Car Data Management
System is given below,
Cost Budget Estimation
Sydney Car Rental Project for developing Car Data Management System
Resource Name Type of
Resource
Work/Units Standard
Rate
Cost
Analyst Human 24.00 $45.00 $1,080.00
Documenter Human 104.00 $50.00 $5,200.00
Project Manager Human 16.00 $180.00 $2,880.00
Planner Human 24.00 $60.00 $1,440.00
Budgeter Human 16.00 $55.00 $880.00
Risk Analyst Human 32.00 $70.00 $2,240.00
HR Manager Human 24.00 $80.00 $1,920.00
Designer Human 96.00 $100.00 $9,600.00
Database
Developer
Human 56.00 $120.00 $6,720.00
Software Engineer Human 104.00 $150.00 $15,600.00
3.3 Project Budget
The project budget for Sydney car rental project for developing Car Data Management
System is given below,
Cost Budget Estimation
Sydney Car Rental Project for developing Car Data Management System
Resource Name Type of
Resource
Work/Units Standard
Rate
Cost
Analyst Human 24.00 $45.00 $1,080.00
Documenter Human 104.00 $50.00 $5,200.00
Project Manager Human 16.00 $180.00 $2,880.00
Planner Human 24.00 $60.00 $1,440.00
Budgeter Human 16.00 $55.00 $880.00
Risk Analyst Human 32.00 $70.00 $2,240.00
HR Manager Human 24.00 $80.00 $1,920.00
Designer Human 96.00 $100.00 $9,600.00
Database
Developer
Human 56.00 $120.00 $6,720.00
Software Engineer Human 104.00 $150.00 $15,600.00
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide
1 out of 20
Related Documents
Your All-in-One AI-Powered Toolkit for Academic Success.
 +13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
Copyright © 2020–2025 A2Z Services. All Rights Reserved. Developed and managed by ZUCOL.