Developing an Integrated Database System for Country Health Department
VerifiedAdded on 2025/05/10
|21
|3053
|57
AI Summary
Desklib offers solved assignments and past papers to help students succeed.

PROJECT MANAGEMENT
ASSESSMENT 3
ASSESSMENT 3
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Contents
Project Information.....................................................................................................................................4
Project title: CHD Integrated Information System...................................................................................4
Project start and end dates:....................................................................................................................4
Project goals............................................................................................................................................4
Project Objectives:...................................................................................................................................4
Project Requirements..................................................................................................................................5
Functional requirements.........................................................................................................................5
Non-functional Requirements.................................................................................................................5
Human resource requirements................................................................................................................5
Other requirements.................................................................................................................................6
Project team members............................................................................................................................6
Project Plan.................................................................................................................................................7
Project Scope...........................................................................................................................................7
Work Breakdown Structure.....................................................................................................................7
Time.........................................................................................................................................................7
Gantt Chart..............................................................................................................................................9
Network Diagram....................................................................................................................................9
Estimated cost.......................................................................................................................................10
Quality management methods..............................................................................................................11
Stakeholder analysis..............................................................................................................................12
Communication Plan.............................................................................................................................14
Risk management plan..........................................................................................................................15
Project Deployment plan.......................................................................................................................16
Project Sign off..........................................................................................................................................18
Project Information.....................................................................................................................................4
Project title: CHD Integrated Information System...................................................................................4
Project start and end dates:....................................................................................................................4
Project goals............................................................................................................................................4
Project Objectives:...................................................................................................................................4
Project Requirements..................................................................................................................................5
Functional requirements.........................................................................................................................5
Non-functional Requirements.................................................................................................................5
Human resource requirements................................................................................................................5
Other requirements.................................................................................................................................6
Project team members............................................................................................................................6
Project Plan.................................................................................................................................................7
Project Scope...........................................................................................................................................7
Work Breakdown Structure.....................................................................................................................7
Time.........................................................................................................................................................7
Gantt Chart..............................................................................................................................................9
Network Diagram....................................................................................................................................9
Estimated cost.......................................................................................................................................10
Quality management methods..............................................................................................................11
Stakeholder analysis..............................................................................................................................12
Communication Plan.............................................................................................................................14
Risk management plan..........................................................................................................................15
Project Deployment plan.......................................................................................................................16
Project Sign off..........................................................................................................................................18

Recommendation and conclusion.............................................................................................................19
References.................................................................................................................................................20
Table of figures:
Figure 1: WBS..............................................................................................................................................7
Figure 2: Time sheet....................................................................................................................................8
Figure 3: Gantt Chart...................................................................................................................................9
Figure 4: Network diagram..........................................................................................................................9
List of tables:
Table 1: Human resource cost table..........................................................................................................10
Table 2: Stakeholder analysis table...........................................................................................................12
Table 3: Communication plan table...........................................................................................................14
Table 4: Risk management plan.................................................................................................................15
Table 5: Project deployment plan..............................................................................................................16
References.................................................................................................................................................20
Table of figures:
Figure 1: WBS..............................................................................................................................................7
Figure 2: Time sheet....................................................................................................................................8
Figure 3: Gantt Chart...................................................................................................................................9
Figure 4: Network diagram..........................................................................................................................9
List of tables:
Table 1: Human resource cost table..........................................................................................................10
Table 2: Stakeholder analysis table...........................................................................................................12
Table 3: Communication plan table...........................................................................................................14
Table 4: Risk management plan.................................................................................................................15
Table 5: Project deployment plan..............................................................................................................16
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

Project Information
Project title: CHD Integrated Information System
The project developed here is for the Country Health Department and is developed to handle the crucial
situations of the disease and disaster. The new hired epidemiologist which was hired by CHD suggested
that the system should have a system that has integrated database and through which information can
be provided on time. Current system has isolated databases and for obtaining data of a particular
patient one has to go through four different systems.
Project start and end dates:
The start date of the project is 4th March 2019 and will take 195 days estimated to develop and will be
completed on 29th November 2019.
Project goals
The aim of the project is to develop the integrated database for the country health department. The
need for such system has been raised because for now the department consists for several databases
which hinder the accessibility for different users. This is significant because in the cases when any
tragedy arises, manager had to take time to access the details of the patient from several different
databases which can lead to any tragic incident. The system is essential as it provides many benefits like
bas stand out for the integrated data, every member of the country health department can access to it
and be able to manipulate the data. For the successful implementation, project manager should provide
stakeholders with the proper and relevant information.
Project Objectives:
The main objective of this project is to develop an integrated database for storing different information
relevant to the country health department. The epidemiologist has to be hired in order to implement
the integrated public health informatics system. Different team members should be hired in order to
develop the system by going through different phases of the development.
Project title: CHD Integrated Information System
The project developed here is for the Country Health Department and is developed to handle the crucial
situations of the disease and disaster. The new hired epidemiologist which was hired by CHD suggested
that the system should have a system that has integrated database and through which information can
be provided on time. Current system has isolated databases and for obtaining data of a particular
patient one has to go through four different systems.
Project start and end dates:
The start date of the project is 4th March 2019 and will take 195 days estimated to develop and will be
completed on 29th November 2019.
Project goals
The aim of the project is to develop the integrated database for the country health department. The
need for such system has been raised because for now the department consists for several databases
which hinder the accessibility for different users. This is significant because in the cases when any
tragedy arises, manager had to take time to access the details of the patient from several different
databases which can lead to any tragic incident. The system is essential as it provides many benefits like
bas stand out for the integrated data, every member of the country health department can access to it
and be able to manipulate the data. For the successful implementation, project manager should provide
stakeholders with the proper and relevant information.
Project Objectives:
The main objective of this project is to develop an integrated database for storing different information
relevant to the country health department. The epidemiologist has to be hired in order to implement
the integrated public health informatics system. Different team members should be hired in order to
develop the system by going through different phases of the development.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Project Requirements
Functional requirements
Functional requirements are needed to implement the integrated database for the country health
department to make the database functional. Following are the functional requirements for the
integrated database:
Operating system: Windows 10, Linux
RAM: min 8 GB
Hardware: CPU
Software: SQL server
Non-functional Requirements
Non-functional requirements are the requirements which specify the criteria for the system. These
requirements are used to judge the system’s operation. The following are the non-functional
requirements:
Security
Usability
Maintainability
Accessibility
Privacy
Portability
Human resource requirements
These requirements are essential for the overall development of the project. Different human
resources are involved in this project. Following are the involved the human resources:
Project manager: this is the person who manages the entire project from the very beginning till
the end.
System designer: designer is the person who helps in designing the blueprint of the system.
System developer: developer is one who is responsible for making the system functional.
Functional requirements
Functional requirements are needed to implement the integrated database for the country health
department to make the database functional. Following are the functional requirements for the
integrated database:
Operating system: Windows 10, Linux
RAM: min 8 GB
Hardware: CPU
Software: SQL server
Non-functional Requirements
Non-functional requirements are the requirements which specify the criteria for the system. These
requirements are used to judge the system’s operation. The following are the non-functional
requirements:
Security
Usability
Maintainability
Accessibility
Privacy
Portability
Human resource requirements
These requirements are essential for the overall development of the project. Different human
resources are involved in this project. Following are the involved the human resources:
Project manager: this is the person who manages the entire project from the very beginning till
the end.
System designer: designer is the person who helps in designing the blueprint of the system.
System developer: developer is one who is responsible for making the system functional.

Database handler: this person is responsible for the handling of the database i.e. he must know
about the advanced database.
System evaluator: this person is responsible to ensure the proper functioning of the system by
evaluating it on the basis of the criteria.
Document head: this is the person who is expert in reporting and writing the document.
Other requirements
Laptop
Printers
Documents
Project team members
S.No Title Skills
1. Project manager Communication, team management
2. System designer Able to solve complex problems
3. System developer Programming languages, problem-solving skills
4. Database handler Knowledge of database
5. System evaluator Knowledge of the system
6. Document head Writing and reporting skills
about the advanced database.
System evaluator: this person is responsible to ensure the proper functioning of the system by
evaluating it on the basis of the criteria.
Document head: this is the person who is expert in reporting and writing the document.
Other requirements
Laptop
Printers
Documents
Project team members
S.No Title Skills
1. Project manager Communication, team management
2. System designer Able to solve complex problems
3. System developer Programming languages, problem-solving skills
4. Database handler Knowledge of database
5. System evaluator Knowledge of the system
6. Document head Writing and reporting skills
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

Project Plan
Project Scope
The project has the goal to define the objectives to deliver a high quality integrated to help the CHD
department in order to manage the work and to establish a system that can help to gather information
about a patient’s medical data and history of the previous treatments.
Work Breakdown Structure
Figure 1: WBS
The WBS displayed above is to show the series and hierarchy of tasks in the order of tasks and subtasks
arranged in the order of their execution. The main one process is the major project which is the highest
priority work and the remaining are the subparts in which the work will be completed. If proceeded
from down to up (hierarch wise), the work process leads to completion of project (Crawford, 2014).
Time
The time required for the complete development of the system for the CHD will take almost 6 to 12
months to complete. According to the calculations and schedules made in the Times sheet as displayed
CHD Integrated
Information
System
Phase one:
initiating
Elaborate
problem scene
Find solution
Get solution
approved
Phase two:
Requirement
Gathering
Analyse system
requirements
Analayse user
requirements
Get
requirements
approved
Phase three:
Planning
Designing
process planning
Developemnet
process planning
System planning
Testing plan
Phase four:
Executing
Designg work
process
Getting design
approved
Development
initation
Project module
division
Project module
development
Module
integration
Test system
Phase five:
Project closing
Install system
Create
documents
Train employees
Project closure
Project Scope
The project has the goal to define the objectives to deliver a high quality integrated to help the CHD
department in order to manage the work and to establish a system that can help to gather information
about a patient’s medical data and history of the previous treatments.
Work Breakdown Structure
Figure 1: WBS
The WBS displayed above is to show the series and hierarchy of tasks in the order of tasks and subtasks
arranged in the order of their execution. The main one process is the major project which is the highest
priority work and the remaining are the subparts in which the work will be completed. If proceeded
from down to up (hierarch wise), the work process leads to completion of project (Crawford, 2014).
Time
The time required for the complete development of the system for the CHD will take almost 6 to 12
months to complete. According to the calculations and schedules made in the Times sheet as displayed
CHD Integrated
Information
System
Phase one:
initiating
Elaborate
problem scene
Find solution
Get solution
approved
Phase two:
Requirement
Gathering
Analyse system
requirements
Analayse user
requirements
Get
requirements
approved
Phase three:
Planning
Designing
process planning
Developemnet
process planning
System planning
Testing plan
Phase four:
Executing
Designg work
process
Getting design
approved
Development
initation
Project module
division
Project module
development
Module
integration
Test system
Phase five:
Project closing
Install system
Create
documents
Train employees
Project closure
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

in the below image. The project will take almost 195 days for completion. These will consist of the team
working for 8 hours a day and 5 days a week.
ID Task
Mode
Task Name Duration Start Finish PredecessorsResource Names Cost %
Complete
1 CHD Integrated
Information System
195 days Mon
3/4/19
Fri
11/29/19
$71,600.00 0%
2 Phase one: initiating19 days Mon 3/4/19Thu 3/28/19 $7,080.00 0%
3 Elaborate problem scene7 days Mon 3/4/19 Tue 3/12/19 Epidemiologist $4,480.00 0%
4 Find solution 7 days Wed 3/13/19Thu 3/21/193 $0.00 0%
5 Get solution approved5 days Fri 3/22/19 Thu 3/28/194 Document head $2,600.00 0%
6 Milestone 1 0 days Thu 3/28/19Thu 3/28/195 $0.00 0%
7 Phase two:
Requirement
Gathering
20 days Fri 3/29/19 Thu
4/25/19
$8,120.00 0%
8 Analyse system
requirements
7 days Fri 3/29/19 Mon 4/8/19 6 Epidemiologist $4,480.00 0%
9 Analayse user
requirements
6 days Tue 4/9/19 Tue
4/16/19
8 $0.00 0%
10 Get requirements approved7 days Wed 4/17/19Thu 4/25/199 Document head $3,640.00 0%
11 Milestone 2 0 days Thu 4/25/19Thu 4/25/1910 $0.00 0%
12 Phase three: Planning34 days Fri 4/26/19 Wed 6/12/19 $15,520.00 0%
13 Designing process planning10 days Fri 4/26/19 Thu 5/9/19 11 System Designer $5,600.00 0%
14 Developemnet
process planning
10 days Fri 5/10/19 Thu
5/23/19
13 System
Developer
$6,000.00 0%
15 System planning 7 days Fri 5/24/19 Mon 6/3/19 14 $0.00 0%
16 Testing plan 7 days Tue 6/4/19 Wed 6/12/1915 System Evaluator $3,920.00 0%
17 Milestone 3 0 days Wed 6/12/19Wed 6/12/1916 $0.00 0%
18 Phase four: Executing87 days Thu 6/13/19Fri 10/11/19 $21,320.00 0%
19 Designg work process7 days Thu 6/13/19Fri 6/21/19 17 System Designer $3,920.00 0%
20 Getting design approved3 days Mon 6/24/19Wed 6/26/1919 $0.00 0%
21 Development initation5 days Thu 6/27/19Wed 7/3/19 20 System Developer $3,000.00 0%
22 Project module division7 days Thu 7/4/19 Fri 7/12/19 21 $0.00 0%
23 Project module
development
40 days Mon
7/15/19
Fri 9/6/19 22 $0.00 0%
24 Module integration10 days Mon 9/9/19 Fri 9/20/19 23 System Developer $6,000.00 0%
25 Test system 15 days Mon 9/23/19Fri 10/11/1924 System Evaluator $8,400.00 0%
26 Milestone 4 0 days Fri 10/11/19Fri 10/11/1925 $0.00 0%
27 Phase five: Project
closing
35 days Mon
10/14/19
Fri
11/29/19
$19,560.00 0%
28 Install system 10 days Mon 10/14/19Fri 10/25/1926 System Evaluator $5,600.00 0%
29 Create documents7 days Mon 10/28/19Tue 11/5/1928 Document head $3,640.00 0%
30 Train employees 15 days Wed 11/6/19Tue 11/26/1929 System Designer $8,400.00 0%
31 Project closure 3 days Wed 11/27/19Fri 11/29/1930 Epidemiologist $1,920.00 0%
32 Milestone 5 0 days Fri 11/29/19Fri 11/29/1931 $0.00 0%
Qtr 1, 2019
Figure 2: Time sheet
working for 8 hours a day and 5 days a week.
ID Task
Mode
Task Name Duration Start Finish PredecessorsResource Names Cost %
Complete
1 CHD Integrated
Information System
195 days Mon
3/4/19
Fri
11/29/19
$71,600.00 0%
2 Phase one: initiating19 days Mon 3/4/19Thu 3/28/19 $7,080.00 0%
3 Elaborate problem scene7 days Mon 3/4/19 Tue 3/12/19 Epidemiologist $4,480.00 0%
4 Find solution 7 days Wed 3/13/19Thu 3/21/193 $0.00 0%
5 Get solution approved5 days Fri 3/22/19 Thu 3/28/194 Document head $2,600.00 0%
6 Milestone 1 0 days Thu 3/28/19Thu 3/28/195 $0.00 0%
7 Phase two:
Requirement
Gathering
20 days Fri 3/29/19 Thu
4/25/19
$8,120.00 0%
8 Analyse system
requirements
7 days Fri 3/29/19 Mon 4/8/19 6 Epidemiologist $4,480.00 0%
9 Analayse user
requirements
6 days Tue 4/9/19 Tue
4/16/19
8 $0.00 0%
10 Get requirements approved7 days Wed 4/17/19Thu 4/25/199 Document head $3,640.00 0%
11 Milestone 2 0 days Thu 4/25/19Thu 4/25/1910 $0.00 0%
12 Phase three: Planning34 days Fri 4/26/19 Wed 6/12/19 $15,520.00 0%
13 Designing process planning10 days Fri 4/26/19 Thu 5/9/19 11 System Designer $5,600.00 0%
14 Developemnet
process planning
10 days Fri 5/10/19 Thu
5/23/19
13 System
Developer
$6,000.00 0%
15 System planning 7 days Fri 5/24/19 Mon 6/3/19 14 $0.00 0%
16 Testing plan 7 days Tue 6/4/19 Wed 6/12/1915 System Evaluator $3,920.00 0%
17 Milestone 3 0 days Wed 6/12/19Wed 6/12/1916 $0.00 0%
18 Phase four: Executing87 days Thu 6/13/19Fri 10/11/19 $21,320.00 0%
19 Designg work process7 days Thu 6/13/19Fri 6/21/19 17 System Designer $3,920.00 0%
20 Getting design approved3 days Mon 6/24/19Wed 6/26/1919 $0.00 0%
21 Development initation5 days Thu 6/27/19Wed 7/3/19 20 System Developer $3,000.00 0%
22 Project module division7 days Thu 7/4/19 Fri 7/12/19 21 $0.00 0%
23 Project module
development
40 days Mon
7/15/19
Fri 9/6/19 22 $0.00 0%
24 Module integration10 days Mon 9/9/19 Fri 9/20/19 23 System Developer $6,000.00 0%
25 Test system 15 days Mon 9/23/19Fri 10/11/1924 System Evaluator $8,400.00 0%
26 Milestone 4 0 days Fri 10/11/19Fri 10/11/1925 $0.00 0%
27 Phase five: Project
closing
35 days Mon
10/14/19
Fri
11/29/19
$19,560.00 0%
28 Install system 10 days Mon 10/14/19Fri 10/25/1926 System Evaluator $5,600.00 0%
29 Create documents7 days Mon 10/28/19Tue 11/5/1928 Document head $3,640.00 0%
30 Train employees 15 days Wed 11/6/19Tue 11/26/1929 System Designer $8,400.00 0%
31 Project closure 3 days Wed 11/27/19Fri 11/29/1930 Epidemiologist $1,920.00 0%
32 Milestone 5 0 days Fri 11/29/19Fri 11/29/1931 $0.00 0%
Qtr 1, 2019
Figure 2: Time sheet

Gantt Chart
ID Task
Mode
Task Name Duration Start Finish PredecessorsResource Names Cost %
Complete
1 CHD Integrated
Information System
195 days Mon
3/4/19
Fri
11/29/19
$71,600.00 0%
2 Phase one: initiating19 days Mon 3/4/19Thu 3/28/19 $7,080.00 0%
3 Elaborate problem scene7 days Mon 3/4/19 Tue 3/12/19 Epidemiologist $4,480.00 0%
4 Find solution 7 days Wed 3/13/19Thu 3/21/193 $0.00 0%
5 Get solution approved5 days Fri 3/22/19 Thu 3/28/194 Document head $2,600.00 0%
6 Milestone 1 0 days Thu 3/28/19Thu 3/28/195 $0.00 0%
7 Phase two:
Requirement
Gathering
20 days Fri 3/29/19 Thu
4/25/19
$8,120.00 0%
8 Analyse system
requirements
7 days Fri 3/29/19 Mon 4/8/196 Epidemiologist $4,480.00 0%
9 Analayse user
requirements
6 days Tue 4/9/19 Tue
4/16/19
8 $0.00 0%
10 Get requirements approved7 days Wed 4/17/19Thu 4/25/199 Document head $3,640.00 0%
11 Milestone 2 0 days Thu 4/25/19Thu 4/25/1910 $0.00 0%
12 Phase three: Planning34 days Fri 4/26/19 Wed 6/12/19 $15,520.00 0%
13 Designing process planning10 days Fri 4/26/19 Thu 5/9/19 11 System Designer $5,600.00 0%
14 Developemnet
process planning
10 days Fri 5/10/19 Thu
5/23/19
13 System
Developer
$6,000.00 0%
15 System planning 7 days Fri 5/24/19 Mon 6/3/1914 $0.00 0%
16 Testing plan 7 days Tue 6/4/19 Wed 6/12/1915 System Evaluator $3,920.00 0%
17 Milestone 3 0 days Wed 6/12/19Wed 6/12/1916 $0.00 0%
18 Phase four: Executing87 days Thu 6/13/19Fri 10/11/19 $21,320.00 0%
19 Designg work process7 days Thu 6/13/19Fri 6/21/19 17 System Designer $3,920.00 0%
20 Getting design approved3 days Mon 6/24/19Wed 6/26/1919 $0.00 0%
21 Development initation5 days Thu 6/27/19Wed 7/3/1920 System Developer $3,000.00 0%
22 Project module division7 days Thu 7/4/19 Fri 7/12/19 21 $0.00 0%
23 Project module
development
40 days Mon
7/15/19
Fri 9/6/19 22 $0.00 0%
24 Module integration10 days Mon 9/9/19 Fri 9/20/19 23 System Developer $6,000.00 0%
25 Test system 15 days Mon 9/23/19Fri 10/11/1924 System Evaluator $8,400.00 0%
26 Milestone 4 0 days Fri 10/11/19Fri 10/11/1925 $0.00 0%
27 Phase five: Project
closing
35 days Mon
10/14/19
Fri
11/29/19
$19,560.00 0%
28 Install system 10 days Mon 10/14/19Fri 10/25/1926 System Evaluator $5,600.00 0%
29 Create documents7 days Mon 10/28/19Tue 11/5/1928 Document head $3,640.00 0%
30 Train employees 15 days Wed 11/6/19Tue 11/26/1929 System Designer $8,400.00 0%
31 Project closure 3 days Wed 11/27/19Fri 11/29/1930 Epidemiologist $1,920.00 0%
32 Milestone 5 0 days Fri 11/29/19Fri 11/29/1931 $0.00 0%
Epidemiologist
Document head
3/28
Epidemiologist
Document head
4/25
System Designer
System Developer
System Evaluator
6/12
System Designer
System Developer
System Developer
System Evaluator
10/11
System Evaluator
Document head
System Designer
Epidemiologist
11/29
Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019
Figure 3: Gantt Chart
Network Diagram
Figure 4: Network diagram
The diagram above shows the network diagram of the project development plan for the integrated
database system for CHD. It shows the path followed to complete the project and to reach the final
milestone.
ID Task
Mode
Task Name Duration Start Finish PredecessorsResource Names Cost %
Complete
1 CHD Integrated
Information System
195 days Mon
3/4/19
Fri
11/29/19
$71,600.00 0%
2 Phase one: initiating19 days Mon 3/4/19Thu 3/28/19 $7,080.00 0%
3 Elaborate problem scene7 days Mon 3/4/19 Tue 3/12/19 Epidemiologist $4,480.00 0%
4 Find solution 7 days Wed 3/13/19Thu 3/21/193 $0.00 0%
5 Get solution approved5 days Fri 3/22/19 Thu 3/28/194 Document head $2,600.00 0%
6 Milestone 1 0 days Thu 3/28/19Thu 3/28/195 $0.00 0%
7 Phase two:
Requirement
Gathering
20 days Fri 3/29/19 Thu
4/25/19
$8,120.00 0%
8 Analyse system
requirements
7 days Fri 3/29/19 Mon 4/8/196 Epidemiologist $4,480.00 0%
9 Analayse user
requirements
6 days Tue 4/9/19 Tue
4/16/19
8 $0.00 0%
10 Get requirements approved7 days Wed 4/17/19Thu 4/25/199 Document head $3,640.00 0%
11 Milestone 2 0 days Thu 4/25/19Thu 4/25/1910 $0.00 0%
12 Phase three: Planning34 days Fri 4/26/19 Wed 6/12/19 $15,520.00 0%
13 Designing process planning10 days Fri 4/26/19 Thu 5/9/19 11 System Designer $5,600.00 0%
14 Developemnet
process planning
10 days Fri 5/10/19 Thu
5/23/19
13 System
Developer
$6,000.00 0%
15 System planning 7 days Fri 5/24/19 Mon 6/3/1914 $0.00 0%
16 Testing plan 7 days Tue 6/4/19 Wed 6/12/1915 System Evaluator $3,920.00 0%
17 Milestone 3 0 days Wed 6/12/19Wed 6/12/1916 $0.00 0%
18 Phase four: Executing87 days Thu 6/13/19Fri 10/11/19 $21,320.00 0%
19 Designg work process7 days Thu 6/13/19Fri 6/21/19 17 System Designer $3,920.00 0%
20 Getting design approved3 days Mon 6/24/19Wed 6/26/1919 $0.00 0%
21 Development initation5 days Thu 6/27/19Wed 7/3/1920 System Developer $3,000.00 0%
22 Project module division7 days Thu 7/4/19 Fri 7/12/19 21 $0.00 0%
23 Project module
development
40 days Mon
7/15/19
Fri 9/6/19 22 $0.00 0%
24 Module integration10 days Mon 9/9/19 Fri 9/20/19 23 System Developer $6,000.00 0%
25 Test system 15 days Mon 9/23/19Fri 10/11/1924 System Evaluator $8,400.00 0%
26 Milestone 4 0 days Fri 10/11/19Fri 10/11/1925 $0.00 0%
27 Phase five: Project
closing
35 days Mon
10/14/19
Fri
11/29/19
$19,560.00 0%
28 Install system 10 days Mon 10/14/19Fri 10/25/1926 System Evaluator $5,600.00 0%
29 Create documents7 days Mon 10/28/19Tue 11/5/1928 Document head $3,640.00 0%
30 Train employees 15 days Wed 11/6/19Tue 11/26/1929 System Designer $8,400.00 0%
31 Project closure 3 days Wed 11/27/19Fri 11/29/1930 Epidemiologist $1,920.00 0%
32 Milestone 5 0 days Fri 11/29/19Fri 11/29/1931 $0.00 0%
Epidemiologist
Document head
3/28
Epidemiologist
Document head
4/25
System Designer
System Developer
System Evaluator
6/12
System Designer
System Developer
System Developer
System Evaluator
10/11
System Evaluator
Document head
System Designer
Epidemiologist
11/29
Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Qtr 1, 2019 Qtr 2, 2019 Qtr 3, 2019 Qtr 4, 2019
Figure 3: Gantt Chart
Network Diagram
Figure 4: Network diagram
The diagram above shows the network diagram of the project development plan for the integrated
database system for CHD. It shows the path followed to complete the project and to reach the final
milestone.
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

Estimated cost
The cost of the project will be sanctioned from the Robert Wood Johnson Foundation also known as the
RWJF which is affiliated by the PHII i.e. the Public Health Informatics Institute. The organization RWJF is
known for supporting the health organizations that are struggling to meet the daily needs of the
organization due to the lack of the funding and capital support.
The project cost is going to include the cost of the human resources which is paid according to their
work and effort required for the project work and completion. The final cost is $21,280.00, and this is
the final cost of core development work. The other costs of the project might include the small charges
for the project related resources like documents and other.
Table 1: Human resource cost table
Resource Name Type Std. Rate Over time Rate Cost/Use
Epidemiologist Work $80.00/hour $0.00/hour $0.00
System Designer Work $70.00/hour $0.00/hour $0.00
System Developer Work $75.00/hour $0.00/hour $0.00
Database Handler Work $75.00/hour $0.00/hour $0.00
System Evaluator Work $70.00/hour $0.00/hour $0.00
Document head Work $65.00/hour $0.00/hour $0.00
The cost of the project will be sanctioned from the Robert Wood Johnson Foundation also known as the
RWJF which is affiliated by the PHII i.e. the Public Health Informatics Institute. The organization RWJF is
known for supporting the health organizations that are struggling to meet the daily needs of the
organization due to the lack of the funding and capital support.
The project cost is going to include the cost of the human resources which is paid according to their
work and effort required for the project work and completion. The final cost is $21,280.00, and this is
the final cost of core development work. The other costs of the project might include the small charges
for the project related resources like documents and other.
Table 1: Human resource cost table
Resource Name Type Std. Rate Over time Rate Cost/Use
Epidemiologist Work $80.00/hour $0.00/hour $0.00
System Designer Work $70.00/hour $0.00/hour $0.00
System Developer Work $75.00/hour $0.00/hour $0.00
Database Handler Work $75.00/hour $0.00/hour $0.00
System Evaluator Work $70.00/hour $0.00/hour $0.00
Document head Work $65.00/hour $0.00/hour $0.00
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Quality management methods
There are various ways through which the quality of the project is managed. The methods that will be
used to manage the quality of the project developed for CHD are:
Plan the quality: the requirements of the project and the required features and advancements
will be gathered in the initial phase and the deliverables will be approved. This will allow to set
the checkboxes for quality.
Quality control: the process in the development and designing will be monitored by individual
supervisors and the overall supervisors will be headed by the epidemiologist. A proper hierarchy
plan will be made in order to make sure that the quality is maintained.
Quality improvement: for improving the quality of the project and for continuing the system
growth the regular feedback from the people working with the software and the people getting
help from the project will be recorded.
There are various ways through which the quality of the project is managed. The methods that will be
used to manage the quality of the project developed for CHD are:
Plan the quality: the requirements of the project and the required features and advancements
will be gathered in the initial phase and the deliverables will be approved. This will allow to set
the checkboxes for quality.
Quality control: the process in the development and designing will be monitored by individual
supervisors and the overall supervisors will be headed by the epidemiologist. A proper hierarchy
plan will be made in order to make sure that the quality is maintained.
Quality improvement: for improving the quality of the project and for continuing the system
growth the regular feedback from the people working with the software and the people getting
help from the project will be recorded.

Stakeholder analysis
Table 2: Stakeholder analysis table
S. NO. STAKEHOLDER ROLES DIRECT/INDIRECT
1. Project manager The epidemiologist will oversee the progress
and management of the project and will play
the role of the project manager.
Direct
2. System designer The system designer will be provided with
the responsibility to design the overall
system to meet the user and organization
requirements.
Direct
3. System developer The system developer will be provided with
the responsibility to develop the overall
system to meet the user and organization
requirements and match the system design.
Direct
4. Database handler The database handler will be provided with
the responsibility to design the overall
system database to connect organization
data at one place.
Direct
5. System evaluator The system evaluator will be provided with
the responsibility to test the overall system
to evaluate the accuracy of the developed
system and ensure that the user and
organization requirements are met (Sharp,
2012).
Direct
6. Document head The responsibility to maintain all the
documents and get them legalized.
Direct
7. Client To use the system and get the contract
finalized.
Direct
8. Sponsor To provide the fund for the development
and implementation of project.
Indirect
9. Senior Management To manage the project and the Indirect
Table 2: Stakeholder analysis table
S. NO. STAKEHOLDER ROLES DIRECT/INDIRECT
1. Project manager The epidemiologist will oversee the progress
and management of the project and will play
the role of the project manager.
Direct
2. System designer The system designer will be provided with
the responsibility to design the overall
system to meet the user and organization
requirements.
Direct
3. System developer The system developer will be provided with
the responsibility to develop the overall
system to meet the user and organization
requirements and match the system design.
Direct
4. Database handler The database handler will be provided with
the responsibility to design the overall
system database to connect organization
data at one place.
Direct
5. System evaluator The system evaluator will be provided with
the responsibility to test the overall system
to evaluate the accuracy of the developed
system and ensure that the user and
organization requirements are met (Sharp,
2012).
Direct
6. Document head The responsibility to maintain all the
documents and get them legalized.
Direct
7. Client To use the system and get the contract
finalized.
Direct
8. Sponsor To provide the fund for the development
and implementation of project.
Indirect
9. Senior Management To manage the project and the Indirect
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide
1 out of 21
Related Documents

Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
Copyright © 2020–2025 A2Z Services. All Rights Reserved. Developed and managed by ZUCOL.