University Project: Chinese Restaurant Construction and Management

Verified

Added on  2023/05/28

|19
|3520
|497
Project
AI Summary
This project report details the construction of a Chinese restaurant in London, UK, aiming to provide affordable Chinese cuisine. The project encompasses various phases, including initiation, planning, execution, development, and closure. The report defines project scope, develops a Work Breakdown Structure (WBS) for food preparation, and establishes a detailed project timeline with a critical path analysis. It provides cost estimations for each task, sets a comprehensive budget, and outlines quality management strategies, including identifying quality requirements and measurement tools. The report also addresses communication plans and stakeholder management, identifying key stakeholders and strategies for effective engagement. The project aims to construct a restaurant with a Chinese theme, focusing on providing quality food within a reasonable price range, thereby addressing the needs of the middle-class population.
Document Page
Running head: CONSTRUCTION OF CHINESE RESTURANT
Construction of a Chinese restaurant
Name of the Student
Name of the University
Author’s Note
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
1
CONSTRUCTION OF CHINESE RESTURANT
Table of Contents
Part 1:.........................................................................................................................................2
Part 2:.........................................................................................................................................3
1) Project scope (Planning, monitor/control).............................................................................3
1.1 Scope................................................................................................................................3
1.2 Development of WBS for cooking food..........................................................................4
2) Project time (Planning)..........................................................................................................4
2.1 Detailed timeline based on the WBS...............................................................................4
2.2 Identification of critical path............................................................................................8
3) Project cost (Planning, monitor/control.................................................................................9
3.1 Estimation of the costs that is identified in the WBS.......................................................9
3.2 Setting budget based on the estimated costs..................................................................10
4) Project quality management (planning, execution, monitoring/control).............................13
4.1 Identification of the quality requirements......................................................................13
4.2 Identification of tool that will be used for measuring the quality..................................13
5) Communication (Planning, executing, monitoring/control)................................................13
5.1 Indication of who requires to kept informed about the project progress.......................13
5.2 Type of information generally needed...........................................................................14
6) Stakeholders (planning, executing, monitoring/control).....................................................14
6.1 Identification of the stakeholders...................................................................................14
6.2 Planning and managing stakeholders.............................................................................15
Bibliography.............................................................................................................................16
Document Page
2
CONSTRUCTION OF CHINESE RESTURANT
Part 1:
Project introduction
The paper focuses on the construction of Chinese restaurant in London, UK. It is
found that the Chinese restaurants which are generally present in Australia are very much
expensive and therefore the middle-class people face difficulty in affording food in the
existing Chinese restaurants. In order to resolve this issue, a new Chinese restaurant will be
constructed in London. The restaurant that will be constructed will be able to provide
different types of Chinese food in a proper ambience within a reasonable price.
Timeline of the project lifecycle
Figure 1: Gantt chart
Document Page
3
CONSTRUCTION OF CHINESE RESTURANT
(Source: Created by Author)
Part 2:
State the selected activity
It is found that the framework for the restaurant is generally constructed by taking the
Chinese theme. It is found that in order to execute this activity of the project, it is very much
important to apply the processes of project management that generally includes initiation,
execution, monitoring as well and closing phase. It is found that in the planning phase, cost as
well as time needed for developing the framework is identified however in the project
initiation phase, proper meeting is arrangement with the stakeholders of the project. In the
project execution phase it is found that the framework for the restaurant is developed as per
the Chinese theme. Furthermore, in the monitoring phase, the executed activity is monitored.
Lastly in the closure phase, stakeholder sign off as well as project documentation are
generally done for closing the project.
1) Project scope (Planning, monitor/control)
1.1 Scope
The project scope generally include the following:
Construction of the Chinese restaurant
Development of restaurant with the help of Chinese theme
Development of entry as well as exit spaces
Installation of the electric circuit and more
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
4
CONSTRUCTION OF CHINESE RESTURANT
1.2 Development of WBS for cooking food
Cooking food
Initiation phase
Determining the
item that is being
cooked
Determining the cook
for cooking the item
Planning phase
Identyfying the neede
requirements
Determining the
needed money
Execution phase
Making arrangement
for cooking
Keep disjes at
minimum
Focussing on
mastering food
prepration
Using the tools
required for cooking
Decoration
Closure phase
Cooking of the item
complete
Figure 2: WBS
(Source: Created by Author)
2) Project time (Planning)
2.1 Detailed timeline based on the WBS
The detailed timeline is provided in the table below. It is reflected that the project can
be finished successfully within 368days and the time that is required for executing each of the
activities of the project is generally showcased in the table that is given below.
WBS Task Name Duration Start Finish
0
Construction of Chinese restaurant in
Australia
368 days Mon 03-12-18 Wed 29-04-20
1 Project planning 47 days Mon 03-12-18 Tue 05-02-19
1.1 Analysis of the project requirements 6 days Mon 03-12-18 Mon 10-12-18
1.2 Analysis of the project nature 5 days Tue 11-12-18 Mon 17-12-18
Document Page
5
CONSTRUCTION OF CHINESE RESTURANT
1.3 Resources estimation 4 days Tue 18-12-18 Fri 21-12-18
1.4 Estimation of time 5 days Mon 24-12-18 Fri 28-12-18
1.5 Budget estimation 10 days Mon 31-12-18 Fri 11-01-19
1.6 Manpower estimation 8 days Mon 14-01-19 Wed 23-01-19
1.7 Resource analysis 9 days Thu 24-01-19 Tue 05-02-19
1.8
Milestone 1: Completion of
planning phase
0 days Tue 05-02-19 Tue 05-02-19
2 Initiation phase 105 days Wed 06-02-19 Tue 02-07-19
2.1 Land procurement 7 days Wed 06-02-19 Thu 14-02-19
2.2 Stakeholders appointment 8 days Fri 15-02-19 Tue 26-02-19
2.3 Meeting arrangement 6 days Wed 27-02-19 Wed 06-03-19
2.4 Financial plan arrangement 9 days Thu 07-03-19 Tue 19-03-19
2.5 Workers appointment 8 days Wed 20-03-19 Fri 29-03-19
2.6 Blueprint preparation 7 days Mon 01-04-19 Tue 09-04-19
2.7 Procurement of land area 5 days Wed 10-04-19 Tue 16-04-19
2.8 Release of legal notice 7 days Wed 17-04-19 Thu 25-04-19
2.9 Allocation of budget 9 days Fri 26-04-19 Wed 08-05-19
2.10 Procurement of resources 8 days Thu 09-05-19 Mon 20-05-19
2.11 Time allocation 7 days Tue 21-05-19 Wed 29-05-19
2.12 Duty allocation 8 days Thu 30-05-19 Mon 10-06-19
2.13 Analysis of risk 9 days Tue 11-06-19 Fri 21-06-19
2.14 Risk mitigation plan 7 days Mon 24-06-19 Tue 02-07-19
2.15 Completion of project initiation 0 days Tue 02-07-19 Tue 02-07-19
3 Execution phase 178 days Wed 03-07-19 Fri 06-03-20
Document Page
6
CONSTRUCTION OF CHINESE RESTURANT
3.1 Preparation of land 12 days Wed 03-07-19 Thu 18-07-19
3.2 Resource assortment 13 days Fri 19-07-19 Tue 06-08-19
3.3 Restaurant construction 9 days Wed 07-08-19 Mon 19-08-19
3.4
Framework construction by taking
Chinese’s theme
10 days Tue 20-08-19 Mon 02-09-19
3.5 Selection of entry and exit spaces 11 days Tue 03-09-19 Tue 17-09-19
3.6 Bricks application 14 days Wed 18-09-19 Mon 07-10-19
3.7 Plumbing 12 days Tue 08-10-19 Wed 23-10-19
3.8 Installation of electric circuit 13 days Thu 24-10-19 Mon 11-11-19
3.9 Application of concrete 15 days Tue 12-11-19 Mon 02-12-19
3.10 Colour application 11 days Tue 03-12-19 Tue 17-12-19
3.11 System implementation 10 days Wed 18-12-19 Tue 31-12-19
3.12 Tiles application 9 days Wed 01-01-20 Mon 13-01-20
3.13 Film processing implementation 15 days Tue 14-01-20 Mon 03-02-20
3.14 Dining room construction 13 days Tue 04-02-20 Thu 20-02-20
3.15 Central heating zones construction 11 days Fri 21-02-20 Fri 06-03-20
3.16 Project execution completion 0 days Fri 06-03-20 Fri 06-03-20
4 Development phase 35 days Mon 09-03-20 Fri 24-04-20
4.1 Restaurant board formation 8 days Mon 09-03-20 Wed 18-03-20
4.2 Preparation of statement vision 7 days Thu 19-03-20 Fri 27-03-20
4.3 Preparation of standard service 9 days Mon 30-03-20 Thu 09-04-20
4.4 Parking a lot implementation 6 days Fri 10-04-20 Fri 17-04-20
4.5 Finalization 5 days Mon 20-04-20 Fri 24-04-20
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
7
CONSTRUCTION OF CHINESE RESTURANT
4.6 Development phase completion 0 days Fri 24-04-20 Fri 24-04-20
5 Closure phase 3 days Mon 27-04-20 Wed 29-04-20
5.1 Sign off stakeholder 2 days Mon 27-04-20 Tue 28-04-20
5.2 Review of post project 1 day Wed 29-04-20 Wed 29-04-20
5.3 Completion of project closure phase 0 days Wed 29-04-20 Wed 29-04-20
Document Page
8
CONSTRUCTION OF CHINESE RESTURANT
2.2 Identification of critical path
Figure 3: Critical path
(Source: Created by Author)
Document Page
9
CONSTRUCTION OF CHINESE RESTURANT
3) Project cost (Planning, monitor/control
3.1 Estimation of the costs that is identified in the WBS
0
1
1.1
1.2
1.3
1.4
1.5
1.6
1.7
1.8
2
2.1
2.2
2.3
2.4
2.5
2.6
2.7
2.8
2.9
2.10
2.11
2.12
2.13
2.14
2.15
3
3.1
3.2
3.3
3.4
3.5
3.6
3.7
3.8
3.9
3.10
3.11
3.12
3.13
3.14
3.15
3.16
4
4.1
4.2
4.3
4.4
4.5
4.6
5
5.1
5.2
5.3
Construction of chinese
resturant in Australia
£258,568.00 6,080 hours
Project planning
£15,600.00 376 hours
Analysis of the project
requirements
£1,920.00 48 hours
Analysis of the project
nature
£1,400.00 40 hours
Resources estimation
£1,600.00 32 hours
Estimation of time
£1,600.00 40 hours
Budget estimatation
£4,000.00 80 hours
Manpower estimation
£2,560.00 64 hours
Resource analysis
£2,520.00 72 hours
Milestone 1:Completion of
planning phase
£0.00 0 hours
Initiation phase
£52,168.00 1,344 hours
Land procurement
£0.00 56 hours
Stakeholders
appointment
£2,560.00 64 hours
Meeting arrangement
£1,920.00 48 hours
Financial plan
arrangement
£3,600.00 72 hours
Workers appointment
£2,240.00 64 hours
Blueprint preparation
£3,360.00 56 hours
Procurement of land area
£2,400.00 40 hours
Release of legal notice
£6,160.00 112 hours
Allocation of budget
£3,600.00 144 hours
Procurement of
resources
£5,568.00 128 hours
Time allocation
£4,760.00 112 hours
Duty allocation
£6,400.00 192 hours
Analysis of risk
£5,400.00 144 hours
Risk mitigation plan
£4,200.00 112 hours
Completion of project
initiation
£0.00 0 hours
Execution phase
£163,728.00 3,704 hours
Preparation of land
£13,920.00 288 hours
Resource assortment
£8,840.00 208 hours
Resturant construction
£6,120.00 144 hours
Framework
constructution by taking
chineses theme
£8,800.00 160 hours
Selection of entry and
exit spaces
£8,536.00 176 hours
Bricks application
£16,464.00 336 hours
Plumbing
£10,272.00 288 hours
Installation of electric
circuit
£13,728.00 312 hours
Application of concrete
£19,440.00 480 hours
Colour application
£10,120.00 264 hours
System implementation
£6,160.00 160 hours
Tiles application
£11,520.00 216 hours
Film processing
implementation
£17,640.00 360 hours
Dining room construction
£12,168.00 312 hours
Central heating zones
construction
£0.00 0 hours
Project execution
completion
£0.00 0 hours
Development phase
£26,152.00 632 hours
Resturant board
formation
£4,928.00 128 hours
Preparation of statement
vision
£4,760.00 112 hours
Preparation of standard
service
£9,144.00 216 hours
Parking a lot
implementation
£4,320.00 96 hours
Finalization
£3,000.00 80 hours
Development phase
completion
£0.00 0 hours
Closure phase
£920.00 24 hours
Sign off stakeholder
£640.00 16 hours
Review of post project
£280.00 8 hours
Completion of project
closure phase
£0.00 0 hours
Figure 4: Project cost as per WBS
(Source: Created by Author)
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
10
CONSTRUCTION OF CHINESE RESTURANT
3.2 Setting budget based on the estimated costs
The budget that is generally assumed as per the estimation for the construction of the
Chinese restaurant is generally provided in the table below. The table reflects that the project
will be finished within the budget £258,568.00.
WBS Task Name Duration Resource Names Cost
0
Construction of Chinese
restaurant in Australia
368 days £258,568.00
1 Project planning 47 days £15,600.00
1.1
Analysis of the project
requirements
6 days Project manager £1,920.00
1.2
Analysis of the project
nature
5 days Project planner £1,400.00
1.3 Resources estimation 4 days Finance manager £1,600.00
1.4 Estimation of time 5 days Project manager £1,600.00
1.5 Budget estimation 10 days Finance manager £4,000.00
1.6 Manpower estimation 8 days Project manager £2,560.00
1.7 Resource analysis 9 days Project planner £2,520.00
1.8
Milestone 1: Completion of
planning phase
0 days Project manager £0.00
2 Initiation phase 105 days £52,168.00
2.1 Land procurement 7 days Sponsor £0.00
2.2 Stakeholders appointment 8 days Project manager £2,560.00
2.3 Meeting arrangement 6 days Project manager £1,920.00
2.4 Financial plan arrangement 9 days Finance manager £3,600.00
Document Page
11
CONSTRUCTION OF CHINESE RESTURANT
2.5 Workers appointment 8 days Project planner £2,240.00
2.6 Blueprint preparation 7 days Site supervisor £3,360.00
2.7 Procurement of land area 5 days Site supervisor £2,400.00
2.8 Release of legal notice 7 days
Contractor, Site
supervisor
£6,160.00
2.9 Allocation of budget 9 days
Finance manager,
Sponsor
£3,600.00
2.10 Procurement of resources 8 days
Contractor, System
planner
£5,568.00
2.11 Time allocation 7 days
Contractor, Project
planner
£4,760.00
2.12 Duty allocation 8 days
Contractor, Finance
manager, Sponsor
£6,400.00
2.13 Analysis of risk 9 days
Risk manager,
Project planner
£5,400.00
2.14 Risk mitigation plan 7 days
Risk manager,
Project planner
£4,200.00
2.15
Completion of project
initiation
0 days Project manager £0.00
3 Execution phase 178 days £163,728.00
3.1 Preparation of land 12 days
Site supervisor,
Contractor, Project
planner
£13,920.00
chevron_up_icon
1 out of 19
circle_padding
hide_on_mobile
zoom_out_icon
[object Object]