University Project: Chinese Restaurant Construction and Management
VerifiedAdded on 2023/05/28
|19
|3520
|497
Project
AI Summary
This project report details the construction of a Chinese restaurant in London, UK, aiming to provide affordable Chinese cuisine. The project encompasses various phases, including initiation, planning, execution, development, and closure. The report defines project scope, develops a Work Breakdown Structure (WBS) for food preparation, and establishes a detailed project timeline with a critical path analysis. It provides cost estimations for each task, sets a comprehensive budget, and outlines quality management strategies, including identifying quality requirements and measurement tools. The report also addresses communication plans and stakeholder management, identifying key stakeholders and strategies for effective engagement. The project aims to construct a restaurant with a Chinese theme, focusing on providing quality food within a reasonable price range, thereby addressing the needs of the middle-class population.

Running head: CONSTRUCTION OF CHINESE RESTURANT
Construction of a Chinese restaurant
Name of the Student
Name of the University
Author’s Note
Construction of a Chinese restaurant
Name of the Student
Name of the University
Author’s Note
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.

1
CONSTRUCTION OF CHINESE RESTURANT
Table of Contents
Part 1:.........................................................................................................................................2
Part 2:.........................................................................................................................................3
1) Project scope (Planning, monitor/control).............................................................................3
1.1 Scope................................................................................................................................3
1.2 Development of WBS for cooking food..........................................................................4
2) Project time (Planning)..........................................................................................................4
2.1 Detailed timeline based on the WBS...............................................................................4
2.2 Identification of critical path............................................................................................8
3) Project cost (Planning, monitor/control.................................................................................9
3.1 Estimation of the costs that is identified in the WBS.......................................................9
3.2 Setting budget based on the estimated costs..................................................................10
4) Project quality management (planning, execution, monitoring/control).............................13
4.1 Identification of the quality requirements......................................................................13
4.2 Identification of tool that will be used for measuring the quality..................................13
5) Communication (Planning, executing, monitoring/control)................................................13
5.1 Indication of who requires to kept informed about the project progress.......................13
5.2 Type of information generally needed...........................................................................14
6) Stakeholders (planning, executing, monitoring/control).....................................................14
6.1 Identification of the stakeholders...................................................................................14
6.2 Planning and managing stakeholders.............................................................................15
Bibliography.............................................................................................................................16
CONSTRUCTION OF CHINESE RESTURANT
Table of Contents
Part 1:.........................................................................................................................................2
Part 2:.........................................................................................................................................3
1) Project scope (Planning, monitor/control).............................................................................3
1.1 Scope................................................................................................................................3
1.2 Development of WBS for cooking food..........................................................................4
2) Project time (Planning)..........................................................................................................4
2.1 Detailed timeline based on the WBS...............................................................................4
2.2 Identification of critical path............................................................................................8
3) Project cost (Planning, monitor/control.................................................................................9
3.1 Estimation of the costs that is identified in the WBS.......................................................9
3.2 Setting budget based on the estimated costs..................................................................10
4) Project quality management (planning, execution, monitoring/control).............................13
4.1 Identification of the quality requirements......................................................................13
4.2 Identification of tool that will be used for measuring the quality..................................13
5) Communication (Planning, executing, monitoring/control)................................................13
5.1 Indication of who requires to kept informed about the project progress.......................13
5.2 Type of information generally needed...........................................................................14
6) Stakeholders (planning, executing, monitoring/control).....................................................14
6.1 Identification of the stakeholders...................................................................................14
6.2 Planning and managing stakeholders.............................................................................15
Bibliography.............................................................................................................................16

2
CONSTRUCTION OF CHINESE RESTURANT
Part 1:
Project introduction
The paper focuses on the construction of Chinese restaurant in London, UK. It is
found that the Chinese restaurants which are generally present in Australia are very much
expensive and therefore the middle-class people face difficulty in affording food in the
existing Chinese restaurants. In order to resolve this issue, a new Chinese restaurant will be
constructed in London. The restaurant that will be constructed will be able to provide
different types of Chinese food in a proper ambience within a reasonable price.
Timeline of the project lifecycle
Figure 1: Gantt chart
CONSTRUCTION OF CHINESE RESTURANT
Part 1:
Project introduction
The paper focuses on the construction of Chinese restaurant in London, UK. It is
found that the Chinese restaurants which are generally present in Australia are very much
expensive and therefore the middle-class people face difficulty in affording food in the
existing Chinese restaurants. In order to resolve this issue, a new Chinese restaurant will be
constructed in London. The restaurant that will be constructed will be able to provide
different types of Chinese food in a proper ambience within a reasonable price.
Timeline of the project lifecycle
Figure 1: Gantt chart

3
CONSTRUCTION OF CHINESE RESTURANT
(Source: Created by Author)
Part 2:
State the selected activity
It is found that the framework for the restaurant is generally constructed by taking the
Chinese theme. It is found that in order to execute this activity of the project, it is very much
important to apply the processes of project management that generally includes initiation,
execution, monitoring as well and closing phase. It is found that in the planning phase, cost as
well as time needed for developing the framework is identified however in the project
initiation phase, proper meeting is arrangement with the stakeholders of the project. In the
project execution phase it is found that the framework for the restaurant is developed as per
the Chinese theme. Furthermore, in the monitoring phase, the executed activity is monitored.
Lastly in the closure phase, stakeholder sign off as well as project documentation are
generally done for closing the project.
1) Project scope (Planning, monitor/control)
1.1 Scope
The project scope generally include the following:
Construction of the Chinese restaurant
Development of restaurant with the help of Chinese theme
Development of entry as well as exit spaces
Installation of the electric circuit and more
CONSTRUCTION OF CHINESE RESTURANT
(Source: Created by Author)
Part 2:
State the selected activity
It is found that the framework for the restaurant is generally constructed by taking the
Chinese theme. It is found that in order to execute this activity of the project, it is very much
important to apply the processes of project management that generally includes initiation,
execution, monitoring as well and closing phase. It is found that in the planning phase, cost as
well as time needed for developing the framework is identified however in the project
initiation phase, proper meeting is arrangement with the stakeholders of the project. In the
project execution phase it is found that the framework for the restaurant is developed as per
the Chinese theme. Furthermore, in the monitoring phase, the executed activity is monitored.
Lastly in the closure phase, stakeholder sign off as well as project documentation are
generally done for closing the project.
1) Project scope (Planning, monitor/control)
1.1 Scope
The project scope generally include the following:
Construction of the Chinese restaurant
Development of restaurant with the help of Chinese theme
Development of entry as well as exit spaces
Installation of the electric circuit and more
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.

4
CONSTRUCTION OF CHINESE RESTURANT
1.2 Development of WBS for cooking food
Cooking food
Initiation phase
Determining the
item that is being
cooked
Determining the cook
for cooking the item
Planning phase
Identyfying the neede
requirements
Determining the
needed money
Execution phase
Making arrangement
for cooking
Keep disjes at
minimum
Focussing on
mastering food
prepration
Using the tools
required for cooking
Decoration
Closure phase
Cooking of the item
complete
Figure 2: WBS
(Source: Created by Author)
2) Project time (Planning)
2.1 Detailed timeline based on the WBS
The detailed timeline is provided in the table below. It is reflected that the project can
be finished successfully within 368days and the time that is required for executing each of the
activities of the project is generally showcased in the table that is given below.
WBS Task Name Duration Start Finish
0
Construction of Chinese restaurant in
Australia
368 days Mon 03-12-18 Wed 29-04-20
1 Project planning 47 days Mon 03-12-18 Tue 05-02-19
1.1 Analysis of the project requirements 6 days Mon 03-12-18 Mon 10-12-18
1.2 Analysis of the project nature 5 days Tue 11-12-18 Mon 17-12-18
CONSTRUCTION OF CHINESE RESTURANT
1.2 Development of WBS for cooking food
Cooking food
Initiation phase
Determining the
item that is being
cooked
Determining the cook
for cooking the item
Planning phase
Identyfying the neede
requirements
Determining the
needed money
Execution phase
Making arrangement
for cooking
Keep disjes at
minimum
Focussing on
mastering food
prepration
Using the tools
required for cooking
Decoration
Closure phase
Cooking of the item
complete
Figure 2: WBS
(Source: Created by Author)
2) Project time (Planning)
2.1 Detailed timeline based on the WBS
The detailed timeline is provided in the table below. It is reflected that the project can
be finished successfully within 368days and the time that is required for executing each of the
activities of the project is generally showcased in the table that is given below.
WBS Task Name Duration Start Finish
0
Construction of Chinese restaurant in
Australia
368 days Mon 03-12-18 Wed 29-04-20
1 Project planning 47 days Mon 03-12-18 Tue 05-02-19
1.1 Analysis of the project requirements 6 days Mon 03-12-18 Mon 10-12-18
1.2 Analysis of the project nature 5 days Tue 11-12-18 Mon 17-12-18

5
CONSTRUCTION OF CHINESE RESTURANT
1.3 Resources estimation 4 days Tue 18-12-18 Fri 21-12-18
1.4 Estimation of time 5 days Mon 24-12-18 Fri 28-12-18
1.5 Budget estimation 10 days Mon 31-12-18 Fri 11-01-19
1.6 Manpower estimation 8 days Mon 14-01-19 Wed 23-01-19
1.7 Resource analysis 9 days Thu 24-01-19 Tue 05-02-19
1.8
Milestone 1: Completion of
planning phase
0 days Tue 05-02-19 Tue 05-02-19
2 Initiation phase 105 days Wed 06-02-19 Tue 02-07-19
2.1 Land procurement 7 days Wed 06-02-19 Thu 14-02-19
2.2 Stakeholders appointment 8 days Fri 15-02-19 Tue 26-02-19
2.3 Meeting arrangement 6 days Wed 27-02-19 Wed 06-03-19
2.4 Financial plan arrangement 9 days Thu 07-03-19 Tue 19-03-19
2.5 Workers appointment 8 days Wed 20-03-19 Fri 29-03-19
2.6 Blueprint preparation 7 days Mon 01-04-19 Tue 09-04-19
2.7 Procurement of land area 5 days Wed 10-04-19 Tue 16-04-19
2.8 Release of legal notice 7 days Wed 17-04-19 Thu 25-04-19
2.9 Allocation of budget 9 days Fri 26-04-19 Wed 08-05-19
2.10 Procurement of resources 8 days Thu 09-05-19 Mon 20-05-19
2.11 Time allocation 7 days Tue 21-05-19 Wed 29-05-19
2.12 Duty allocation 8 days Thu 30-05-19 Mon 10-06-19
2.13 Analysis of risk 9 days Tue 11-06-19 Fri 21-06-19
2.14 Risk mitigation plan 7 days Mon 24-06-19 Tue 02-07-19
2.15 Completion of project initiation 0 days Tue 02-07-19 Tue 02-07-19
3 Execution phase 178 days Wed 03-07-19 Fri 06-03-20
CONSTRUCTION OF CHINESE RESTURANT
1.3 Resources estimation 4 days Tue 18-12-18 Fri 21-12-18
1.4 Estimation of time 5 days Mon 24-12-18 Fri 28-12-18
1.5 Budget estimation 10 days Mon 31-12-18 Fri 11-01-19
1.6 Manpower estimation 8 days Mon 14-01-19 Wed 23-01-19
1.7 Resource analysis 9 days Thu 24-01-19 Tue 05-02-19
1.8
Milestone 1: Completion of
planning phase
0 days Tue 05-02-19 Tue 05-02-19
2 Initiation phase 105 days Wed 06-02-19 Tue 02-07-19
2.1 Land procurement 7 days Wed 06-02-19 Thu 14-02-19
2.2 Stakeholders appointment 8 days Fri 15-02-19 Tue 26-02-19
2.3 Meeting arrangement 6 days Wed 27-02-19 Wed 06-03-19
2.4 Financial plan arrangement 9 days Thu 07-03-19 Tue 19-03-19
2.5 Workers appointment 8 days Wed 20-03-19 Fri 29-03-19
2.6 Blueprint preparation 7 days Mon 01-04-19 Tue 09-04-19
2.7 Procurement of land area 5 days Wed 10-04-19 Tue 16-04-19
2.8 Release of legal notice 7 days Wed 17-04-19 Thu 25-04-19
2.9 Allocation of budget 9 days Fri 26-04-19 Wed 08-05-19
2.10 Procurement of resources 8 days Thu 09-05-19 Mon 20-05-19
2.11 Time allocation 7 days Tue 21-05-19 Wed 29-05-19
2.12 Duty allocation 8 days Thu 30-05-19 Mon 10-06-19
2.13 Analysis of risk 9 days Tue 11-06-19 Fri 21-06-19
2.14 Risk mitigation plan 7 days Mon 24-06-19 Tue 02-07-19
2.15 Completion of project initiation 0 days Tue 02-07-19 Tue 02-07-19
3 Execution phase 178 days Wed 03-07-19 Fri 06-03-20

6
CONSTRUCTION OF CHINESE RESTURANT
3.1 Preparation of land 12 days Wed 03-07-19 Thu 18-07-19
3.2 Resource assortment 13 days Fri 19-07-19 Tue 06-08-19
3.3 Restaurant construction 9 days Wed 07-08-19 Mon 19-08-19
3.4
Framework construction by taking
Chinese’s theme
10 days Tue 20-08-19 Mon 02-09-19
3.5 Selection of entry and exit spaces 11 days Tue 03-09-19 Tue 17-09-19
3.6 Bricks application 14 days Wed 18-09-19 Mon 07-10-19
3.7 Plumbing 12 days Tue 08-10-19 Wed 23-10-19
3.8 Installation of electric circuit 13 days Thu 24-10-19 Mon 11-11-19
3.9 Application of concrete 15 days Tue 12-11-19 Mon 02-12-19
3.10 Colour application 11 days Tue 03-12-19 Tue 17-12-19
3.11 System implementation 10 days Wed 18-12-19 Tue 31-12-19
3.12 Tiles application 9 days Wed 01-01-20 Mon 13-01-20
3.13 Film processing implementation 15 days Tue 14-01-20 Mon 03-02-20
3.14 Dining room construction 13 days Tue 04-02-20 Thu 20-02-20
3.15 Central heating zones construction 11 days Fri 21-02-20 Fri 06-03-20
3.16 Project execution completion 0 days Fri 06-03-20 Fri 06-03-20
4 Development phase 35 days Mon 09-03-20 Fri 24-04-20
4.1 Restaurant board formation 8 days Mon 09-03-20 Wed 18-03-20
4.2 Preparation of statement vision 7 days Thu 19-03-20 Fri 27-03-20
4.3 Preparation of standard service 9 days Mon 30-03-20 Thu 09-04-20
4.4 Parking a lot implementation 6 days Fri 10-04-20 Fri 17-04-20
4.5 Finalization 5 days Mon 20-04-20 Fri 24-04-20
CONSTRUCTION OF CHINESE RESTURANT
3.1 Preparation of land 12 days Wed 03-07-19 Thu 18-07-19
3.2 Resource assortment 13 days Fri 19-07-19 Tue 06-08-19
3.3 Restaurant construction 9 days Wed 07-08-19 Mon 19-08-19
3.4
Framework construction by taking
Chinese’s theme
10 days Tue 20-08-19 Mon 02-09-19
3.5 Selection of entry and exit spaces 11 days Tue 03-09-19 Tue 17-09-19
3.6 Bricks application 14 days Wed 18-09-19 Mon 07-10-19
3.7 Plumbing 12 days Tue 08-10-19 Wed 23-10-19
3.8 Installation of electric circuit 13 days Thu 24-10-19 Mon 11-11-19
3.9 Application of concrete 15 days Tue 12-11-19 Mon 02-12-19
3.10 Colour application 11 days Tue 03-12-19 Tue 17-12-19
3.11 System implementation 10 days Wed 18-12-19 Tue 31-12-19
3.12 Tiles application 9 days Wed 01-01-20 Mon 13-01-20
3.13 Film processing implementation 15 days Tue 14-01-20 Mon 03-02-20
3.14 Dining room construction 13 days Tue 04-02-20 Thu 20-02-20
3.15 Central heating zones construction 11 days Fri 21-02-20 Fri 06-03-20
3.16 Project execution completion 0 days Fri 06-03-20 Fri 06-03-20
4 Development phase 35 days Mon 09-03-20 Fri 24-04-20
4.1 Restaurant board formation 8 days Mon 09-03-20 Wed 18-03-20
4.2 Preparation of statement vision 7 days Thu 19-03-20 Fri 27-03-20
4.3 Preparation of standard service 9 days Mon 30-03-20 Thu 09-04-20
4.4 Parking a lot implementation 6 days Fri 10-04-20 Fri 17-04-20
4.5 Finalization 5 days Mon 20-04-20 Fri 24-04-20
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

7
CONSTRUCTION OF CHINESE RESTURANT
4.6 Development phase completion 0 days Fri 24-04-20 Fri 24-04-20
5 Closure phase 3 days Mon 27-04-20 Wed 29-04-20
5.1 Sign off stakeholder 2 days Mon 27-04-20 Tue 28-04-20
5.2 Review of post project 1 day Wed 29-04-20 Wed 29-04-20
5.3 Completion of project closure phase 0 days Wed 29-04-20 Wed 29-04-20
CONSTRUCTION OF CHINESE RESTURANT
4.6 Development phase completion 0 days Fri 24-04-20 Fri 24-04-20
5 Closure phase 3 days Mon 27-04-20 Wed 29-04-20
5.1 Sign off stakeholder 2 days Mon 27-04-20 Tue 28-04-20
5.2 Review of post project 1 day Wed 29-04-20 Wed 29-04-20
5.3 Completion of project closure phase 0 days Wed 29-04-20 Wed 29-04-20

8
CONSTRUCTION OF CHINESE RESTURANT
2.2 Identification of critical path
Figure 3: Critical path
(Source: Created by Author)
CONSTRUCTION OF CHINESE RESTURANT
2.2 Identification of critical path
Figure 3: Critical path
(Source: Created by Author)

9
CONSTRUCTION OF CHINESE RESTURANT
3) Project cost (Planning, monitor/control
3.1 Estimation of the costs that is identified in the WBS
0
1
1.1
1.2
1.3
1.4
1.5
1.6
1.7
1.8
2
2.1
2.2
2.3
2.4
2.5
2.6
2.7
2.8
2.9
2.10
2.11
2.12
2.13
2.14
2.15
3
3.1
3.2
3.3
3.4
3.5
3.6
3.7
3.8
3.9
3.10
3.11
3.12
3.13
3.14
3.15
3.16
4
4.1
4.2
4.3
4.4
4.5
4.6
5
5.1
5.2
5.3
Construction of chinese
resturant in Australia
£258,568.00 6,080 hours
Project planning
£15,600.00 376 hours
Analysis of the project
requirements
£1,920.00 48 hours
Analysis of the project
nature
£1,400.00 40 hours
Resources estimation
£1,600.00 32 hours
Estimation of time
£1,600.00 40 hours
Budget estimatation
£4,000.00 80 hours
Manpower estimation
£2,560.00 64 hours
Resource analysis
£2,520.00 72 hours
Milestone 1:Completion of
planning phase
£0.00 0 hours
Initiation phase
£52,168.00 1,344 hours
Land procurement
£0.00 56 hours
Stakeholders
appointment
£2,560.00 64 hours
Meeting arrangement
£1,920.00 48 hours
Financial plan
arrangement
£3,600.00 72 hours
Workers appointment
£2,240.00 64 hours
Blueprint preparation
£3,360.00 56 hours
Procurement of land area
£2,400.00 40 hours
Release of legal notice
£6,160.00 112 hours
Allocation of budget
£3,600.00 144 hours
Procurement of
resources
£5,568.00 128 hours
Time allocation
£4,760.00 112 hours
Duty allocation
£6,400.00 192 hours
Analysis of risk
£5,400.00 144 hours
Risk mitigation plan
£4,200.00 112 hours
Completion of project
initiation
£0.00 0 hours
Execution phase
£163,728.00 3,704 hours
Preparation of land
£13,920.00 288 hours
Resource assortment
£8,840.00 208 hours
Resturant construction
£6,120.00 144 hours
Framework
constructution by taking
chineses theme
£8,800.00 160 hours
Selection of entry and
exit spaces
£8,536.00 176 hours
Bricks application
£16,464.00 336 hours
Plumbing
£10,272.00 288 hours
Installation of electric
circuit
£13,728.00 312 hours
Application of concrete
£19,440.00 480 hours
Colour application
£10,120.00 264 hours
System implementation
£6,160.00 160 hours
Tiles application
£11,520.00 216 hours
Film processing
implementation
£17,640.00 360 hours
Dining room construction
£12,168.00 312 hours
Central heating zones
construction
£0.00 0 hours
Project execution
completion
£0.00 0 hours
Development phase
£26,152.00 632 hours
Resturant board
formation
£4,928.00 128 hours
Preparation of statement
vision
£4,760.00 112 hours
Preparation of standard
service
£9,144.00 216 hours
Parking a lot
implementation
£4,320.00 96 hours
Finalization
£3,000.00 80 hours
Development phase
completion
£0.00 0 hours
Closure phase
£920.00 24 hours
Sign off stakeholder
£640.00 16 hours
Review of post project
£280.00 8 hours
Completion of project
closure phase
£0.00 0 hours
Figure 4: Project cost as per WBS
(Source: Created by Author)
CONSTRUCTION OF CHINESE RESTURANT
3) Project cost (Planning, monitor/control
3.1 Estimation of the costs that is identified in the WBS
0
1
1.1
1.2
1.3
1.4
1.5
1.6
1.7
1.8
2
2.1
2.2
2.3
2.4
2.5
2.6
2.7
2.8
2.9
2.10
2.11
2.12
2.13
2.14
2.15
3
3.1
3.2
3.3
3.4
3.5
3.6
3.7
3.8
3.9
3.10
3.11
3.12
3.13
3.14
3.15
3.16
4
4.1
4.2
4.3
4.4
4.5
4.6
5
5.1
5.2
5.3
Construction of chinese
resturant in Australia
£258,568.00 6,080 hours
Project planning
£15,600.00 376 hours
Analysis of the project
requirements
£1,920.00 48 hours
Analysis of the project
nature
£1,400.00 40 hours
Resources estimation
£1,600.00 32 hours
Estimation of time
£1,600.00 40 hours
Budget estimatation
£4,000.00 80 hours
Manpower estimation
£2,560.00 64 hours
Resource analysis
£2,520.00 72 hours
Milestone 1:Completion of
planning phase
£0.00 0 hours
Initiation phase
£52,168.00 1,344 hours
Land procurement
£0.00 56 hours
Stakeholders
appointment
£2,560.00 64 hours
Meeting arrangement
£1,920.00 48 hours
Financial plan
arrangement
£3,600.00 72 hours
Workers appointment
£2,240.00 64 hours
Blueprint preparation
£3,360.00 56 hours
Procurement of land area
£2,400.00 40 hours
Release of legal notice
£6,160.00 112 hours
Allocation of budget
£3,600.00 144 hours
Procurement of
resources
£5,568.00 128 hours
Time allocation
£4,760.00 112 hours
Duty allocation
£6,400.00 192 hours
Analysis of risk
£5,400.00 144 hours
Risk mitigation plan
£4,200.00 112 hours
Completion of project
initiation
£0.00 0 hours
Execution phase
£163,728.00 3,704 hours
Preparation of land
£13,920.00 288 hours
Resource assortment
£8,840.00 208 hours
Resturant construction
£6,120.00 144 hours
Framework
constructution by taking
chineses theme
£8,800.00 160 hours
Selection of entry and
exit spaces
£8,536.00 176 hours
Bricks application
£16,464.00 336 hours
Plumbing
£10,272.00 288 hours
Installation of electric
circuit
£13,728.00 312 hours
Application of concrete
£19,440.00 480 hours
Colour application
£10,120.00 264 hours
System implementation
£6,160.00 160 hours
Tiles application
£11,520.00 216 hours
Film processing
implementation
£17,640.00 360 hours
Dining room construction
£12,168.00 312 hours
Central heating zones
construction
£0.00 0 hours
Project execution
completion
£0.00 0 hours
Development phase
£26,152.00 632 hours
Resturant board
formation
£4,928.00 128 hours
Preparation of statement
vision
£4,760.00 112 hours
Preparation of standard
service
£9,144.00 216 hours
Parking a lot
implementation
£4,320.00 96 hours
Finalization
£3,000.00 80 hours
Development phase
completion
£0.00 0 hours
Closure phase
£920.00 24 hours
Sign off stakeholder
£640.00 16 hours
Review of post project
£280.00 8 hours
Completion of project
closure phase
£0.00 0 hours
Figure 4: Project cost as per WBS
(Source: Created by Author)
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.

10
CONSTRUCTION OF CHINESE RESTURANT
3.2 Setting budget based on the estimated costs
The budget that is generally assumed as per the estimation for the construction of the
Chinese restaurant is generally provided in the table below. The table reflects that the project
will be finished within the budget £258,568.00.
WBS Task Name Duration Resource Names Cost
0
Construction of Chinese
restaurant in Australia
368 days £258,568.00
1 Project planning 47 days £15,600.00
1.1
Analysis of the project
requirements
6 days Project manager £1,920.00
1.2
Analysis of the project
nature
5 days Project planner £1,400.00
1.3 Resources estimation 4 days Finance manager £1,600.00
1.4 Estimation of time 5 days Project manager £1,600.00
1.5 Budget estimation 10 days Finance manager £4,000.00
1.6 Manpower estimation 8 days Project manager £2,560.00
1.7 Resource analysis 9 days Project planner £2,520.00
1.8
Milestone 1: Completion of
planning phase
0 days Project manager £0.00
2 Initiation phase 105 days £52,168.00
2.1 Land procurement 7 days Sponsor £0.00
2.2 Stakeholders appointment 8 days Project manager £2,560.00
2.3 Meeting arrangement 6 days Project manager £1,920.00
2.4 Financial plan arrangement 9 days Finance manager £3,600.00
CONSTRUCTION OF CHINESE RESTURANT
3.2 Setting budget based on the estimated costs
The budget that is generally assumed as per the estimation for the construction of the
Chinese restaurant is generally provided in the table below. The table reflects that the project
will be finished within the budget £258,568.00.
WBS Task Name Duration Resource Names Cost
0
Construction of Chinese
restaurant in Australia
368 days £258,568.00
1 Project planning 47 days £15,600.00
1.1
Analysis of the project
requirements
6 days Project manager £1,920.00
1.2
Analysis of the project
nature
5 days Project planner £1,400.00
1.3 Resources estimation 4 days Finance manager £1,600.00
1.4 Estimation of time 5 days Project manager £1,600.00
1.5 Budget estimation 10 days Finance manager £4,000.00
1.6 Manpower estimation 8 days Project manager £2,560.00
1.7 Resource analysis 9 days Project planner £2,520.00
1.8
Milestone 1: Completion of
planning phase
0 days Project manager £0.00
2 Initiation phase 105 days £52,168.00
2.1 Land procurement 7 days Sponsor £0.00
2.2 Stakeholders appointment 8 days Project manager £2,560.00
2.3 Meeting arrangement 6 days Project manager £1,920.00
2.4 Financial plan arrangement 9 days Finance manager £3,600.00

11
CONSTRUCTION OF CHINESE RESTURANT
2.5 Workers appointment 8 days Project planner £2,240.00
2.6 Blueprint preparation 7 days Site supervisor £3,360.00
2.7 Procurement of land area 5 days Site supervisor £2,400.00
2.8 Release of legal notice 7 days
Contractor, Site
supervisor
£6,160.00
2.9 Allocation of budget 9 days
Finance manager,
Sponsor
£3,600.00
2.10 Procurement of resources 8 days
Contractor, System
planner
£5,568.00
2.11 Time allocation 7 days
Contractor, Project
planner
£4,760.00
2.12 Duty allocation 8 days
Contractor, Finance
manager, Sponsor
£6,400.00
2.13 Analysis of risk 9 days
Risk manager,
Project planner
£5,400.00
2.14 Risk mitigation plan 7 days
Risk manager,
Project planner
£4,200.00
2.15
Completion of project
initiation
0 days Project manager £0.00
3 Execution phase 178 days £163,728.00
3.1 Preparation of land 12 days
Site supervisor,
Contractor, Project
planner
£13,920.00
CONSTRUCTION OF CHINESE RESTURANT
2.5 Workers appointment 8 days Project planner £2,240.00
2.6 Blueprint preparation 7 days Site supervisor £3,360.00
2.7 Procurement of land area 5 days Site supervisor £2,400.00
2.8 Release of legal notice 7 days
Contractor, Site
supervisor
£6,160.00
2.9 Allocation of budget 9 days
Finance manager,
Sponsor
£3,600.00
2.10 Procurement of resources 8 days
Contractor, System
planner
£5,568.00
2.11 Time allocation 7 days
Contractor, Project
planner
£4,760.00
2.12 Duty allocation 8 days
Contractor, Finance
manager, Sponsor
£6,400.00
2.13 Analysis of risk 9 days
Risk manager,
Project planner
£5,400.00
2.14 Risk mitigation plan 7 days
Risk manager,
Project planner
£4,200.00
2.15
Completion of project
initiation
0 days Project manager £0.00
3 Execution phase 178 days £163,728.00
3.1 Preparation of land 12 days
Site supervisor,
Contractor, Project
planner
£13,920.00

12
CONSTRUCTION OF CHINESE RESTURANT
3.2 Resource assortment 13 days
Contractor, Project
planner
£8,840.00
3.3 Restaurant construction 9 days
Project planner,
Contractor
£6,120.00
3.4
Framework construction by
taking chinses theme
10 days
Site supervisor,
Contractor
£8,800.00
3.5
Selection of entry and exit
spaces
11 days
Site supervisor,
System planner
£8,536.00
3.6 Bricks application 14 days
Contractor, Site
supervisor, System
planner
£16,464.00
3.7 Plumbing 12 days
Plumber, Project
manager, System
planner
£10,272.00
3.8
Installation of electric
circuit
13 days
Site supervisor,
Project planner,
System planner
£13,728.00
3.9 Application of concrete 15 days
Contractor, Project
manager, Project
planner, System
planner
£19,440.00
3.10 Colour application 11 days
Risk manager,
Project manager,
Project planner
£10,120.00
3.11 System implementation 10 days Risk manager, £6,160.00
CONSTRUCTION OF CHINESE RESTURANT
3.2 Resource assortment 13 days
Contractor, Project
planner
£8,840.00
3.3 Restaurant construction 9 days
Project planner,
Contractor
£6,120.00
3.4
Framework construction by
taking chinses theme
10 days
Site supervisor,
Contractor
£8,800.00
3.5
Selection of entry and exit
spaces
11 days
Site supervisor,
System planner
£8,536.00
3.6 Bricks application 14 days
Contractor, Site
supervisor, System
planner
£16,464.00
3.7 Plumbing 12 days
Plumber, Project
manager, System
planner
£10,272.00
3.8
Installation of electric
circuit
13 days
Site supervisor,
Project planner,
System planner
£13,728.00
3.9 Application of concrete 15 days
Contractor, Project
manager, Project
planner, System
planner
£19,440.00
3.10 Colour application 11 days
Risk manager,
Project manager,
Project planner
£10,120.00
3.11 System implementation 10 days Risk manager, £6,160.00
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

13
CONSTRUCTION OF CHINESE RESTURANT
System planner
3.12 Tiles application 9 days
Contractor, Finance
manager, Site
supervisor
£11,520.00
3.13
Film processing
implementation
15 days
System planner,
Contractor, Site
supervisor
£17,640.00
3.14 Dining room construction 13 days
System planner,
Contractor, Plumber
£12,168.00
3.15
Central heating zones
construction
11 days £0.00
3.16
Project execution
completion
0 days Project manager £0.00
4 Development phase 35 days £26,152.00
4.1 Restaurant board formation 8 days
System planner,
Project manager
£4,928.00
4.2
Preparation of statement
vision
7 days
Contractor, Project
planner
£4,760.00
4.3
Preparation of standard
service
9 days
System planner,
Contractor, Project
manager
£9,144.00
4.4
Parking a lot
implementation
6 days
Finance manager,
Project manager
£4,320.00
4.5 Finalization 5 days Project manager, £3,000.00
CONSTRUCTION OF CHINESE RESTURANT
System planner
3.12 Tiles application 9 days
Contractor, Finance
manager, Site
supervisor
£11,520.00
3.13
Film processing
implementation
15 days
System planner,
Contractor, Site
supervisor
£17,640.00
3.14 Dining room construction 13 days
System planner,
Contractor, Plumber
£12,168.00
3.15
Central heating zones
construction
11 days £0.00
3.16
Project execution
completion
0 days Project manager £0.00
4 Development phase 35 days £26,152.00
4.1 Restaurant board formation 8 days
System planner,
Project manager
£4,928.00
4.2
Preparation of statement
vision
7 days
Contractor, Project
planner
£4,760.00
4.3
Preparation of standard
service
9 days
System planner,
Contractor, Project
manager
£9,144.00
4.4
Parking a lot
implementation
6 days
Finance manager,
Project manager
£4,320.00
4.5 Finalization 5 days Project manager, £3,000.00

14
CONSTRUCTION OF CHINESE RESTURANT
Project planner
4.6
Development phase
completion
0 days Project manager £0.00
5 Closure phase 3 days £920.00
5.1 Sign off stakeholder 2 days Project manager £640.00
5.2 Review of post project 1 day Project planner £280.00
5.3
Completion of project
closure phase
0 days Project manager £0.00
4) Project quality management (planning, execution, monitoring/control)
4.1 Identification of the quality requirements
The quality requirements of the project are generally illustrated below:
Proper quality of food: It is quite necessary for the restaurant to focus on the quality
of food that is served in the restaurant by following the proper quality standards.
Proper service at reasonable price: It is very much necessary for the restaurants to
serve proper food within excellent ambience in a very much reasonable price
Excellent service in less time: It is found that the Chinese restaurant that was
generally developed must be able to serve the food to the customers in a very much less time
by maintain proper quality standards of the food.
4.2 Identification of tool that will be used for measuring the quality
It is found that cause and effect analysis is mainly utilized as a tool for measuring the
project quality. It is found that with the help of this tool proper problem is identified with
proper possible data requirements. In addition to this, it is found that proper development of
objectives is mainly needed for managing the quality of the project. The cause and impact
CONSTRUCTION OF CHINESE RESTURANT
Project planner
4.6
Development phase
completion
0 days Project manager £0.00
5 Closure phase 3 days £920.00
5.1 Sign off stakeholder 2 days Project manager £640.00
5.2 Review of post project 1 day Project planner £280.00
5.3
Completion of project
closure phase
0 days Project manager £0.00
4) Project quality management (planning, execution, monitoring/control)
4.1 Identification of the quality requirements
The quality requirements of the project are generally illustrated below:
Proper quality of food: It is quite necessary for the restaurant to focus on the quality
of food that is served in the restaurant by following the proper quality standards.
Proper service at reasonable price: It is very much necessary for the restaurants to
serve proper food within excellent ambience in a very much reasonable price
Excellent service in less time: It is found that the Chinese restaurant that was
generally developed must be able to serve the food to the customers in a very much less time
by maintain proper quality standards of the food.
4.2 Identification of tool that will be used for measuring the quality
It is found that cause and effect analysis is mainly utilized as a tool for measuring the
project quality. It is found that with the help of this tool proper problem is identified with
proper possible data requirements. In addition to this, it is found that proper development of
objectives is mainly needed for managing the quality of the project. The cause and impact

15
CONSTRUCTION OF CHINESE RESTURANT
analysis generally help in combining both the brainstorming with the type of mind map that
further assists in considering all possible causes of problems which helps in measuring the
quality.
5) Communication (Planning, executing, monitoring/control)
5.1 Indication of who requires to kept informed about the project progress
The persons who are generally needed to be kept informed about the progress of the
project are generally listed below:
Project manager: The project manager must be kept informed about the progress of
the project so that they can take proper actions in keeping the project on track.
Financial manager: It is quite important for financial manger to know about the
budget that is generally spent on the project progress.
Team leader: The team leaders must know about the progress of the team members
so that they can be able to take proper action that is associated with the project.
5.2 Type of information generally needed
Type of information that are generally required are mainly elaborated below:
Project progress: It is very much important to discuss about the progress of the
project for tracking the project quite effectively.
Financial reports: It is quite necessary to discuss on the financial reports for
knowing the budget that is generally spent on the project for finishing the project
successfully.
Objectives of the project: It is very much necessary to discuss the objective of the
project within kick off meeting so that the project stakeholders can be able to know about the
project and its gaols.
CONSTRUCTION OF CHINESE RESTURANT
analysis generally help in combining both the brainstorming with the type of mind map that
further assists in considering all possible causes of problems which helps in measuring the
quality.
5) Communication (Planning, executing, monitoring/control)
5.1 Indication of who requires to kept informed about the project progress
The persons who are generally needed to be kept informed about the progress of the
project are generally listed below:
Project manager: The project manager must be kept informed about the progress of
the project so that they can take proper actions in keeping the project on track.
Financial manager: It is quite important for financial manger to know about the
budget that is generally spent on the project progress.
Team leader: The team leaders must know about the progress of the team members
so that they can be able to take proper action that is associated with the project.
5.2 Type of information generally needed
Type of information that are generally required are mainly elaborated below:
Project progress: It is very much important to discuss about the progress of the
project for tracking the project quite effectively.
Financial reports: It is quite necessary to discuss on the financial reports for
knowing the budget that is generally spent on the project for finishing the project
successfully.
Objectives of the project: It is very much necessary to discuss the objective of the
project within kick off meeting so that the project stakeholders can be able to know about the
project and its gaols.
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.

16
CONSTRUCTION OF CHINESE RESTURANT
Project status: Information about the status of the project is generally is discussed in
order to know about the present status of the project.
6) Stakeholders (planning, executing, monitoring/control)
6.1 Identification of the stakeholders
The stakeholders who are mainly associated with the project are listed below:
Project manager
Sponsor
Finance manager
Site supervisor
Contractor
Plumber
System planner
Risk manager
Project planner
6.2 Planning and managing stakeholders
The steps that are generally undertaken in order to plan as well as manage the
stakeholders of the project are generally elaborated below:
Development of the organizational breakdown structure
Categorizing stakeholders
Understanding impact as well as power of the project stakeholders
Completing power interest grid
Completing communication plan as well a stakeholder management
CONSTRUCTION OF CHINESE RESTURANT
Project status: Information about the status of the project is generally is discussed in
order to know about the present status of the project.
6) Stakeholders (planning, executing, monitoring/control)
6.1 Identification of the stakeholders
The stakeholders who are mainly associated with the project are listed below:
Project manager
Sponsor
Finance manager
Site supervisor
Contractor
Plumber
System planner
Risk manager
Project planner
6.2 Planning and managing stakeholders
The steps that are generally undertaken in order to plan as well as manage the
stakeholders of the project are generally elaborated below:
Development of the organizational breakdown structure
Categorizing stakeholders
Understanding impact as well as power of the project stakeholders
Completing power interest grid
Completing communication plan as well a stakeholder management

17
CONSTRUCTION OF CHINESE RESTURANT
Bibliography
Badewi, A. (2016). The impact of project management (PM) and benefits management (BM)
practices on project success: Towards developing a project benefits governance
framework. International Journal of Project Management, 34(4), 761-778.
Conforto, E. C., Salum, F., Amaral, D. C., da Silva, S. L., & de Almeida, L. F. M. (2014).
Can agile project management be adopted by industries other than software
development?. Project Management Journal, 45(3), 21-34.
Heldman, K. (2018). PMP: project management professional exam study guide. John Wiley
& Sons.
Hornstein, H. A. (2015). The integration of project management and organizational change
management is now a necessity. International Journal of Project Management, 33(2),
291-298.
Joslin, R., & Müller, R. (2015). Relationships between a project management methodology
and project success in different project governance contexts. International Journal of
Project Management, 33(6), 1377-1392.
Kaiser, M. G., El Arbi, F., & Ahlemann, F. (2015). Successful project portfolio management
beyond project selection techniques: Understanding the role of structural
alignment. International Journal of Project Management, 33(1), 126-139.
Kerzner, H. (2017). Project management metrics, KPIs, and dashboards: a guide to
measuring and monitoring project performance. John Wiley & Sons.
Marcelino-Sádaba, S., Pérez-Ezcurdia, A., Lazcano, A. M. E., & Villanueva, P. (2014).
Project risk management methodology for small firms. International journal of
project management, 32(2), 327-340.
CONSTRUCTION OF CHINESE RESTURANT
Bibliography
Badewi, A. (2016). The impact of project management (PM) and benefits management (BM)
practices on project success: Towards developing a project benefits governance
framework. International Journal of Project Management, 34(4), 761-778.
Conforto, E. C., Salum, F., Amaral, D. C., da Silva, S. L., & de Almeida, L. F. M. (2014).
Can agile project management be adopted by industries other than software
development?. Project Management Journal, 45(3), 21-34.
Heldman, K. (2018). PMP: project management professional exam study guide. John Wiley
& Sons.
Hornstein, H. A. (2015). The integration of project management and organizational change
management is now a necessity. International Journal of Project Management, 33(2),
291-298.
Joslin, R., & Müller, R. (2015). Relationships between a project management methodology
and project success in different project governance contexts. International Journal of
Project Management, 33(6), 1377-1392.
Kaiser, M. G., El Arbi, F., & Ahlemann, F. (2015). Successful project portfolio management
beyond project selection techniques: Understanding the role of structural
alignment. International Journal of Project Management, 33(1), 126-139.
Kerzner, H. (2017). Project management metrics, KPIs, and dashboards: a guide to
measuring and monitoring project performance. John Wiley & Sons.
Marcelino-Sádaba, S., Pérez-Ezcurdia, A., Lazcano, A. M. E., & Villanueva, P. (2014).
Project risk management methodology for small firms. International journal of
project management, 32(2), 327-340.

18
CONSTRUCTION OF CHINESE RESTURANT
Sánchez, M. A. (2015). Integrating sustainability issues into project management. Journal of
Cleaner Production, 96, 319-330.
Serra, C. E. M., & Kunc, M. (2015). Benefits realisation management and its influence on
project success and on the execution of business strategies. International Journal of
Project Management, 33(1), 53-66.
Svejvig, P., & Andersen, P. (2015). Rethinking project management: A structured literature
review with a critical look at the brave new world. International Journal of Project
Management, 33(2), 278-290.
Todorović, M. L., Petrović, D. Č., Mihić, M. M., Obradović, V. L., & Bushuyev, S. D.
(2015). Project success analysis framework: A knowledge-based approach in project
management. International Journal of Project Management, 33(4), 772-783.
Too, E. G., & Weaver, P. (2014). The management of project management: A conceptual
framework for project governance. International Journal of Project
Management, 32(8), 1382-1394.
CONSTRUCTION OF CHINESE RESTURANT
Sánchez, M. A. (2015). Integrating sustainability issues into project management. Journal of
Cleaner Production, 96, 319-330.
Serra, C. E. M., & Kunc, M. (2015). Benefits realisation management and its influence on
project success and on the execution of business strategies. International Journal of
Project Management, 33(1), 53-66.
Svejvig, P., & Andersen, P. (2015). Rethinking project management: A structured literature
review with a critical look at the brave new world. International Journal of Project
Management, 33(2), 278-290.
Todorović, M. L., Petrović, D. Č., Mihić, M. M., Obradović, V. L., & Bushuyev, S. D.
(2015). Project success analysis framework: A knowledge-based approach in project
management. International Journal of Project Management, 33(4), 772-783.
Too, E. G., & Weaver, P. (2014). The management of project management: A conceptual
framework for project governance. International Journal of Project
Management, 32(8), 1382-1394.
1 out of 19
Related Documents

Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
© 2024 | Zucol Services PVT LTD | All rights reserved.