This project report focuses on designing an event for the East Kent Cider Festival, detailing the refurbishment of Ye Olde Barn theatre. The report includes a project charter outlining purpose, scope, objectives, assumptions, constraints, and quality measurement criteria. It presents a work breakdown structure, network analysis diagrams, Gantt chart, and a comprehensive risk management plan identifying potential risks such as contract disputes, cost increases, material shortages, labor expertise, natural disasters, and poor project management. Each risk is assessed with likelihood, consequence, rating, and proposed treatment actions, along with required resources. The report utilizes various project management methodologies to ensure successful event design and execution, including financial aspects, project scheduling, and risk mitigation strategies to achieve the desired outcomes.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.

Running head: DESIGNING AN EVENT FOR THE EAST KENT CIDER FESTIVAL
Designing an Event for the East Kent Cider Festival
Name of the Student
Name of the University
Author note
Designing an Event for the East Kent Cider Festival
Name of the Student
Name of the University
Author note
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.

2DESIGNING AN EVENT FOR THE EAST KENT CIDER FESTIVAL
Table of Contents
1. Project Charter.............................................................................................................................3
1.1 Purpose..................................................................................................................................3
1.2 Scope......................................................................................................................................3
1.3 Objectives..............................................................................................................................4
1.4 Assumptions..........................................................................................................................4
1.5 Constraints.............................................................................................................................5
1.6 Quality Measurement Criteria...............................................................................................6
2. The Work Breakdown Structure..................................................................................................7
3. The Network Analysis Diagrams/Critical Path Analysis............................................................8
4. The Gantt chart............................................................................................................................9
5. Risk Management Plan..............................................................................................................10
Bibliography..................................................................................................................................13
Table of Contents
1. Project Charter.............................................................................................................................3
1.1 Purpose..................................................................................................................................3
1.2 Scope......................................................................................................................................3
1.3 Objectives..............................................................................................................................4
1.4 Assumptions..........................................................................................................................4
1.5 Constraints.............................................................................................................................5
1.6 Quality Measurement Criteria...............................................................................................6
2. The Work Breakdown Structure..................................................................................................7
3. The Network Analysis Diagrams/Critical Path Analysis............................................................8
4. The Gantt chart............................................................................................................................9
5. Risk Management Plan..............................................................................................................10
Bibliography..................................................................................................................................13

3DESIGNING AN EVENT FOR THE EAST KENT CIDER FESTIVAL
1. Project Charter
1.1 Purpose
Construction projects are in high demand in the recent times and thus the construction
companies are highly demanded to create substantial form of research for the creation of
beautiful projects. The primary purpose of the report is to put major form of focus over research
in the various areas of project management in relation to designing of a ceremony for the
flagship event for the East Kent Cider Festival event. The event based on designing of the event
stage and other arrangements would likely to take place before the main event that is held on an
annual basis. The primary purpose of performing the project is to mark the occasion before the
start of the project based on refurbishment. The East Kent Cider Festival would mark the end of
the old theatre and would attract guests from all over to participate during the event.
1.2 Scope
During the design of the project report, each of the necessary aspects in relation to the
project such as the financial aspects, project scheduling, assumptions and constraints would be
discussed. In the following parts of the report, the different tasks would need to be planned and
discussed in such a manner that it would thus be able to achieve the expected outcomes from the
project.
The financial analysis that would be described for the project would be helpful in listing
out the costs that would be set for performing each of the activities performed. Creating a list of
each of the activities would help in understanding the exact cash in-flow and out-flow of money
spent for the project.
1. Project Charter
1.1 Purpose
Construction projects are in high demand in the recent times and thus the construction
companies are highly demanded to create substantial form of research for the creation of
beautiful projects. The primary purpose of the report is to put major form of focus over research
in the various areas of project management in relation to designing of a ceremony for the
flagship event for the East Kent Cider Festival event. The event based on designing of the event
stage and other arrangements would likely to take place before the main event that is held on an
annual basis. The primary purpose of performing the project is to mark the occasion before the
start of the project based on refurbishment. The East Kent Cider Festival would mark the end of
the old theatre and would attract guests from all over to participate during the event.
1.2 Scope
During the design of the project report, each of the necessary aspects in relation to the
project such as the financial aspects, project scheduling, assumptions and constraints would be
discussed. In the following parts of the report, the different tasks would need to be planned and
discussed in such a manner that it would thus be able to achieve the expected outcomes from the
project.
The financial analysis that would be described for the project would be helpful in listing
out the costs that would be set for performing each of the activities performed. Creating a list of
each of the activities would help in understanding the exact cash in-flow and out-flow of money
spent for the project.

4DESIGNING AN EVENT FOR THE EAST KENT CIDER FESTIVAL
This report would also discuss the different kind of assumptions in relation to the project.
These assumptions would be helpful in understanding whether the project would be performed in
a proper manner based on considering each of the necessary inclusions made. By describing the
assumptions made for the project, it would be helpful for understanding whether each of the
tasks mentioned within the project would be met successfully. On the other hand, the constraints
that would be described for the project would be describing the boundaries that might be set for
the concerned project.
1.3 Objectives
The objectives of the construction project based on refurbishing the Ye Olde Barn theatre
are described as:
To meet with the set directions and instructions provided by the local council at Ye Olde
Barn
To design a proper architecture based on bringing some form of innovation during the
festival event
Completion of the project within the proper time period and appropriate budget
To identify and mitigate each of the approachable risks towards the projects with proper
efficiency
1.4 Assumptions
The project is based on understanding each of the aspects in relation to the design and
arranging for the East Kent Cider Festival. The assumptions that could be set for the
refurbishment project are listed below:
1. The entire planning for the project would be approved by the local council.
This report would also discuss the different kind of assumptions in relation to the project.
These assumptions would be helpful in understanding whether the project would be performed in
a proper manner based on considering each of the necessary inclusions made. By describing the
assumptions made for the project, it would be helpful for understanding whether each of the
tasks mentioned within the project would be met successfully. On the other hand, the constraints
that would be described for the project would be describing the boundaries that might be set for
the concerned project.
1.3 Objectives
The objectives of the construction project based on refurbishing the Ye Olde Barn theatre
are described as:
To meet with the set directions and instructions provided by the local council at Ye Olde
Barn
To design a proper architecture based on bringing some form of innovation during the
festival event
Completion of the project within the proper time period and appropriate budget
To identify and mitigate each of the approachable risks towards the projects with proper
efficiency
1.4 Assumptions
The project is based on understanding each of the aspects in relation to the design and
arranging for the East Kent Cider Festival. The assumptions that could be set for the
refurbishment project are listed below:
1. The entire planning for the project would be approved by the local council.
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.

5DESIGNING AN EVENT FOR THE EAST KENT CIDER FESTIVAL
2. The event would become a huge success based on the proper amount of planning and
engagement during the event.
3. Each of the budget that would be estimated for the project would be proper. The
sponsors within the local council would be able to provide sufficient budget to complete the
project.
4. The event design project would comply with the laws based on project management
and event planning and management. The laws set by the Government during any work of
construction would be heavily followed during performing the work of event design.
1.5 Constraints
The project managed by the CCC Developments Ltd. could have some form of
constraints. These kind of constraints could be further be managed by CCC Developments Ltd in
order to develop a proper form of project as described by the council. The different constraints
that could affect the project are:
1. The budget estimated for the project can be discussed as a major constraint. Any extra
changes if required during the execution stage of the project would need a sponsorship.
2. The time taken in order to complete the project is limited as directed by the council.
Hence, the project team involved with the project should have a proper understanding of each
stage of the project.
3. The health factor of the labours working for the refurbishment project can also be
defined as a certain constraint. These labours would only be directed to work in a certain region.
2. The event would become a huge success based on the proper amount of planning and
engagement during the event.
3. Each of the budget that would be estimated for the project would be proper. The
sponsors within the local council would be able to provide sufficient budget to complete the
project.
4. The event design project would comply with the laws based on project management
and event planning and management. The laws set by the Government during any work of
construction would be heavily followed during performing the work of event design.
1.5 Constraints
The project managed by the CCC Developments Ltd. could have some form of
constraints. These kind of constraints could be further be managed by CCC Developments Ltd in
order to develop a proper form of project as described by the council. The different constraints
that could affect the project are:
1. The budget estimated for the project can be discussed as a major constraint. Any extra
changes if required during the execution stage of the project would need a sponsorship.
2. The time taken in order to complete the project is limited as directed by the council.
Hence, the project team involved with the project should have a proper understanding of each
stage of the project.
3. The health factor of the labours working for the refurbishment project can also be
defined as a certain constraint. These labours would only be directed to work in a certain region.

6DESIGNING AN EVENT FOR THE EAST KENT CIDER FESTIVAL
4. The layout of the event has been properly set by the management team and thus the
work of stage design would be limited according to a certain set of practices.
5. The CCC Developments Ltd and the concerned employees and labours would be
bounded according to the laws set by the Government. These laws are in relation to safety
requirements, employment law, building and planning regulations.
1.6 Quality Measurement Criteria
The project based on the development of an event would be completely judged by the
council. Quality is a major factor that should not be compromised. Hence, the local council
would look into each necessary details and thus approve over the same. Moreover, in order to
increase the efficiency of performance, the council would implement the ISO 9000 series of
quality management. This would help in understanding the ways in which CCC Developments
Ltd could be evaluated and thus the performance would be managed.
4. The layout of the event has been properly set by the management team and thus the
work of stage design would be limited according to a certain set of practices.
5. The CCC Developments Ltd and the concerned employees and labours would be
bounded according to the laws set by the Government. These laws are in relation to safety
requirements, employment law, building and planning regulations.
1.6 Quality Measurement Criteria
The project based on the development of an event would be completely judged by the
council. Quality is a major factor that should not be compromised. Hence, the local council
would look into each necessary details and thus approve over the same. Moreover, in order to
increase the efficiency of performance, the council would implement the ISO 9000 series of
quality management. This would help in understanding the ways in which CCC Developments
Ltd could be evaluated and thus the performance would be managed.

7DESIGNING AN EVENT FOR THE EAST KENT CIDER FESTIVAL
2. The Work Breakdown Structure
(Figure 1: The WBS for the Project)
(Source: Created by author)
2. The Work Breakdown Structure
(Figure 1: The WBS for the Project)
(Source: Created by author)
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

8DESIGNING AN EVENT FOR THE EAST KENT CIDER FESTIVAL
3. The Network Analysis Diagrams/Critical Path Analysis
(Figure 2: The Network Analysis Diagram)
(Source: Created by author)
3. The Network Analysis Diagrams/Critical Path Analysis
(Figure 2: The Network Analysis Diagram)
(Source: Created by author)

9DESIGNING AN EVENT FOR THE EAST KENT CIDER FESTIVAL
4. The Gantt chart
ID Outline
Number
Task
Mode
Task Name Duration Start Finish
0 0 East Kent Cider Festival:
100-year celebration
209 days Wed 05-12-18 Tue 27-08-19
1 1 Start of Project 0 days Wed 05-12-18 Wed 05-12-18
2 2 Setting a Meeting and
Project Activities
100 days Wed 05-12-18 Wed 10-04-19
3 2.1 Setting out project
brief
1 day Wed 05-12-18 Wed 05-12-18
4 2.2 Site Visit of Ye Old
Barn
1 day Thu 06-12-18 Thu 06-12-18
5 2.3 Identification of key
tasks and
constructing a base
plan
5 days Fri 07-12-18 Thu 13-12-18
6 2.4 Waiting for reply 5 days Thu 13-12-18 Wed 19-12-18
7 2.5 Contacting
thearetical agents,
contractors and
artistes
5 days Thu 20-12-18 Wed 26-12-18
8 2.6 Waiting for reply 20 days Wed 26-12-18 Mon 21-01-19
9 2.7 Selection of artists 4 days Mon 21-01-19 Fri 25-01-19
10 2.8 Making of artist
bookings
25 days Fri 25-01-19 Tue 26-02-19
11 2.9 Identification of
lighting, scenery and
other requirements
5 days Wed 27-02-19 Tue 05-03-19
12 2.10 Identification of
requirements for
staffi ng and
resources
5 days Tue 05-03-19 Mon 11-03-19
13 2.11 Selection of
contractors
5 days Tue 05-03-19 Mon 11-03-19
14 2.12 Identification of
markleting media
activities and costs
10 days Tue 12-03-19 Sat 23-03-19
15 2.13 Preparing final
project presentation
5 days Mon 25-03-19 Fri 29-03-19
16 2.14 Waiting for client
reply
5 days Sat 30-03-19 Fri 05-04-19
17 2.15 Meeting with client
for finalising over
specification and
contract signature
4 days Fri 05-04-19 Wed 10-04-19
18 3 Post-Contract Award
Stage
87 days Thu 11-04-19 Tue 30-07-19
19 3.1 Gaining final
confirmation from
artistes
25 days Thu 11-04-19 Mon 13-05-19
20 3.2 Gaining confirmation
of booking with
contractors
2 days Mon 13-05-19 Wed 15-05-19
21 3.3 Additional site visit 1 day Wed 15-05-19 Thu 16-05-19
22 3.4 Arranging of PR 10 days Thu 16-05-19 Wed 29-05-19
23 3.5 Marketing of activities18 days Wed 29-05-19 Thu 20-06-19
24 3.6 Review over staffi ng
requirements
28 days Fri 21-06-19 Fri 26-07-19
25 3.7 Design stages and
gain final
conformation
3 days Fri 26-07-19 Tue 30-07-19
26 4 The Final Event 0 days Sat 24-08-19 Sat 24-08-19
27 5 Payment to Artistes 2 days Mon 26-08-19 Tue 27-08-19
28 6 End Project 0 days Tue 27-08-19 Tue 27-08-19
05-12
24-08
27-08
02-12 16-12 30-12 13-01 27-01 10-02 24-02 10-03 24-03 07-04 21-04 05-05 19-05 02-06 16-06 30-06 14-07 28-07 11-08 25-08 08-09
01 December 01 January 01 February 01 March 01 April 01 May 01 June 01 July 01 August 01 September
(Figure 3: The Gantt chart for the Project)
(Source: Created by author)
4. The Gantt chart
ID Outline
Number
Task
Mode
Task Name Duration Start Finish
0 0 East Kent Cider Festival:
100-year celebration
209 days Wed 05-12-18 Tue 27-08-19
1 1 Start of Project 0 days Wed 05-12-18 Wed 05-12-18
2 2 Setting a Meeting and
Project Activities
100 days Wed 05-12-18 Wed 10-04-19
3 2.1 Setting out project
brief
1 day Wed 05-12-18 Wed 05-12-18
4 2.2 Site Visit of Ye Old
Barn
1 day Thu 06-12-18 Thu 06-12-18
5 2.3 Identification of key
tasks and
constructing a base
plan
5 days Fri 07-12-18 Thu 13-12-18
6 2.4 Waiting for reply 5 days Thu 13-12-18 Wed 19-12-18
7 2.5 Contacting
thearetical agents,
contractors and
artistes
5 days Thu 20-12-18 Wed 26-12-18
8 2.6 Waiting for reply 20 days Wed 26-12-18 Mon 21-01-19
9 2.7 Selection of artists 4 days Mon 21-01-19 Fri 25-01-19
10 2.8 Making of artist
bookings
25 days Fri 25-01-19 Tue 26-02-19
11 2.9 Identification of
lighting, scenery and
other requirements
5 days Wed 27-02-19 Tue 05-03-19
12 2.10 Identification of
requirements for
staffi ng and
resources
5 days Tue 05-03-19 Mon 11-03-19
13 2.11 Selection of
contractors
5 days Tue 05-03-19 Mon 11-03-19
14 2.12 Identification of
markleting media
activities and costs
10 days Tue 12-03-19 Sat 23-03-19
15 2.13 Preparing final
project presentation
5 days Mon 25-03-19 Fri 29-03-19
16 2.14 Waiting for client
reply
5 days Sat 30-03-19 Fri 05-04-19
17 2.15 Meeting with client
for finalising over
specification and
contract signature
4 days Fri 05-04-19 Wed 10-04-19
18 3 Post-Contract Award
Stage
87 days Thu 11-04-19 Tue 30-07-19
19 3.1 Gaining final
confirmation from
artistes
25 days Thu 11-04-19 Mon 13-05-19
20 3.2 Gaining confirmation
of booking with
contractors
2 days Mon 13-05-19 Wed 15-05-19
21 3.3 Additional site visit 1 day Wed 15-05-19 Thu 16-05-19
22 3.4 Arranging of PR 10 days Thu 16-05-19 Wed 29-05-19
23 3.5 Marketing of activities18 days Wed 29-05-19 Thu 20-06-19
24 3.6 Review over staffi ng
requirements
28 days Fri 21-06-19 Fri 26-07-19
25 3.7 Design stages and
gain final
conformation
3 days Fri 26-07-19 Tue 30-07-19
26 4 The Final Event 0 days Sat 24-08-19 Sat 24-08-19
27 5 Payment to Artistes 2 days Mon 26-08-19 Tue 27-08-19
28 6 End Project 0 days Tue 27-08-19 Tue 27-08-19
05-12
24-08
27-08
02-12 16-12 30-12 13-01 27-01 10-02 24-02 10-03 24-03 07-04 21-04 05-05 19-05 02-06 16-06 30-06 14-07 28-07 11-08 25-08 08-09
01 December 01 January 01 February 01 March 01 April 01 May 01 June 01 July 01 August 01 September
(Figure 3: The Gantt chart for the Project)
(Source: Created by author)

10DESIGNING AN EVENT FOR THE EAST KENT CIDER FESTIVAL
5. Risk Management Plan
No
.
Description of Risk Risk Outcome Likelihood Consequenc
e
Rating Proposed Risk
Treatment Actions to-
be taken
Resources
required
1 Dispute in certain
contracts. The contracts
in relation to employee
safety might not be
properly managed by
the local council. The
Workers Compensation
Act might not be
properly imposed by the
local council.
Employees
experiencing injuries
might not be covered
under any contract.
This might result in
lack of proper form of
treatment for the
employees who would
be hurt during any
work.
Medium High High The council who is
proposing the project
should have a proper
legal contract that would
be approved by the
Government. The
contracts should also
bend under the provision
of the Workers’
Compensation Act.
The Council
Members,
Project
manager
2 The unexpected form of
increases within the cost
factor for the
refurbishment project
could lead to severe
risks. Different
additional requirements
that might creep within
the project could lead to
rise in the cost factor
than the previously
estimated costs.
Any form of increase in
the cost factor could
lead to problems in
estimation of the cost
incurred for the project
at the time of project
completion. Moreover,
unexpected changes in
cost factor could lead to
shortage of funds
during the later stages
of the project.
High High High In order to mitigate or
prevent such kind of
factor of cost increase
during the project work,
the project sponsor
should allocate some
extra funds during project
cost estimation stage.
This additional cost
should be estimated and
kept properly in order to
use them at any later
stages if needed.
Project
Sponsor,
Project
Manager
3 There might be some Low availability of Low Medium Medium The materials required Project
5. Risk Management Plan
No
.
Description of Risk Risk Outcome Likelihood Consequenc
e
Rating Proposed Risk
Treatment Actions to-
be taken
Resources
required
1 Dispute in certain
contracts. The contracts
in relation to employee
safety might not be
properly managed by
the local council. The
Workers Compensation
Act might not be
properly imposed by the
local council.
Employees
experiencing injuries
might not be covered
under any contract.
This might result in
lack of proper form of
treatment for the
employees who would
be hurt during any
work.
Medium High High The council who is
proposing the project
should have a proper
legal contract that would
be approved by the
Government. The
contracts should also
bend under the provision
of the Workers’
Compensation Act.
The Council
Members,
Project
manager
2 The unexpected form of
increases within the cost
factor for the
refurbishment project
could lead to severe
risks. Different
additional requirements
that might creep within
the project could lead to
rise in the cost factor
than the previously
estimated costs.
Any form of increase in
the cost factor could
lead to problems in
estimation of the cost
incurred for the project
at the time of project
completion. Moreover,
unexpected changes in
cost factor could lead to
shortage of funds
during the later stages
of the project.
High High High In order to mitigate or
prevent such kind of
factor of cost increase
during the project work,
the project sponsor
should allocate some
extra funds during project
cost estimation stage.
This additional cost
should be estimated and
kept properly in order to
use them at any later
stages if needed.
Project
Sponsor,
Project
Manager
3 There might be some Low availability of Low Medium Medium The materials required Project
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.

11DESIGNING AN EVENT FOR THE EAST KENT CIDER FESTIVAL
shortage of construction
materials during the
time of constructing the
project. The supplier
might face problems
with supplying the
materials during
approximate time of
project execution stage.
construction materials
could lead to some
negative impacts. The
time taken to complete
the entire project could
get delayed to a certain
extent. This would thus
result in extension of
the time for the entire
project completion.
for the project execution
should be procured one
week prior to the
execution of any
particular stage of the
project. This would result
in easy determination of
any other supplier if
necessary. This would
not hamper the quality of
work and also help in
smooth execution.
manager,
Suppliers
4 Low expertise with new
requirements for
labours. The labours
hired for the
refurbishment project
might not be experts
with the changing
requirements.
Due to low level of
expertise in performing
of work over the
project, the labours
might not be able to
fulfil the new age
design project for Ye
Olde Barn. New
advancements within
the project might not
suit the theatre due to
incomplete expertise
level.
Low Low Low The labours should be
made to understand about
the requirements and
objectives from the
project. These labours
should have a proper
form of understanding
about every aspect of
design and refurbishment
of the theatre. Any kind
of lack within the
expertise of the labours
should be sorted before
the project start date.
Labours,
Contractors
and Project
Manager
5 Any form of natural
disasters could make a
certain amount of
Natural disasters such
as rain and fire related
accidents could lead to
Low Medium Medium The contractor team
should procure materials
that would help in
Contractors,
Project
Manager,
shortage of construction
materials during the
time of constructing the
project. The supplier
might face problems
with supplying the
materials during
approximate time of
project execution stage.
construction materials
could lead to some
negative impacts. The
time taken to complete
the entire project could
get delayed to a certain
extent. This would thus
result in extension of
the time for the entire
project completion.
for the project execution
should be procured one
week prior to the
execution of any
particular stage of the
project. This would result
in easy determination of
any other supplier if
necessary. This would
not hamper the quality of
work and also help in
smooth execution.
manager,
Suppliers
4 Low expertise with new
requirements for
labours. The labours
hired for the
refurbishment project
might not be experts
with the changing
requirements.
Due to low level of
expertise in performing
of work over the
project, the labours
might not be able to
fulfil the new age
design project for Ye
Olde Barn. New
advancements within
the project might not
suit the theatre due to
incomplete expertise
level.
Low Low Low The labours should be
made to understand about
the requirements and
objectives from the
project. These labours
should have a proper
form of understanding
about every aspect of
design and refurbishment
of the theatre. Any kind
of lack within the
expertise of the labours
should be sorted before
the project start date.
Labours,
Contractors
and Project
Manager
5 Any form of natural
disasters could make a
certain amount of
Natural disasters such
as rain and fire related
accidents could lead to
Low Medium Medium The contractor team
should procure materials
that would help in
Contractors,
Project
Manager,

12DESIGNING AN EVENT FOR THE EAST KENT CIDER FESTIVAL
impact towards the
project.
tremendous impacts
such as delay in project
delivery.
protecting them and the
project. Fire safety
devices should be
procured before the start
of project. The labours
should also be provided
with rain safety
equipment.
Suppliers
6 Poor project
management could arise
within the project
works. This could lead
to poor form of risks
such as delay in project
delivery, budgetary
issues and many others.
An improper
arrangement of project
works could lead to
delay in the time of
delivery of the project.
The project might not
be completed within the
estimated time due to
lack of proper
management skills and
incorrect scheduling
approach.
Medium High High The project manager and
contractual manager
working over the project
should have a certain
sense of understanding
about properly managing
the work essentials. They
should design the work
schedule in such a
manner that it would
completely match with
the desired work
outcomes of the
refurbishment project.
Project
Manager,
Contractor
Manager
impact towards the
project.
tremendous impacts
such as delay in project
delivery.
protecting them and the
project. Fire safety
devices should be
procured before the start
of project. The labours
should also be provided
with rain safety
equipment.
Suppliers
6 Poor project
management could arise
within the project
works. This could lead
to poor form of risks
such as delay in project
delivery, budgetary
issues and many others.
An improper
arrangement of project
works could lead to
delay in the time of
delivery of the project.
The project might not
be completed within the
estimated time due to
lack of proper
management skills and
incorrect scheduling
approach.
Medium High High The project manager and
contractual manager
working over the project
should have a certain
sense of understanding
about properly managing
the work essentials. They
should design the work
schedule in such a
manner that it would
completely match with
the desired work
outcomes of the
refurbishment project.
Project
Manager,
Contractor
Manager

13DESIGNING AN EVENT FOR THE EAST KENT CIDER FESTIVAL
Bibliography
Fleming, Q.W. and Koppelman, J.M., 2016, December. Earned value project management.
Project Management Institute.
Harrison, F. and Lock, D., 2017. Advanced project management: a structured approach.
Routledge.
Kim, J.L., Greene, M. and Kim, S., 2014. Cost comparative analysis of a new green building
code for residential project development. Journal of construction engineering and
management, 140(5), p.05014002.
Kliem, R.L. and Ludin, I.S., 2019. Reducing project risk. Routledge.
Marcelino-Sádaba, S., Pérez-Ezcurdia, A., Lazcano, A.M.E. and Villanueva, P., 2014. Project
risk management methodology for small firms. International journal of project
management, 32(2), pp.327-340.
Memon, A.H. and Rahman, I.A., 2014. SEM-PLS analysis of inhibiting factors of cost
performance for large construction projects in Malaysia: perspective of clients and
consultants. The Scientific World Journal, 2014.
Meredith, J.R., Mantel Jr, S.J. and Shafer, S.M., 2017. Project management: a managerial
approach. John Wiley & Sons.
Muriana, C. and Vizzini, G., 2017. Project risk management: A deterministic quantitative
technique for assessment and mitigation. International Journal of Project Management, 35(3),
pp.320-340.
Bibliography
Fleming, Q.W. and Koppelman, J.M., 2016, December. Earned value project management.
Project Management Institute.
Harrison, F. and Lock, D., 2017. Advanced project management: a structured approach.
Routledge.
Kim, J.L., Greene, M. and Kim, S., 2014. Cost comparative analysis of a new green building
code for residential project development. Journal of construction engineering and
management, 140(5), p.05014002.
Kliem, R.L. and Ludin, I.S., 2019. Reducing project risk. Routledge.
Marcelino-Sádaba, S., Pérez-Ezcurdia, A., Lazcano, A.M.E. and Villanueva, P., 2014. Project
risk management methodology for small firms. International journal of project
management, 32(2), pp.327-340.
Memon, A.H. and Rahman, I.A., 2014. SEM-PLS analysis of inhibiting factors of cost
performance for large construction projects in Malaysia: perspective of clients and
consultants. The Scientific World Journal, 2014.
Meredith, J.R., Mantel Jr, S.J. and Shafer, S.M., 2017. Project management: a managerial
approach. John Wiley & Sons.
Muriana, C. and Vizzini, G., 2017. Project risk management: A deterministic quantitative
technique for assessment and mitigation. International Journal of Project Management, 35(3),
pp.320-340.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

14DESIGNING AN EVENT FOR THE EAST KENT CIDER FESTIVAL
Sage, A.P. and Rouse, W.B., 2014. Handbook of systems engineering and management. John
Wiley & Sons.
Shehu, Z., Endut, I.R. and Akintoye, A., 2014. Factors contributing to project time and hence
cost overrun in the Malaysian construction industry. Journal of Financial Management of
Property and Construction, 19(1), pp.55-75.
Taroun, A., 2014. Towards a better modelling and assessment of construction risk: Insights from
a literature review. International journal of Project management, 32(1), pp.101-115.
Zhou, Z., Goh, Y.M. and Li, Q., 2015. Overview and analysis of safety management studies in
the construction industry. Safety science, 72, pp.337-350.
Sage, A.P. and Rouse, W.B., 2014. Handbook of systems engineering and management. John
Wiley & Sons.
Shehu, Z., Endut, I.R. and Akintoye, A., 2014. Factors contributing to project time and hence
cost overrun in the Malaysian construction industry. Journal of Financial Management of
Property and Construction, 19(1), pp.55-75.
Taroun, A., 2014. Towards a better modelling and assessment of construction risk: Insights from
a literature review. International journal of Project management, 32(1), pp.101-115.
Zhou, Z., Goh, Y.M. and Li, Q., 2015. Overview and analysis of safety management studies in
the construction industry. Safety science, 72, pp.337-350.
1 out of 14
Related Documents

Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
© 2024 | Zucol Services PVT LTD | All rights reserved.