Project Risk Management Plan for Clinic Management System - Report

Verified

Added on  2022/12/27

|23
|4324
|1
Report
AI Summary
Document Page
RUNNING HEAD: Risk Management Plan
Risk Management Plan
For Clinic Management System Project
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Risk Management Plan 2
Executive Summary
Risk management is vital for any project. The paper develops a risk management plan for the
Clinic Management System. The project is scheduled to run for a period of 120 days at an
estimated budget of AED 120,240.00. The main risks that face this project include;
Incomplete or confusing requirements
Shortage of funds
Inadequate resources
Scope Creep
Schedule overrun
Shortage of qualified software developers for the project.
Quality of developed system
Software Bugs; which may affect user experience during live testing and delay the project
sign-off
Unrealistic cost estimates
For each identified risk, an appropriate response and control has been established and
documented. However, risks can occur at any stage of the project and it’s impossible to identify
and deal with all risks. We therefore recommend a continuous monitoring and evaluation of the
project – as it progresses- to identify new risk and catch them in time, before they cause any
impacts on the project.
Document Page
Risk Management Plan 3
Table of Contents
Executive Summary.....................................................................................................................................2
1.0 Introduction......................................................................................................................................4
1.1 Background of the Clinic...............................................................................................................4
1.2 Main Issue....................................................................................................................................4
1.3 Foreseeable accomplishments.....................................................................................................4
1.4 Plan of the Project........................................................................................................................5
2.0 Risk Management Plan.....................................................................................................................5
2.1 WBS.............................................................................................................................................5
2.1.1 Activities Precedence table...................................................................................................6
2.2 Time Estimates.............................................................................................................................7
Gantt chart...........................................................................................................................................8
2.3 Cost Estimates..............................................................................................................................9
2.4 CPM, Crashing & Crashing Schedule.........................................................................................11
2.5 Monte Carlo Simulation..............................................................................................................12
2.6 3.2 RACI....................................................................................................................................12
2.7 Risk identification + develop RBS.............................................................................................13
2.8 Risk quantification......................................................................................................................14
Risk Occurrence Probability................................................................................................................15
Impact................................................................................................................................................16
2.9 Risk response development........................................................................................................16
2.10 Risk response control/Risk Contingency Plan............................................................................17
Decision Tree.............................................................................................................................................21
Net Present Value...................................................................................................................................21
3.0 Conclusions....................................................................................................................................22
3.1 Discussion..................................................................................................................................22
3.2 Conclusion..................................................................................................................................22
3.3 Recommendation........................................................................................................................23
References..................................................................................................................................................24
Document Page
Risk Management Plan 4
1.0 Introduction
Risk management is an integral part of project management. The PMBOK Guide version five
defines project risk; as anything with potential to impact a project’s budget, performance or
schedule (Snyder, 2013). In any project, the critical trade-offs are time, quality and resources.
Risks in a project tend to affect the three critical aspects of a project; a negative effect on a
project schedule translates to a potential budget increase, as resources are used longer than
planned (Snyder, 2013). On the other hand, a risk that negatively affects project resources affects
the quality of project deliverables, as fewer resources are used to produce the deliverables. As
such, managing project risk is extremely vital.
1.1 Background of the Clinic
WellToDo clinic is a comprehensive family health clinic, located in Al Ain. The clinic provides
healthcare related services in its large complex at Al Ain. Currently the clinic uses a manual
system, where patients are issued with a card, with a unique patient id; so that their records can
be retrieved the next time they visit the clinic. The manual system is highly inefficient and the
management has decided to embark on developing a Clinic Management system, to automate
processes and record keeping at the clinic.
1.2 Main Issue
The process of establishing effective project risk management entails identifying, analyzing and
responding to risks as they arise over the project’s life cycle. Managing project risks helps keep
the project on track and meet the goals of the project (Webb, 2017). Effective risk management is
not reactive; rather, it has to be incorporate in every phase of the project, right from the planning
stage. This approach helps to figure out risks and establish controls and mitigation strategies for
the identified risks. Risk management is therefore defined as a process of “identifying,
categorizing, prioritizing and planning for risks before they happen” (Snyder, 2013).
1.3 Foreseeable accomplishments
This document presents a risk management plan for the project that seeks to implement a Medical
Clinic Management System, for WellToDo clinic in Al Ain. The document outlines the 5 phases
of risk management planning; risk identification, analysis of the risks, evaluation and ranking of
the risk, development of a risk response plan in a risk register and review of the risk register to
track and control the risks. The foreseeable accomplishments of the project include;
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Risk Management Plan 5

1.4 Plan of the Project
The document first presents the project details through a work breakdown structure, a project
schedule in form of time estimates, cost estimates and finally the five processes of risk
management planning. The techniques used in developing the risk management plan includes;
RBS, RACI, Matrix/Probability, Occurrences/Impact graph(s), Decision Tree(s) and Break Even
Analysis.
2.0 Risk Management Plan
2.1 WBS
The project entails the design, coding and deployment of a Clinic Management System. The
proposed system will be a web-based system, developed using Angular JS for the front end and
python Django for the back-end; with a MySQL database. The specific project tasks and work
breakdown structure is as presented below;
Document Page
Risk Management Plan 6
Figure 1.0 Work Breakdown structure of the proposed Clinic Management System
2.1.1 Activities Precedence table
Task Name Predecessors
Clinic Management System
Project Planning
Initiation Meeting
Gather Project requirements 3
Develop a project plan 3
System Analysis and Design 2
Design the system 4
Design database schemas 4
Develop an SDD 8
Project Implementation 6
Code the application 7
Perform unit testing 11
Perform complete system testing 12
Develop system documentation 11
Deploy the system 13
User Training 10
Train system end users 15,9
Live system training with users 17
Project Closure 16
Evaluate the project 18,14
Document lessons learnt 20
Project Sign-offs 21
Close the project 22
Document Page
Risk Management Plan 7
2.2 Time Estimates
Time estimates for the project were done at the work package level of the Work Breakdown
Structure. The project will run for a period of 120 days; with each work package assigned an
estimate in days. In order to develop the project path and critical path, predecessors for each
activity were established, as shown below.
Task Name Optimistic
Most Likely
Duration (In
Days)
Pessimistic Estimated Duration
Analyze Requirements 7.00 10.00 13 10.00
Design the System 8.00 10.00 12 10.00
Develop an SDD 4.00 5.00 6 5.00
Code the application 60.00 65.00 70 65.00
Unit testing 5.00 7.00 8 6.67
Complete system testing 3.00 5.00 6 4.67
Install the System 1.00 3.00 4 2.67
End User Training 5.00 7.00 9 7.00
Live testing of the system 2.00 3.00 4 3.00
Evaluate the project 1.00 1.00 2 1.33
Document lessons learnt 1.00 2.00 3 2.00
Project Sign-offs 1.00 1.00 2 1.33
Close the project 1.00 1.00 1 1.00
Total Project Duration [In Days] 99.00 120.00 140 119.67
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Risk Management Plan 8
Gantt chart
2.3 Cost Estimates
Cost is a critical component of a project. A number of techniques are used in project cost
estimates. Key among them includes use of expert judgment, analogous estimation, parametric
estimation, three-point estimation and bottom-up estimation (Chapman & Ward, 1996). With
parametric estimation previous projects parameters such as scope, size, budget and duration of
similar previous projects are taken into account (Chapman & Ward, 1996). A similar approach is
employed with analogous estimation, where budgets from previous projects help in estimating the
current budget (Hopkin, 2018). Parametric estimation uses an almost similar approach, where
Document Page
Risk Management Plan 9
algorithms are utilized in calculating cost basing the estimates on previous data. A more accurate
estimation technique is used in Bottom-up estimation, where estimations are performed at a work
package level of the work breakdown structure (WBS) and then rolled up to higher levels
(Hopkin, 2018).
For this project, a bottom-up approach is used, where each project activity is assigned a resource
and duration. Cost estimation is then based on the amount of resources assigned, duration of the
activity and the estimated cost of utilizing the resource per a given hour. The tools used in
estimating the cost are Microsoft Project and QM Version 5.2.
Task Name Cost
Analyze Requirements AED 24,000.00
Design the System AED 13,600.00
Develop an SDD AED 14,800.00
Code the application AED 36,400.00
Unit testing AED 2,800.00
Complete system testing AED 4,800.00
Install the System AED 10,080.00
End User Training AED 3,920.00
Live testing of the system AED 1,680.00
Evaluate the project AED 3,360.00
Document lessons learnt AED 3,200.00
Project Sign-offs AED 1,600.00
Total AED 120,240.00
This Most Likely cost estimation was done using a Bottom-Up estimation technique; for each
work package, we took the resource assigned, the number of work hours and the cost of the
resource per hour. The pay for each resource is as summarized below.
Resource Name Std. Rate
Project Manager AED 200.00/hr
System Analyst AED 100.00/hr
Software Engineers AED 70.00/hr
Test Analyst AED 50.00/hr
Document Page
Risk Management Plan 10
Breakeven Analysis
With the estimated cost of developing the software being AED 120,240.00, and total operating
costs of around AED 50 per patient, expected revenue of AED 150 per patient; the breakeven point
is at 1202 patients, and the breakeven point will happen when the clinic generates revenue of AED
180,360
2.4 CPM, Crashing & Crashing Schedule
The critical path method (CPM) is a technique of defining the critical and non-critical tasks in a
project (Kliem & Ludin, 2019). With Crashing, resources are added to the activities of the
project, after calculating the least cost possible. This is a form of compression that is achieved
after calculating cost and schedule trade-offs, to determine maximum time compression at
minimum cost (Kliem & Ludin, 2019). The Initial CPM of the project is as follows;
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Risk Management Plan 11
With crashing, more programmers were added to short the coding stage; the result is a slight
increase in the budget, but it is the minimal achievable increase possible.
2.5 Monte Carlo Simulation
In project risk management, Monte Carlo Analysis is used to conduct a quantitative analysis of
risks in a project. For this project the major risk that is likely to affect other aspects of the project
is unrealistic time estimates. To further analyze this major risk, a Monte Carlo Simulation was
performed. The advantage of the analysis is that it provides an early identification of how likely a
project is to meet project milestones and deadlines. The approach is also critical in evaluating
how realistic a schedule and budget is, and the probability and likelihood of cost and schedule
overruns.
The Monte Carlo simulation shows low chance of completing the project on time, due to the fact
that the schedule has a lot of variable factors.
Document Page
Risk Management Plan 12
2.6 3.2 RACI
A RACI matrix is a project management too, that provides an avenue for defining and showing
project roles and responsibilities (Larson & Gray, 2017). The acronym RACI stands for
Responsible, Accountable, Consulted and Informed (Larson & Gray, 2017). The matrix
documents the person responsible for every tasks of the project.
Task Name Project
Sponsor
Owner Project
Manager
Latifa(Syste
m Analyst)
Hedaya
(Lead
Engineer)
Noura(Software
Engineer)
Hamda(Test
Engineer)
Gather Project
requirements
I I A R I
Develop a project
plan
I C R I I I I
Design the
system
I I A R C I I
Design database
schemas
I I I R C I
Develop an SDD I I I C C I
Code the
application
I I I C A R I
Perform unit
testing
I I I C A C R
Perform complete
system testing
I I I I A C R
Develop system
documentation
I I A C R C C
Deploy the system I I A C R C C
Train system end
users
I I A C R C C
Live system
training with users
I I A C R C C
Evaluate the
project
I A R C C C C
Document lessons
learnt
I A R C C C C
Project Sign-offs C A R I I I I
Close the project I A R I I I I
Document Page
Risk Management Plan 13
2.7 Risk identification + develop RBS
For effective identification and management of risks in this project, periodic assessment will be
performed throughout the project life-cycle. The main risks that face this project include;
Incomplete or confusing
requirements
Shortage of funds
Inadequate resources
Scope Creep
Schedule overrun
Unrealistic cost estimates
Shortage of qualified software
developers for the project.
Quality of developed system
Software Bugs; which may affect
user experience during live testing
and delay the project sign-off
Risk Breakdown Structure (RBS) presents identified risks in a hierarchical representation. The
hierarchy starts with the highest level of the project to the lowest, similar to a Work Breakdown
Structure (McNeil, Frey & Embrechts, 2015). For this project, the risk categories are classified as
technical risks, organizational risks and project management risks. The risks are then sub-divided
to finer categories.
Figure 4.0 Risk Breakdown Structure (RBS)
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Risk Management Plan 14
2.8 Risk quantification
Risk quantification entails evaluating the identified risks and developing appropriate data for use
in decision making (McNeil, Frey & Embrechts, 2015). Qualitative and quantitative analysis
techniques are used in quantifying risks. The goal of risk quantification is to develop an approach
of arranging risks in the order of importance (Snyder, 2013). This is done to establish risks that
need to be address; as not all risks can be dealt with in a project, due to shortage of resources and
time (Snyder, 2013).
A practical measure of qualifying risks is the severity of the given risk. Severity is estimated by
combining risk impact and risk probability. A simple way of ranking risk severity entails
classifying them as High, Medium or Low. A more complex approach involves ranking the
severity as a percentage value, while the impact can be estimated as a dollar value. The product
of the percentage value of severity and the dollar value of impact produces a quantitative value of
the risk (Hopkin, 2018).
In quantifying the risks, we followed the following table of
Figure 5.0 Risk Qualitative evaluation table
Document Page
Risk Management Plan 15
Risk Occurrence Probability
For quantitative evaluation of risks, an evaluation table was developed, with the following factors
considered, when evaluating and quantifying the risks
Probability of 5: translates to a risk that has a 90 – 100% likelihood of occurrence
Probability of 4: a risk with a 60% – 89% chance of occurring
Probability of 3: the risk has an occurrence likelihood of 40% – 59%
With a probability of 2: the given risk is unlikely to occur as it has a 10% – 39% chance
of occurring.
With a probability of 1, the risk is very unlikely to occur and has an occurrence
probability below 10%
Impact
Risk impact is a measure of the possible effects of a risk on a project (Hopkin, 2018). For this
project, the impact ranging from 1 (minimal) to 5 (high); the minimal value indicates that the
consequences of the risks are very minimal while the high translates to devastating effects on the
project.
Project Risk quantification
Id Identified Risk Likelihood Impact
1 Scope Creep Unlikely 3 Medium 3
2 Shortage of funds Unlikely 1 High 4
3 Shortage of qualified software developers for the
project
Likely 3 Medium 3
4 Unrealistic cost estimates Unlikely 2 High 4
5 Low Quality of developed system Likely 2 High 4
6 Incomplete or confusing requirements Likely 3 Medium 3
Document Page
Risk Management Plan 16
7 Schedule Overrun Likely 4 Medium 4
8 Software Bugs; which may affect user
experience during live testing and delay the
project sign-off
Very Likely 5 Medium 3
2.9 Risk response development
Risk response development entails identifying and putting in place strategies, geared towards enhancing
opportunities and reducing threats to a project’s goals (Snyder, 2013). For each risk response, a project
team member is assigned, to take responsibility.
Id Identified Risk Risk Response Assign to
1 Scope Creep Avoid: Define the project scope early in the project
and evaluate the conformity to the scope in the
weekly project status meetings.
Project Manager
2 Shortage of funds Avoid: Ensure availability of funds before the
project starts
Project Manager
3 Shortage of qualified software developers for the
project
Mitigate: Source for skilled and experienced
developers before the coding stage begins, also offer
on-job training before they start the coding phase
Hedaya (Lead
Engineer)
4 Unrealistic cost estimates Avoid: Perform thorough bottom-up cost estimation;
analyse previous similar projects to confirm the
costs.
Noura(Software
Engineer) and the
Project Manager
5 Low Quality of developed system Mitigate: Embed quality checks at every stage of
the project
Hamda(Test
Engineer)
6 Incomplete or confusing requirements Avoid: Perform thorough requirement gathering and
analyse the requirements with users
Latifa(System
Analyst)
7 Schedule Overrun Mitigate: Evaluate schedule in weekly project
meetings, and take corrective measures. Clearly
analyse change requests that may affect the schedule
Project Manager
8 Software Bugs; which may affect user
experience during live testing and delay
the project sign-off
Mitigate: Perform comprehensive unit test as well
as complete system test; debug any bugs found and
re-test the system.
Hamda(Test
Engineer)
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Risk Management Plan 17
2.10 Risk response control/Risk Contingency Plan
Risk response control entails executing the developed risk management plan, when risk events
arise over the project’s life-cycle (Snyder, 2013). For this project the risk response plan is as
outline below; the action column defines what is to be done in case the risk occurs.
Id Identified Risk Risk Contingency Action Assign to
1 Scope Creep Review weekly deliverables against
defined scope; take corrective measures
Project Manager
2 Shortage of funds Re-adjust project budget or seek different
source of funding.
Project Manager
3 Shortage of qualified software developers
for the project
Upgrade developers skills by on-job
training
Hedaya (Lead Engineer)
4 Unrealistic cost estimates Use best practices in defining cost; add a
contingency percentage
Noura(Software Engineer) and the
Project Manager
5 Low Quality of developed system Perform quality checks for every
deliverable while the project is in
progress
Hamda(Test Engineer)
6 Incomplete or confusing requirements Re-visit requirements gathering to
verify the requirements
Latifa(System Analyst)
7 Schedule Overrun Adjust schedule or increase resources Project Manager
8 Software Bugs; which may affect user
experience during live testing and
delay the project sign-off
Debug the application and re-test till
all bugs are eliminated.
Hamda(Test Engineer)
Document Page
Risk Management Plan 18
RISK REGISTER
No Rank Identified Risk Category Root
Cause
Trigger Risk Response Owner Probabilit
y
Impact
R1 1. Scope Creep Management Lack of
close
observatio
n
Change
in scope Avoid: Define the project scope
early in the project and evaluate the
conformity to the scope in the
weekly project status meetings.
Project
Manager
Unlikely Medium
R2 2. Shortage of funds Organization
al
Organizati
onal
challenge
s
- Avoid: Ensure availability of funds
before the project starts
Project
Manager
Unlikely High
R3 3. Shortage of qualified software
developers for the project
Organization
al
External - Mitigate: Source for skilled and
experienced developers before the
coding stage begins, also offer on-
job training before they start the
coding phase
Hedaya
(Lead
Engineer)
Likely Medium
R4 4. Unrealistic cost estimates Management Poor cost
estimatio
n
- Avoid: Perform thorough bottom-
up cost estimation; analyse
previous similar projects to
confirm the costs.
Noura(Softw
are
Engineer)
and the
Project
Manager
Unlikely High
R5 5. Low Quality of developed
system
Technical Unqualifie
d
personnel
- Mitigate: Embed quality checks at
every stage of the project
Hamda(Test
Engineer)
Likely High
Document Page
Risk Management Plan 19
R6 6. Incomplete or confusing
requirements
Technical Poor
requireme
nts
gathering
- Avoid: Perform thorough
requirement gathering and analyse
the requirements with users
Latifa(Syste
m Analyst)
Likely Medium
R7 7. Schedule Overrun Management Scope
Creep
Scope
Creep,
resouce
unavaila
bility
Mitigate: Evaluate schedule in
weekly project meetings, and take
corrective measures. Clearly
analyse change requests that may
affect the schedule
Project
Manager
Likely Medium
R8 8. Software Bugs; which may
affect user experience
during live testing and
delay the project sign-off
Technical Poor or
inadequat
e testing
Inadequa
te
testing
Mitigate: Perform comprehensive
unit test as well as complete system
test; debug any bugs found and re-
test the system.
Hamda(Test
Engineer)
Very
Likely
Medium
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Risk Management Plan 20
Decision Tree
In risk analysis, decision trees help in calculating the Expected Monetary Value (EMV).
The four steps involved in calculating EMV are;
Documenting a decision in a decision tree.
Assigning probability of risk occurrence for each decision.
Assigning monetary value of the impact of the risk if it were to occur.
Computing the EMV for each decision.
For this project, the decision is whether to build the software or streamline the manual system.
If the software is developed and it is successful, the monetary value will be around AED
150,000 ; with a probability of success being 0.7, and 0.3 probability of failure
If the manual system if streamlined to eliminate current problems; the probability of
having efficient operations is 0.5, with a monetary value of AED 40,000 per year in
savings on labor
Net Present Value
To further establish the viability of the project, we evaluate the Net Present Value (NPV); which
tells if the investment is profitable over a period of time. For this project, the initial cost of
developing the Software is AED 120,240. It is expected that the inflow from patients will be
around AED 40,000. However, the software and the associated hardware infrastructure will
require annual maintenance, support and upgrades totaling to AED 5,000. To establish if it is
worth investing in the software that can be used for a period of 10 years, before requiring a major
upgrade, we analyze the NPV of the project, using QM.
Document Page
Risk Management Plan 21
From the analysis, the project is viable; over the 10 year period, the value of the investment will
be around AED 229,760.
3.0 Conclusions
3.1 Discussion
Risk management is very critical in any project. As defined earlier, risk is any occurrence with a
potential to affect a project’s schedule, budget or quality. Risks can have negative or positive
effects in a project; however, the threat is always on the negative risks. Conventionally, projects
are resource and time constrained. The effects of risk therefore affect the two most critical limited
resources of a project; time and budget. Eliminating these risks requires good planning,
identification of the risks, and setting up mitigation strategies for the risks. Additionally, risks
have to be evaluated at continuously as the project progresses; this is critical in dealing with
hidden risks such as scope creep, which may have significant effects on the project.
3.2 Conclusion
This project has developed a risk management plan for the Clinic Management System project.
The risk plan outlined has identified the main risks that may affect the project, ranked the risks,
quantified them and established response, controls and mitigation strategies. For each risk
response defined, a member of the team has been assigned; this ensures that the response and
mitigation strategy defined is implemented in time when a given risk occurs.
Document Page
Risk Management Plan 22
3.3 Recommendation
As risks can occur at any stage of the project; and the fact that it is not possible to identify and
deal with all risks, we recommend a continuous monitoring and evaluation of the project – as it
progresses- to identify new risk and catch them in time, before they cause any impacts on the
project.
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Risk Management Plan 23
References
Chapman, C., & Ward, S. (1996). Project risk management: processes, techniques and insights.
John Wiley.
Hopkin, P. (2018). Fundamentals of risk management: understanding, evaluating and
implementing effective risk management. Kogan Page Publishers.
Kliem, R. L., & Ludin, I. S. (2019). Reducing project risk. Routledge.
Larson, E. W., & Gray, C. F. (2017). Project management: The managerial process. McGraw-
Hill Education.
McNeil, A. J., Frey, R., & Embrechts, P. (2015). Quantitative risk management:
Concepts. Economics Books.
Snyder, C. (2013). A User's Manual to the PMBOK Guide. New Jersey: Wiley.
Webb, A. (2017). The project manager's guide to handling risk. Routledge.
chevron_up_icon
1 out of 23
circle_padding
hide_on_mobile
zoom_out_icon
[object Object]