Project Management Project: Club Soccer Tournament in South Africa

Verified

Added on  2022/08/26

|13
|1756
|20
Project
AI Summary
This project is a comprehensive analysis of managing a club soccer tournament in South Africa, aiming to provide a fun opportunity and promote health benefits for local soccer teams. The project outlines the need, objectives, and scope, defining in-scope and out-scope elements. It identifies assumptions and constraints, including time, resources, and advertisement. A detailed work breakdown structure (WBS) breaks down the project into manageable tasks. A project schedule, Gantt chart, and network diagram are developed to visualize timelines and dependencies. The project also includes a cost estimate, budgeting $40,000 for various expenses. The document covers initiation, planning, execution, and closure phases, providing a complete project management overview with references to relevant literature.
tabler-icon-diamond-filled.svg

Contribute Materials

Your contribution can guide someone’s learning journey. Share your documents today.
Document Page
Running head: PROJECT MANAGEMENT
Club Soccer tournament
Name of the Student
Name of the University
Author’s Note
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
1
PROJECT MANAGEMENT
Table of Contents
1. Need of the project.................................................................................................................2
2. Project objectives...................................................................................................................2
3. Scope definition.....................................................................................................................2
4. Assumptions and constraints..................................................................................................3
4. 1Assumptions.....................................................................................................................3
4.2 Constraints........................................................................................................................3
5. Work breakdown structure.....................................................................................................4
6. Project schedule.....................................................................................................................5
7. Gantt chart..............................................................................................................................7
8. Network diagram....................................................................................................................9
9. Cost estimate..........................................................................................................................9
Bibliography.............................................................................................................................11
Document Page
2
PROJECT MANAGEMENT
1. Need of the project
The main focus of the paper is on hosing a club soccer tournament in South Africa for
providing fun opportunity for the local soccer teams. The project mainly aims to involve the
entire soccer team for promoting sports for different types of health benefits. In addition to
this, this kind of sporting event helps in making the entire team physically fit. The entire
soccer team tournament will be organized within budget $40,000 in 50 days of time by
properly finding a good location, establishing tournament, attracting teams as well as hosting
the tournament effectively.
2. Project objectives
The project objectives are mainly listed below:
To organize a club soccer tournament in South Africa for providing fun opportunity
for the local soccer teams
To promote a club soccer tournament for health benefits
3. Scope definition
In-scope
Development of proper project and resource plan
Finding a good location
Asking about the needs for using the field
Establishment of the tournament
Advertising tournament
Assigning duties to the volunteers
Document Page
3
PROJECT MANAGEMENT
Out-scope
The facility of workshop as well as training is not given to the members of project
team
Amendments within the scope can generally impact the project feasibility
4. Assumptions and constraints
4. 1Assumptions
An assumption is made by the project manager as per which the club soccer
tournament will get executed within the time-period of 50 days.
As per the financial manager, the hosting of the club soccer tournament will get
completed within $40,000.
Posting signs and ads will be done effectively in order to advertise the tournament
effectively.
4.2 Constraints
Time: The project will face delay if the timeline which is prepared in the of the
project kick off phase of the project does not get tracked effectively and therefore the
completion date for the project can generally get extended.
Resource: Lack of knowledge and experience among the volunteers will create few
challenges due to which they will face a lot of challenges in managing the hosting of the
tournament.
Improper advertisement: If advertisement prior to the hosing of the tournament is
not done then only few people can be able to know about it.
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
4
PROJECT MANAGEMENT
5. Work breakdown structure
It is considered as a method that assists in organizing and finishing the work that is
associated with the project by successfully by breaking the activities down into smaller
chunks such that the work can be done simultaneously by taking help from the team members
(Siami-Irdemoosa, Dindarloo & Sharifzadeh, 2015). By determining the deliverable from the
below WBS, the project manager can be capable of estimating the cost as well as project time
which is required by the project in order to complete the project quite successfully.
Additionally, the WBS helps in simplifying communication outside the project team as the
team members can be able to understand each task effectively.
Figure 1: Work breakdown structure
(Source: Created by Author)
6. Project schedule
Project schedule is one of the tools that helps in communicating the work that is
required to be performed within the given project timeline such that the work gets delivered
successfully on time. The club soccer tournament will be organized in 50 days of time and it
is found that the project will get accomplished by 20th March 2020.
Document Page
5
PROJECT MANAGEMENT
WBS Task Name Duration Start Finish
0 Club soccer tournament 50 days Mon 13-01-20 Fri 20-03-20
1 Initiation phase 10 days Mon 13-01-20 Fri 24-01-20
1.1
Development of business
case
2 days Mon 13-01-20 Tue 14-01-20
1.2 Feasibility study 3 days Wed 15-01-20 Fri 17-01-20
1.3 Establishing project charter 2 days Mon 20-01-20 Tue 21-01-20
1.4 Appointing team members 3 days Wed 22-01-20 Fri 24-01-20
1.5
Milestone 1: Completion of
initiation phase
0 days Fri 24-01-20 Fri 24-01-20
2 Planning phase 7 days Mon 27-01-20 Tue 04-02-20
2.1 Development of project plan 1 day Mon 27-01-20 Mon 27-01-20
2.2
Development of resource
plan
1 day Tue 28-01-20 Tue 28-01-20
2.3
Development of financial
plan
2 days Wed 29-01-20 Thu 30-01-20
2.4 Quality plan 2 days Fri 31-01-20 Mon 03-02-20
2.5 Risk management plan 1 day Tue 04-02-20 Tue 04-02-20
2.6 Milestone 2: Planning phase 0 days Tue 04-02-20 Tue 04-02-20
3 Execution phase 27 days Wed 05-02-20 Thu 12-03-20
3.1 Finding a good location 6 days Wed 05-02-20 Wed 12-02-20
3.1.1 Selection of date 1 day Wed 05-02-20 Wed 05-02-20
3.1.2 Finding an available field 2 days Thu 06-02-20 Fri 07-02-20
3.1.3 Analyzing field seating 1 day Mon 10-02-20 Mon 10-02-20
Document Page
6
PROJECT MANAGEMENT
3.1.4
Asking about the
requirement for using the field
2 days Tue 11-02-20 Wed 12-02-20
3.2 Establishing tournament 5 days Thu 13-02-20 Wed 19-02-20
3.2.1 Naming the tournament 1 day Thu 13-02-20 Thu 13-02-20
3.2.2 Recruit volunteers 2 days Fri 14-02-20 Mon 17-02-20
3.2.3 Setting tournament rules 1 day Tue 18-02-20 Tue 18-02-20
3.2.4
Getting teams to play
tournament
1 day Wed 19-02-20 Wed 19-02-20
3.3 Advertise the tournament 5 days Thu 20-02-20 Wed 26-02-20
3.3.1
Calling soccer
organizations
2 days Thu 20-02-20 Fri 21-02-20
3.3.2 Organizing teams 1 day Mon 24-02-20 Mon 24-02-20
3.3.3 Hosting soccer tournament 2 days Tue 25-02-20 Wed 26-02-20
3.4 Creating schedule 3 days Thu 27-02-20 Mon 02-03-20
3.5 Purchase supplies 3 days Tue 03-03-20 Thu 05-03-20
3.6 Setting up the field 2 days Fri 06-03-20 Mon 09-03-20
3.7
Assigning duties to the
volunteers
3 days Tue 10-03-20 Thu 12-03-20
3.8
Milestone 3: Completion of
execution phase
0 days Thu 12-03-20 Thu 12-03-20
4 Closure phase 6 days Fri 13-03-20 Fri 20-03-20
4.1 Post project review 3 days Fri 13-03-20 Tue 17-03-20
4.2 Stakeholder sign off 1 day Wed 18-03-20 Wed 18-03-20
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
7
PROJECT MANAGEMENT
4.3 Documentation 2 days Thu 19-03-20 Fri 20-03-20
4.4
Milestone 4: Completion of
closure phase
0 days Fri 20-03-20 Fri 20-03-20
7. Gantt chart
It is a horizontal bar that visually assists in properly representing the project plan for
organizing a club soccer tournament. It helps in giving proper prioritization as well as
visualization in order to give proper overview about the entire project. It is found that the
problem of resource overload gets avoided due to the utilization of Gantt chart and
additionally, it assists in measuring the progress of the project by enabling the project
manager to make changes (Dayani & Gelbard, 2015). Moreover, Gantt chart helps in
practicing better time management by providing better understanding about the entire project
and thus it is analyzed that Gantt charts helps in providing better clarity for the entire
schedule of the project. The Gantt chart that is provide showcases that the tournament of club
soccer will be arranged within the time span of 50 days.
Document Page
8
PROJECT MANAGEMENT
Figure 2: Gantt chart
(Source: Created by Author)
Document Page
9
PROJECT MANAGEMENT
8. Network diagram
The network diagram which is provided below helps in graphically representing all
tasks as well as responsibilities that are mainly associated with the club soccer tournament
project. It generally helps in properly mapping the work sequence as well as schedule of the
project and further helps in tracking the progress of each stage of the project (Nicholas &
Steyn, 2017). In addition to this, it helps in planning and helps in determining different
opportunities which are beneficial for successfully compressing the entire schedule for
finishing the tournament in the estimated time.
Figure 3: Network diagram
(Source: Created by Author)
9. Cost estimate
The table that is given below showcases that in order to organize a club soccer
tournament, budget of around $40,000 is mainly needed which mainly include cost of
material, arrangement cost, venue cost and as well as human resource cost.
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
10
PROJECT MANAGEMENT
Cost Expense
Planning cost $5,000
Human resource cost $ 10,000
Material cost $10,000
Cost for arrangement $5,000
Venue cost $5,000
Additional cost $5,000
Total cost $40,000
Document Page
11
PROJECT MANAGEMENT
Bibliography
Chih, Y. Y., & Zwikael, O. (2015). Project benefit management: A conceptual framework of
target benefit formulation. International Journal of Project Management, 33(2), 352-
362.
Dayani, M., & Gelbard, R. (2015). Automatic Conversion of Software Specification into a
Gantt-chart subject to Organization's Constraints. Procedia Computer Science, 64, 73-
78.
Nicholas, J. M., & Steyn, H. (2017). Project management for engineering, business and
technology. Routledge.
Papke-Shields, K. E., & Boyer-Wright, K. M. (2017). Strategic planning characteristics
applied to project management. International Journal of Project Management, 35(2),
169-179.
Qazi, A., Quigley, J., Dickson, A., & Kirytopoulos, K. (2016). Project Complexity and Risk
Management (ProCRiM): Towards modelling project complexity driven risk paths in
construction projects. International Journal of Project Management, 34(7), 1183-
1198.
Ramazani, J., & Jergeas, G. (2015). Project managers and the journey from good to great:
The benefits of investment in project management training and
education. International Journal of Project Management, 33(1), 41-52.
Serra, C.E.M. & Kunc, M. (2015). Benefits realisation management and its influence on
project success and on the execution of business strategies. International Journal of
Project Management, 33(1), pp.53-66.
Document Page
12
PROJECT MANAGEMENT
Siami-Irdemoosa, E., Dindarloo, S. R., & Sharifzadeh, M. (2015). Work breakdown structure
(WBS) development for underground construction. Automation in Construction, 58,
85-94.
chevron_up_icon
1 out of 13
circle_padding
hide_on_mobile
zoom_out_icon
logo.png

Your All-in-One AI-Powered Toolkit for Academic Success.

Available 24*7 on WhatsApp / Email

[object Object]