This project plan outlines the construction of twin monuments in the coastal town of Portmouthempton, aiming to celebrate the town's success and enhance its heritage. The plan includes project aims, objectives, success criteria, scope, assumptions, and constraints. It details the implementation and project schedule using a Gantt chart, identifies key milestones and deliverables, and presents a work breakdown structure. Stakeholder analysis and a communication management plan are provided to ensure effective collaboration. The plan also addresses risk management and includes a comprehensive project cost estimate, covering various aspects of the construction process to ensure the project is completed on time and within budget. Desklib offers a variety of resources, including past papers and solved assignments, to support students in similar projects.
Document Page
1PROJECT ENVIRONMENT AND PLANNING
Project Plan: Building of twin monuments in coastal town of Portmouthempton
Name of the Student:
Name of the University:
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
2PROJECT ENVIRONMENT AND PLANNING
Table of Contents
Introduction......................................................................................................................................3
1.0 Background of the project.........................................................................................................3
2.0 Project Aim and objectives........................................................................................................3
3.0 Success criteria of the project....................................................................................................4
4.0 Project scope, assumptions and constraints...............................................................................4
4.1 Project Scope.........................................................................................................................4
4.2 Assumptions and constraints.................................................................................................4
5.0 Implementation and project schedule of the project..................................................................5
5.1 Gantt chart.............................................................................................................................5
5.2 Project Milestones.................................................................................................................7
5.3 Project Deliverables...............................................................................................................8
5.4 Work breakdown structure....................................................................................................8
6.0 Stakeholder Analysis...............................................................................................................11
7.0 Communication Management Plan..........................................................................................13
8.0 Risk management plan.............................................................................................................14
9.0 Project cost...............................................................................................................................15
References......................................................................................................................................19
Document Page
3PROJECT ENVIRONMENT AND PLANNING
Introduction
The project plan consists of project aims and objectives with some success criteria for the
project. The scope of project, its assumptions and also constraints are identified with proper
scheduling of the plan. The project stakeholders are identified those are involved in the project
work with a communication plan to interact with each other. Risks are identified on time before
it affects the project completion time and causes delay into finishing of the project. Cost is
estimated by providing justification on cost with its control.
1.0 Background of the project
The project plan is based on building of monuments in coastal town of Portmouthempton
to celebrate the success of their town. Twin monuments are built on either side of the main road
in the town. The council of the town is concerned about the completion of the project on time
and within estimated budget. The council estimated the budget as £ 10,000,000 and the total time
to finish the building work of twin monument is within two years.
2.0 Project Aim and objectives
The project aim is to plan and design of twin monuments for the success of coastal town
of Portmouthempton with representing of complex architectural challenges. It needs of civil
engineering along with coordination of labor. The purpose behind building of the monuments is
to bring the monuments as well as local heritage into heart of the community. The coastal town
of Portmouthempton helps the community to embrace the heritage and medieval the town wall.
The main aim is to build the monument for serving the focal point for the heritage, educational as
well as recreational activities to encourage the population of the town.
The objectives of this project plan are:
To build of twin monuments in coastal town of Portmouthempton to celebrate the
success of their town.
To involve into conservation as well as interpretation of the heritage sites into the
local area
Document Page
4PROJECT ENVIRONMENT AND PLANNING
To collaborate into the building plan as community and participate into the
development of community
To complete the building work of the monuments within 2 years in addition to a
budget of £ 10,000,000
To serve of historical and educational understanding among the community of the
locality
To select of the project team members based on the experience to work into the
construction plan
3.0 Success criteria of the project
The success criteria of the project plan are that the entire project plan is discussed with all
the departments so that each and every one should provide their feedback on them. Before
building of the monuments, the quality of soil is being checked. All the raw materials for the
building work are to be procured properly with better quality. The raw material should be of best
quality along with the ordered should be delivered on time. A report is being made based on
length as well as breadth of the pillar of the monuments. The leveling of the monuments and the
side road of the twin monuments should be same as estimated by the civil department. From all
the departmental heads such as civil, mechanical, financial, electrical and procurement, the data
reports are gathered to become familiar with the project status. The project plan should finish
within estimated time and budget so that there should be no possibility of project delay.
4.0 Project scope, assumptions and constraints
4.1 Project Scope
The scope of this project work is to include of work surface cleaning, preparation as well
as painting of the twin monuments which is built on either side of the main road in the town. The
building of the monuments are based on providing historical education to people of the coastal
town of Portmouthempton in order to celebrate their town’s success.
4.2 Assumptions and constraints
Following are the project assumptions:
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
5PROJECT ENVIRONMENT AND PLANNING
1. It is assumed that the project resources are manpower as well as materials. It is also
assumed that the human resources work for 40 hours per week on day shift. All the
materials required to complete the project is available.
2. The estimated project budget should meet with the actual cost of the project plan. It is
assumed that the total cost will not increase on daily basis. There are no such changes
into personnel cost, material cost and resource cost.
Following are the project constraints:
Design constraints: It includes of technology availability, design materials, specific
requirement of performance, site form and restrictions of planning in addition to building
regulations. When the design of the project work will not meet with the building plan, then it
becomes a constraint for the project plan.
Technical constraints: It consists of processes to complete the construction activities
such as building methods and construction standards. At the time of construction foundation, site
is leveled before excavation is taken place. Other constraints are tolerances related to
construction, available storage, site access routes and others.
Time constraints: It includes of project schedule and milestones. There should be proper
start of the project plan along with on time completion within scheduled date.
Economic constraints: It is related to the project budget along with resource allocation.
When the cost of the project plan becomes over budgeted, then it provides a negative impact on
the project success along with its quality.
5.0 Implementation and project schedule of the project
5.1 Gantt chart
The project is based on building of monuments in coastal town of Portmouthempton with
total duration of 523 days. The estimated start data is Tue 12/5/17 and end date is Thu 12/5/19.
Initiation phase takes of 227 days starts from Tue 12/5/17 to Wed 10/17/18. Planning phase takes
of total duration of 88 days starts from Thu 10/18/18 and ends in Mon 2/18/19. Execution phase
starts from Tue 2/19/19 to Wed 10/30/19 with total duration of 182 days. The final project phase
Document Page
6PROJECT ENVIRONMENT AND PLANNING
is closure phase with total duration of 26 days, from Thu 10/31/19 to Thu 12/5/19. Under the
initiation phase, there is development of project plan with duration of 74 days (from Tue 12/5/17
to Fri 3/16/18), Document review from 100 days (Mon 3/19/18-Fri 8/3/18), Bids and contracts
with duration of 53 days starts from Mon 8/6/18 to Wed 10/17/18. There are no sub-activities
under the planning phase. The execution phase has sub-activities of site work of 19 days (Tue
2/19/19- Fri 3/15/19), Foundation with 79 days (Mon 3/18/19- Thu 7/4/19), Electrical work of 47
days (from Fri 7/5/19 to Mon 9/9/19), Procurement is total duration of 27 days from Tue 9/24/19
to Wed 10/30/19. Finally, the closure phase has no such sub-activities.
Document Page
7PROJECT ENVIRONMENT AND PLANNING
Figure 1: Gantt chart
(Source: Created by author)
5.2 Project Milestones
Following are the project milestone activities with its expected start date as:
Milestone 1: Completion of initiation phase: 10/17/18
Milestone 2: Completion of planning phase: 2/18/19
Milestone 3: Completion of execution phase: 10/30/19
Milestone 4: Completion of closure phase: 12/5/19
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
8PROJECT ENVIRONMENT AND PLANNING
5.3 Project Deliverables
The list of project deliverables is:
I. Construction report of the twin monuments
II. Project proposal
III. Design drawings, documents
IV. Site investigation report
V. Technical report
VI. Strategic and progress status report
VII. Marketing study
VIII. Product prototype
IX. Improved in response procedures
X. Usability report
5.4 Work breakdown structure
The work packages for the project activities are shown as:
1. Initiation phase: It is the main activity and under this activity, the sub-activities are:
1.1 Development of project plan
1.1.1 Perform of the feasibility study
1.1.2 Appoint of the project team
1.1.3 Contracts
1.1.4 Agreement of supply construction
1.1.5 Supply contract plans
1.1.6 Secure the financing
1.2 Document review
1.2.1 Review of finalize plans
1.2.2 Review of finalize plans
Document Page
9PROJECT ENVIRONMENT AND PLANNING
1.2.3 Printing of construction drawings
1.2.4 Approve the plan
1.2.5 Architectural planning of the monuments
1.3 Bids and contracts
1.3.1 Making the copies of project plan
1.3.2 Distribution of project plan
1.3.3 Receive the bids
2. Planning phase: It is the main activity and under this activity, the sub-activities are:
2.1 Create of project plan
2.2 Create of resource plan
2.3 Financial plan
2.4 Risk plan
2.5 Communication plan
3. Execution phase: It is the main activity and under this activity, the sub-activities are:
3.1 Site work
3.2 Foundation
3.2.1 Layout footings
3.2.2 Inspection of the footings
3.2.3 Location survey
3.2.4 Layout and measure
3.3 Electrical work
3.3.1 Set the electrical boxes
Document Page
10PROJECT ENVIRONMENT AND PLANNING
3.3.2 Installation of electrical panel
3.4 Mechanical work
3.5 Procurement
3.5.1 Identify the supplier vendor
3.5.2 Supply of the raw materials
4. Closure phase: It is the main activity and under this activity, the sub-activities are:
4.1 Perform of project closure
4.2 Perform of stakeholder sign off
4.3 Final review of the project plan
4.4 Submission of project report
Building of monuments in
coastal town of
Portmouthempton
Initiation phase
Development of project
plan
Perform of the
feasibility study
Appoint of the
project team
Contracts
Agreement of supply
construction
Supply contract
plans
Secure the financing
Document review
Review of finalize
plans
Review the project
specifications
Printing of
construction
drawings
Approve the plan
Architectural
planning of the
monuments
Bids and contracts
Making the copies of
project plan
Distribution of
project plan
Receive the bids
Milestone 1:
Completion of
initiation phase
Planning phase
Create of project
plan
Create of resource
plan
Financial plan
Risk plan
Communication plan
Milestone 2:
Completion of
planning phase
Execution phase
Site work
Clear the road side
Foundation
Layout footings
Inspection of the
footings
Location survey
Layout and measure
Electrical work
Set the electrical
boxes
Installation of
electrical panel
Mechanical work Procurement
Identify the supplier
vendor
Supply of the raw
materials
Milestone 3:
Completion of
execution phase
Closure phase
Perform of project
closure
Perform of
stakeholder sign off
Final review of the
project plan
Submission of
project report
Milestone 4:
Completion of
closure phase
Figure 2: Work breakdown structure
(Source: Created by author)
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
11PROJECT ENVIRONMENT AND PLANNING
6.0 Stakeholder Analysis
The following are the stakeholders and its respective responsibilities are:
Project Manager:
Plan the entire project
Control the project schedule and cost (Coronel & Morris, 2016).
Deliver the project on time and run it on daily basis
Design and apply of project management standards in the construction project work
(Andersen, 2014).
Manage the production of the deliverables
Manage the project risks includes of contingency plans
Project Sponsor:
To collect of fund for the project plan (Maier & Branzei, 2014).
To estimate the entire project cost
Gather support for the project plan (Abdel Azeem, Hosny & Ibrahim, 2014).
Providing of project work statement
Providing of information regards to initial project scope (Galliers & Leidner, 2014).
Civil Engineer:
Preparing a blue print of the structure of twin monuments
Estimating the raw material required to build the monument
Design and plan the entire build up project (Burke, 2013).
Perform technical and feasibility study includes of site investigation
Resolve of design along with development issues
Document Page
12PROJECT ENVIRONMENT AND PLANNING
Mechanical Engineer:
Confirm the capabilities of product by perform of feasibility study
Prepare of product report (Goetsch & Davis, 2014).
Maintain of system in addition to product database (Davis, 2014).
Assure of quality of product by design of testing methods
Development of manufacturing processes by making modifications into equipments for
fabrication
Development of mechanical products by study of customer’s requirements (Eric
Kirkland, 2014).
Financial Manager:
Oversee of the cash flow as well as financial resources of the project
Plan and direct the activities of project workers
Prepare of reports as required by the regulations and construction policies (Kerzner,
2013).
Involve into capital budgeting and financing of the project plan
Determine the sources of the project funds and investment into the funds
Allocation of the funds into the project plan (Stark, 2015).
Understanding of the capital markets (Maier & Branzei, 2014).
Electrical Engineer:
Evaluate of the electrical system, components as well as applications by designing of the
electrical materials
Development of the electrical products by study on customer’s requirements (Randolph,
2014).