Replacing AC System in 20-Storey Commercial Building
VerifiedAdded on 2023/03/29
|19
|1508
|423
Project
AI Summary
This project outlines the replacement of an air conditioning system in a 20-story commercial building. It begins with meeting records, team responsibilities, and a project plan that includes background information, timeframes, and budget. The project details specifications such as project title, description, scope of work, and general and particular specifications. It also addresses contract time, cost, drawings, constraints, terminations, project acceptance, quality standards, working hours, and site constraints. Furthermore, it formulates three proposals: a contract-based approach, a self-labor approach, and a tender process. The project concludes with document evidences, final proposal meetings, and an evaluation recommending the contract proposal due to its cost-effectiveness and quality of HVAC technology. The project emphasizes the importance of proper planning, adherence to specifications, and the selection of the most suitable proposal for successful project completion.

Replace air-conditioning
system in 20 storey
commercial building.
system in 20 storey
commercial building.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Cont...
Content of meeting :-
It is important that all the data and information related with the
project should be performed properly so that the entire project
for replacing the air conditioning should be carried out
successfully. Meetings will be organised and discussions will
be made with the staff members so that required data and
information should be completed in proper way. Further all the
important points of the discussions will be noted down and
they will be properly recorded so that the while carrying out
the project it can be used in effective way.
Content of meeting :-
It is important that all the data and information related with the
project should be performed properly so that the entire project
for replacing the air conditioning should be carried out
successfully. Meetings will be organised and discussions will
be made with the staff members so that required data and
information should be completed in proper way. Further all the
important points of the discussions will be noted down and
they will be properly recorded so that the while carrying out
the project it can be used in effective way.

Cont...
Meeting's records :-
Initially the entire group will be divided into the group of 3 or 4
members and a person will be declared as a team leader.
Leader of team : Mao_Tse-tung
Members : Sun_Wen
Keeper of records : Zhao_Dao
2. Responsibilities :-
Team leader will be asked to lead the team and the person will be
made accountable for holding and organizing meetings with
the other team members. In addition to that the leader will be
directing the team and on the basis of that all the activities and
tasks of the team will be performed.
Meeting's records :-
Initially the entire group will be divided into the group of 3 or 4
members and a person will be declared as a team leader.
Leader of team : Mao_Tse-tung
Members : Sun_Wen
Keeper of records : Zhao_Dao
2. Responsibilities :-
Team leader will be asked to lead the team and the person will be
made accountable for holding and organizing meetings with
the other team members. In addition to that the leader will be
directing the team and on the basis of that all the activities and
tasks of the team will be performed.
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

Cont....
3. Plan discussion :-
Background : There is commercial building in the western area
of Hong Kong where the air conditioning systems have been
in use for more than 15 long years. As a result the system has
become defective thereby causing problems for people
working there.
Time needed for replacement : 3 months
Budget involved : 9 million
Next schedule of meeting
Date : 20 Nov 2017
Time : 13 :00
Venue : TBA
3. Plan discussion :-
Background : There is commercial building in the western area
of Hong Kong where the air conditioning systems have been
in use for more than 15 long years. As a result the system has
become defective thereby causing problems for people
working there.
Time needed for replacement : 3 months
Budget involved : 9 million
Next schedule of meeting
Date : 20 Nov 2017
Time : 13 :00
Venue : TBA
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

1.2 Specifications and Constraints of the
project
(a) Project Title :- Title of the project is Replacing Air
Conditioning system in 20 Storey Commercial building.
The project of replacing Air Conditioning system in 20 Storey
Commercial building is taken into consideration. It helps in
deep understanding of the project related to replacing the air
conditioner.
(b) Brief description
New technology is Opening ways for providing better and
effective services to various organizations that are operating.
project
(a) Project Title :- Title of the project is Replacing Air
Conditioning system in 20 Storey Commercial building.
The project of replacing Air Conditioning system in 20 Storey
Commercial building is taken into consideration. It helps in
deep understanding of the project related to replacing the air
conditioner.
(b) Brief description
New technology is Opening ways for providing better and
effective services to various organizations that are operating.

Cont...
(c) Scope of work
The project helps for designing an improved air conditioning
system in which high tech equipments will be used for
replacing the existing air conditioning system in the building.
(d) General specification:
A proper design specification is required so that air conditioning
system should be replaced. The entire process of replacing
could be broken down into three steps and it comprise of
1- Installing a proper air conditioning system in the 20 Story
commercial building.
2- Cost of planned Preventive maintenance.
3- Supplying and installing the air conditioning system in the
commercial organisation.
(c) Scope of work
The project helps for designing an improved air conditioning
system in which high tech equipments will be used for
replacing the existing air conditioning system in the building.
(d) General specification:
A proper design specification is required so that air conditioning
system should be replaced. The entire process of replacing
could be broken down into three steps and it comprise of
1- Installing a proper air conditioning system in the 20 Story
commercial building.
2- Cost of planned Preventive maintenance.
3- Supplying and installing the air conditioning system in the
commercial organisation.
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

Cont...
(e) Particular specification
Evidences will be collected for the design of the project and on
the basis of that entire air conditioning replacement system
will be executed. Details about company structure chart and
detailed information about the qualification of the personnel
should also be determined.
(f) Contract Time
Total contract time of this project is 2 Months and in this period
the entire project will be completed. It is critical that entire
activities of the project will be completed in due time so that
extra cost for implementing the project could be reduced
(e) Particular specification
Evidences will be collected for the design of the project and on
the basis of that entire air conditioning replacement system
will be executed. Details about company structure chart and
detailed information about the qualification of the personnel
should also be determined.
(f) Contract Time
Total contract time of this project is 2 Months and in this period
the entire project will be completed. It is critical that entire
activities of the project will be completed in due time so that
extra cost for implementing the project could be reduced
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Cont...
(g) Contract Cost
Total cost for completing the project has been estimated to be £
10000. The project for replacing the air conditioning system
will be given to a contracting organisation and the firm will be
given instructions for replacing the existing air conditioning
system in the firm.
(h) Any Standard Drawings
Project plan will be plotted on paper for how the plan will be
successfully executed in the 20 story Commercial buildings.
The entire plan was discussed with contractor and through
drawing a plan will show the location and connection of
equipment system involves in different elements which can be
manage using concept draw.
(g) Contract Cost
Total cost for completing the project has been estimated to be £
10000. The project for replacing the air conditioning system
will be given to a contracting organisation and the firm will be
given instructions for replacing the existing air conditioning
system in the firm.
(h) Any Standard Drawings
Project plan will be plotted on paper for how the plan will be
successfully executed in the 20 story Commercial buildings.
The entire plan was discussed with contractor and through
drawing a plan will show the location and connection of
equipment system involves in different elements which can be
manage using concept draw.

Cont...
(I) Constraints
There are several constraints that are faced while implementing
the project as per the plan and thus it will affect the overall
project that is being planned for changing the air conditioning
system used in the 20 Storey Commercial building. Total time
line for this project has been estimated to be 2 months and it is
vital that the project should be completed in this period of
time.
(j) Terminations : There are some condition on the basis of which
contract can be terminated by contractor or manager of 20
storey building.
(I) Constraints
There are several constraints that are faced while implementing
the project as per the plan and thus it will affect the overall
project that is being planned for changing the air conditioning
system used in the 20 Storey Commercial building. Total time
line for this project has been estimated to be 2 months and it is
vital that the project should be completed in this period of
time.
(j) Terminations : There are some condition on the basis of which
contract can be terminated by contractor or manager of 20
storey building.
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

Cont...
(k) Project acceptance : Acceptance of the project show the
gaining contractee approval. For the project acceptance it is
important to sign the contract by both the party. Further the
project can be accepted at the time when both the party accept
all the terms and condition of the project.
(l) Quality of standards
It is critical that proper quality of standards should be used so
that a very effective air conditioning system should be
implemented in the organisation. All standards for quality will
be used so that chances of failure and risks should be reduced
by adopting specific quality of standards.
(k) Project acceptance : Acceptance of the project show the
gaining contractee approval. For the project acceptance it is
important to sign the contract by both the party. Further the
project can be accepted at the time when both the party accept
all the terms and condition of the project.
(l) Quality of standards
It is critical that proper quality of standards should be used so
that a very effective air conditioning system should be
implemented in the organisation. All standards for quality will
be used so that chances of failure and risks should be reduced
by adopting specific quality of standards.
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Cont...
(m) Working Hours
Working hours for all the individuals that are associated with this
project will be determined so that all the individuals should be
given opportunity for completing the project on required time
interval.
(n) Site Constraints
The replacement of Air-conditioned system will be taking place
in the 20 Story commercial building and it will support for
completing the entire project on due time interval.
(m) Working Hours
Working hours for all the individuals that are associated with this
project will be determined so that all the individuals should be
given opportunity for completing the project on required time
interval.
(n) Site Constraints
The replacement of Air-conditioned system will be taking place
in the 20 Story commercial building and it will support for
completing the entire project on due time interval.

Cont...
(o) Other necessary Information
It is important that all the necessary data and information should
be available so that all the activities of the project should be
successfully implemented. In addition to that there are some
other necessary information which is required for completing
the project. Data and information will be collected from the
sources such as internet and other sources so that details about
all the equipments and machineries required for the project
could be gained. In addition to that information is also
required for completing the project on due time.
(o) Other necessary Information
It is important that all the necessary data and information should
be available so that all the activities of the project should be
successfully implemented. In addition to that there are some
other necessary information which is required for completing
the project. Data and information will be collected from the
sources such as internet and other sources so that details about
all the equipments and machineries required for the project
could be gained. In addition to that information is also
required for completing the project on due time.
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide
1 out of 19
Related Documents

Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
Copyright © 2020–2025 A2Z Services. All Rights Reserved. Developed and managed by ZUCOL.