Analysis of Concrete Floor Cycle in Project Management Report

Verified

Added on  2023/06/10

|11
|1469
|276
Report
AI Summary
Read More
tabler-icon-diamond-filled.svg

Contribute Materials

Your contribution can guide someone’s learning journey. Share your documents today.
Document Page
PROJECT MANAGEMENT AND SOFTWARE
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Implementations
Microsoft Project Software Implementations
This section represents the abilities of Microsoft Project software and defines the complete
structural construction programme for the selected trade package.
Complete Construction Programme
The complete tasks for the construction project are mentioned in the below table.
Task Name
Construction Floor Cycle Project
Gathering the Project Requirements
Analysis the Project Requirements
Pre construction of Construction Project
Prepare project contract Drawings
Permit Foundation for Project
Permit full building
Site utility relocation
Construction Project Procurement
Subcontractor bid
Interview period
Recommendation of subcontracts
Approval of subcontracts
Shoring and sheeting procurement
Other material procurement
Construction
Notice to proceed
Drill Dewatering Wells
Install Solider Piles, lagging and Tiebacks
Excavation
2
Document Page
Concrete Footings, Walls, Columns and Slab
Lift screens
Reinforce and form columns
Position forms for the band and
Perimeter beams
Form beams
Position metal deck
Reinforce including stressing
Cables
Concrete floor slab
Inspections & CloseOut
Weather Day Allowance
Commissioning & Training
Final Clean
Punch list Generation
O&M Manual Submission
Substantial Completion Process
Substantial Completion
Resources
Project’s resources are listed below.
Resource Name Type Initials Max.
Units Std. Rate Accrue
At
Base
Calendar
Project Executive Work P 100% $2,500.00/hr Prorated Standard
Senior Project Manager Work S 100% $3,000.00/hr Prorated Standard
Project Engineer Work P 100% $2,000.00/hr Prorated Standard
Project Admin Work P 100% $1,900.00/hr Prorated Standard
Project Accountant Work P 100% $1,500.00/hr Prorated Standard
3
Document Page
Project Scheduler Work P 100% $1,500.00/hr Prorated Standard
Senior Superintendent Work S 100% $2,000.00/hr Prorated Standard
Safety Manager Work S 100% $1,500.00/hr Prorated Standard
Layout Engineer Work L 100% $1,000.00/hr Prorated Standard
Unskilled Laborer Work U 100% $1,000.00/hr Prorated Standard
Equipment and Facilities Work E 100% $2,500.00/hr Prorated Standard
Contractor Work C 100% $1,000.00/hr Prorated Standard
Sub-Contractor Work S 100% $1,000.00/hr Prorated Standard
The overall construction project plan is shown below.
Task
Mode Task Name Duration Start Finish Predecessors Resource Names
Auto
Scheduled
Construction
Floor Cycle
Project
173
days
Fri
3/16/18
Tue
11/13/18
Auto
Scheduled
Gathering the
Project
Requirements
1 day Fri
3/16/18
Fri
3/16/18
Project Engineer, Project
Scheduler, Senior Project
Manager
Auto
Scheduled
Analysis the
Project
Requirements
2 days Fri
3/16/18
Mon
3/19/18
Project Engineer, Senior
Project Manager
Auto
Scheduled
Pre construction
of Construction
Project
10 days Fri
3/16/18
Thu
3/29/18
Layout Engineer, Project
Engineer, Senior Project
Manager
Auto
Scheduled
Prepare project
contract Drawings 2 days Fri
3/30/18
Mon
4/2/18 4
Equipment and Facilities,
Layout Engineer, Project
Engineer
Auto
Scheduled
Permit
Foundation for
1 day Tue
4/3/18
Tue
4/3/18
5 Equipment and Facilities,
Senior Project Manager,
4
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Project Senior Superintendent
Auto
Scheduled
Permit full
building 3 days Wed
4/4/18
Fri
4/6/18 6
Equipment and Facilities,
Project Engineer, Senior
Project Manager
Auto
Scheduled
Site utility
relocation 5 days Mon
4/9/18
Fri
4/13/18 7
Layout Engineer, Senior
Project Manager, Senior
Superintendent
Auto
Scheduled
Construction
Project
Procurement
14 days Mon
4/16/18
Thu
5/3/18 8
Auto
Scheduled
Subcontractor
bid 3 days Mon
4/16/18
Wed
4/18/18
Project Engineer, Senior
Project Manager, Sub-
Contractor
Auto
Scheduled
Interview
period 2 days Mon
4/16/18
Tue
4/17/18
Project Engineer, Senior
Project Manager
Auto
Scheduled Recommendation
of subcontracts
6 days Thu
4/19/18
Thu
4/26/18 10
Contractor, Project
Admin, Project
Executive, Senior Project
Manager
Auto
Scheduled
Approval of
subcontracts 1 day Mon
4/16/18
Mon
4/16/18
Project
Engineer[50%],Project
Scheduler[50%],Senior
Project Manager[50%]
Auto
Scheduled
Shoring and
sheeting
procurement
2 days Fri
4/27/18
Mon
4/30/18 12
Equipment and Facilities,
Layout Engineer, Senior
Project Manager, Senior
Superintendent
Auto
Scheduled
Other material
procurement 3 days Tue
5/1/18
Thu
5/3/18 14
Project Admin, Project
Engineer, Senior Project
Manager
5
Document Page
Auto
Scheduled Construction 106
days
Fri
5/4/18
Fri
9/28/18 9
Auto
Scheduled
Notice to
proceed 1 day Fri
5/4/18
Fri
5/4/18
Contractor, Equipment
and Facilities, Layout
Engineer, Senior Project
Manager, Senior
Superintendent
Auto
Scheduled
Drill
Dewatering Wells 30 days Mon
5/7/18
Fri
6/15/18 17
Contractor, Equipment
and Facilities, Project
Executive, Sub-
Contractor, Unskilled
Laborer
Auto
Scheduled
Install Solider
Piles, lagging and
Tiebacks
20 days Mon
6/18/18
Fri
7/13/18 18
Contractor, Equipment
and Facilities, Project
Executive, Sub-
Contractor, Unskilled
Laborer
Auto
Scheduled Excavation 10 days Mon
7/16/18
Fri
7/27/18 19
Equipment and Facilities,
Project Executive, Sub-
Contractor, Unskilled
Laborer
Auto
Scheduled
Concrete
Footings, Walls,
Columns and Slab
6 days Fri
5/4/18
Fri
5/11/18
Equipment and Facilities,
Project Engineer, Project
Executive, Sub-
Contractor, Unskilled
Laborer
Auto
Scheduled
Lift screens 12 days Fri
6/1/18
Mon
6/18/18
23 Equipment and Facilities,
Project Engineer, Project
Executive, Sub-
Contractor, Unskilled
6
Document Page
Laborer
Auto
Scheduled
Reinforce and
form columns 5 days Tue
6/19/18
Mon
6/25/18 24
Contractor, Equipment
and Facilities, Project
Engineer, Sub-
Contractor, Unskilled
Laborer
Auto
Scheduled
Position forms
for the band and 7 days Tue
6/26/18
Wed
7/4/18 25
Contractor, Equipment
and Facilities, Project
Engineer, Project
Executive, Safety
Manager
Auto
Scheduled
Perimeter
beams 8 days Thu
7/5/18
Mon
7/16/18 26
Equipment and Facilities,
Project Executive, Sub-
Contractor, Unskilled
Laborer
Auto
Scheduled Form beams 9 days Tue
7/17/18
Fri
7/27/18 27
Project Executive,
Project Scheduler, Sub-
Contractor
Auto
Scheduled
Position metal
deck 12 days Mon
7/30/18
Tue
8/14/18 28
Equipment and Facilities,
Layout Engineer, Project
Admin, Sub-Contractor
Auto
Scheduled
Reinforce
including stressing 8 days Wed
8/15/18
Fri
8/24/18 29
Project Engineer, Project
Executive, Sub-
Contractor
Auto
Scheduled Cables 10 days Mon
8/27/18
Fri
9/7/18 30
Equipment and Facilities,
Layout Engineer, Project
Accountant, Project
Engineer
Auto
Scheduled
Concrete floor
slab
15 days Mon
9/10/18
Fri
9/28/18
31 Contractor, Layout
Engineer, Project
7
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Executive, Project
Scheduler, Safety
Manager, Sub-
Contractor, Unskilled
Laborer
Auto
Scheduled
Inspections &
CloseOut 32 days Mon
10/1/18
Tue
11/13/18 32
Auto
Scheduled
Weather Day
Allowance 4 days Mon
10/1/18
Thu
10/4/18 10
Project Admin, Project
Engineer, Project
Executive, Project
Scheduler, Senior
Superintendent
Auto
Scheduled Commissioning &
Training
7 days Fri
10/5/18
Mon
10/15/18 34
Equipment and Facilities,
Project Engineer, Senior
Project Manager
Auto
Scheduled Final Clean 9 days Tue
10/16/18
Fri
10/26/18 35
Contractor, Equipment
and Facilities, Project
Admin, Unskilled
Laborer
Auto
Scheduled
Punch list
Generation 4 days Mon
10/29/18
Thu
11/1/18 36
Contractor, Layout
Engineer, Project
Engineer, Project
Executive, Sub-
Contractor
Auto
Scheduled
O&M Manual
Submission 6 days Fri
11/2/18
Fri
11/9/18 37
Layout Engineer, Senior
Project Manager, Senior
Superintendent, Project
Admin
Auto
Scheduled
Substantial
Completion
1 day Mon
11/12/18
Mon
11/12/18
38 Project Accountant,
Project Admin, Senior
8
Document Page
Process Project Manager, Senior
Superintendent
Auto
Scheduled
Substantial
Completion 1 day Tue
11/13/18
Tue
11/13/18 39
Project Admin, Project
Executive, Project
Scheduler, Senior Project
Manager, Senior
Superintendent
Work Breakdown Structure
Work breakdown structure represented as shown below.
Timing required for the Project Completion
The time required to finish this construction project is 153 days.
Project Cost
The overall project cost is as shown below.
9
Document Page
Name Remaining Cost Actual
Cost
Cost ACWP BCWP BCWS
Construction
Floor Cycle
Project
$13,544,400.00 $0.00 $13,544,400.00 $0.00 $0.00 $0.00
Construction Floor Cycle Project
$0.00
$2,000,000.00
$4,000,000.00
$6,000,000.00
$8,000,000.00
$10,000,000.00
$12,000,000.00
$14,000,000.00
$16,000,000.00
Actual Cost Remaining Cost Baseline Cost
The above graph depicts the cost of the whole project.
Cost of the Resources
The total cost of the resources cost are presented in the following table.
Name Actual Work Actual Cost Standard Rate
Project Executive 0 hrs $0.00 $2,500.00/hr
Senior Project Manager 0 hrs $0.00 $3,000.00/hr
Project Engineer 0 hrs $0.00 $2,000.00/hr
Project Admin 0 hrs $0.00 $1,900.00/hr
10
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Project Accountant 0 hrs $0.00 $1,500.00/hr
Project Scheduler 0 hrs $0.00 $1,500.00/hr
Senior Superintendent 0 hrs $0.00 $2,000.00/hr
Safety Manager 0 hrs $0.00 $1,500.00/hr
Layout Engineer 0 hrs $0.00 $1,000.00/hr
Unskilled Laborer 0 hrs $0.00 $1,000.00/hr
Equipment and Facilities 0 hrs $0.00 $2,500.00/hr
Contractor 0 hrs $0.00 $1,000.00/hr
Sub-Contractor 0 hrs $0.00 $1,000.00/hr
$0.00
$500,000.00
$1,000,000.00
$1,500,000.00
$2,000,000.00
$2,500,000.00
$3,000,000.00
$3,500,000.00
Actual Cost Remaining Cost Baseline Cost
The above graph depicts the cost of the whole project.
11
chevron_up_icon
1 out of 11
circle_padding
hide_on_mobile
zoom_out_icon
logo.png

Your All-in-One AI-Powered Toolkit for Academic Success.

Available 24*7 on WhatsApp / Email

[object Object]