This assignment presents a comprehensive construction project management plan for a bus repair facility in Loganholme, Qld, based on provided architectural plans. It includes a thorough review of the site and architectural plans, detailing requirements for structural, mechanical, and electrical layouts. The project encompasses an itemized task list, a detailed work breakdown structure (WBS), resource estimations, and cost allocations for each activity. Furthermore, the assignment employs project management tools such as PDM diagrams, Gantt charts, resource analysis with histograms, and discusses strategies for optimal resource utilization. A cost estimate, including all relevant costs like site establishment, materials, labor, and overheads, is also provided. The project emphasizes the importance of efficient project management techniques in the construction industry, covering all stages from planning to execution and post-project activities.
Document Page
CONSTRUCTION PROJECT MANAGEMENT FOR ‘BUS REPAIR FACILITY
Construction Project Management for ‘Bus Repair
Facility
Student name
Institution affiliation
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
CONSTRUCTION PROJECT MANAGEMENT FOR ‘BUS REPAIR FACILITY
2
Table of Contents
Figure 1 site plan review.......................................................................................................2
Figure 2 first floor plan snapshot, from CIC architectural plans provided..............................2
Figure 3 sample electrical components on the plans............................................................2
Figure 4 work breakdown structure for the project, formatting not clear due to page and cell
sizes, clear copy with full boxes provided in a different file as attached................................2
Introduction.................................................................................................................................. 3
Review of the provided plans in Loganholme, Qld for bus repair facility......................................3
Review of site plan................................................................................................................... 4
Review of architectural plans...................................................................................................5
Structural plans review.............................................................................................................8
Mechanical and electrical layouts review on plan.....................................................................8
Electrical plans review........................................................................................................10
Itemized list of the tasks required for constructing bus repair facility and its surroundings.........11
Project work breakdown structure..............................................................................................11
Bus repair Project management tools........................................................................................13
Figure 1 site plan review.............................................................................................................. 4
Figure 2 first floor plan snapshot, from CIC architectural plans provided.....................................5
Figure 3 sample electrical components on the plans.................................................................10
Figure 4 work breakdown structure for the project, formatting not clear due to page and cell
sizes, clear copy with full boxes provided in a different file as attached.....................................13
Table 1 Gant chart table showing, deadlines, cost of detailed materials and resources, required
personnel, who does the work...................................................................................................14
Table 2 MS word PDM, check for ES, LS and floats for all time analysis, file too large to be
reported in word document........................................................................................................28
Table 3 cash flow diagram, check MS project file......................................................................29
Table 4 resource histogram.......................................................................................................29
Document Page
CONSTRUCTION PROJECT MANAGEMENT FOR ‘BUS REPAIR FACILITY
3
Introduction
Construction Management (CM) is a professional service devoted to oversight of project
planning, design and construction from start to finish by using advanced project
management techniques. The goal is to monitor time ,cost and performance of projects
— including project execution, design-build, CM At-Risk and Public Private
Partenariates, which can also include project management and project bid management
triangles or' triple constraints.' CM is compatible with all projects delivery systems.
In every company, project management is implemented in all industries (Cha & Kim,
2013). There's no difference in the building industry. Building managers combines
regular project manager's duties and source expertise to perform project management.
Construction administration generally has the following functions:
a. Description of project goals and plans, including range identification, budgeting,
planning, performance criteria specification and project participant choice.
b. Maximize resource productivity by purchasing manpower, equipment and
materials.
c. Implementing different operations by proper coordination and control of the entire
process, including scheduling, design, evaluation, contracting and construction.
d. Efficient communications and conflict resolution mechanisms are established.
Review of the provided plans in Loganholme, Qld for bus repair facility
The analysis of code criteria such as minimum building type, preliminal means for
egress, building of fire resistance specifications, layout of foundations and fire protection
systems requirements is the first phase of the project review. The entire package can be
re-entered for a full Final Building Plan Review once the project drawings and
requirements are completed. If a complete set of building plans and requirements is not
available, you may want to request a CCIS Preliminary construction review to Fastrack
the projects and others managerial activities, such as permit application for a foundation
permit.
The following requirements, sketches and descriptions should be given in order to
complete a thorough review of the building plan.
1. Architectural plans
2. Structural plans
3. Site plan
Document Page
CONSTRUCTION PROJECT MANAGEMENT FOR ‘BUS REPAIR FACILITY
4
4. Materteral description of all the works to be done
The above requirements should satisfy all the building codes, complete,
authenticated by relevant bodies or engineers, and should be sealed.
Review of site plan
Figure 1 site plan review
Scale and location of all new buildings and all current site structures have been
provided. Lot rows lengths given . The street grades have been developed and the
grades proposed.
A licensed architect, landscape architect, builder, surveyor or designer shall seal the
drawings in respect of their expertise
The plans of the site must be drawn to the engineer’s scale as shown on project
plan.
Elevations and heights of the building can be built to the level of the architect.
The person or company responsible for the preparation of the letter, name,
telephone and fax numbers, and contact information must be included in site
plan.
North arrow, distance, date.
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
CONSTRUCTION PROJECT MANAGEMENT FOR ‘BUS REPAIR FACILITY
5
Devolution name(s) in the title block, on the cover sheet, and each after sheet, if
necessary, national identity numbers.
Data on land, including an adjacent map, legal description and, where
applicable, general description of deed limitations provided.
Review of architectural plans
The plan of the architectural floor determines the planned configuration of the
workspace. The plan shows circulation routes to and within the egress space and paths.
Indicate all existing and new partitions and doors, built in case work, furniture, monitors
and permanent floor space equipment: caps, tanks, chemical storage cases. Indicate all
old, new and existing partitions and doors.
It should Specify which items (where applicable) are to be accessible such as labs,
kitchens, etc.
Figure 2 first floor plan snapshot, from CIC architectural plans provided
a. Building style proposed for the house
b. Suitable information and sizes for determining exit modes, including floor loads,
exit design and sizes, halls, gates have been provided
c. Evacuation signs / means, have not been indicated on this plan
d. Description and uses for all areas of the building and the proposed group(s). The
definition of mixed applications (as applicable) have been provided
e. Fully sized drawings to define areas and the height of the house provided.
f. Provisions of access.
g. Definition and descriptions of special arrangements planned, such as a mall
elevated, high-rise, mezzanine, atrium, public garage, etc.
h. Sufficient information, with data that support required scores, to determine fire
resistive construction specifications.
i. Plastic measurements, reinforcement and installation of safety glazing.
Document Page
CONSTRUCTION PROJECT MANAGEMENT FOR ‘BUS REPAIR FACILITY
6
j. Fire protection systems information needed
Compliance notes for the project are listed below.
Document Page
CONSTRUCTION PROJECT MANAGEMENT FOR ‘BUS REPAIR FACILITY
7
Site notes Rules, standards and general notes
concrete construction ¿ comply withas 2870.1as 3600.
termite treatment ¿ comply withthe provisions of
part 3.13 of the bcawithas 3660.1
timber construction¿ comply with as 1684.2 ,
steel roofing ¿ comply withas 1562.1 .
steel roof ¿ accordance withthe manufacturers
specifications for the noted conditions .
roof tiles¿ comply with as 2049as 2050.
tiled roof ¿ accordance withthe manufacturers
specifications for the noted conditions .
wet areas ¿ comply withbca 3.8 .1 , volii .
weepholes masonry walls at 900 crs .
glass installation ¿ comply with as 1288as 2047.
denotes smoke detector ; smoke alarms ¿ comply with
the provisions of part 3.7 .2 of the bca .
manhole position. only¿ be determined on site .
provide alcor barrier between lead flashingzincalume
valley as required .
hwc ¿ be kept 100 mm away ¿ walls.
protection of masonry wallties ¿ comply with the
provisions of part 3.3.3 .2 of the bca .
protection of lintelsmasonry ¿ comply withthe
provisions of part 3.3.3 .4 of the bca .
vertical articulation joints ¿ comply withthe provisions
of part 3.3 .1.8 of the bca .
downpipes ¿ comply as/ nzs 3500.3.2as / nz 3500.5 .
green efficient hot water systems ¿ comply withbca
sustainable building practices .
aaa rated shower headsreticulated town water ¿
comply with bca sustainable building practices.
energyefficient lighting ¿
fluorescent ¿ be used ¿ illuminate at least 40 % of internal
floor space ¿dual flush toilets
water pressure limiting devices ¿ restrict maximum
water pressure ¿ no more than500 kilopascals.
hot water reticulation shall be temperature controlled
¿ 50 ° celsiusbelow ,¿ baths , showersbasins¿
accordance with as .3500
the building code of australia(bca)relevant amendments
¿ updates ,including the standards association of aust .
(as ). codes shall be the minimum standards for compliance .
ˇall dimensions of sitebuilding set out plans¿
ˇagainst surveyors site set out . clarify any
discrepancy ¿ noted dimensionsoffsets prior ¿
construction of any work . ensure surveyors work relates
¿ current site field worknot complied vide title .
noted dimensions shall take precedence ¿ scaled
dimensions .
ˇhydraulicmechanical plans for set out¿
sizing of service ducts where applicable .
coordinate all consultantsdocumentsbringany
discrepancies ¿ the attention of the relevant
consultants prior ¿ the construction of that part of the
works .
ˇon siteopenings before fabrication of doors ,
windowsany other fixtures . givensizes are for quotation
purposes onlymust be confirmed on site .
ˇthe construction planis the most recent
amendment .if doubt confirm withrelevant consultant .
refer specific conditions of building approval for any
additional requirements .
ensure doors ¿ sanitary compartments comply withthe
building code of australia f 2.5have either :
a ¿ lift off hinges for inward swinging doors¿
b ¿ outwards swinging doors .
all areasunder building work ¿ be protected ¿
termite attack accordance withan approved method
under a . s .3660 .1
timber framing shall be accordance withthe building
code of australia(bca) plus all amendments ,the' light
timber framing code ' a . s .1684 , part 2 for noncyclonic area
¿ a . s .1684 part 1 for cyclonic areas
Structural plans review
The structural project plans have not been provided. However, for smooth and
successful project completion, the requirements for the structural design are as listed
below.
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
CONSTRUCTION PROJECT MANAGEMENT FOR ‘BUS REPAIR FACILITY
8
a. Report of soils showing type of soil and suggested type of load and base
b. Criteria for localized model load, with depth of frost.
c. Fundamental and superstructure details.
d. Special inspection criteria.
e. The building and material requirements are valid (e.g. masonry, concrete, stone,
iron, etc.).
f. Signed and sealed measurements of architectural structures matching the
members ' sizes
g. Seismic earthquake area / effective coefficient of peak acceleration.
Mechanical and electrical layouts review on plan
The design submission explains how these systems interact with available building
services and how they are operated by all mechanical systems proposed. Exceptional
development parameters (e.g. humidity, particle control, etc., strict temperature
regulation) should be quantified.
The following requirements, diagrams and descriptions must be submitted for a detailed
review of the Mechanical Plan: full models signed and sealed and specifications
covering all heating, air-conditioning and ventilation activities. Criteria for marking all
equipment.
Information on heating equipment with details as follows:
Capability of machinery (b.t.u.).
Reviews. Checks.
The location, access and clearance configuration of the equipment.
Switches to break.
Project temperatures both indoor and outdoor.
Information about ventilation, ductwork and appliances including:
The air valve system (in c.f.m.) supplied in each room or space shows the
volume of outside air.
External air intakes format.
Installation of ducts including the size of supports and plates.
Piping and fire spread protection materials and smoke-developed ratings.
Document Page
CONSTRUCTION PROJECT MANAGEMENT FOR ‘BUS REPAIR FACILITY
9
Duct configuration and start to the outside of exhaust fan.
Width of the attic ventilation grids and louvers.
Position of equipment and approximate size
Full-line diagrams and approximate width of ducts.
Provisional sizing and tubing races.
Building envelope penetration, sources of external air
Connection points of existing services: air control pneumatics, drains, fuel,
cooling water, steam.
Existing services incorporation.
Thermostats and control devices physical location
Electrical plans review
The design submission will detail the interface these systems with the existing building
infrastructure for all planned electrical systems.
Document Page
CONSTRUCTION PROJECT MANAGEMENT FOR ‘BUS REPAIR FACILITY
10
Figure 3 sample electrical components on the plans
Physical location of the new panel, power supply Preliminary localization of new
electricity supply , Description of the types of light fixtures / lamps / ballast ,List of
electrical power supply equipment and operational ampere.
Fire alarm, panel location, (confirm the fire alarm system's capability to use additional
devices)
Itemized list of the tasks required for constructing bus repair facility and its
surroundings
The Building Manager is responsible for supervising the design from beginning to end.
Depending on the project size and complexities, they can individually manage or
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
CONSTRUCTION PROJECT MANAGEMENT FOR ‘BUS REPAIR FACILITY
11
collaborate with other building managers. We prepare, budget and supervise
development. It is the responsibility. We will have to determine during the planning
process what resources to use, how to assign staff and build a project schedule. You
have to interact regularly with everyone else on the plan and the customer. They are
always on-call, as if anything goes wrong with the plan, it is their duty. Because of the
variety of jobs in a construction manager, a number of people have advantages in
implementing cloud-based software that helps them prepare, execute and connect from
start to finish.
The following list of activities summarizes the main tasks to be done ins constructing
the building and its surrounding.
Processing of land acquisition, holding, or land and upgrading.
Studies in planning and feasibilities.
Engineering and architectural design.
Building, including construction materials, machinery, and labour.
Financing of construction.
Land insurance and taxes
Owner's general office overhead
Not included in construction equipment and furnishings.
Testing and inspection.
Project work breakdown structure
A project structure (WBS) is a product-oriented or deliverable grouping of project work
elements displayed in the graphic display to organize and subdivide the overall project
work context. The WBS is a task tool of particular importance. Design and
implementation should be considered and designed to avoid future changes. Because
of its scope to a wide range of projects activities, major evaluations of a WBS involve
both considerable effort and resources. WBSs for projects guided by a project context
should not be confused for other WBS-like systems. A WBS is the key to effective
project management, implementation ,tracking, statusing and monitoring. All the work in
the WBS should be defined, measured, scheduled and cost allocated. The WBS is the
framework and code for all project work (scope, timing, and cost). The WBS therefore
includes the basic size of the project required to achieve the defined technical goals of
the work. WBS is used as a tool for defining, assigning and tracking the entire scope of
work throughout the life cycle of the project.
Document Page
CONSTRUCTION PROJECT MANAGEMENT FOR ‘BUS REPAIR FACILITY
12
WORK BREAKDOWN STRUCTURE FOR BUS REPAIR
CONSTRUCTION PROJECT
Bus Repair Facility CI
C
PROJECT MANAGER
s
s
Bus repair facility Construction
Project
Project
idealization
(2000)
project
specifica
tions
and
definitio
Develo
p
project
manag
ement
tool
contractors
tendering
($2000)
Actual
Construction
($ 60000)
Project
Close/Post
Project ($
2000 )
site
cleaners
( asbesto
s, bushes
and
remainin
provision
of
complete
detailed
drawings
choose
tenderes
-
mechanic
al works,
Switch
off heat
Certify
all areas
clear
a
ll
f
i
n
Ass
ess
the
deli
vera
bles
Proj
ect
rep
ort
Aw
ard
of
cert
ific
Con
trac
tor
de
mo
submit
results
cost
olan,
project
plan
generat
short
brief,
busines
s
implicati
project
activity
checklist
all
drawin
gs-
schedu
ling
works
superstruct
ure
constructio
n-
walls,struct
surveying,
foundation
works -
earthwork
s, slabs
absetos
remove
d, soils
aprove
d and
End reports
Contractor
mobilization
supply of
construction