This final project report, focusing on the construction of a residential complex in Queensland, Australia, details the project's time and cost planning. It includes a comprehensive project activity list, task dependencies, and activity sequencing, crucial for effective project management. The report outlines resource requirements, activity durations, and the creation of a bar chart and critical path network to visualize the project timeline. It predicts the project's completion date and addresses resource allocation challenges. Furthermore, the report utilizes MS-Project to generate computer outputs, aiding in the alignment of the construction project plan. The project follows traditional agile methodology to ease construction activities and ensure effective operations. The report covers the project scope, objectives, milestones, limitations, assumptions, and constraints, providing a complete overview of the project's lifecycle. The report shows the activities, predecessors, and successors of the project in a tabular form.
Document Page
1FINAL PROJECT REPORT
Final Project Report:
Construction of Residential Complex in Queensland, Australia (Part B)
Name of the Student:
Student ID:
Name of the University:
Author’s note:
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
2FINAL PROJECT REPORT
Table of Contents
Part B: Project Cost and Time Plan.................................................................................................3
Introduction..................................................................................................................................3
1. Time and Cost Planning of the case project............................................................................3
1.1 Project Activity List...........................................................................................................3
1.2 Project Task Dependencies and Activity Sequence...........................................................6
2.3 Resource Requirements of the Project.............................................................................10
2.4 Duration of each activity of the Project...........................................................................13
2.5 Bar Chart and Critical Path Network of the Project........................................................16
2.6 Prediction of the Project Completion Date......................................................................18
2.7 Resource Profile of Project and Solving Over-allocation................................................18
2.8 Computer Output of the Project.......................................................................................20
Conclusion.................................................................................................................................25
Bibliography..............................................................................................................................26
Document Page
3FINAL PROJECT REPORT
Part B: Project Cost and Time Plan
Introduction
The construction projects are developed for the implication of the operations for the
deployment of the effective construction activities. The development of the final project
deliverable is based on the development of the finite project deliverable. The project completion
would help in yielding the effective and improved operations (Sahebjamnia, Torabi & Mansouri,
2015). The construction project would yield in using the concepts of project management for
developing the final project.
The following assignment comprises of project tender documentation that would provide
a detailed explanation of the project scope statement. The implication of the project development
report would form the overview of the project boundaries, objectives, milestones, and project
limitations. The review with the customer is another major element present in the project report.
The report would provide the brief of the project assumptions and constraints.
The project scheduling for residential complex construction project is developed by
listing the activities that would be carried on within the project. The activities would allow the
formation of the dependencies and the resource alignment. The completion of the activities,
sequencing them, and adding resources to the project would tend to form the final project plan.
The report would help in easing the flow of information and aligning the final project delivery.
The use of Ms-Project would be helpful for the alignment of the construction project plan. It
would list the project activities in a table and a timeline too.
1. Time and Cost Planning of the case project
1.1 Project Activity List
The project activity list is developed for forming the effective calculation of the project
schedule and the development of the final project deliverable for the alignment of the operations
and forming support for the integration of the operations (Larson & Gray, 2013). The project of
Construction of Residential Complex in Queensland, Australia is a construction project and the
traditional agile methodology is followed for making the project. The implication of agile
methodology would help in easing the construction activities of the project. The implication of
project activities would be helpful for the deployment of the construction activities in more
sequential and effective operations. The project activities had been formed considering the
Document Page
4FINAL PROJECT REPORT
development of the project activities and alignment of the improved operations (Matsuo &
Nakahara, 2013). The following table would show the list of activities of the project of
Construction of Residential Complex in Queensland, Australia,
Work Package Sub-work packages Activities
Project Initialization
NA Analysis of requirements
NA Development of project tender form
NA Submission and approval of the tender
form
NA Applying for permits of construction
NA Securing foundation permit, electrical
permit, and plumbing permit
Planning and Initial
Documentation
NA Resource Analysis and Accumulation
NA Listing required activities of the
project
NA Developing Project Schedule
NA Assigning resources to the activities
NA Project Charter is formed
NA Project Initiation document is formed
Design Development
NA Hiring an architect for the building
design
NA Forming an outline of building design
NA Review of the design outline
NA Completion of the residential building
complex design
NA Feasibility analysis of the complete
design
NA Approval of the design
Site Work
Site clearing and grubbing
Installing temporary power and
groundwork utilities
Excavation of foundations
Development of basement walls
Adding concrete and cementing the
basement structure
Backfilling the foundation
Infrastructure
development
Installation of 1st floor joists and
decking
Installation of 2nd floor joists and
decking
Installation of 3rd floor joists and
decking
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
5FINAL PROJECT REPORT
Construction Activities
Installation of 4th floor joists and
decking
Installation of 5th floor joists and
decking
Complete Roof Framing and decking
Partitioning of floors in flat structure
Completing remaining brick works
Windows and doors are added
Plumbing line is installed
Main Electric lining is done
Phone wires are installed
Interior Final works
Insulation of the walls and ceiling
Installing drywalls
Paintings and wallpaper works from
internal
Texture is also added to required
walls
Cabinet works in kitchen, bedroom,
hall, bathroom, and balcony
Carpets and Tiles are laid
External Final works
Main gate is made
Painting of the building from outside
Fencing the building
Laying of grass surrounding the
building
Making passage way for vehicles
Installing Mailboxes
Security Cameras are installed
Fire Extinguishers are installed
Addition of appliances
and equipments
Bathroom Equipments are added
Kitchen Appliances are added
Beds, Chairs, Dining table, Sofa, and
side tables are added
Fans, Lights, Air conditioners, and
Room heaters are added
Inspection Activities
NA Site is inspected
NA Inspection of infrastructure
NA Electrical Line Inspection
NA Plumbing line Inspection
NA Appliances installed are inspected
NA Final walk-through Inspection
Document Page
6FINAL PROJECT REPORT
Closure
NA Developing final checklist
NA All inspection results are documented
NA Final Report is made
NA Sign off the final report
NA Project is Closed
Table 3: Project Activity List
(Source: Created by the author)
1.2 Project Task Dependencies and Activity Sequence
The project task dependency can be shown with the help of WBS predecessors and WBS
successors and their relation (Kuster et al., 2016). The following table would show the elements
of WBS ID, task name, WBS predecessors, and WBS Successors. It would help in listing the
activities of the project and showing the predecessors and successors of the task. The activities
would be sequentially arranged for the alignment of the final project deliverable. The task
dependency for the project of Construction of Residential Complex in Queensland, Australia is
shown in the table below,
WBS Predecessors WBS Task Name WBS
Successors
0 Construction of Residential Complex in
Queensland, Australia
1 Project Initialization
1.1 Analysis of requirements 1.4
2.1 1.2 Development of project tender form 1.3
1.2 1.3 Submission and approval of the tender form 3.1
1.1 1.4 Applying for permits of construction 1.5
1.4 1.5 Securing foundation permit, electrical permit,
and plumbing permit 2.1
2 Planning and Initial Documentation
1.5 2.1 Resource Analysis and Accumulation 1.2, 2.2
2.1 2.2 Listing required activities of the project 2.3
2.2 2.3 Developing Project Schedule 2.4
2.3 2.4 Assigning resources to the activities 2.5
2.4 2.5 Project Charter is formed 2.6
2.5 2.6 Project Initiation document is formed
3 Design Development
1.3 3.1 Hiring an architect for the building design 3.2
3.1 3.2 Forming an outline of building design 3.3
Document Page
7FINAL PROJECT REPORT
3.2 3.3 Review of the design outline 3.4,4.1.1
3.3 3.4 Completion of the residential building complex
design 3.5
3.4 3.5 Feasibility analysis of the complete design 3.6
3.5 3.6 Approval of the design
4 Construction Activities
4.1 Site Work
3.3 4.1.1 Site clearing and grubbing 4.1.2,4.1.5
4.1.1 4.1.2 Installing temporary power and groundwork
utilities 4.1.3
4.1.2 4.1.3 Excavation of foundations 4.1.4
4.1.3 4.1.4 Development of basement walls
4.1.1 4.1.5 Adding concrete and cementing the basement
structure 4.1.6
4.1.5 4.1.6 Backfilling the foundation 5.1,4.2.1
4.2 Infrastructure development
4.1.6 4.2.1 Installation of 1st floor joists and decking 4.2.2
4.2.1 4.2.2 Installation of 2nd floor joists and decking 4.2.3,4.2.11
4.2.2 4.2.3 Installation of 3rd floor joists and decking 4.2.4,4.2.10
4.2.3 4.2.4 Installation of 4th floor joists and decking 4.2.5
4.2.4 4.2.5 Installation of 5th floor joists and decking 4.2.6,4.2.8
4.2.5 4.2.6 Complete Roof Framing and decking 4.2.7
4.2.6 4.2.7 Partitioning of floors in flat structure 4.3.5
4.2.5 4.2.8 Completing remaining brick works 4.2.9,4.3.1
4.2.8 4.2.9 Windows and doors are added 4.4.5,5.2
4.2.3 4.2.10 Plumbing line is installed 4.2.12,4.5.1,5.4
4.2.2 4.2.11 Main Electric lining is done 5.3
4.2.10 4.2.12 Phone wires are installed 4.3.1
4.3 Interior Final works
4.2.12,4.2.8 4.3.1 Insulation of the walls and ceiling 4.3.2
4.3.1 4.3.2 Installing drywalls 4.3.3,4.4.1
4.3.2 4.3.3 Paintings and wallpaper works from internal 4.3.4
4.3.3 4.3.4 Texture is also added to required walls 4.4.2
4.2.7 4.3.5 Cabinet works in kitchen, bedroom, hall,
bathroom, and balcony 4.3.6
4.3.5 4.3.6 Carpets and Tiles are laid 4.5.3
4.4 External Final works
4.3.2 4.4.1 Main gate is made 4.4.3
4.3.4 4.4.2 Painting of the building from outside
4.4.1 4.4.3 Fencing the building 4.4.4
4.4.3 4.4.4 Laying of grass surrounding the building
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
8FINAL PROJECT REPORT
4.2.9 4.4.5 Making passage way for vehicles 4.4.6,4.4.7
4.4.5 4.4.6 Installing Mailboxes
4.4.5 4.4.7 Security Cameras are installed 4.4.8
4.4.7 4.4.8 Fire Extinguishers are installed 4.5.2
4.5 Addition of appliances and equipments
4.2.10 4.5.1 Bathroom Equipments are added 5.5
4.4.8 4.5.2 Kitchen Appliances are added 4.5.4,5.5
4.3.6 4.5.3 Beds, Chairs, Dining table, Sofa, and side
tables are added 5.5
4.5.2 4.5.4 Fans, Lights, Air conditioners, and Room
heaters are added 5.5,5.6
5 Inspection Activities
4.1.6 5.1 Site is inspected
4.2.9 5.2 Inspection of infrastructure
4.2.11 5.3 Electrical Line Inspection
4.2.10 5.4 Plumbing line Inspection
4.5.1,4.5.2,4.5.3,4.5.4 5.5 Appliances installed are inspected
4.5.4 5.6 Final walk-through Inspection 6.2,6.1
6 Closure
5.6 6.1 Developing final checklist
5.6 6.2 All inspection results are documented 6.3
6.2 6.3 Final Report is made 6.4
6.3 6.4 Sign off the final report 6.5
6.4 6.5 Project is Closed
Table 4: Dependencies of the Project Activities
(Source: Created by the author)
The task dependency for the activities of the project of Construction of Residential
Complex in Queensland, Australia can be shown in the following diagram below,
Document Page
9FINAL PROJECT REPORT
0 - Construction of Residential Complex in Queensland, Australia
1 - Project Initialization
1.1 - Analysis of requirements 1.2 - Development of project tender form 1.3 - Submission and approval of the tender form 1.4 - Applying for permits of construction 1.5 - Securing foundation permit, electrical permit, and plumbing permit
2 - Planning and Initial Documentation
2.1 - Resource Analysis and Accumulation 2.2 - Listing required activities of the project 2.3 - Developing Project Schedule 2.4 - Assigning resources to the activities 2.5 - Project Charter is formed 2.6 - Project Initiation document is formed
3 - Design Development
3.1 - Hiring an architect for the building design 3.2 - Forming an outline of building design 3.3 - Review of the design outline 3.4 - Completion of the residential building complex design 3.5 - Feasibility analysis of the complete design 3.6 - Approval of the design
4 - Construction Activities
4.1 - Site Work
4.1.1 - Site clearing and grubbing 4.1.2 - Installing temporary power and groundwork utilities 4.1.3 - Excavation of foundations 4.1.4 - Development of basement walls 4.1.5 - Adding concrete and cementing the basement structure 4.1.6 - Backfilling the foundation
4.2 - Infrastructure development
4.2.1 - Installation of 1st floor joists and decking 4.2.2 - Installation of 2nd floor joists and decking 4.2.3 - Installation of 3rd floor joists and decking 4.2.4 - Installation of 4th floor joists and decking 4.2.5 - Installation of 5th floor joists and decking 4.2.6 - Complete Roof Framing and decking 4.2.7 - Partitioning of floors in flat structure 4.2.8 - Completing remaining brick works 4.2.9 - Windows and doors are added 4.2.10 - Plumbing line is installed 4.2.11 - Main Electric lining is done 4.2.12 - Phone wires are installed
4.3 - Interior Final works
4.3.1 - Insulation of the walls and ceiling 4.3.2 - Installing drywalls 4.3.3 - Paintings and wallpaper works from internal 4.3.4 - Texture is also added to required walls 4.3.5 - Cabinet works in kitchen, bedroom, hall, bathroom, and balcony 4.3.6 - Carpets and Tiles are layed
4.4 - External Final works
4.4.1 - Main gate is made 4.4.2 - Painting of the building from outside 4.4.3 - Fencing the building 4.4.4 - Laying of grass surrounding the building 4.4.5 - Making passage way for vehicles 4.4.6 - Installing Mailboxes 4.4.7 - Security Cameras are installed 4.4.8 - Fire Extinguishers are installed
4.5 - Addition of appliances and equipments
4.5.1 - Bathroom Equipments are added 4.5.2 - Kitchen Appliances are added 4.5.3 - Beds, Chairs, Dining table, Sofa, and side tables are added 4.5.4 - Fans, Lights, Air conditioners, and Room heaters are added
5 - Inspection Activities
5.1 - Site is inspected 5.2 - Inspection of infrastructure 5.3 - Electrical Line Inspection 5.4 - Plumbing line Inspection 5.5 - Appliances installed are inspected 5.6 - Final walk-through Inspection
6 - Closure
6.1 - Developing final checklist 6.2 - All inspection results are documented 6.3 - Final Report is made 6.4 - Sign off the final report 6.5 - Project is Closed
Figure 2: Project Activity Sequence
(Source: Created by the author)
Document Page
10FINAL PROJECT REPORT
2.3 Resource Requirements of the Project
The resource requirements for the project of the developing the effective implementation
and alignment of the operations would be helpful for the deployment of the effective and
improved estimation (Sahebjamnia, Torabi & Mansouri, 2015). The top down estimation had
helped in listing the development of the operations that are favourable for the development of the
operations. The alignment of the operations had helped in alignment of the activities and it would
help in forming the final deliverable of the project. Both human and material resources are used
in the project for developing the final achievement of the project. The resource requirements for
the project of Construction of Residential Complex in Queensland, Australia is shown in the
table below,
Resource Name Type of
Resource
Activities Involved in
Analyst Human Analysis of requirements
Feasibility analysis of the complete design
Documenter
Human Development of project tender form
Project Charter is formed
Project Initiation document is formed
All inspection results are documented
Final Report is made
Project Manager
Human Applying for permits of construction
Securing foundation permit, electrical permit, and
plumbing permit
Hiring an architect for the building design
Approval of the design
Sign off the final report
Project is Closed
Submission and approval of the tender form
Budgeter
Human Resource Analysis and Accumulation
Assigning resources to the activities
Planner
Human Listing required activities of the project
Developing Project Schedule
Architect
Human Forming an outline of building design
Review of the design outline
Completion of the residential building complex
design
Contractor Human Installing temporary power and groundwork utilities
Excavation of foundations
Development of basement walls
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
11FINAL PROJECT REPORT
Complete Roof Framing and decking
Partitioning of floors in flat structure
Workers
Human Backfilling the foundation
Installation of 1st floor joists and decking
Installation of 2nd floor joists and decking
Installation of 3rd floor joists and decking
Installation of 4th floor joists and decking
Installation of 5th floor joists and decking
Making passage way for vehicles
Installing Mailboxes
Site clearing and grubbing
Adding concrete and cementing the basement
structure
Windows and doors are added
Completing remaining brick works
Plumber Contractor Human Plumbing line is installed
Bathroom Equipments are added
Electrical Contractor Human Main Electric lining is done
Telecom Contractor Human Phone wires are installed
Civil Engineer
Human Insulation of the walls and ceiling
Installing drywalls
Fencing the building
Main gate is made
House Painter
Human Paintings and wallpaper works from internal
Texture is also added to required walls
Painting of the building from outside
Carpenter
Human Cabinet works in kitchen, bedroom, hall, bathroom,
and balcony
Carpets and Tiles are laid
Beds, Chairs, Dining table, Sofa, and side tables are
added
Gardener Human Laying of grass surrounding the building
Technician
Human Kitchen Appliances are added
Fans, Lights, Air conditioners, and Room heaters are
added
Security Cameras are installed
Fire Extinguishers are installed
External Inspection Officer Human Site is inspected
Final walk-through Inspection
Developing final checklist
Inspection of infrastructure
Document Page
12FINAL PROJECT REPORT
Electrical Line Inspection
Plumbing line Inspection
Appliances installed are inspected
Construction Equipments
Rent
Material Site clearing and grubbing
Temporary Power Cost Material Installing temporary power and groundwork utilities
Doors and Windows Material Windows and doors are added
Construction Raw
Materials
Material Resource Analysis and Accumulation
Plumbing Equipments and
Pipes
Material Plumbing line is installed
Electric Wires and
Equipments
Material Main Electric lining is done
Telecom Cost Material Phone wires are installed
Carpentry Equipments Material Cabinet works in kitchen, bedroom, hall, bathroom,
and balcony
Tiles and Carpet Material Carpets and Tiles are laid
Main gate Material Main gate is made
Fences Material Fencing the building
Gardening tools Material Laying of grass surrounding the building
Mailboxes Material Installing Mailboxes
Cameras Material Security Cameras are installed
Fire Extinguishers Material Fire Extinguishers are installed
Bathroom Equipments Material Bathroom Equipments are added
Kitchen Appliances Material Kitchen Appliances are added
Furniture and Fixtures Material Beds, Chairs, Dining table, Sofa, and side tables are
added
Fans and Lights Material Fans, Lights, Air conditioners, and Room heaters are
added
Air Conditioners Material Fans, Lights, Air conditioners, and Room heaters are
added
Room Heaters Material Fans, Lights, Air conditioners, and Room heaters are
added
Table 5: Project Resource Requirements
(Source: Created by the author)