CPCCBC5002A Assignment: Precedence Diagram and Critical Path Analysis

Verified

Added on  2022/10/02

|115
|2991
|4
Homework Assignment
AI Summary
This assignment focuses on the analysis of a proposed commercial and residential development project located at 2135 The Boulevarde, Strathfield, NSW. The project, undertaken for AKM Developments Limited, involves the construction of medium-rise apartments. The task requires the creation of a precedence diagram to illustrate the project's schedule. The diagram will be used to determine early start, early finish, late start, late finish dates, and float for each activity. The ultimate goal is to identify the critical path, which represents the sequence of tasks that directly impacts the project's overall duration. This analysis is crucial for effective project management, ensuring timely completion and efficient resource allocation. The assignment uses provided plans, a bill of quantities, and a specification of works to facilitate the diagram creation and critical path identification.
Document Page
Start
Start: Mon 13/01/14ID: 2
Finish: Mon 10/02/14Dur: 25 days
Comp: 0%
Concrete
Start: Wed 19/02/14ID: 5
Finish: Mon 18/08/14Dur: 155 days
Comp: 0%
Masonry
Start: Tue 11/03/14ID: 13
Finish: Mon 25/08/14Dur: 144 days
Comp: 0%
Metalwork
Start: Wed 12/03/14ID: 21
Finish: Mon 27/10/14Dur: 197 days
Comp: 0%
Job Duration
Start: Mon 13/01/14ID: 1
Finish: Mon 10/11/14Dur: 259 days
Comp: 0%
Page 1
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Hydraulics
Start: Tue 11/02/14ID: 34
Finish: Wed 29/10/14Dur: 224 days
Comp: 0%
Electrical
Start: Tue 11/02/14ID: 50
Finish: Sat 25/10/14Dur: 221 days
Comp: 0%
Page 2
Document Page
Page 3
Document Page
Mechanical
Start: Sat 05/04/14ID: 66
Finish: Fri 12/09/14Dur: 138 days
Comp: 0%
Waterproofing
Start: Mon 02/06/14ID: 83
Finish: Wed 10/09/14Dur: 87 days
Comp: 0%
Page 4
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Plasterer
Start: Thu 20/03/14ID: 90
Finish: Tue 02/09/14Dur: 143 days
Comp: 0%
Carpenter Fitout
Start: Sat 30/08/14ID: 98
Finish: Sat 20/09/14Dur: 19 days
Comp: 0%
Painter
Start: Sat 30/08/14ID: 106
Finish: Thu 30/10/14Dur: 53 days
Comp: 0%
Ceramic Tiler
Start: Mon 08/09/14ID: 114
Finish: Thu 23/10/14Dur: 40 days
Comp: 0%
Carpet
Start: Wed 24/09/14ID: 120
Finish: Sat 08/11/14Dur: 40 days
Comp: 0%
Page 5
Document Page
Cleaner
Start: Fri 03/10/14ID: 126
Finish: Mon 10/11/14Dur: 33 days
Comp: 0%
Page 6
Document Page
Preliminaries
Start: Mon 13/01/14ID: 3
Finish: Fri 17/01/14 Dur: 5 days
Res:
Groundworks
Start: Sat 18/01/14 ID: 4
Finish: Mon 10/02/14Dur: 20 days
Res:
Page 7
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Page 8
Document Page
Page 9
Document Page
Page 10
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Page 11
Document Page
Page 12
chevron_up_icon
1 out of 115
circle_padding
hide_on_mobile
zoom_out_icon
[object Object]