This project report outlines a comprehensive plan for the construction of a 500 sq. m house in Melbourne, encompassing all stages from initial scope development to final inspection and acceptance. It includes a detailed Work Breakdown Structure (WBS), project calendar, and a Responsibility Assignment Matrix (RAM) to define roles. The report presents a Program Evaluation and Review Technique (PERT) diagram and Gantt chart for project scheduling, along with a budget report detailing costs and resource allocation. Various resources schedules are presented, including a detailed budget and cost forecast. An S-curve analysis visualizes project progress, and the report concludes with a bibliography of relevant project management resources. The project aims to provide a clear, structured approach to managing a construction project, demonstrating effective planning and execution strategies.
Document Page
Running head: CONSTRUCTION OF HOUSE
Project Management: Construction of House
Name of the student:
Name of the University:
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
1CONSTRUCTION OF HOUSE
List of task and WBS schedule for the project
The report depicts the roles of project management practices for executing the
construction of a new 500 Sq house in Western Suburb of Melbourne. The list of work activities
considered while executing the project are as follows:
WBS Task Name
0 CONSTRUCTION Of A NEW HOUSE
1 PROJECT SCOPE DEVELOPMENT
1.1 Meeting Client
1.2 Prepare Project Scope
1.3 Design
2 APPOINT ADVISER
2.1 Structural
2.2 Electrical
2.3 Architect
3 LICENSE
3.1 Lodge Application
3.2 Approval
4 TENDER
4.1 Documentations
4.2 Evaluation
4.3 Process
5 CONSTRUCTION
5.1 Foundation
5.2 Location Preparation
5.3 Surveying
6 SUPERSTRUCTURE
6.1 Floor
6.2 Roof
6.3 Frame
6.4 Window and Doors
7 EXTERNAL
7.1 Rain Water
7.2 Solar
7.3 Fence
8 INTERNAL
Document Page
2CONSTRUCTION OF HOUSE
8.1 Plumbing
8.2 Technician
8.3 Electrical
9 DELIVER
9.1 Inspection
9.2 Acceptance
Project calendar
The assigned labours for the project will not work on the following days:
Figure 1: The calendar of the project
(Source: created by author)
Document Page
3CONSTRUCTION OF HOUSE
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
CONSTRUCTION OF HOUSE 4
PDM diagram and Gantt chart
Figure 2: PDM diagram for the project activities
(Source: created by author)
Document Page
CONSTRUCTION OF HOUSE 5
Figure 3: Gantt chart for the project
(Source: created by author)
Document Page
CONSTRUCTION OF HOUSE 6
A weekly Gantt chart sorted by WBS
Figure 4: Weekly Gantt chart
(Source: created by author)
List and cost and all resources
Resource Name Max. Units Std. Rate
Contractor 100% $80.00/hr
Project lead 100% $150.00/hr
architect 100% $120.00/hr
civil engineer 100% $125.00/hr
Masons $11,000.00
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
CONSTRUCTION OF HOUSE 7
Water Proofing Contractors $80,000.00
Paving Contractors $80,000.00
Framers $7,000.00
Roofers $70,000.00
Plumbers $100,000.00
Electricians $100,000.00
HVAC Contractors $40,900.00
Insulation and air sealing contractors $30,830.00
Dry Wallers $24,000.00
Plaster Contractors $57,000.00
Final cost and details budget report
The final cost estimated for the successful accomplishment of the construction project is
$1000, 000 and the details of the budget report is given in the below section:
Document Page
CONSTRUCTION OF HOUSE 8
Figure 5: Budget repost presented for the project
(Source: created by author)
Document Page
CONSTRUCTION OF HOUSE 9
Various resources schedules in the form of Gantt chart
The resources assigned for each project activities are elaborated in the below table:
WB
S Task Name Duratio
n Resource Names
0 CONSTRUCTION Of A NEW
HOUSE 358 days
1 PROJECT SCOPE
DEVELOPMENT 24 days
1.1 Meeting Client 5 days Project lead
1.2 Prepare Project Scope 5 days Contractor
1.3 Design 14 days architect, civil engineer
2 APPOINT ADVISER 14 days
2.1 Structural 5 days HVAC Contractors[1]
2.2 Electrical 4 days Electricians[1]
2.3 Architect 5 days architect
3 LICENSE 30 days
3.1 Lodge Application 5 days Contractor
3.2 Approval 25 days Paving Contractors[1]
4 TENDER 27 days
4.1 Documentations 10 days Insulation and air sealing contractors[1]
4.2 Evaluation 10 days Contractor
4.3 Process 7 days Masons[1]
5 CONSTRUCTION 60 days
5.1 Foundation 14 days HVAC Contractors[1]
5.2 Location Preparation 36 days civil engineer
5.3 Surveying 10 days architect
6 SUPERSTRUCTURE 150 days
6.1 Floor 20 days Plaster Contractors[1]
6.2 Roof 20 days Roofers[1]
6.3 Frame 95 days Framers[1]
6.4 Window and Doors 15 days Framers[1]
7 EXTERNAL 14 days
7.1 Rain Water 6 days Dry Wallers[1],Water Proofing
Contractors[1]
7.2 Solar 4 days Insulation and air sealing contractors[1]
7.3 Fence 4 days Dry Wallers[1]
8 INTERNAL 35 days
8.1 Plumbing 12 days Plumbers[1]
8.2 Technician 11 days HVAC Contractors[1]
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
CONSTRUCTION OF HOUSE 10
8.3 Electrical 12 days Electricians[1]
9 DELIVER 4 days
9.1 Inspection 2 days Plaster Contractors[1]
9.2 Acceptance 2 days civil engineer
A budget and cost forecast
There is a small difference between budget and a cost forecast. The project budget is
prepared based on the project activities and ultimate project objectives on the other hand, the
forecast identified the actual expectation in a summarized manner. The project forecast updates
for this project throughout in a weekly interval and there is no presence of variance analysis
which compares the forecast with actual result. The “S curve” developed for the project is
elaborated in the below section.
Document Page
CONSTRUCTION OF HOUSE 11
Development of S curve
2 3 4 1 2 3
$0.00
$200,000.00
$400,000.00
$600,000.00
$800,000.00
$1,000,000.00
$1,200,000.00
$223,940.00
$366,670.00
$488,770.00
$531,101.58
$652,977.50
$1,000,000.00
S curve
Cumulative Cost
Figure 6: S curve for the construction project
(Source: created by author)