Detailed Construction Schedule Report for Control Room Project

Verified

Added on  2022/09/25

|13
|798
|22
Report
AI Summary
This report presents a comprehensive construction schedule for a proposed control room project. It begins with a Work Breakdown Structure (WBS) to outline the project's major deliverables and sub-steps. A Precedence Diagram Method (PDM) is then used to visualize the construction tasks and identify the critical path. The report also includes a detailed resource analysis, estimating the equipment, resources, and human resources required for each activity. Cost estimates are provided, covering labor, overheads, materials, and site establishment. The time analysis identifies major tasks and their order, and a construction schedule diagram is included. The report concludes with references to relevant sources. The report covers site preparation, foundation, structural works, floor slab, formwork, wall work, M&E, and finishes.
Document Page
Construction schedule
CONSTRUCTION SCHEDULE FOR THE PROPOSED CONTROL ROOM
By (Name)
Course
Professor’s name
University name
City, State
Date of submission
1
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Construction schedule
Construction schedule
The architectural plans of the building indicate that the building consists of three rooms: the
control room, storage and a washroom. The building has one storey level, cavity walls and a
strip foundation.
To construct the construction schedule, the following tasks were carried out first:
1. Work Breakdown Structure (WBS):
Indicates the major deliverables for the construction of the propose control room
2. Precedence Diagram Method (PDM):
A visual depiction of the construction tasks and the critical path of construction
3. Resource Analysis
An estimation of the resources required for construction
4. Cost Estimates
An estimate of the cost incurred for the construction
2
Document Page
Construction schedule
Work breakdown structure (WBS) for the proposed project
The work breakdown structure illustrates the map of the project; showing the major steps and the sub steps to be followed up to the completion
of the project. The diagram below illustrates the proposed work breakdown structure for the control room
3
Fig. WBS diagram for the control room
Document Page
Construction schedule
4
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Construction schedule
Precedence Diagram Method (PDM)
The figure below illustrates the critical path of the major construction tasks (Bathhurst &
Butler, 2010).
Resources
This section will contain a detail of the equipment, resources and human resources required
for the construction of the control room the table below outlines an estimate of all the
resources required for each activity listed in the WBS (A.S, et al., 2009).
5
Document Page
Construction schedule
The following table shows the man-hours required of the skilled ma-power listed in the
resource estimates:
6
Document Page
Construction schedule
Table. Human Resource Time estimates
7
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Construction schedule
Time analysis
The following time analysis is carried out by identifying the major tasks in the WBS and
identify the order that they follow from the PDM.
8
Construction of
Control Room
Site
Preparation
WBS 1.1
Strip foundation &
ground beams
WBS 1.2
Structural
works
WBS 4
Floor Slab
WBS 1.3
Formwork
&
Concrete
WBS 1.3.2
Wall
work
WBS
1.4.2
M&E
WBS
1.5
Finishes
WBS 1.7
17d 26d
23 d 33d
23 d 35d
32d 42d
74 d 97d 22 d 45d
20 d 30d 30 d 45d
ES LS
Fig. Critical Path Diagram
Document Page
Construction schedule
Construction schedule
The diagram below indicates the construction schedule for the construction of the control
room
Site preparation
Strip foundations
Floor slab
Structural frame
Formwork & concrete
Wall work
M&E Services
Finishes
4/29/2020 6/8/2020 7/18/2020 8/27/2020 10/6/2020 11/15/2020
Cost estimates
The following section will provide relevant estimates for the proposed control room
construction including the labour, overheads, materials and site establishment.
Table. Cost estimates for the construction
9
Document Page
Construction schedule
10
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Construction schedule
11
Document Page
Construction schedule
12
Document Page
Construction schedule
References
(CIOB), T. C. I. o. B., 2009. The Code of Estimating Practice. London: Rotal Minds Press.
A., A. S. & Thomson, D., 2011. Consruction Value Management revisited: The designer's
role. Glasglow, UK: Glasglow Caledonian University.
A.S, A., D.L., K. & Z., A.-S., 2009. Information required in managing the design process of
refurbishment projects, New Delhi: Selah Publishers.
Albert, Chan, P. & P.M, B., 2016. Value Management in Construction. Journal of Building
Economist, 05(77), pp. 23-68.
B.G, K., Verster, J. & Berry, F., 2017. Construction Industry Standardisaton and Effective
Communication. 2nd ed. Newark: J&J press.
Bathhurst, P. & Butler, D., 2010. Building Cost Control Techniques and Economics. 3rd ed.
Chicago: Heinemann.
Bogenstatter, U., 2013. Prediction and Optimization of Life-cycle costs. Washington: Build.
Res. Information.
Corne P, d. L., 2011. Value Management: An Optimum Solution. Nairobi, Sciatic Press, pp.
234-89.
Emmitt, S. & Christopher, G., 2010. Barry's Advanced Construction of Buildings. 2nd ed.
London: Wiley-Blsckwell.
Flanagan & Tate, 2017. Cost Control in Building Design. 2nd ed. London: Blackwell
Science.
Siami-Irdemoosa, E., Dindarloo, S. & Sharifzadeh, 2010.
13
chevron_up_icon
1 out of 13
circle_padding
hide_on_mobile
zoom_out_icon
logo.png

Your All-in-One AI-Powered Toolkit for Academic Success.

Available 24*7 on WhatsApp / Email

[object Object]