This project provides a comprehensive overview of construction site management, focusing on the creation of a Work Breakdown Structure (WBS) for the construction of a western abutment and a detailed schedule for the construction of a central pier for a bridge. The schedule includes a Gantt chart, a baselined Gantt chart, and a cost overview dashboard. A logical explanation for the construction process is provided, emphasizing a step-by-step approach to ensure successful project completion. Additionally, the project includes a Safe Work Method Statement, identifying potential hazards and risks associated with tasks such as pier reinforcement, concreting, and formwork removal, along with corresponding control measures to ensure worker safety and quality control.
Document Page
Running head: CONSTRUCTION SITE MANAGEMENT
Construction Site Management ENS5112
Student Name:
University Name:
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
1CONSTRUCTION SITE MANAGEMENT
Table of Contents
Task 1 – WBS and Project Schedule....................................................................................................2
1.1 WBS (Work Breakdown Structure) for construction of the western abutment.........................2
1.2 Schedule for the construction of the central pier for the bridge.................................................2
1.2.1 Gantt chart for construction.................................................................................................2
1.2.2 Baselined Gantt chart..........................................................................................................3
1.2.3 Cost overview dashboard....................................................................................................4
1.2.4 Logical explanation for the construction.............................................................................4
Task 2 - Safe Work Method Statement................................................................................................5
Bibliography.........................................................................................................................................6
Document Page
2CONSTRUCTION SITE MANAGEMENT
Task 1 – WBS and Project Schedule
1.1 WBS (Work Breakdown Structure) for construction of the western abutment
0. Construction of the
western abutment
1. Pour footing
1.1 Pour concrete
2. Prepare and pour wall
2.1 Removal of
formwork
2.2 Concrete curing
2.3 Bridge bearing
installation
2.4 Form connector
at top of abutment
2.5 Fixing of bridge
joints
3. Backfill behind
Abutment
3.1 Deciding the
option for backfill
3.2 Backfilling
3.3 Compaction of
backfill
3.4 Field test
4. Traffic control
4.1 Rerouting the
traffic on existing
road
Document Page
3CONSTRUCTION SITE MANAGEMENT
1.2 Schedule for the construction of the central pier for the bridge
1.2.1 Gantt chart for construction
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
4CONSTRUCTION SITE MANAGEMENT
1.2.2 Baselined Gantt chart
Document Page
5CONSTRUCTION SITE MANAGEMENT
1.2.3 Cost overview dashboard
1.2.4 Logical explanation for the construction
The construction will be carried out in a step by step manner so that required tasks are not piled up
and the complete project could be successfully completed. The construction will be carried out in a
sequential manner such that no work can proceed before completion of the previous task as
provided with predecessors while developing the schedule.
Document Page
6CONSTRUCTION SITE MANAGEMENT
Task 2 - Safe Work Method Statement
What are the tasks involved? What are the hazards and risks? What are the control measures?
Marking of points for pier
reinforcement
Improper marking of points The marking points should be
identified and reviewed properly
before reinforcement
Tie up of reinforcement bars
with stirrups
Risk of person falling Proper safety measures should be
maintained in the worksite
Providing starter at the bottom Improper setup of the starter The starter should be
implemented with proper
checking and quality evaluation
Concreting the pier Concrete mixture is of not proper
quality
The amount concrete mix should
be identified properly as per the
height of pier
Removal of formwork Damage to pier during formwork
removal
The formwork removal works
should be carried out under the
supervision of specialists
Quality checking of pier Quality has not been checked
properly
Quality supervisor has to identify
the criteria for measuring quality
and proper checking measures
should be implemented
Name of Worker(s) Worker signature(s)
Worker 1 Worker 1
Worker 2 Worker 2
Worker 3 Worker 3
Worker 4 Worker 4
Date SWMS received by
workers:
15 October 2018
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
7CONSTRUCTION SITE MANAGEMENT
Bibliography
Cagliano, A. C., Grimaldi, S., & Rafele, C. (2015). Choosing project risk management techniques.
A theoretical framework. Journal of Risk Research, 18(2), 232-248.
Lock, D. (2016). Project management in construction. Routledge.
Martinelli, R. J., & Milosevic, D. Z. (2016). Project management toolbox: tools and techniques for
the practicing project manager. John Wiley & Sons.
Walker, A. (2015). Project management in construction. John Wiley & Sons.