Cost Baseline and Funding Requirements Report - Project Overview

Verified

Added on  2020/03/23

|4
|310
|212
Report
AI Summary
This report provides a detailed analysis of a project's cost baseline and funding requirements. It includes a breakdown of costs, presented in a table format, outlining monthly and cumulative expenses. The cost baseline covers planning, sign design, manufacturing, and installation phases. Additionally, the report specifies the funding requirements for different project stages (gates), including planning, design, manufacturing, installation, and handover. A management reserve is also included. The report references key sources, such as the Association for Project Management (APM) and a PMP preparation blog, providing a comprehensive overview of project financial planning and resource allocation.
tabler-icon-diamond-filled.svg

Contribute Materials

Your contribution can guide someone’s learning journey. Share your documents today.
Document Page
[----- For Internal Purpose Only-----]
Student’s name
Name of university
9/19/20172017
COST BASELINE & FUNDING REQUIREMENTS
OUR LANGUAGE IS IMPORTANT
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Cost Baseline (Pmp-preparation, 2008)
COST BASELINE
WB
S
Activities Februar
y
March April May June July August Septembe
r
Octobe
r
Novembe
r
1 Planning & Reporting
1.1 Develop Planning
documents
$5,000 $5,000 $5,000
1.2 Start progress
reporting
$1,500 $1,500 $1,500 $1,500 $1,500 $1,500 $1,500
2 Designing Signs &
Manufacture the
Boards
2.1 Design Signage $10,00
0
2.2 Manufacture them
with Sign Boards &
deliver
$12,00
0
$5,000
3 Installation
3.1 Erect at site $3,000 $3,000 $3,000 $3,000
3.2 Handover $1,000
Monthly Total $5,000 $5,000 $5,000 $11,50
0
$13,50
0
$6,500 $4,500 $4,500 $4,500 $5,500
Cumulative Total $5,000 $10,00
0
$15,00
0
$26,50
0
$40,00
0
$46,50
0
$51,00
0
$55,500 $60,00
0
$65,500
[----- For Internal purpose Only-----]
Document Page
Funding Requirement (APM (Association for Project Management), 2017)
FUNDING REQUIREMENTS
Gate Funding Required
Planning & Reporting $25,500.00
Designing gate $10,000.00
Manufacturing gate $17,000.00
Installation gate $12,000.00
Handover gate $1,000.00
Management Reserve (20% of Cost Baseline) $13,100.00
Total Funding Requirements $78,600.00
References
1 BIBLIOGRAPHY
APM (Association for Project Management). (2017). Funding. Retrieved September 18, 2017, from www.apm.org.uk: https://www.apm.org.uk/body-of-
knowledge/delivery/financial-cost-management/funding/
Pmp-preparation. (2008, February 21). What is Cost Baseline? Retrieved September 18, 2017, from http://pmp-preparation.blogspot.in: http://pmp-
preparation.blogspot.in/2008/02/what-is-cost-baseline.html
[----- For Internal purpose Only-----]
Document Page
[----- For Internal purpose Only-----]
chevron_up_icon
1 out of 4
circle_padding
hide_on_mobile
zoom_out_icon
logo.png

Your All-in-One AI-Powered Toolkit for Academic Success.

Available 24*7 on WhatsApp / Email

[object Object]