CQU Educational Hubs for Indigenous Studies: Project Plan (PPMP20008)
VerifiedAdded on 2022/12/19
|17
|2751
|30
Project
AI Summary
This project plan, developed for the CQU Educational Hubs for Indigenous Studies project (PPMP20008), outlines the key aspects of establishing educational hubs across multiple CQU campuses. The plan details the project description, background, and major deliverables, including finding suitable facility spaces, designing and building the hubs, and organizing opening ceremonies. It analyzes stakeholder engagement, including identifying key stakeholders like local indigenous people, the SET, NAIDOC committee, CQU Campuses, students and project managers and assessing their influence and support levels. The plan also addresses requirements management, encompassing requirements gathering, traceability, and prioritization. The scope of the project is defined through a work breakdown structure (WBS) and WBS dictionary, detailing costs and timelines for each phase. The schedule, cost baseline, risk assessment, and tolerance levels are also included. Finally, the project plan incorporates lessons learned from previous initiatives and proposes actions to improve the outcome of the current project.
Contribute Materials
Your contribution can guide someone’s learning journey. Share your
documents today.

PMMP 20008 – Initiating and Planning Projects (T2) Assignment 2
PROJECT NAME: CQU EDUCATIONAL HUBS
FOR INDIGENOUS STUDIES
PROJECT
TERM & ASSIGNMENT # TERM 2, ASSIGNMENT 2
TITLE: PROJECT PLAN
STUDENT
NAME
STUDENT
NUMBER
QUESTIONS
ANSWERED (BE
SPECIFIC)
Please Insert Please Insert Please Insert
Please Insert Please Insert Please Insert
Please Insert Please Insert Please Insert
Please Insert Please Insert Please Insert
CAMPUS: Please Insert
TUTOR: Please Insert
TUTORIAL NUMBER: Please Insert
Assignment 2 PPMP20008 (T2 – 2019) V5
PROJECT NAME: CQU EDUCATIONAL HUBS
FOR INDIGENOUS STUDIES
PROJECT
TERM & ASSIGNMENT # TERM 2, ASSIGNMENT 2
TITLE: PROJECT PLAN
STUDENT
NAME
STUDENT
NUMBER
QUESTIONS
ANSWERED (BE
SPECIFIC)
Please Insert Please Insert Please Insert
Please Insert Please Insert Please Insert
Please Insert Please Insert Please Insert
Please Insert Please Insert Please Insert
CAMPUS: Please Insert
TUTOR: Please Insert
TUTORIAL NUMBER: Please Insert
Assignment 2 PPMP20008 (T2 – 2019) V5
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.

PMMP 20008 – Initiating and Planning Projects (T2) Assignment 2
1 PROJECT DESCRIPTION (TOTAL = 4 MARKS)
1.1 PROJECT DESCRIPTION, BACKGROUND AND MAJOR DELIVERABLES (1
MARK)
Response Table
1 Description A project is undertaken by the School of Engineering and
Technology (SET), to provide visibility and sustainability to
the some of the oldest culture in the world. The project aims
in development of the educational hubs
2 Background The project of establishing the educational hubs are
considered for encouraging and supporting the need of
education among the local indigenous people
3 Major Deliverables The main deliverables of the chosen project include-
1. Finding suitable Facility Space
2. Designing and Building Educational Hubs
3. Organizing and conducting opening ceremonies.
1.2 JUSTIFICATION (3 MARKS)
Response Table
Output Outcome Benefits
Development of Educational
Hubs
Awareness among local
indigenous people
Acknowledge of the
traditional culture
2 STAKEHOLDERS (TOTAL = 10 MARKS)
2.1 KEY STAKEHOLDER LIST (6 MARKS)
Response Table
# Stakeholder Category (i.ie Sponsor /
Supplier / User)
Description of
Interest
Description of
Influence
1. Local Indigenous
People
User High Medium
2. SET Sponsor High High
3. NAIDOC
committee
Supplier Medium High
Assignment 2 PPMP20008 (T2 – 2019) V5
1 PROJECT DESCRIPTION (TOTAL = 4 MARKS)
1.1 PROJECT DESCRIPTION, BACKGROUND AND MAJOR DELIVERABLES (1
MARK)
Response Table
1 Description A project is undertaken by the School of Engineering and
Technology (SET), to provide visibility and sustainability to
the some of the oldest culture in the world. The project aims
in development of the educational hubs
2 Background The project of establishing the educational hubs are
considered for encouraging and supporting the need of
education among the local indigenous people
3 Major Deliverables The main deliverables of the chosen project include-
1. Finding suitable Facility Space
2. Designing and Building Educational Hubs
3. Organizing and conducting opening ceremonies.
1.2 JUSTIFICATION (3 MARKS)
Response Table
Output Outcome Benefits
Development of Educational
Hubs
Awareness among local
indigenous people
Acknowledge of the
traditional culture
2 STAKEHOLDERS (TOTAL = 10 MARKS)
2.1 KEY STAKEHOLDER LIST (6 MARKS)
Response Table
# Stakeholder Category (i.ie Sponsor /
Supplier / User)
Description of
Interest
Description of
Influence
1. Local Indigenous
People
User High Medium
2. SET Sponsor High High
3. NAIDOC
committee
Supplier Medium High
Assignment 2 PPMP20008 (T2 – 2019) V5

PMMP 20008 – Initiating and Planning Projects (T2) Assignment 2
4. CQU Campuses Sponsor High High
5. Students Users Low Low
6. Project Manager Supplier High Low
2.2 STAKEHOLDERS ENGAGEMENT ASSESSMENT MATRIX (3 MARKS)
Response Table
# Stakeholders Unaware Resistant Neutral Supportive Leading
1. Local Indigenous People C D
2. SET C D
3. NAIDOC committee C D
4. CQU Campuses D C
5. Students C D
6. Project Manager C D
Assignment 2 PPMP20008 (T2 – 2019) V5
4. CQU Campuses Sponsor High High
5. Students Users Low Low
6. Project Manager Supplier High Low
2.2 STAKEHOLDERS ENGAGEMENT ASSESSMENT MATRIX (3 MARKS)
Response Table
# Stakeholders Unaware Resistant Neutral Supportive Leading
1. Local Indigenous People C D
2. SET C D
3. NAIDOC committee C D
4. CQU Campuses D C
5. Students C D
6. Project Manager C D
Assignment 2 PPMP20008 (T2 – 2019) V5

PMMP 20008 – Initiating and Planning Projects (T2) Assignment 2
2.3 STAKEHOLDER COMMUNICATION (1 MARK)
Response Table
Communication Method Interactive, Pull or Push Justification
Email and communication in face
to face mode
Interactive The interactive type of
communication is chosen for
this case as it will help all the
stakeholders to easily
communicate with each other.
Prompt response is absent in
Push type of communication
and therefore it should be
avoided, while the pull type of
communication is accessible
to a recipient on his terms and
therefore indicates delayed
communication (Butt,
Naaranoja & Savolainen,
2016).
2.4 OBTAINING EXPERT JUDGEMENT (1 MARK)
Response Table
Experts Methods / Techniques
SET Brainstorming (Iglesias et al. 2016)
NAIDOC Interview (Wilson 2017)
Assignment 2 PPMP20008 (T2 – 2019) V5
2.3 STAKEHOLDER COMMUNICATION (1 MARK)
Response Table
Communication Method Interactive, Pull or Push Justification
Email and communication in face
to face mode
Interactive The interactive type of
communication is chosen for
this case as it will help all the
stakeholders to easily
communicate with each other.
Prompt response is absent in
Push type of communication
and therefore it should be
avoided, while the pull type of
communication is accessible
to a recipient on his terms and
therefore indicates delayed
communication (Butt,
Naaranoja & Savolainen,
2016).
2.4 OBTAINING EXPERT JUDGEMENT (1 MARK)
Response Table
Experts Methods / Techniques
SET Brainstorming (Iglesias et al. 2016)
NAIDOC Interview (Wilson 2017)
Assignment 2 PPMP20008 (T2 – 2019) V5
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.

PMMP 20008 – Initiating and Planning Projects (T2) Assignment 2
3. REQUIREMENTS MANAGEMENT (TOTAL = 5 MARKS)
3.1 TRADITIONAL CUSTODIAN/S OF THE LAND ON WHICH CQ UNIVERSITY CAMPUSES
ARE LOCATED (1 MARK).
Response Table
The suggestion of keeping more than one main stakeholder for representation of the custodians of land is
suggested as it will help in easier management of all the work processes linked with this undertaken project
(Kossmann 2016). A single stakeholder may not be able to know about all the campuses simultaneously in a
proper manner.
3.2. OPENING STATEMENT STYLE (1 MARK)
Response Table
The opening statement “Acknowledgement of Country” will be appropriate for the campus leader to use
at the opening ceremony that is related to development of the educational hubs. This is appropriate as it
justifies the project’s theme.
3.3 REQUIREMENTS GATHERING FOR CQU EDUCATIONAL HUBS FOR INDIGENOUS
STUDIES PROJECT (1 MARK)
Response Table
Although the documentation from a Vietnamese community can be a good reference for the current
project, only online search may not be a good idea to collect requirements of the project. The project team
needs to have a direct meeting with the local people for information collection about the need of the
educational hubs and collect their feedback regarding the proposed idea. This will help in designing the
project in an effective manner (Aryana, Clemmensen & Boks, 2015).
3.4 REQUIREMENTS TRACEABILITY (0.5 MARK)
Response Table
Daily progress report that will be shared over email from all the campuses can be centrally tracked to
trace the project requirements.
3.5 REQUIREMENTS PRIORITIZATION PROCESS (1 MARK)
Response Table
Prioritization of the Requirements helps in determining the most important requirements to be
incorporated in a particular release. Requirements needed to be prioritized for minimization of the risks
while implementation of a project (Bourne, 2016). It is crucial to communicate the requirements
prioritization process to the main stakeholders as they are a vital part of the undertaken project and needs
to be updated with all major project requirements (Kerzner, 2017).
Assignment 2 PPMP20008 (T2 – 2019) V5
3. REQUIREMENTS MANAGEMENT (TOTAL = 5 MARKS)
3.1 TRADITIONAL CUSTODIAN/S OF THE LAND ON WHICH CQ UNIVERSITY CAMPUSES
ARE LOCATED (1 MARK).
Response Table
The suggestion of keeping more than one main stakeholder for representation of the custodians of land is
suggested as it will help in easier management of all the work processes linked with this undertaken project
(Kossmann 2016). A single stakeholder may not be able to know about all the campuses simultaneously in a
proper manner.
3.2. OPENING STATEMENT STYLE (1 MARK)
Response Table
The opening statement “Acknowledgement of Country” will be appropriate for the campus leader to use
at the opening ceremony that is related to development of the educational hubs. This is appropriate as it
justifies the project’s theme.
3.3 REQUIREMENTS GATHERING FOR CQU EDUCATIONAL HUBS FOR INDIGENOUS
STUDIES PROJECT (1 MARK)
Response Table
Although the documentation from a Vietnamese community can be a good reference for the current
project, only online search may not be a good idea to collect requirements of the project. The project team
needs to have a direct meeting with the local people for information collection about the need of the
educational hubs and collect their feedback regarding the proposed idea. This will help in designing the
project in an effective manner (Aryana, Clemmensen & Boks, 2015).
3.4 REQUIREMENTS TRACEABILITY (0.5 MARK)
Response Table
Daily progress report that will be shared over email from all the campuses can be centrally tracked to
trace the project requirements.
3.5 REQUIREMENTS PRIORITIZATION PROCESS (1 MARK)
Response Table
Prioritization of the Requirements helps in determining the most important requirements to be
incorporated in a particular release. Requirements needed to be prioritized for minimization of the risks
while implementation of a project (Bourne, 2016). It is crucial to communicate the requirements
prioritization process to the main stakeholders as they are a vital part of the undertaken project and needs
to be updated with all major project requirements (Kerzner, 2017).
Assignment 2 PPMP20008 (T2 – 2019) V5

PMMP 20008 – Initiating and Planning Projects (T2) Assignment 2
3.6 MoSCoW TECHNIQUE (0.5 MARK)
Response Table
# Components Explanation
1. M=Must have This include the needed requirements of a
project determined in advance
2. S=Should Have This include the additional requirements of a
project
3. C=Could Have These requirements include the requirement
that could be included in a project if there is
time
4. W=Won’t have/ Would Have These requirement might not be achievable or
could have been achieved if lot of time or
money is spent to the undertaken project.
Assignment 2 PPMP20008 (T2 – 2019) V5
3.6 MoSCoW TECHNIQUE (0.5 MARK)
Response Table
# Components Explanation
1. M=Must have This include the needed requirements of a
project determined in advance
2. S=Should Have This include the additional requirements of a
project
3. C=Could Have These requirements include the requirement
that could be included in a project if there is
time
4. W=Won’t have/ Would Have These requirement might not be achievable or
could have been achieved if lot of time or
money is spent to the undertaken project.
Assignment 2 PPMP20008 (T2 – 2019) V5

PMMP 20008 – Initiating and Planning Projects (T2) Assignment 2
4 SCOPE (TOTAL = 10 MARKS)
4.1 INTRODUCTION TO SCOPE (1 MARK)
Response Table
The project’s scope involves finding of different facility centres that can be converted to the education hubs.
For better planning of the projects, the work break down structure and the schedule of the project is
identified. The cost baseline and the budget of the project is identified as well (Meredith, Mantel & Shafer,
2017).
4.2 WORK BREAKDOWN STRUCTURE (3 MARKS)
Assignment 2 PPMP20008 (T2 – 2019) V5
CQU Educational
Hubs for Indigenous
Studies Project
Facility
space
Research And
Planning
Leasing the
Facility Space
Educational hubs
Researching the
Need
Setting up of the
Educational
Hubs
Opening
ceremonies
Project
Evaluation Project Launch
4 SCOPE (TOTAL = 10 MARKS)
4.1 INTRODUCTION TO SCOPE (1 MARK)
Response Table
The project’s scope involves finding of different facility centres that can be converted to the education hubs.
For better planning of the projects, the work break down structure and the schedule of the project is
identified. The cost baseline and the budget of the project is identified as well (Meredith, Mantel & Shafer,
2017).
4.2 WORK BREAKDOWN STRUCTURE (3 MARKS)
Assignment 2 PPMP20008 (T2 – 2019) V5
CQU Educational
Hubs for Indigenous
Studies Project
Facility
space
Research And
Planning
Leasing the
Facility Space
Educational hubs
Researching the
Need
Setting up of the
Educational
Hubs
Opening
ceremonies
Project
Evaluation Project Launch
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

PMMP 20008 – Initiating and Planning Projects (T2) Assignment 2
4.3 WBS DICTIONARY (6 MARKS)
Research And Planning
WBS ID 1.1.1
Description of work This is a crucial stage of setting up of a facility space
as researching the need of developing a facility space
is crucial
Cost Estimate $13,200.00
Start and Finish Dates Mon 01-06-20 and Tue 07-07-20
Leasing the Facility Space
WBS ID 1.1.2.
Description of work As per the research done, he suitable facility space
are taken on a lease
Cost Estimate $81,200.00
Start and Finish Dates Wed 08-07-20 and Tue 08-12-20
Researching the Need
WBS ID 1.2.1.
Description of work In this phase, the need of setting up of education
hubs is examined
Cost Estimate $13,000.00
Start and Finish Dates Wed 09-12-20 and Tue 26-01-21
Setting up of the Educational Hubs
WBS ID 1.2.2.
Description of work This phase aims in conversion of the facility centre to
educational hubs
Cost Estimate $805,800.00
Start and Finish Dates Wed 27-01-21 and Tue 11-05-21
Project Evaluation
WBS ID 1.3.1.
Description of work The conversion to the educational hubs are evaluated
in this phase
Cost Estimate $10,400.00
Start and Finish Dates Wed 12-05-21 and Tue 08-06-21
Assignment 2 PPMP20008 (T2 – 2019) V5
4.3 WBS DICTIONARY (6 MARKS)
Research And Planning
WBS ID 1.1.1
Description of work This is a crucial stage of setting up of a facility space
as researching the need of developing a facility space
is crucial
Cost Estimate $13,200.00
Start and Finish Dates Mon 01-06-20 and Tue 07-07-20
Leasing the Facility Space
WBS ID 1.1.2.
Description of work As per the research done, he suitable facility space
are taken on a lease
Cost Estimate $81,200.00
Start and Finish Dates Wed 08-07-20 and Tue 08-12-20
Researching the Need
WBS ID 1.2.1.
Description of work In this phase, the need of setting up of education
hubs is examined
Cost Estimate $13,000.00
Start and Finish Dates Wed 09-12-20 and Tue 26-01-21
Setting up of the Educational Hubs
WBS ID 1.2.2.
Description of work This phase aims in conversion of the facility centre to
educational hubs
Cost Estimate $805,800.00
Start and Finish Dates Wed 27-01-21 and Tue 11-05-21
Project Evaluation
WBS ID 1.3.1.
Description of work The conversion to the educational hubs are evaluated
in this phase
Cost Estimate $10,400.00
Start and Finish Dates Wed 12-05-21 and Tue 08-06-21
Assignment 2 PPMP20008 (T2 – 2019) V5

PMMP 20008 – Initiating and Planning Projects (T2) Assignment 2
Project Launch
WBS ID 1.3.2.
Description of work The undertaken project will launch in mid of 2021
Cost Estimate $6,600.00
Start and Finish Dates Wed 09-06-21and Fri 25-06-21
Assignment 2 PPMP20008 (T2 – 2019) V5
Project Launch
WBS ID 1.3.2.
Description of work The undertaken project will launch in mid of 2021
Cost Estimate $6,600.00
Start and Finish Dates Wed 09-06-21and Fri 25-06-21
Assignment 2 PPMP20008 (T2 – 2019) V5

PMMP 20008 – Initiating and Planning Projects (T2) Assignment 2
5 SCHEDULE (TOTAL = 6 MARKS)
5.1 SCHEDULE
Research and Planning
ACTIVITY DESCRIPTION OF WORK START DATE END DATE DURATION
(DAYS)
1.1.1.1 Researching the Need of this Project Mon 01-06-20 Fri 19-06-
20
15
1.1.1.2 Documentation Mon 22-06-20 Fri 26-06-
20
5
1.1.1.3 Release of the Project Plan Mon 29-06-20 Tue 07-
07-20
7
Leasing the Facility Space
ACTIVITY DESCRIPTION OF WORK START DATE END DATE DURATION
(DAYS)
1.1.2.1 Inspection of the shortlisted facility
centre
Wed 08-07-20 Tue 29-09-
20
60
1.1.2.2 Negotiating the cost Wed 30-09-20 Tue 27-10-
20
20
1.1.2.3 Completion of all legal
Requirements
Wed 28-10-20 Tue 08-12-
20
30
Researching the Need
ACTIVITY DESCRIPTION OF WORK START DATE END DATE DURATION
(DAYS)
1.2.1.1 Identification of Project needs Wed 09-12-20 Tue 29-12-
20
15
1.2.1.2 Documentation Wed 30-12-20 Tue 05-01-
21
5
1.2.1.2 Finalization of Project Plan Wed 06-01-21 Tue 26-01-
21
15
Setting up of the Educational Hubs
ACTIVITY DESCRIPTION OF WORK START DATE END DATE DURATION
(DAYS)
1.2.2.1 Selection of CQU campuses Wed 27-01-21 Tue 09-02-
21
10
1.2.2.2 Design and built of educational
Hubs
Wed 10-02-21 Tue 04-05-
21
60
1.2.2.3 Documentation Wed 05-05-21
Tue 11-05-
21
5
Project Evaluation
ACTIVITY DESCRIPTION OF WORK START DATE END DATE DURATION
(DAYS)
1.3.1.1 Checking if all the requirements are
met
Wed 12-05-21 Tue 18-05-
21
5
1.3.1.2 Preparation of Opening Ceremony Wed 19-05-21 Tue 01-06-
21
10
Assignment 2 PPMP20008 (T2 – 2019) V5
5 SCHEDULE (TOTAL = 6 MARKS)
5.1 SCHEDULE
Research and Planning
ACTIVITY DESCRIPTION OF WORK START DATE END DATE DURATION
(DAYS)
1.1.1.1 Researching the Need of this Project Mon 01-06-20 Fri 19-06-
20
15
1.1.1.2 Documentation Mon 22-06-20 Fri 26-06-
20
5
1.1.1.3 Release of the Project Plan Mon 29-06-20 Tue 07-
07-20
7
Leasing the Facility Space
ACTIVITY DESCRIPTION OF WORK START DATE END DATE DURATION
(DAYS)
1.1.2.1 Inspection of the shortlisted facility
centre
Wed 08-07-20 Tue 29-09-
20
60
1.1.2.2 Negotiating the cost Wed 30-09-20 Tue 27-10-
20
20
1.1.2.3 Completion of all legal
Requirements
Wed 28-10-20 Tue 08-12-
20
30
Researching the Need
ACTIVITY DESCRIPTION OF WORK START DATE END DATE DURATION
(DAYS)
1.2.1.1 Identification of Project needs Wed 09-12-20 Tue 29-12-
20
15
1.2.1.2 Documentation Wed 30-12-20 Tue 05-01-
21
5
1.2.1.2 Finalization of Project Plan Wed 06-01-21 Tue 26-01-
21
15
Setting up of the Educational Hubs
ACTIVITY DESCRIPTION OF WORK START DATE END DATE DURATION
(DAYS)
1.2.2.1 Selection of CQU campuses Wed 27-01-21 Tue 09-02-
21
10
1.2.2.2 Design and built of educational
Hubs
Wed 10-02-21 Tue 04-05-
21
60
1.2.2.3 Documentation Wed 05-05-21
Tue 11-05-
21
5
Project Evaluation
ACTIVITY DESCRIPTION OF WORK START DATE END DATE DURATION
(DAYS)
1.3.1.1 Checking if all the requirements are
met
Wed 12-05-21 Tue 18-05-
21
5
1.3.1.2 Preparation of Opening Ceremony Wed 19-05-21 Tue 01-06-
21
10
Assignment 2 PPMP20008 (T2 – 2019) V5
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.

PMMP 20008 – Initiating and Planning Projects (T2) Assignment 2
1.3.1.3 Preparation of Project Evaluation
Report
Wed 02-06-21 Tue 08-06-
21
5
Project Launch
ACTIVITY DESCRIPTION OF WORK START DATE END DATE DURATION
(DAYS)
1.3.2.1 organizing opening ceremony Wed 09-06-21 Tue 15-06-
21
5
1.3.2.2 Sending out invites Wed 16-06-21 Thu 24-06-
21
7
1.3.2.3 End of the Project Fri 25-06-21 Fri 25-06-21 1
Assignment 2 PPMP20008 (T2 – 2019) V5
1.3.1.3 Preparation of Project Evaluation
Report
Wed 02-06-21 Tue 08-06-
21
5
Project Launch
ACTIVITY DESCRIPTION OF WORK START DATE END DATE DURATION
(DAYS)
1.3.2.1 organizing opening ceremony Wed 09-06-21 Tue 15-06-
21
5
1.3.2.2 Sending out invites Wed 16-06-21 Thu 24-06-
21
7
1.3.2.3 End of the Project Fri 25-06-21 Fri 25-06-21 1
Assignment 2 PPMP20008 (T2 – 2019) V5

PMMP 20008 – Initiating and Planning Projects (T2) Assignment 2
6. COST BASELINE (TOTAL = 6 MARKS)
Response Table
Timeline (months)
W
BS
id
WP /
Activit
y
name
1 2 3 4 5 6 7 8 9 10 11 12
1.1
.1
Resear
ch and
Plannin
g
1.1
.2
Leasin
g the
Facility
Space
1.2
.1
Resear
ching
the
Need
1.2
.2
Setting
up of
the
Educati
onal
Hubs
1.3
.1
Project
Evaluat
ion
1.3
.2
Project
Launch
Total
monthl
y
costs
$13
200
$20
000
$80
00
$38
000
$14
400
$13
000
$48
00
$400
000
$400
000
$100
0
$10
400
$66
00
Cumul
ative
costs
$13
200
$81
200
$13
000
$805
800
$10
400
$66
00
Assignment 2 PPMP20008 (T2 – 2019) V5
6. COST BASELINE (TOTAL = 6 MARKS)
Response Table
Timeline (months)
W
BS
id
WP /
Activit
y
name
1 2 3 4 5 6 7 8 9 10 11 12
1.1
.1
Resear
ch and
Plannin
g
1.1
.2
Leasin
g the
Facility
Space
1.2
.1
Resear
ching
the
Need
1.2
.2
Setting
up of
the
Educati
onal
Hubs
1.3
.1
Project
Evaluat
ion
1.3
.2
Project
Launch
Total
monthl
y
costs
$13
200
$20
000
$80
00
$38
000
$14
400
$13
000
$48
00
$400
000
$400
000
$100
0
$10
400
$66
00
Cumul
ative
costs
$13
200
$81
200
$13
000
$805
800
$10
400
$66
00
Assignment 2 PPMP20008 (T2 – 2019) V5

PMMP 20008 – Initiating and Planning Projects (T2) Assignment 2
7 RISKS (TOTAL = 5 MARKS)
Response Table
Project Name
Name Description Likelihood Impact Response
Type
Mitigation
Strategy
Threat 1 Incorrect
Requirements
Gathering
Medium High Avoid This can be
mitigated by
development of a
detailed project
plan prior to
project start
Threat 2 Schedule
Issue
Low High Mitigate The schedule
issues can be
mitigated by
reducing the
project delays
Threat 3 Budget Issue High Medium Avoid The budget issue
can be avoided
by completion of
each task within
deadline
Threat 4 Technical
Issue
Medium High Transfer A technical
expert can be
appointed for
project
supervision
(Heagney, 2016)
Opportunity 1 Involvement
of the
Students of
CQU
campuses
Low High Accept Participation of
the students is
anticipated in
this project
Assignment 2 PPMP20008 (T2 – 2019) V5
7 RISKS (TOTAL = 5 MARKS)
Response Table
Project Name
Name Description Likelihood Impact Response
Type
Mitigation
Strategy
Threat 1 Incorrect
Requirements
Gathering
Medium High Avoid This can be
mitigated by
development of a
detailed project
plan prior to
project start
Threat 2 Schedule
Issue
Low High Mitigate The schedule
issues can be
mitigated by
reducing the
project delays
Threat 3 Budget Issue High Medium Avoid The budget issue
can be avoided
by completion of
each task within
deadline
Threat 4 Technical
Issue
Medium High Transfer A technical
expert can be
appointed for
project
supervision
(Heagney, 2016)
Opportunity 1 Involvement
of the
Students of
CQU
campuses
Low High Accept Participation of
the students is
anticipated in
this project
Assignment 2 PPMP20008 (T2 – 2019) V5
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

PMMP 20008 – Initiating and Planning Projects (T2) Assignment 2
8 TOLERANCES (TOTAL = 2 MARKS)
Response Table
Tolerance Specific Tolerance Allowance
Tolerance specified for time +20 days
Tolerance specified for cost +$15,000
Assignment 2 PPMP20008 (T2 – 2019) V5
8 TOLERANCES (TOTAL = 2 MARKS)
Response Table
Tolerance Specific Tolerance Allowance
Tolerance specified for time +20 days
Tolerance specified for cost +$15,000
Assignment 2 PPMP20008 (T2 – 2019) V5

PMMP 20008 – Initiating and Planning Projects (T2) Assignment 2
9 LESSONS LEARNT (TOTAL = 2 MARKS)
Response Table
Previous Lessons Learnt Proposed Action to
Address (In the
Current Project)
In the Work Package
which activity will be
added
Lesson 1
A higher (than expected) number of people,
attending opening ceremonies at some of the
campuses. The higher number of people
resulted in overcrowding in small areas and
some confusion in campus responsibilities for
workplace health and safety compliance.
Appointment of the
volunteers for
managing and guiding
the crowd (Mir &
Pinnington, 2014)
Appointment of
volunteers during
launch of the Project
Lesson 2:
A supplier of goods and services who failed to
address the various nuances existing between
different indigenous Australians located in
various geographical areas.
Proper Research
about the indigenous
Australians, prior to
project start
Detailed research in
the Initial Stage
Assignment 2 PPMP20008 (T2 – 2019) V5
9 LESSONS LEARNT (TOTAL = 2 MARKS)
Response Table
Previous Lessons Learnt Proposed Action to
Address (In the
Current Project)
In the Work Package
which activity will be
added
Lesson 1
A higher (than expected) number of people,
attending opening ceremonies at some of the
campuses. The higher number of people
resulted in overcrowding in small areas and
some confusion in campus responsibilities for
workplace health and safety compliance.
Appointment of the
volunteers for
managing and guiding
the crowd (Mir &
Pinnington, 2014)
Appointment of
volunteers during
launch of the Project
Lesson 2:
A supplier of goods and services who failed to
address the various nuances existing between
different indigenous Australians located in
various geographical areas.
Proper Research
about the indigenous
Australians, prior to
project start
Detailed research in
the Initial Stage
Assignment 2 PPMP20008 (T2 – 2019) V5

PMMP 20008 – Initiating and Planning Projects (T2) Assignment 2
PROJECT SUBMISSION APPROVAL (TO BE COMPLETED BY THE
STUDENTS)
The undersigned acknowledge that they have reviewed the CQU Educational Hubs for
Indigenous Studies Project Assessment Task 2 and agree with the information
presented within this document.
Signature: Please Insert………………………………………..
Date: 05-09-2019……………………………………………..
Print Name:
Please Insert
……………………………………………..
Title:
Please Insert
……………………………………………………..
Organisation: Please Insert
…………………………………………………………..
Assignment 2 PPMP20008 (T2 – 2019) V5
PROJECT SUBMISSION APPROVAL (TO BE COMPLETED BY THE
STUDENTS)
The undersigned acknowledge that they have reviewed the CQU Educational Hubs for
Indigenous Studies Project Assessment Task 2 and agree with the information
presented within this document.
Signature: Please Insert………………………………………..
Date: 05-09-2019……………………………………………..
Print Name:
Please Insert
……………………………………………..
Title:
Please Insert
……………………………………………………..
Organisation: Please Insert
…………………………………………………………..
Assignment 2 PPMP20008 (T2 – 2019) V5
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.

PMMP 20008 – Initiating and Planning Projects (T2) Assignment 2
REFERENCES:
# REFERENCE LIST
1. Aryana, B., Clemmensen, T., & Boks, C. (2015). Users’ participation in requirements
gathering for smart phones applications in emerging markets. Universal Access in the
Information Society, 14(2), 265-280.
2. Bourne, L. (2016). Stakeholder relationship management: a maturity model for
organisational implementation. Routledge.
3. Butt, A., Naaranoja, M., & Savolainen, J. (2016). Project change stakeholder
communication. International Journal of Project Management, 34(8), 1579-1595.
4. Heagney, J. (2016). Fundamentals of project management. Amacom.
5. Iglesias, C.P., Thompson, A., Rogowski, W.H. & Payne, K., (2016). Reporting
guidelines for the use of expert judgement in model-based economic
evaluations. Pharmacoeconomics, 34(11), pp.1161-1172.
6. Kerzner, H. (2017). Project management: a systems approach to planning,
scheduling, and controlling. John Wiley & Sons.
7. Kossmann, M., (2016). Requirements management: How to ensure you achieve what
you need from your projects. Routledge.
8. Meredith, J. R., Mantel Jr, S. J., & Shafer, S. M. (2017). Project management: a
managerial approach. John Wiley & Sons.
9. Mir, F. A., & Pinnington, A. H. (2014). Exploring the value of project management:
linking project management performance and project success. International journal of
project management, 32(2), 202-217.
10. Wilson, K.J., (2017). An investigation of dependence in expert judgement studies with
multiple experts. International Journal of Forecasting, 33(1), pp.325-336.
Assignment 2 PPMP20008 (T2 – 2019) V5
REFERENCES:
# REFERENCE LIST
1. Aryana, B., Clemmensen, T., & Boks, C. (2015). Users’ participation in requirements
gathering for smart phones applications in emerging markets. Universal Access in the
Information Society, 14(2), 265-280.
2. Bourne, L. (2016). Stakeholder relationship management: a maturity model for
organisational implementation. Routledge.
3. Butt, A., Naaranoja, M., & Savolainen, J. (2016). Project change stakeholder
communication. International Journal of Project Management, 34(8), 1579-1595.
4. Heagney, J. (2016). Fundamentals of project management. Amacom.
5. Iglesias, C.P., Thompson, A., Rogowski, W.H. & Payne, K., (2016). Reporting
guidelines for the use of expert judgement in model-based economic
evaluations. Pharmacoeconomics, 34(11), pp.1161-1172.
6. Kerzner, H. (2017). Project management: a systems approach to planning,
scheduling, and controlling. John Wiley & Sons.
7. Kossmann, M., (2016). Requirements management: How to ensure you achieve what
you need from your projects. Routledge.
8. Meredith, J. R., Mantel Jr, S. J., & Shafer, S. M. (2017). Project management: a
managerial approach. John Wiley & Sons.
9. Mir, F. A., & Pinnington, A. H. (2014). Exploring the value of project management:
linking project management performance and project success. International journal of
project management, 32(2), 202-217.
10. Wilson, K.J., (2017). An investigation of dependence in expert judgement studies with
multiple experts. International Journal of Forecasting, 33(1), pp.325-336.
Assignment 2 PPMP20008 (T2 – 2019) V5
1 out of 17
Related Documents

Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
© 2024 | Zucol Services PVT LTD | All rights reserved.