This assignment presents a comprehensive project plan for the establishment of CQU Educational Hubs for Indigenous Studies. The project aims to develop educational hubs across five CQU campuses to enhance students' understanding of indigenous culture. The plan meticulously details the project description, including background and major deliverables, and identifies key stakeholders, categorizing their interests and influence. It addresses requirements management, including gathering, traceability, and prioritization. The scope is defined through a Work Breakdown Structure (WBS) and a WBS dictionary, providing cost estimates and timelines for each phase. A schedule is provided, along with a cost baseline. Furthermore, the project plan includes a risk assessment, tolerance levels, and lessons learned, offering a holistic approach to project management. The plan also covers the process for obtaining expert judgement and communication methods for stakeholders. The project plan's structure follows the assignment brief, which details the requirements for the project including the design and build of educational hubs at CQU campuses. The project plan covers various aspects of the project management life cycle.
tabler-icon-diamond-filled.svg

Contribute Materials

Your contribution can guide someone’s learning journey. Share your documents today.
Document Page
PMMP 20008 – Initiating and Planning Projects (T2) Assignment 2
INFORMATION PAGE
[Students to complete]
PROJECT NAME: CQU EDUCATIONAL HUBS
FOR INDIGENOUS STUDIES
PROJECT
TERM & ASSIGNMENT # TERM 2, ASSIGNMENT 2
TITLE: PROJECT PLAN
STUDENT
NAME
STUDENT
NUMBER
QUESTIONS
ANSWERED (BE
SPECIFIC)
CAMPUS: <<Insert campus or distance>>
TUTOR: <<Insert tutor name>>
TUTORIAL NUMBER: <<Insert the tutorial number>>
Assignment 2 PPMP20008 (T2 – 2019) V5
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
PMMP 20008 – Initiating and Planning Projects (T2) Assignment 2
TABLE OF CONTENTS
1. Project Description (Total = 4 marks)
2. Stakeholders (Total = 10 marks)
3. Requirements Management (Total = 5 marks)
4. Scope (Total = 10 marks)
5. Schedule (Total = 6 marks)
6. Cost Baseline (Total = 6 marks)
7. Risks (Total = 5 marks)
8. Tolerances (Total = 2 marks)
9. Lessons Learnt (Total = 2 marks)
Assignment 2 PPMP20008 (T2 – 2019) V5
Document Page
PMMP 20008 – Initiating and Planning Projects (T2) Assignment 2
Instructions for Students
1. This document is a template with response tables for you to complete and has been
tailored to suit the assessment.
2. Instructions and guidance notes are provided in blue italicized to provide an
explanation of what should be included in your responses.
3. Please remove all blue text prior to using Turnitin and uploading your
complete response into Moodle.
4. Where there are two or more options for you to decide between, revert to the option
you are keeping in black and remove the other.
5. This assignment is designed for educational purposes to assess your
understanding of specific topics presented in this scenario.
6. Marks by Section:
Sections Mark %
Section 1 4 8 %
Section 2 10 20 %
Section 3 5 10 %
Section 4 10 20 %
Section 5 6 12 %
Section 6 6 12 %
Section 7 5 10 %
Section 8 2 4 %
Section 9 2 4 %
Totals 50 100 %
Assignment 2 PPMP20008 (T2 – 2019) V5
Document Page
PMMP 20008 – Initiating and Planning Projects (T2) Assignment 2
1 PROJECT DESCRIPTION (TOTAL = 4 MARKS)
1.1 PROJECT DESCRIPTION, BACKGROUND AND MAJOR DELIVERABLES (1
MARK)
Response Table
1 Description The project is focused over the development of educational
hubs at five different locations of Australia. The primary
scope of the project would be focused over the selection of
suitable facilities and venues, organise and conduct the
design aspects of the educational hubs.
2 Background The School of Engineering and Technology (SET) have
been involved in the process of developing projects based
on acknowledging the culture of local custodians. Hence,
they have planned for the building of educational hubs at 5
different locations.
3 Major Deliverables The primary deliverables of the project comprise of:
1. Preparing a well manageable project plan to develop the
entire project.
2. Designing the technical plan for the development of
educational hubs (Chen, 2015)
3. To organise the different procurable items for managing
the ceremonies.
1.2 JUSTIFICATION (3 MARKS)
Response Table
Output Outcome Benefits
Tangible products, which are
the educational hubs (Ibnouf,
Dou & Knight, 2014)
Educational changes and
new focusing over various
improvements
Long-term benefits for the
educational sector that would
be supported from the latest
technology present within the
educational hubs
2 STAKEHOLDERS (TOTAL = 10 MARKS)
2.1 KEY STAKEHOLDER LIST (6 MARKS)
Response Table
# Stakeholder Category (i.ie Sponsor /
Supplier / User)
Description of
Interest
Description of
Influence
1. Project Manager Sponsor They would
manage the
project
management
aspects and
scheduling of
They would help in
scheduling of every
kind of activity that
would be
performed during
the work of
Assignment 2 PPMP20008 (T2 – 2019) V5
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
PMMP 20008 – Initiating and Planning Projects (T2) Assignment 2
work construction.
2. Construction
Manager
Sponsor They would be
highly interested
in developing a
high quality
technical plan
based on putting
positive impacts
towards the
project.
They would form
specific decisions
that would further
help in putting
impacts towards
the betterment of
the project and the
outcomes.
3. Labours User They would be
interested in
completion of
the project
within the
assigned time
period and
expecting
payments in
return
(Houghton, Foth
& Miller, 2014).
They would have a
higher influence as
the outcomes of
the project would
depend on the type
of work that would
be done by them.
4. Guest Artists User They would
have an interest
based on
encouraging
people to make
use of the
facility provided
at the
educational
hubs.
Based on the
encouragement
provided to people
for the educational
hubs, people would
join these hubs.
5. Educational
Board
Sponsor The board
would have a
high interest
over the project
as they would
expect the
project to be
completed
within the
required
deadline (Qian
Walker &
Bryant, 2016).
They would majorly
influence the
construction
manager based on
developing the
project plan within
the assigned
deadline.
6. Teachers User They would
have interest
within the
project as they
would be able to
teach new
educational
aspects to
students.
They would be able
to influence the
students based on
making use of the
new learning
concepts.
2.2 STAKEHOLDERS ENGAGEMENT ASSESSMENT MATRIX (3 MARKS)
Assignment 2 PPMP20008 (T2 – 2019) V5
Document Page
PMMP 20008 – Initiating and Planning Projects (T2) Assignment 2
Response Table
# Stakeholders Unaware Resistant Neutral Supportive Leading
1. Project
Manager
C
2. Construction
Manager
C
3. Labours
4. Guest Artists
5. Educational
Board
D C D
6. Teachers C D
Assignment 2 PPMP20008 (T2 – 2019) V5
Document Page
PMMP 20008 – Initiating and Planning Projects (T2) Assignment 2
2.3 STAKEHOLDER COMMUNICATION (1 MARK)
Response Table
Communication Method Interactive, Pull or Push Justification
Face-to-Face Interaction Interactive This mode of communication
is highly interactive in nature
as it helps in understanding
the necessities of each
employee working over the
project (Waisbord, 2018).
2.4 OBTAINING EXPERT JUDGEMENT (1 MARK)
Response Table
Experts Methods / Techniques
Construction Manager Interviews
Project Manager Brainstorming
Assignment 2 PPMP20008 (T2 – 2019) V5
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
PMMP 20008 – Initiating and Planning Projects (T2) Assignment 2
3. REQUIREMENTS MANAGEMENT (TOTAL = 5 MARKS)
3.1 TRADITIONAL CUSTODIAN/S OF THE LAND ON WHICH CQ UNIVERSITY CAMPUSES
ARE LOCATED (1 MARK).
Response Table
Public Relationship Manager
3.2. OPENING STATEMENT STYLE (1 MARK)
Response Table
Welcome to Country – This kind of opening statement style will help would help the campus
leaders to understand the importance of the educational hubs and would also gain a feeling that
these educational hubs would be able to integrate the massive functionalities.
3.3 REQUIREMENTS GATHERING FOR CQU EDUCATIONAL HUBS FOR INDIGENOUS
STUDIES PROJECT (1 MARK)
Response Table
Different requirements that would be gathered based on designing the educational hubs should be
gathered from top level of research over the developmental aspects. It would also help in saving a
considerable amount of time and money from the research (Lee, Park, & Lee, 2015). Research
from previous successful project would also help in designing the current project in a successful
manner.
3.4 REQUIREMENTS TRACEABILITY (0.5 MARK)
Response Table
Regular update on mail – Any kind of requirements that would be required during the project
life cycle should be updated on mail. This would help the project manager and construction
manager to carefully trace each of the requirements and thus gain an understanding over the
necessities for the project.
3.5 REQUIREMENTS PRIORITIZATION PROCESS (1 MARK)
Response Table
Each of the requirements that would be required for the project should be communicated to the
stakeholders. Any kind of new requirement should be communicated to the higher management
who would process and assess each of the requirements carefully.
3.6 MoSCoW TECHNIQUE (0.5 MARK)
Response Table
# Components Explanation
Assignment 2 PPMP20008 (T2 – 2019) V5
Document Page
PMMP 20008 – Initiating and Planning Projects (T2) Assignment 2
1. Must-have initiatives Some of the initiatives such as the implementation of the
educational hubs should be planned in advance. Hence, the
project manager should take a major initiative for planning of the
developmental aspects.
2. Should-have initiatives The project manager and construction manager should prepare a
construction plan and a project plan, which can be discussed as
should-have initiatives within the entire project (Tyagi et al.,
2015).
3. Could-have initiatives The project could have included future development and
maintenance plans based on incurring the best form of culture for
the students.
4. Will not have (this time) The project would not have the discussion initiatives based on
understanding the particular technologies that would be
implemented at the new hubs.
Assignment 2 PPMP20008 (T2 – 2019) V5
Document Page
PMMP 20008 – Initiating and Planning Projects (T2) Assignment 2
4 SCOPE (TOTAL = 10 MARKS)
4.1 INTRODUCTION TO SCOPE (1 MARK)
Response Table
Preparing a Technical Plan for Construction – The construction plans would be discussed with
the different companies who would perform the construction works. The plan would be designed by
construction manager who would be responsible for mapping of the regions and making
appropriate construction plans.
Developing the facility space – The facility space would be constructed after the partial designing
of the construction work.
Planning of locations for developing the educational hubs – After the facility space have been
developed, the locations would be mapped based on building of educational hubs. These locations
would be spread across Australia. During this phase, the suitable venue and included facilities
would be discussed.
Implementation of construction phase – After the location have been selected and the contract
has been signed, the construction phase would be initiated (Grudin, 2017). This would include the
purchasing of construction materials and dealing with the entire phase of construction.
Procuring items for ceremony – After the construction have been completed, a ceremony would
be conducted. Before the ceremony, the items would be procured that would help in implementing
the ceremony.
Management of opening ceremony – After each of the arrangements would be made, the
ceremony would commence. Guests would be invited for the event in order to demonstrate the
educational hubs.
4.2 WORK BREAKDOWN STRUCTURE (3 MARKS)
Assignment 2 PPMP20008 (T2 – 2019) V5
CQU Educational
Hubs for Indigenous
Studies Project
Facility
space
Preparing a
Technical Plan
for Construction
Developing the
facility space
Educational hubs
Planning of
locations for
development
Implementation
of construction
phase
Opening
ceremonies
Procuring items
for ceremony
Management of
opening
ceremony
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
PMMP 20008 – Initiating and Planning Projects (T2) Assignment 2
4.3 WBS DICTIONARY (6 MARKS)
Preparing a Technical Plan for Construction
WBS ID 2.1
Description of work A plan for understanding of the technical work would
be understood and thus be approved by the
committee.
Cost Estimate $64800
Start and Finish Dates Mon 26-08-19 to Wed 18-09-19
Developing the facility space
WBS ID 2.2
Description of work After the approval have been gained, the work for the
development of facility space would initiate.
Cost Estimate $581480
Start and Finish Dates Thu 19-09-19 to Wed 13-05-20
Planning of locations for developing the educational hubs
WBS ID 3.1
Description of work After the facility space would be developed, the
locations would be planned based on understanding
the development space.
Cost Estimate $93600
Start and Finish Dates Thu 14-05-20 to Thu 18-06-20
Implementation of construction phase
WBS ID 3.2
Description of work After the locations have been planned, the
construction phase would begin.
Cost Estimate $187440
Start and Finish Dates Fri 19-06-20 to Tue 29-06-21
Procuring items for ceremony
Assignment 2 PPMP20008 (T2 – 2019) V5
Document Page
PMMP 20008 – Initiating and Planning Projects (T2) Assignment 2
WBS ID 4.1
Description of work In this phase, the list of items that need to be
procured for the ceremony would be listed and
procured for the ceremony
Cost Estimate $54000
Start and Finish Dates Wed 30-06-21 to Wed 21-07-21
Management of opening ceremony
WBS ID 4.2
Description of work After the items have been procured, the ceremony
would begin and a dinner event would be hosted
Cost Estimate $8000
Start and Finish Dates Thu 22-07-21 to Tue 27-07-21
Assignment 2 PPMP20008 (T2 – 2019) V5
Document Page
PMMP 20008 – Initiating and Planning Projects (T2) Assignment 2
5 SCHEDULE (TOTAL = 6 MARKS)
5.1 SCHEDULE
Preparing a Technical Plan for Construction
ACTIVITY DESCRIPTION OF WORK START DATE END DATE DURATION
(DAYS)
2.1.1 Preparing for a meeting Mon 26-08-19 Tue 03-09-19 7
2.1.2 Proposing a project plan for
facility space
Wed 04-09-19 Wed 18-09-19 11
2.1.3 Approval over the project
plan
Wed 18-09-19 Wed 18-09-19 0
Developing the facility space
ACTIVITY DESCRIPTION OF WORK START DATE END DATE DURATION
(DAYS)
2.2.1 Procurement of materials Thu 19-09-19 Tue 15-
10-19
19
2.2.2 Initiation of construction works Wed 16-10-19 Thu 26-
03-20
117
2.2.3 Maintenance over the construction
works
Fri 27-03-20 Wed 13-
05-20
34
Planning of locations for developing the educational hubs
ACTIVITY DESCRIPTION OF WORK START DATE END DATE DURATION
(DAYS)
3.1.1 Mapping of the locations Wed 13-05-20 Tue 09-06-20 19
3.1.2 Preparing contracts Wed 10-06-20 Thu 18-06-20 7
3.1.3 Signing over the different
business contracts
Thu 18-06-20 Thu 18-06-20 0
Implementation of construction phase
ACTIVITY DESCRIPTION OF WORK START DATE END DATE DURATION
(DAYS)
3.2.1 Preparing for the initial
construction works
Fri 19-06-20 Thu 02-07-20 10
3.2.2 Initiation of construction
works for educational hubs
Fri 03-07-20 Tue 29-06-21 258
3.3.3 Completion of Construction
phase
Tue 29-06-21 Tue 29-06-21 0
Procuring items for ceremony
ACTIVITY DESCRIPTION OF WORK START DATE END DATE DURATION
(DAYS)
4.1.1 Procuring items Wed 30-06-21 Fri 02-07-21 3
4.1.2 Contract with artists Mon 05-07-21 Tue 20-07-21 12
4.1.3 Procurement of catering
materials and stage
decoration
Wed 21-07-21 Wed 21-07-21 1
Management of opening ceremony
ACTIVITY DESCRIPTION OF WORK START DATE END DATE DURATION
(DAYS)
Assignment 2 PPMP20008 (T2 – 2019) V5
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
PMMP 20008 – Initiating and Planning Projects (T2) Assignment 2
4.2.1 Event program Thu 22-07-21 Thu 22-07-21 1
4.2.2 Demonstration of the various
educational hubs
Fri 23-07-21 Mon 26-07-
21
2
4.2.3 Dining event Tue 27-07-21 Tue 27-07-21 1
6. COST BASELINE (TOTAL = 6 MARKS)
Response Table
Timeline (months)
WBS
id
WP / Activity
name 1 2 3 4 5 6 7 8 9 10 11 12
2.1 Preparing a
Technical Plan
for
Construction
2.2 Developing the
facility space
3.1 Planning of
locations
3.2 Implementation
of construction
phase
4.1 Procuring
items for
ceremony
4.2 Management of
opening
ceremony
Total monthly
costs
64800 581480 281040 54000 8000
Cumulative
costs
$989320
Assignment 2 PPMP20008 (T2 – 2019) V5
Document Page
PMMP 20008 – Initiating and Planning Projects (T2) Assignment 2
7 RISKS (TOTAL = 5 MARKS)
Response Table
Project Name
Name Description Likelihood Impact Response
Type
Mitigation Strategy
Threat 1 The
construction
phase might
get
elongated
due to
natural
disasters
Medium High Proper
Planning
A separate plan
should be designed
to avoid the risks due
to natural disasters.
The workers should
be provided with an
insurance facility in
case they would be
affected by disasters.
Threat 2 The budget
for the
project might
get
elongated
due to
incurring of
other aspects
within the
project
Medium Low Estimation Planning over the
budget should be
prepared in advance.
An additional budget
should also be kept
at hand in case any
form of emergency
affects the project.
Threat 3 The
resources for
the project
might be
inefficient to
perform the
required
tasks.
High Medium Strategic Each of the
resources that would
be allocated for the
project should be
allocated during the
preparation of project
plan (Guo et al.,
2014).
Threat 4 The
agreement
for the land
might not be
approved
based on
improper
documents
or project
plan.
Low Low Planning The agreement for
the project and
approval of the
project plan should
be made before the
mapping of locations.
Opportunity 1 The
educational
hubs would
open a major
opportunity
to expand
the business.
High High Strategic The future plans for
the business and
incurring of benefits
after the
development of the
educational hubs
should be focused
before the project
plan would be
developed and
planned.
Assignment 2 PPMP20008 (T2 – 2019) V5
Document Page
PMMP 20008 – Initiating and Planning Projects (T2) Assignment 2
Assignment 2 PPMP20008 (T2 – 2019) V5
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
PMMP 20008 – Initiating and Planning Projects (T2) Assignment 2
8 TOLERANCES (TOTAL = 2 MARKS)
Response Table
Tolerance Specific Tolerance Allowance
Tolerance specified for time 502
Tolerance specified for cost $1000000
Assignment 2 PPMP20008 (T2 – 2019) V5
Document Page
PMMP 20008 – Initiating and Planning Projects (T2) Assignment 2
9 LESSONS LEARNT (TOTAL = 2 MARKS)
Response Table
Previous Lessons Learnt Proposed Action to Address
(In the Current Project)
In the Work Package
which activity will be
added
Lesson 1
The project plan for the development of
the educational hubs should be
prepared by the construction manager
after the land agreement have been
planned
The project plan should be
designed by the construction
manager with the help of
project manager
2.1.2 Proposing a
technical plan
Lesson 2:
The concept of the educational hubs
should be shared with the construction
manager in order to help them in
assisting and suggesting new sectors
that could also be included within the
project plan.
During the meeting phase, a
separate presentation need to
be shown to the construction
manager and thus ideas
should be collected for
successful development of
project
3.1.1 Planning of the
desired locations
Assignment 2 PPMP20008 (T2 – 2019) V5
Document Page
PMMP 20008 – Initiating and Planning Projects (T2) Assignment 2
PROJECT SUBMISSION APPROVAL (TO BE COMPLETED BY THE
STUDENTS)
The undersigned acknowledge that they have reviewed the (Project Name) Assessment
Task 2 and agree with the information presented within this document.
Signature: ……………………………………………………………..
Date: ……………………………………………………………..
Print Name: ……………………………………………………………..
Title: ……………………………………………………………..
Organisation:
[Guidance Notes:
Consider who would have the authority
to approve the start of this project?] ……………………………………………………………..
Assignment 2 PPMP20008 (T2 – 2019) V5
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
PMMP 20008 – Initiating and Planning Projects (T2) Assignment 2
REFERENCES:
[Guidance Notes:
Include your reference list and ensure that you have used in-text referencing as per the APA
referencing style.] Please note that at least nine (9) references must be used.
# REFERENCE LIST
1. Chen, P. Y. (2015). Transnational education: Trend, modes of practices and
development. International Journal of Information and Education
Technology, 5(8), 634.
2. Grudin, J. (2017). Obstacles to participatory design in large product
development organizations. In Participatory Design(pp. 99-119). CRC
Press.
3. Guo, F., Chang-Richards, Y., Wilkinson, S., & Li, T. C. (2014). Effects of project
governance structures on the management of risks in major
infrastructure projects: A comparative analysis. International Journal of
Project Management, 32(5), 815-826.
4. Houghton, K., Foth, M., & Miller, E. (2014). The local library across the digital
and physical city: Opportunities for economic
development. Commonwealth journal of local governance, 39-60.
5. Ibnouf, A., Dou, L., & Knight, J. (2014). The evolution of Qatar as an education
hub: Moving to a knowledge-based economy. In International education
hubs (pp. 43-61). Springer, Dordrecht.
6. Lee, J., Park, J. G., & Lee, S. (2015). Raising team social capital with
knowledge and communication in information systems development
projects. International Journal of Project Management, 33(4), 797-807.
7. Qian, H., Walker, A., & Bryant, D. A. (2016). Global trends and issues in the
development of educational leaders. In Handbook of research on the
education of school leaders (pp. 67-88). Routledge.
8. Tyagi, S., Cai, X., Yang, K., & Chambers, T. (2015). Lean tools and methods to
support efficient knowledge creation. International Journal of Information
Management, 35(2), 204-214.
9. Waisbord, S. (2018). Family tree of theories, methodologies, and strategies in
development communication. Handbook of Communication for
Development and Social Change, 1-40.
Assignment 2 PPMP20008 (T2 – 2019) V5
chevron_up_icon
1 out of 20
circle_padding
hide_on_mobile
zoom_out_icon
logo.png

Your All-in-One AI-Powered Toolkit for Academic Success.

Available 24*7 on WhatsApp / Email

[object Object]