This report provides a comprehensive overview of various procurement methods available for building projects, aiming to guide clients in selecting the most suitable approach based on their objectives and priorities. It delves into three primary methods: Traditional, Design and Construct, and Construction Management, detailing their characteristics, advantages, and disadvantages. The report emphasizes the importance of early decision-making, informed by the client's business case and an understanding of the associated risks. It explores the distinctions between the methods, such as the separation of design and construction in the Traditional approach, the contractor's design responsibilities in Design and Construct, and the management-focused role in Construction Management. The analysis includes competitive tendering, price certainty, and the potential for innovation and time savings, while also acknowledging challenges such as the time-consuming nature of the Traditional method and the complexities of preparing a comprehensive brief for Design and Construct. The report concludes by highlighting the importance of considering the client's specific needs and the potential impact of each procurement method on project outcomes.
tabler-icon-diamond-filled.svg

Contribute Materials

Your contribution can guide someone’s learning journey. Share your documents today.
Document Page
Procurement methods
Assessment
Name:
Submitted to:
Date:
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
Executive Summary
There are a plethora of methods so as to procure a building project that is available in the market
and fulfill the needs of the clients. It is a daunting task to decide the method to be used for the
project according to the objectives and priorities of the client which are improve the projected
likelihood that is being procured successfully. It is imperative to make the decision as early as
possible, and it must be underpinned by the business case of the client and his project. Further,
the client must be provided with the insights of the risks and the effects of the procurement
method on the project.
This report provides an insight to the procurement method to be adopted by the client and
outlines the various means which can help in obtaining the objectives of the projects related to
the procurement method. A clear understand towards the characteristics of various procurement
methods have been provided in the report. The procurement methods provided in the traditional,
design and construct and management. Further the report discusses the advantages and
disadvantages of each method.
1
Document Page
Table of Contents
Executive Summary.........................................................................................................................2
Introduction......................................................................................................................................4
Discussion........................................................................................................................................6
A. Traditional Procurement...................................................................................................6
Advantages and disadvantages................................................................................................7
B. Design and Construct Procurement.........................................................................................8
Advantages and disadvantages................................................................................................9
C. Construction Management Procurement.........................................................................10
Advantages and disadvantages..............................................................................................11
References......................................................................................................................................14
2
Document Page
Introduction
A procurement system is also known as the delivery system and can be defined as an
organizational system which is responsible for assigning authorities and responsibilities to the
people as well as the organization. The procurement system helps in defining the various
elements present in the project construction (Love et al. 1998:p.222). The procurement systems
are classified as Traditional, Design and construct, Management and Collaborative.
These systems have been sub-classified but these sub-divisions are seen to proliferate as per the
market demands. It has been stated by Holt et al. (2000), many variables are presented to each of
the adopted procurement strategies. For instance, about eight variants of the design, as well as
construct systems, have been identified in the procurement guidelines of the NSW Government
(2005). There are a variety of commonly adopted contract methods and the procurement systems
which have been discussed below. This report discusses the first three procurement systems
namely Traditional, Design and construct and Construction Management. The report provides a
detailed description of the various characteristics and the conditions for using these procurement
systems. The paper further discusses the various risks associated with the procurement system
and the client will be affected by all the discussed methods. A figure provided below provides
insight on how the client will be affected and the speculative risks for the client and the
contractor for a particular procurement method.
3
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
The contractor first assumes various risks in the design and construct forms of procurement
present in the project. The variations in the design and construct are present where the various
levels of the design risks are apportioned. The intention is usually to balance the fair and risks
among the parties in the tradition lump sum contracts. However, greater the risks assumed by the
contractor with greater balance there is a higher tendency to have the larger tender figure. The
balance of the risk is seen to be most onerous for the client in the management forms of
procurement as the contracts provide only the ‘management expertise' to his project.
4
Document Page
Discussion
A. Traditional Procurement
In this traditional procurement approach, it is accepted by the employer that the design work will
be going to be separated from the construction. The consultants must be appointed for the design
and cost control, and furthermore, the contractor is hired for taking responsibility of the carrying
out the work. The authority and the responsibility must be extended to all the material, and
workmanship and hence encompasses the subcontractor's and supplier's works. One usual
method of appointing the contractor is through the competitive tendering on the basis of
complete information and knowledge. However, in some cases, the appointment takes place by
negotiation on the basis of notional or partial knowledge.
There are two-stage tendering in the traditional method and sometimes occurrence of the
negotiated tendering takes place and therefore it is also known as the ‘Accelerated Traditional
Method.' In this procurement method, the design and construction is usually seen to run in a
parallel manner in a limited extent. This form of procurement method allows start of the project
on the site at a comparative early stage and also less certainty is entailed regarding the cost
issues. There are three types of contracts in this procurement method:
1. Lump sum contract: The contract sum is usually seen to be determined before the
construction starts and the agreement also has the amount entered in it.
2. Measurement contracts – The contract sum is identified on the completion of the project.
3. Cost reimbursement – Based on the actual labor costs, material and plant costs, and the
contract sum is seen to be identified, and a cover overhead along with profit is also added
to it. (Rowlinson, S., 1999).
5
Document Page
Advantages and disadvantages
The main benefits of this approach towards the procurement are listed below:
1. Because the contractor's bid on the same criteria and basis, there is a competitive equity;
2. Accountability owing to the competitive selection;
3. There is a direct influence among the design lead and the client facilitating an advanced
level of functionality and therefore improving the overall design and its quality;
4. The certainty of the price at the contract award;
5. Any change or variation in the contract is easy to manage and arrange;
6. The market is familiar with the tried and test method of procurement.
The main disadvantages of this approach towards the procurement are listed below:
1. The process of full contract documentation is a timely process. Although there is a
provision of production of an incomplete design from the tender documents but this case
might lead to less cost as well as time and therefore its ultimately leads to disputes.
6
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
2. The overall direction of the project is seen to take a longer time as compared to the other
procurement methods of the sequential strategy. Furthermore the construction cannot be
commenced before the design gets completed; and
3. There is no input given to the planning or designing of the project by the contractor
because the contractors are not seen to be appointed by the design stage.
B. Design and Construct Procurement
In the design and construct procurement method, the responsibility of for almost all the designs
is given to the contractor. Hence there must be a provision like the express reference in the
contract along with setting up of the design liability in a clear manner. In case the statements in
the contract are stating otherwise then the liability for design becomes an absolute liability which
helps the contractor to warrant the purpose and its fitness. The design liability of the contractor is
seen to be limited in the cases of some of the design and construct forms to the professional duty
which has to be exercised with reasonable skill and care. When the contractor hires an
independent consultant, they are, hence, under the liability which is no greater than the normal
ones. Unless it is backed by some kind of indemnity insurance, the acceptance of this liability is
seen to be worthless. Therefore it must be checked before appointing any contractor. The
contractor can use external consultants in the absence of the in-house designers, but the identity
has to be established before the acceptance of the tender (Skitmore, R.M., and Marsden, D.E.,
1998).
The requirement of the clients can be stated in a simple and brief manner more than the
accommodation schedule and the site plan. Or it includes a hundred pages of specifications. This
procurement method offers a certainty on the sum of the contract and therefore brings cost
benefits. A competitive price is provided to the client due to a close integration of the freedom
7
Document Page
given to the contractor for using their purchasing power with the efficient market knowledge and
design and construction methods. This method helps in ensuring the quicker start at the site and
even results in effective programming. But the process required time due to the consultants of the
client preparing the requirements and further comparing and evaluation of schemes so as to
compete in the tenders. Any change in the contract can be costly afterward.
Advantages and disadvantages
The main benefits of this approach towards the procurement are listed below:
1. The client is allowed only to deal with one firm at a time thereby reducing the
need for committing towards the resources and time for contracting all the
designers and contractors individually;
2. Before the construction commences the price certainty is obtained due to the
requirement of the client which are highly specified and changes are not
introduced;
3. Stimulation towards the innovation and reduction in the time and cost takes place
due to use of a guaranteed maximum price with a savings option split;
4. The project time can be reduced due to overlap of the design and construction
activities; and
8
Document Page
5. The constructability due to input of the contractor into the design.
The main disadvantages this approach to procurement are:
1. There are high chances of difficulties to be experienced by the clients during the
preparation of an adequate as well as appropriately comprehensive brief;
2. Any client changes in the scope of the project can be expensive;
3. There is always a difficulty in comparing bids due to different design and
variations of the project program among the bidders, and lastly, the project prices
are going to be different for each design;
4. The commitment from the client towards the concept design is required at an
early stage and is usually demanded before the completion of the detailed designs;
and
5. Limitations of the design liability to the available standard contracts.
C. Construction Management Procurement
In this procurement method, a contractor is paid the fees in order to manage, develop the
program and then the coordination of the design and construction activities. Further, he is
responsible for facilitating the collaboration in order to improve the constructability of the
project. The contractor in this method is selected after an intensive selection process and is then
paid the promised management fee. The work contracts are arranged, and the consequently
administered by the management contractor but they are in a direct contact between the work
contractor and the client. Therefore, this procurement method provides a higher control measure
but it indirectly possesses a considerable amount of risk to the client. The management
contractor does not guarantee the completion time as well as cost and is merely considered as an
agent. Walker (1999) identified various advantages which are summarized as given below:
9
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
• There is a reduced confrontation among the supervising team and the design teams.
• The construction management expertise are involved in an early stage;
• There is a good overlap of design and construction;
• In the large projects, there is an increased competition towards the construction work because
of the work packaging as well as the construction activities are digested into a more digestible
'chunks';
• Higher level of documentation development;
• There are lesser number of contract variations;
• This method provides public accountability;
• There is no need for the nominated trade contractors.
Advantages and disadvantages
The main advantages of this approach procurement are:
10
Document Page
• The client is usually committed to the one firm only which helps in improved coordination as
great collaboration among the designers and the constructors;
• There is a high potential of the saving of time for the overall project in the design and
construction activities being overlapped efficiently;
• It is the responsibility of the contractor to assume the risk as well as the responsibility for the
integration of the construction and the designing.
• The works packages are let at the current competitive prices;
• There is an improved constructability through constructor input;
• All the roles, risks as well as the responsibilities of all parties are extremely clear; and
• There is a scope of flexibility for changes in design and construction.
The main disadvantages of this approach in procurement are:
• The price certainty cannot be achieved until letting of final works package takes place.
• There is a requirement of the informed and proactive client.
• The price certainty is relatively poor.
• Requirement of the close time and information control
• The client loses all the direct control towards the design quality because is it directly swayed by
the constructors.
• A good quality instruction must be provided to the design team due the incompletion of the
design until resources are intensively committed to the project.
11
Document Page
12
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
References
Walker, D., Sidwell, A. & Hampson, K. (1999), Project Procurement and Alliances - A
Continuum of Competition to Cooperation, RMIT, Melbourne
Love, P.E.D., Skitmore, R.M., and Earl, G. (1998). Selecting a suitable procurement method for
a building project. Construction Management and Economics, 16(2), pp.221-233.
Love, P.E.D., Gunasekaran A., and Li, H. (1998). Concurrent engineering: a strategy for
procuring construction projects. International Journal of Project Management, 16(6), pp.375-383.
Holt, G.D., Proverbs, D., and Love, P.E.D. (2000). Survey findings on UK construction
procurement: Is it achieving lowest cost, or value? Asia Pacific Building and Construction
Management Journal, 5, pp.13-20.
New South Wales Government (2005). Procurement Methodology Guidelines for Construction.
Version 1, February, NSW Government, Sydney, Australia.
Skitmore, R.M., and Marsden, D.E. (1998). Which procurement system? – towards a universal
procurement selection technique. Construction Management and Economics, 6, pp.71-89.
Rowlinson, S. (1999). Selection criteria. In. Rowlinson, S., and McDermott, P. Procurement
Systems: A Guide to Best Practice in Construction. E & F Spon, London, pp.276-299.
13
chevron_up_icon
1 out of 14
circle_padding
hide_on_mobile
zoom_out_icon
logo.png

Your All-in-One AI-Powered Toolkit for Academic Success.

Available 24*7 on WhatsApp / Email

[object Object]