Project Management: Designing Supermarket Management System
VerifiedAdded on  2022/09/30
|9
|923
|25
Project
AI Summary
This project designs a supermarket management system to improve supermarket operations. The project's scope includes managing stock, purchases, billing, and transactions. The schedule outlines phases such as initiation, requirement analysis, design, development, validation, and sign-off, spanning 77 days. The cost analysis details expenses for each task, including project management, design, and development, totaling $19,280. The system aims to enhance customer service and operational efficiency by effectively managing data, sales, and payments. The project also includes a detailed bibliography with references to project management principles.

Running head: PROJECT MANAGEMENT
PROJECT MANAGEMENT-
DESIGNING SUPERMARKET MANAGEMENT SYSTEM
Name of the Student
Name of the University
Author Note
PROJECT MANAGEMENT-
DESIGNING SUPERMARKET MANAGEMENT SYSTEM
Name of the Student
Name of the University
Author Note
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

1PROJECT MANAGEMENT
Table of Contents
Project scope....................................................................................................................................2
Schedule for the supermarket..........................................................................................................2
Cost for the supermarket..................................................................................................................5
Bibliography....................................................................................................................................8
Table of Contents
Project scope....................................................................................................................................2
Schedule for the supermarket..........................................................................................................2
Cost for the supermarket..................................................................................................................5
Bibliography....................................................................................................................................8

2PROJECT MANAGEMENT
Project scope
The main aim of the project is to design a supermarket management system that will be
able to provide better support towards the activities performed within the supermarket. The
problems that are faced within the supermarket are plenty and thus it becomes essential to
understand each component effectively. Supermarket management system is one of the essential
management system that has the potential to meet the needs the customers. It has been expected
that the supermarket management system will be able to manage the information related to each
stock and purchase that is taking place within the market. The main aim behind designing the
supermarket management system is to ensure that the billing and transactions process have been
carried out successfully. Each products have been entered within the system so that it becomes
easy to manage the performance. The supermarket management system has the potential to
manage the sales activity and will ensure that proper monitoring is done on the supermarket
system. Supermarket management system will ensure that the data related to each login and
payments have been stored effectively. With the implementation of supermarket management
system the reliability and flexibility of the system will increase. This will enhance the services
offered towards the customers and the supermarket authorities. The advanced system will be
able to meet the needs of the customer and will enhance the system. This will provide better way
of functioning the activities and will ensure that the time has been consumed for carrying out the
project.
Schedule for the supermarket
Task Name Duration Start Finish
Project scope
The main aim of the project is to design a supermarket management system that will be
able to provide better support towards the activities performed within the supermarket. The
problems that are faced within the supermarket are plenty and thus it becomes essential to
understand each component effectively. Supermarket management system is one of the essential
management system that has the potential to meet the needs the customers. It has been expected
that the supermarket management system will be able to manage the information related to each
stock and purchase that is taking place within the market. The main aim behind designing the
supermarket management system is to ensure that the billing and transactions process have been
carried out successfully. Each products have been entered within the system so that it becomes
easy to manage the performance. The supermarket management system has the potential to
manage the sales activity and will ensure that proper monitoring is done on the supermarket
system. Supermarket management system will ensure that the data related to each login and
payments have been stored effectively. With the implementation of supermarket management
system the reliability and flexibility of the system will increase. This will enhance the services
offered towards the customers and the supermarket authorities. The advanced system will be
able to meet the needs of the customer and will enhance the system. This will provide better way
of functioning the activities and will ensure that the time has been consumed for carrying out the
project.
Schedule for the supermarket
Task Name Duration Start Finish
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

3PROJECT MANAGEMENT
Supermarket management system 77 days Tue 9/17/19 Wed 1/1/20
Phase1: Initiation 10 days Tue 9/17/19 Mon 9/30/19
Identify issues 2 days Tue 9/17/19 Wed 9/18/19
Provide planning for MIS 3 days Thu 9/19/19 Mon 9/23/19
Blue print for supermarket 2 days Tue 9/24/19 Wed 9/25/19
Identifying the benefits 3 days Thu 9/26/19 Mon 9/30/19
Phase 2: Requirement analysis 4 days Tue 10/1/19 Fri 10/4/19
Specify requirements 4 days Tue 10/1/19 Fri 10/4/19
Requirements elicitation 2 days Tue 10/1/19 Wed 10/2/19
Gathering requirements 2 days Thu 10/3/19 Fri 10/4/19
Phase 3: Designing 20 days Mon 10/7/19 Fri 11/1/19
System designing 2 days Mon 10/7/19 Tue 10/8/19
Developing the architecture 3 days Wed 10/9/19 Fri 10/11/19
user interface designing 4 days
Mon
10/14/19
Thu 10/17/19
requirements analysis 4 days Fri 10/18/19 Wed 10/23/19
Feasibility analysis 2 days Thu 10/24/19 Fri 10/25/19
Creating awareness about the use 5 days Mon Fri 11/1/19
Supermarket management system 77 days Tue 9/17/19 Wed 1/1/20
Phase1: Initiation 10 days Tue 9/17/19 Mon 9/30/19
Identify issues 2 days Tue 9/17/19 Wed 9/18/19
Provide planning for MIS 3 days Thu 9/19/19 Mon 9/23/19
Blue print for supermarket 2 days Tue 9/24/19 Wed 9/25/19
Identifying the benefits 3 days Thu 9/26/19 Mon 9/30/19
Phase 2: Requirement analysis 4 days Tue 10/1/19 Fri 10/4/19
Specify requirements 4 days Tue 10/1/19 Fri 10/4/19
Requirements elicitation 2 days Tue 10/1/19 Wed 10/2/19
Gathering requirements 2 days Thu 10/3/19 Fri 10/4/19
Phase 3: Designing 20 days Mon 10/7/19 Fri 11/1/19
System designing 2 days Mon 10/7/19 Tue 10/8/19
Developing the architecture 3 days Wed 10/9/19 Fri 10/11/19
user interface designing 4 days
Mon
10/14/19
Thu 10/17/19
requirements analysis 4 days Fri 10/18/19 Wed 10/23/19
Feasibility analysis 2 days Thu 10/24/19 Fri 10/25/19
Creating awareness about the use 5 days Mon Fri 11/1/19
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

4PROJECT MANAGEMENT
10/28/19
Phase 5: Development phase 32 days Mon 11/4/19 Tue 12/17/19
designing objects for system 4 days Mon 11/4/19 Thu 11/7/19
defining user interface 3 days Fri 11/8/19 Tue 11/12/19
designing architecture 2 days
Wed
11/13/19
Thu 11/14/19
prototyping 6 days Fri 11/15/19 Fri 11/22/19
Testing and feasibility analysis 6 days
Mon
11/25/19
Mon 12/2/19
Phase 6: Validation 11 days Tue 12/3/19 Tue 12/17/19
Implement the system 3 days Tue 12/3/19 Thu 12/5/19
evaluating the system with
requirements
5 days Fri 12/6/19 Thu 12/12/19
validating the system 3 days Fri 12/13/19 Tue 12/17/19
Phase 7: Signing Off 11 days
Wed
12/18/19
Wed 1/1/20
Checking feasibility 3 days
Wed
12/18/19
Fri 12/20/19
providing update towards the 4 days Mon Thu 12/26/19
10/28/19
Phase 5: Development phase 32 days Mon 11/4/19 Tue 12/17/19
designing objects for system 4 days Mon 11/4/19 Thu 11/7/19
defining user interface 3 days Fri 11/8/19 Tue 11/12/19
designing architecture 2 days
Wed
11/13/19
Thu 11/14/19
prototyping 6 days Fri 11/15/19 Fri 11/22/19
Testing and feasibility analysis 6 days
Mon
11/25/19
Mon 12/2/19
Phase 6: Validation 11 days Tue 12/3/19 Tue 12/17/19
Implement the system 3 days Tue 12/3/19 Thu 12/5/19
evaluating the system with
requirements
5 days Fri 12/6/19 Thu 12/12/19
validating the system 3 days Fri 12/13/19 Tue 12/17/19
Phase 7: Signing Off 11 days
Wed
12/18/19
Wed 1/1/20
Checking feasibility 3 days
Wed
12/18/19
Fri 12/20/19
providing update towards the 4 days Mon Thu 12/26/19

5PROJECT MANAGEMENT
supermarket 12/23/19
Signing off 4 days Fri 12/27/19 Wed 1/1/20
Cost for the supermarket
Task Name Resource Names Cost
Supermarket management system $19,280.00
Phase1: Initiation $2,000.00
Identify issues Project manager $320.00
Provide planning for MIS market analyst $480.00
Blue print for supermarket Project manager ,designer $720.00
Identifying the benefits Project manager $480.00
Phase 2: Requirement analysis $1,120.00
Specify requirements $1,120.00
Requirements elicitation Requirements analyst $400.00
Gathering requirements
Requirements
analyst ,system analyst
$720.00
Phase 3: Designing $5,576.00
System designing market analyst $320.00
supermarket 12/23/19
Signing off 4 days Fri 12/27/19 Wed 1/1/20
Cost for the supermarket
Task Name Resource Names Cost
Supermarket management system $19,280.00
Phase1: Initiation $2,000.00
Identify issues Project manager $320.00
Provide planning for MIS market analyst $480.00
Blue print for supermarket Project manager ,designer $720.00
Identifying the benefits Project manager $480.00
Phase 2: Requirement analysis $1,120.00
Specify requirements $1,120.00
Requirements elicitation Requirements analyst $400.00
Gathering requirements
Requirements
analyst ,system analyst
$720.00
Phase 3: Designing $5,576.00
System designing market analyst $320.00
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

6PROJECT MANAGEMENT
Developing the architecture designer, system analyst $1,080.00
user interface designing $0.00
requirements analysis Project manager ,developer $1,536.00
Feasibility analysis Project manager ,designer $720.00
Creating awareness about the use developer, market analyst $1,920.00
Phase 5: Development phase $8,448.00
designing objects for system developer, market analyst $1,536.00
defining user interface designer, market analyst $1,080.00
designing architecture
Project
manager ,Requirements
analyst
$720.00
prototyping
market analyst, software
analyst
$2,400.00
Testing and feasibility analysis market analyst $960.00
Phase 6: Validation $1,752.00
Implement the system designer,market analyst $1,080.00
evaluating the system with requirements $0.00
Developing the architecture designer, system analyst $1,080.00
user interface designing $0.00
requirements analysis Project manager ,developer $1,536.00
Feasibility analysis Project manager ,designer $720.00
Creating awareness about the use developer, market analyst $1,920.00
Phase 5: Development phase $8,448.00
designing objects for system developer, market analyst $1,536.00
defining user interface designer, market analyst $1,080.00
designing architecture
Project
manager ,Requirements
analyst
$720.00
prototyping
market analyst, software
analyst
$2,400.00
Testing and feasibility analysis market analyst $960.00
Phase 6: Validation $1,752.00
Implement the system designer,market analyst $1,080.00
evaluating the system with requirements $0.00
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

7PROJECT MANAGEMENT
validating the system developer $672.00
Phase 7: Signing Off $2,136.00
Checking feasibility designer $600.00
providing update towards the supermarket developer $896.00
Signing off Project manager $640.00
validating the system developer $672.00
Phase 7: Signing Off $2,136.00
Checking feasibility designer $600.00
providing update towards the supermarket developer $896.00
Signing off Project manager $640.00

8PROJECT MANAGEMENT
Bibliography
Hornstein, H.A., 2015. The integration of project management and organizational change
management is now a necessity. International Journal of Project Management, 33(2), pp.291-
298.
Kerzner, H., 2017. Project management: a systems approach to planning, scheduling, and
controlling. John Wiley & Sons.
Meredith, J.R., Mantel Jr, S.J. and Shafer, S.M., 2017. Project management: a managerial
approach. John Wiley & Sons.
Bibliography
Hornstein, H.A., 2015. The integration of project management and organizational change
management is now a necessity. International Journal of Project Management, 33(2), pp.291-
298.
Kerzner, H., 2017. Project management: a systems approach to planning, scheduling, and
controlling. John Wiley & Sons.
Meredith, J.R., Mantel Jr, S.J. and Shafer, S.M., 2017. Project management: a managerial
approach. John Wiley & Sons.
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide
1 out of 9
Related Documents
Your All-in-One AI-Powered Toolkit for Academic Success.
 +13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
Copyright © 2020–2025 A2Z Services. All Rights Reserved. Developed and managed by ZUCOL.