Managing a Successful Computing Project
AVITA
Aung Pyae Kyaw | 10 Batch
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
24
Table of Contents
P1................................................................................................................................................3
Project aims and objectives for a chosen scenario.....................................................................3
Aims.......................................................................................................................................3
Objective.................................................................................................................................3
P2................................................................................................................................................4
Project management plan that covers aspects of cost, scope, time, quality, communication,
risk and resources.......................................................................................................................4
P3................................................................................................................................................8
Produce a work breakdown structure and a Gantt Chart............................................................8
Gantt Chart.............................................................................................................................8
Work Breakdown structure.....................................................................................................8
M1..............................................................................................................................................9
Project management plan, milestone schedule and project schedule for monitoring and
completing the aims and objectives of the project.....................................................................9
Project schedule for monitoring and completing the aims and objectives of the project........10
P4..............................................................................................................................................11
Carry out small-scale research by applying qualitative and quantitative research methods
appropriate for meeting project aims and objectives..............................................................11
M2............................................................................................................................................12
The accuracy and reliability of different research methods.....................................................12
D1.............................................................................................................................................13
Critically evaluate the project management process appropriate research methodologies
applied......................................................................................................................................13
P7..............................................................................................................................................16
The value of undertaking the research.....................................................................................16
M 4...........................................................................................................................................17
Value of the project management process and use of quality research....................................17
Learning and Performance...................................................................................................18
D 2............................................................................................................................................19
The decision-making process and changes or developments of the initial project management
plan to recommendations and learning during the project.......................................................19
Project Logbook.......................................................................................................................20
Performance Review Template................................................................................................22
References................................................................................................................................24
Document Page
24
P1
Project aims and objectives for a chosen scenario.
Aims
I am project manager at The Great Digital Company. I
have three aims in life about our product. The first thing is I
want to give safety life, second is health and thirdly is
wellbeing for our customer. So, I want to produce fitness
tracker watch at our Company. The name of fitness tracker
watch brand is (Samsung) S6. Fitness tracker watch is giving
support for our customer. Nowadays, many people use phone and watch so fitness tracker
watch can connect both things. It is also easy to use for our customer. Fitness tracker watch
can show notification in phone, can alert so people instance of watch using fitness tracker
watch. We want to give protect for our customer by our company so we want to use digital
wellbeing to our product. Fitness tracker watch is very advantage for our human. Now people
are using dangerous digital wellbeing so we want to produce smart watch to change safety
digital wellbeing.
If someone use smart watch, he or she can know blood pressure, heart rate, motional,
temperature, walking steps, sleep tracking, SpO2, exercises and GPS (location) including
these things can be safety for our customer. A person who is working continuously per a day
not doing activity it can be not good for safety. If he or she put smart watch can be noticing
about their safety by telling fitness tracker watch. But they are not using fitness tracker watch
they cannot notice about their safety.
Fitness tracker watch always checks out our body so it is always careful for our
health. Sometime we are forgot our health at that time fitness tracker watch alert us so we can
be notice and careful our health by our self. It is benefit about fitness tracker watch. Indeed,
people use phone and another digital device it can cause not good for our health. When we
use fitness tracker watch, we don’t need to use another device so our health more better using
fitness tracker watch.
Document Page
24
Objective
We need to making more effective system to get
wellbeing. We cannot get wellbeing using phone due to
frequency, wave and light so we need to change using fitness
tracker watch it has not dangerous than phone. It will be
supporting to get wellbeing for our customer.
Easy to get safety life putting fitness tracker watch. We cannot get safety life using
another digital device. Another device cannot show result of check out our body. But if we
use fitness tracker watch, we can know happening our body easily.
Fitness tracker watch support customer health. For people, main important is good
for health so if we put fitness tracker watch we already know about our health. Basic of this
product aims are to get good health to our customer. In this device, more effective digital
wellbeing is including so we can get profit of our health.
P2
Project management plan that covers aspects of cost, scope, time,
quality, communication, risk and resources.
Cost
If we run one of the projects, the basically need is amount of
cost. Our company give responsibility to do the project. For me, I
need to summit amount of cost for the whole project to our superior.
I want to divide three part for this project. These are cost for
professional programmer, cost of system device and labor charges.
Firstly, we need to use 500$ cost of professional programmer for each person because I will
hire three professional programmers. So, the cost of programmer for 1500$ need to use.
And also, we must hire software designer and software developer. They will be do
better plan to get internal feature for our project. So, this is responsibility for software
designer and software developer. We must use 600$ each for them. We will be use both of
them. That is why, the charges for software designer and software developer is 1200$. After
finish software designer duty, a person needs to tasting for our program. So, we need to hire
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
24
taster for him we must use 500$. If we get better plan to produce our product, we will be
giving our document to analyze. For this step, we must to take a person who do analyzing for
him we must use 600$. Lastly, our project is to get fitness tracker so we need to set up this
watch for thus we need to give a job to our worker. The cost for them will be 300$ each
person. We will hire 5 persons to set up watch. Total cost of this project employee is 5300$.
And then, watch body make the necessary devices for the part. The cost of this part is about
60$. Total cost of this project is about 5360$.
Scope
Before we held meeting, I command my team to take a
note. If we know roughly about our product, we can submit to
our superior about our product. And also, if someone want to
know our product they can know easily and clearly reading
scope.
For the whole project, it will be cost 5360$ including labor charges and machinery.
We need round about 70 days to do our product.
Our product is to get good health for people. So, quality is prefect about health using
digital wellbeing.
Before we start our product, we will collect data from using out of model people.
While we are doing our project, we will communicate with the other member. When
our product come out, we will communicate with customer.
Everything has a lot of problem and also our project. We need to do our product
during 70 days and cost is also 5360$.
Lastly, I give advice to our team member and also, I take suggestion from them. Our team
have unity so we can get better product. I am waiting and seeing to our team member who
has problem or not. If they have problem, I will solve about this problem. Conclusion, I am
expected to get perfect product of fitness tracker.
Time
We need to take seventeen days to finish this cost so we will
take 8 hours per day for our labor. We will give 24 days for training
for program, 7 days for software designing, 8 days for software
developing, another 6 days for testing, 7 days for analyzing and the
Document Page
24
last 18 days is to produce for our product. Program will start their job the first of our project.
After they finish their job, they will combine program and watch so both of things need to
stop before twenty days of the last month. The last month is need to check out which part of
our program need to repair and our watch. Finally, we will be got prefect our job and time is
also fit.
Quality
When we use fitness tracker, we can get more comfortable life for
us. The advantages of using these things is we can know easily blood
pressure, heart rate, motional, temperature, walking steps and GPS
(location). Most people don’t careful about their health. Some body
devotee their time to work business, education and other things. So, they
forget their health but this fitness tracker can be help for everybody. When we put on this
watch, it is light. Even though we are taking bath we can put on this watch. Water cannot be
destroying this watch and also it is smart for using people. The price is also reasonable for
customer. The external feature of watch body is square shape.
In the internal feature, we will be use full color 0.95-inch amole touchscreen (240 x
120 pixels), bright and vibrant amole display, responsive touch, 24 x 7 heart rate monitoring,
lightweight, compact charging cradle, basic phone notifications. Heart rate monitoring
(optical sensor), six-axis accelerometer, gyro sensor. Wight of fitness tracker is 22.7 grams.
5ATM 50-meters water resistant. Swimming Posture Recognition: six-axis sensor recognizes
main strokes, Records speed, distance, number of turn and other data. Long standby time up
to 14 days and saves time on frequent charging, smart assistant and notification reminders or
stopwatch. Bluetooth is 4.2 and battery is 100mAh. Above of things are indigents for fitness
tracker.
Communication
First of all, we communicate our team. Our team
have 11 persons including me. When we start our
projects, we need to communicate each other and also, I
need to communicate our superior to support our project
with money. In our team, if we have not unity, we
cannot get better plan to produce our product. So, in our team whenever we need something
we must say clearly and politely what we need and how can we do to get that. Leader also
Document Page
24
give duty to inferior to their responsibility and need to have mutual understanding. If our
team have good communication, we can get better product before we thinking. When our
product is coming out, we will be communicating our customer to explain and to sell our
product.
Risk
Everything has problem and risk in this project also we met a
lot of risk. Our product is new and customer don’t know before about
this product so they don’t want to use this product. They wander to
use brand in the market but most of the teenager want to use newly
watch. Our team have 11 persons so everybody has like and dislike
thing. For this, we have a lot of risk to have unity and to have mutual
understanding. Everything has struggle to get aim in life. To get this product, we have a lot of
risk with superior and inferior. Our superior force us during this time with this money to
produce better product.
Resource
We use the whole project for three professional
programmers, software designer, software developer, tester, who
do analyze and three labors. The charges of total cost are 5360$.
During three months, we get (S6) fitness tracker watch. We use
lather string in our watch and also body frame is square shape. It
is light and smart for using people. The internal feature of this
watch is to take blood pressure, heart rate, motional, temperature, walking steps, exercises
and GPS (location). We combine internal feature and external feature in other word installing
software and hardware.
P3
Produce a work breakdown structure and a Gantt Chart
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
24
Gantt Chart
Work Breakdown structure
Document Page
24
M1
Project management plan, milestone schedule and project
schedule for monitoring and completing the aims and objectives
of the project.
Requirement analysis
There are two kinds of requirement analysis in our
project. They are admin requirement analysis and user
requirement analysis. Admin requirement is based on
customer requirement analysis because most of customer
always want to use comfortable things, more functionable
things and long-term to save battery but they don’t want to
use much money. So, we always look for our customer feedback to get using people more
and more. This is responsibility for admin. So, admin requirement analysis is really
concerned with customer. Admin give duty to programmer to be a better than first product so
programmer do his program develop day by day. When they doing more effective program,
they need to use money again.
Milestone schedule
Before programming milestone, we are passing
planning and meeting with our team. After that we got
programming milestone. Before software designing
milestone, we are doing choose software frame and
functionable things after that we got a milestone. When
we are doing software developing, we passed preparing
more effective. Lately, we reach software developing milestone. The last step is tasting and
analyzing. Testing performance is doing check out about programming. And also, we
processed tasting milestone. The last one is system analysis including software analysis and
hardware analysis. Finally, we got analysis milestone.
Document Page
24
Project schedule for monitoring and completing the aims and
objectives of the project.
1) Project Initiation
Our superior give duty to
produce new things from our company
so I held metting with superior and
inferior. In this metting, every body
gave suggestion to produce new
things. Among them, we chosed to make digital wellbing. Our superior made me project
manager for this project. So, I collected many people and I choosed co-worker to make team.
After we got a team, we are thinking about produce what digital wellbing. Finally, we got an
idea to produce fitness tracker.
2) Project Planing
Before doing plan, we held metting with our team. Eventhough I am project manager
but I want to take suggestion form my co-worker. What they need and what do they want to
be? They want to support customer health and bussiness so they want to make fitness tracker
watch. It is also reasonable about our burget. First of our planing is to take programmer,
software desinger, software developer, tester and who analyzing for this project. Second step
is divided duty to respective person and remainded them to finish during three months. Last
step is how much we can be used the whole project.
3) Project Execution
Respective person doing their duty step by step. Programmer written his
programming, software desinger choose design and to set up body frame, software developer
is doing update system, tester is checking out one by one and who analyzing is making
analysis the whole system.
4) Project Monitoring and control
After we got fitness tracker watch, we use this watch to test which part is good or bad.
Some part have the problem we need to repare about this part. Project manager is always
watching inferior don’t miss fitness tracker.
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
24
5) Project Closure
After we passed above all stage, we finish our work. Finally, we got our product.
Five step of above all showing things are using with Agile Project Management
Methodology. Our project is concern with this methodology.
P4
Carry out small-scale research by applying qualitative and
quantitative research methods appropriate for meeting project
aims and objectives.
Before we made planning, we collect
information and data collection about weakness point
of fitness tracker watch who invented before we
produce. When we held meeting, we take suggestion
how can we get information about fitness tracker. So,
we made decision to collect information from youtube,
Google and using people. We task duty who is collect information from youtube, Google and
using people. Instance of using watch more effective using fitness tracker watch. Fitness
tracker is helped for people health but watch is not like that. Some of the fitness tracker has
not to take SpO2(amount of oxygen in blood) and Gym exercises.
Qualitative research method
Our team met using people about fitness tracker. We are collected information from
using people and google about fitness tracker. So, we used one on one interview method and
text analysis method. When we interview them, we can guess how is their feeling using that.
Quantitative research method
Even though we collect information from mail, google
and using people but we get answer from using people. So, we
used survey method. When we use survey method, it is easy to
use and also easy to collect data gathering.
Document Page
24
M2
The accuracy and reliability of different research methods.
When we used one on one interview method, we can meet using people one by one.
And also, we can get data information freely and exactly from them. Now, they are using
fitness tracker so their answer must be correct. We can get prefect answer from them because
we met outside. They also want to answering about our question so they met freely.
We can get more information from google using text analysis method. It is also easy
to use and ask to other people on google. So, we don’t need to use energy and time. When we
use internet, we can get more information from Google. Just for fill the form we can get
information exactly. It is really fast to get information.
If we use both of them, we can get more information not to give much time. Now a
day most of the people use a lot of time in their business and education so we cannot get
information fast but if we go to park and road, we can get information. Lastly, for me using
internet is good for us so we find information from google. It will be easy for everyone.
Most of the teenager use of the internet so we can get information other ways like that
mail and Google. Both of things we get data information and also get from using people.
Finally, we get information from them so our data is using survey method. When we use this
method, we can a lot of information because there have three things. Like that, mail, google
and using people.
Document Page
24
D1
Critically evaluate the project management process appropriate
research methodologies applied.
We are showing above our aim and object is to produce (S6) fitness
tracker because we want to take care health about people using this fitness
tracker. We want to give wealthy being using this fitness tracker. When
everybody uses this product, they can know their health easily and quick.
Our product is reasonable price so every class can use this product. Fitness
tracker can check about health every time and everywhere.
Before we start our product, we do twice meet. First of meeting is with our superior
because they give me responsibility to be a project manager of this product. I also accept this
command. Second of meeting is with our team after I get command about this project. For
this project, we spent much money for labor charges and device because our company is
digital wellbeing company so we don’t need to use to buy machine. We use 5360$ for this
product. We need to take a note before we start our product so we are doing note including
cost, scope, time, quality, communication, risk and resource.
We do our product during 70 days. We make training
for programmer during 24 days. For them, cost is 1500$.
During this training, they make a plan, meeting and write a
program. Finish one step they make milestone about their
project. For this project, we use 1500$ about labor charges. We give software designer for
seven days. They also make a plan about their duty. They choose design about this project
and software framework. After that, they do milestone about their designing during about
three days. We use labor charges 600$about this step. We also give software developing for
eighty days to finish their work. Firstly, they prepare about their work during 5 days. They
also make their software to be more effective. Thus, is also make during 3days.They make
milestone step by step. We are using 600$ for them.
Tester also testing the whole product. They are also really important for the whole
project. But I can give them for 6 days so they do in a hurry. First of their step is to check
about software. Another is to make a milestone about testing. They also finish during 6 days.
For them, we use 500$. A person who make analysis also doing their work during 7days.
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
24
First, he makes system analysis and make milestone. For them, we use 600$. Finally, the
project end stage is assembled for watch. I can give them for 18 days. These days include,
made watch body is 15 days and the watch fitted and practical use 3 days. And them, the
watch result is good. So, the worker pays 1500$. Finally, the fitness tracker project
completely finished.
We are doing more effective things for our fitness tracker. Our fitness can take SpO2
for our body. (Samsung) S6 fitness tracker can take amount of Oxygen in the blood pressure.
It is special for our customer and also it is different other fitness tracker. Now a day, most of
the people go to fitness center (or) GYM. At that time, our fitness tracker can help for this
person. When they swim in the swimming pool, fitness tracker will show how many depths
reach this person and also will show process in the body this time. A person who sleep in the
day or in the night our fitness tracker can help for this person because it can show which time
is REM and NREM for this person. It can divide how many hours sleep to need for people.
We have three groups in this project from beginning to end. First group is our team,
second group is data collecting and third group is customer. These three groups are including
communication. In our team, everybody is co-worker so we haven’t problem to
communicate. But we need to have mutual understanding for other people in our group.
When we collect data collection, we need to have good communication from using people out
of date fitness tracker. During this time, we need other people help for our fitness tracker
which need for user and which prefect for user. So, we need to have long temper and also, we
must use polite word. When we distribute our fitness tracker, we must communicate with our
customer. We must do explain clearly and exactly about our fitness tracker and also, we need
to do customer want to buy our product. We need to have good communication and using
polite word.
During this project, we face a lot of problem because we are inferior and also, we
have our team. Our superior force us during this period must be finish our project. Time and
money also problem. When we make plan holding meeting at that time, we have problem.
Software designer finish his work he gives to software developer. They are also problem to
link one part to another part.
When we make decision about analysis, we find two kind of analysis. There are
admin analysis and customer analysis. Most of admin more need time and money about their
project. But it is good for customer and good for product. If quality is good about our product
Document Page
24
so we can get a lot of profit about this product. So, we need more than time and money.
Another is unity in our team. For customer, they need more effective things and reasonable
price. In our protect, we used good quality and prefect programming in this system. So,
admin analysis and customer are concern with each other.
For the whole project, I am project manager so I am thinking about which product can
we do it. Even though superior give me duty to do one product but they don’t give me which
product they need and how can we do that. So, I am thinking about which product can we get
profit for our company. I get an idea to produce fitness tracker. For this product, we passed
six steps. These are Training for programmer, Software designing, Software developing,
Testing, Analysis and Assemble for watch. The first step has three stages. They are planning,
meeting and write a program after that we got programming milestone. After we finished this
milestone, we go to second milestone. Second step has two stages. They are chosen design
and software framework. When we finished one stage, we made milestone. After we finished
two stages, we got designing milestone.
Now, we reach software developing milestone. This milestone has also two stages.
When we finished two stages, we made developing milestone. We reach midterm of our
project so we do test to improve our product. After we make checking and testing, we already
finished testing milestone. After that we do analysis the whole project. This stage has system
analysis. When we finished system analysis, we already finished analysis milestone. The last
is assemble for watch. During this period, this step has three stages. After that we got
working milestone because our program is started to work now.
Now a day, most of the project use Agile method because it is based on customer
service. And also, mostly use for small project because it can be prepared to be good result.
Agile method must be improved for product. For our project, we can use a lot of method but
our project is concerned with Agile method so we use this method. Our product is based on
customer service so we need to take data collection, doing face to face interview. During we
do this product, we need to find which part must to modified our product. If we choose other
method, we cannot modify so this method is really concerned with our product.
When I made decision to produce fitness tracker, I want to influence our product in
market orientation so I find out way to influence. I know if I want to influence our product,
we need to do what customer need so we must take information who use out of date fitness
tracker. Our team go to everywhere like that park and road. When we go to this place, we met
Document Page
24
thousands of people using this fitness tracker. During we take information from them, we get
a lot of data to add and prepare for our product.
We take information from people in this time we use one on one interview method
according to Qualitative research method. Even though we give a lot of time to take
information from people but we know about their mind using this product and also, we can
know what is expected for our product. For us, we know how can we influence our product
using this method. The other method is text analysis according to Qualitative research
method. We have not time to take information from people meeting outside so we use this
method because most of people use internet. We take data collection from google. We get
accuracy information because one on one interview method.
According to Quantitative research method, we gather data collection from google,
mail and using people. We can get information clearly and easily using online. This method
called survey method. Using this method, we don’t use spent much time. We get accuracy
information because survey method. We get a lot of helpful using this method. For this
project, there has a lot of method but our project is concerned with above method so we use
these methods. Our product is based on customer service so using this method we can see
customer mind about this.
P7
The value of undertaking the research
Now a day, most of the company
produce fitness tracker so people are also use
fitness tracker to support about their life. As
soon as we got this project, we make decision
to get success about this project. Our team
also decided to do fitness tracker. Before we
do our project, we divide duty so first step of
our project is to take data collection and information about this project. The purpose of to
take data collection is want to know need and want about customer. We also want to improve
and effective for our customer about our product. After we take data collection, we know
about user requirement so we can add some feature about fitness tracker.
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
24
Everybody wants to influence to their customer about their product. We also want to
influence about our product so our team try hard. Be influence we need to know user
requirement so basically supporting for our product is research. We want to fill customer will
so we go everywhere and we ask them one by one. Most of them are using out of date fitness
tracker so they also want to new model. We think we can get benefit both of us like our team,
our superior and customer.
When we take data collection, we also get also of knowledge before we don’t know
about these things. In our team, most of people don’t know about awareness but after they
take data collection, they get know concern about awareness. Our team aim is we want to
give more effective things for our customer so we need to learn about what we want to ask
from people. Conclusion, just we doing research and taking data collection we get a lot of
knowledge about people.
M 4
Value of the project management process and use of quality
research
Our superior give 70 days so we need to do our work very fast and make sure step by
step. Using this project methodology, we get a lot of success about this product. This project
methodology is easy to use, it is reliable to our product so we get successful life about our
project. Using Agile method, we are already
finish our project be successful. Agile method
has 5 stages. These are Project Initiation, Project
Planning, Project Execution, Project Monitoring
& Control and Project closure.
Project Initiation
Our superior made me project manager
for this project. So, I collected many people and I choosed co-worker to make team. After we
got a team, we are thinking about produce what digital wellbing. Finally, we got an idea to
produce fitness tracker.
Project Planning
Document Page
24
Before doing plan, we held metting with our team. First of our planing is to take
programmer, software desinger, software developer, tester and who analyzing for this project.
Second step is divided duty to respective person and remainded them to finish during three
months. Last step is how much we can be used the whole project.
Project Execution
Respective person doing their duty step by step.
Project Monitoring & Control
After we got fitness tracker watch, we use this watch to test which part is good or bad.
Some part have the problem we need to repare about this part.
Project closure
After we passed above all stage, we finish our work. Finally, we got our product.
We follow project methodology so the whole project is step by step and quickly to
finish our product. Being step by step is really important for us because we can guess
tomorrow which part we can do. And also, we can pretend and prepare during time. If we
face problem we can solve at once because we are doing step by step. For our project,
research method also effective.
Learning and Performance
Fitness tracker watch project is really important for
us and for our company. So, we are trying and doing be
prefect project as much as we can. To get successful
project, we are finding and research who made fitness and
which time they do it. After we know, how can we do good
fitness tracker other them. We are searching google,
YouTube and Facebook to know how to get prefect
product.
During this time, we are looking video and read book about our product. And also, we
bought one of fitness tracker. After that, we learn outer and inner appearance of fitness. We
want to know hardware and software about fitness tracker to know hardware developer and
software developer how did they do about hardware and software. We are trying learning
Document Page
24
about both of things. Our team have unity so we aren’t tired to do about that. Everybody has
responsibilities and duty mind so we are happy to do this project.
At the time, we are made for this project so we got many
different languages. We got good communication skill and time
management skill. We have more confident ourselves. For the whole
project, we learn a lot of things learning must get successful so we
think, we got successful end of our project. After we are learning, we
interview one by one who are using fitness tracker. And also, we are explained about fitness
tracker to our junior who don’t know about it. Other things are we are doing and research
how can we get good quality about our project.
D 2
The decision-making process and changes or developments of the
initial project management plan to recommendations and
learning during the project
For the whole project, really important
things are decision making. First, we are started to
decided which project we must do it. After that, we
got idea to do fitness tracker but first step is we are
doing milestone what to do. And also, we submit to
our superior and continue our project. Second milestone is to get good quality about our
project. Last milestone is to finish our job and to influence our customer.
Our team do step by step to be a good job. And also, last milestone is really
supporting for us because we are decided to give our quality on time to our customer. For
everybody, milestone and decision making are same. For us, it’s not like that. We are doing
decision making first because decision making is just thinking how to do it. We are not
started to do work at decision making step but in milestone step we are doing our work.
We are learning about these two things when we do our project. Our team thinking is
learning to be successful life so we started to learn
about our project and we are making our project with
our unity. Unity is also really important to get
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
24
colorful quality. For me, I think if we have more time, we can get more prefect quality. But,
now also we are doing our quality as much as we can. Our project must get successful and we
can be influencing our customer.
About this project, I have done a lot of things. After we
make decision making, we are started to do work. From that
time on, I have a lot of problem but this problem carries on to
get success. If superior give us more time, we can get more
successful. And also, we can give more effective health take
care of our customer using fitness tracker. Our fitness tracker must be taking care about our
customer healthy and also, they can be stratified our work.
We are doing our project step by step and also, we depth our mind on our project. We
want to give safety life to our environment and also using our fitness tracker can get safety of
our environment. First of all, customer also need to learn and do to know about fitness
tracker.
If they don’t know about our product, they also not to dare using our product. For this
case, we have idea when we produce our product, we need to explain about our product how
can everybody use and this product how can be effective and successful life to get for our
customer.
After they know about our product they will be thinking about our environment and
our company. And also, our aim also will be fulfilling. We are really wanted to give be good
healthy life so we produce this product. In this case, we are trying out of effort. We want to
give comfortable and safety who are sitting everyday in their work. Using our product be to
get safety life.
Project Logbook
Name: Aung Pyae Kyaw
Student ID: 10 Batch
Project Title: Fitness tracker of Digital Wellbeing
Update on weekly research/tasks achieved
What have you completed?
Document Page
24
Milestone is completed for our tasks.
Did you fulfill task requirements?
Yes, I had a lot of fulfill my task requiremments.
Did you need to make any changes to your project management plan?
I don’t think so about my project management plan.
Any risks and/or issues identified?
In our project hasn’t risks.
Did you identify risks/issues with a lack of skill required for undertaking research/tasks?
For me, I think evetything has requirement. And also, in our project also has
requirement.
Did you identify any additional risks/issues that have an impact on the project management
plan?
Customer need more effective things we are understanding but our requirement things
can be
impact on the project managemant plan for a little.
Problems encountered
What barriers did you face?
I face teamwork difficulty and superior pressure to finish our project on time.
How did you overcome them?
Important things is motivation and decision making. Both of them provide me.
What have I learnt about myself this week?
How did I feel when I had to deal with tasks/problems?
My mind is flesh and really comfortable about project.
Did I find it useful to complete the tasks?
Yes, I found it useful to complete the tasks.
Document Page
24
How well have I performed?
Learning, searching and thinking have I performed.
What did I contribute?
Important things is mind. We want to give good quality to our customer. This mind is
supporting for us.
What can I improve on next week?
Learning can be improve on next week.
How might this learning apply in the future?
This learning can be support 100% in the future.
Tasks planned for next week
Which tasks are priority?
Our project haven’t tasks.
Have you set aside sufficient time for completion?
No, I haven’t set aside sufficient time for completion.
Project plan status to date
During this time, we try hard to get good quality and to finish on time. A head, we
will be update, learning and searching about weakness of our project. And also, we will be
preparing about that.
Supervisor comments to address
Supervisor said that we get successful.
Performance Review Template
Performance Review
What was the project supposed to accomplish?
Unity of our team was the project supposed to accomplish.
tabler-icon-diamond-filled.svg

Secure Best Marks with AI Grader

Need help grading? Try our AI Grader for instant feedback on your assignments.
Document Page
24
Did the project succeed in its aims? How do you know?
Yes, our project succeed in its aims. We can influence our customer.
What things do you think worked well and why?
There have a lot of reasons but I wonder want to say three things there are unity,
decision and learning.
What problems emerged during the project and how were they tackled? Was there timely
identification of issues and resolution during the project process?
Everything have problem and also we finish our project on time. But we can solve
problem and now we got success. Yes, there was timely identification of issues and
resolution during the project process.
What did you learn from undertaking the project?
We are learning many from this project but only things we got if we havn’t unity and
aim we cannot fiinsh our work.
What strengths and weaknesses of your performance did you identify?
My strengths is I have aim and decision. My weaknesses is I have pressure to influence
Our customer.
How will this inform and support your continuous professional development?
I got confidence during this project and this confidence can be support in futre and also
I can do everything if I have aim and confidence.
Document Page
24
References
https://en.wikipedia.org/wiki/Smartwatch
https://www.gadgetsnow.com/slideshows/5-features-that-every-smartwatch-needs/
cellular-connectivity/photolist/57307760.cms
https://www.smartgeekwrist.com/advantages-of-smart-watch/
https://smartwatchlabs.com/what-are-the-benefits-of-a-smartwatch/
https://www.digitaltrends.com/mobile/google-digital-wellbeing-experiments-apps/
https://www.researchgate.net/publication/331345742_Digital_wellbeing_-_schools_-
_Research_Report
https://www.clarizen.com/what-are-the-basic-project-planning-steps/
https://experiments.withgoogle.com/collection/digitalwellbeing
https://www.slideshare.net/sazzadkarim2/experimental-38497054
https://www.questionpro.com/blog/qualitative-research-methods/
https://www.projectmanager.com/templates/work-breakdown-structure-template
https://project-management-knowledge.com/definitions/m/milestone-schedule/
https://learn.solent.ac.uk/mod/book/view.php?id=116233&chapterid=15294
https://www.info-trek.com/axelos/Agile-Project-Management//?
utm_source=google&utm_medium=cpc&utm_campaign=googleads&utm_term=agileproject
management&gclid=EAIaIQobChMI-KDLhNOn5gIVRoqPCh2rqg55EAAYASAAEgLkRfD_BwE
https://www.apm.org.uk/resources/find-a-resource/agile-project-management/
https://www.bl.uk/business-and-ip-centre/articles/qualitative-and-quantitative-research-
for-small-business
chevron_up_icon
1 out of 24
circle_padding
hide_on_mobile
zoom_out_icon
logo.png

Your All-in-One AI-Powered Toolkit for Academic Success.

Available 24*7 on WhatsApp / Email

[object Object]