Detailed Project Management Report for Eagle Eye Relocation Project
VerifiedAdded on 2023/01/12
|23
|6422
|65
Report
AI Summary
This report provides a comprehensive project management plan for the Eagle Eye company's relocation to Vancouver, Canada. It begins with an introduction to project management principles, followed by an analysis of the project manager's role in planning and responding to potential situations. The report then examines how performance, time, scope, and cost requirements can impact the project's success and the scope of the project. It emphasizes the importance of planning and scheduling for successful implementation, including a Work Breakdown Structure (WBS) and dictionary for the project. The report also includes a risk assessment and recommendations for managing potential risks, as well as an analysis of the role of process improvement in achieving long-term organizational goals. Finally, it discusses how project management practices can enhance the efficiency of process improvement life cycles, concluding with recommendations for the Eagle Eye relocation project.

Project management
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Table of Contents
INTRODUCTION...........................................................................................................................3
MAIN BODY...................................................................................................................................3
a) Role of project manager during project planning and respond to situation.......................3
b) 'Performance, time, scope and cost' requirement can support in helping or adversely
affecting project and scope of current project........................................................................4
c) Planning and scheduling of project help in successful implementation.............................7
d) WBS for the Eagle eye relocation project and dictionary..................................................8
e) Risk assessment and recommendation for responding to these risk................................12
f) Role of ‘Process improvement’ in being a strategic tool that helps organisations meet its
long term goals and objectives.............................................................................................15
g) g. project management practices can help improve the efficiency of process improvement
life cycles..............................................................................................................................18
Conclusions and Recommendation................................................................................................20
REFERENCES..............................................................................................................................22
INTRODUCTION...........................................................................................................................3
MAIN BODY...................................................................................................................................3
a) Role of project manager during project planning and respond to situation.......................3
b) 'Performance, time, scope and cost' requirement can support in helping or adversely
affecting project and scope of current project........................................................................4
c) Planning and scheduling of project help in successful implementation.............................7
d) WBS for the Eagle eye relocation project and dictionary..................................................8
e) Risk assessment and recommendation for responding to these risk................................12
f) Role of ‘Process improvement’ in being a strategic tool that helps organisations meet its
long term goals and objectives.............................................................................................15
g) g. project management practices can help improve the efficiency of process improvement
life cycles..............................................................................................................................18
Conclusions and Recommendation................................................................................................20
REFERENCES..............................................................................................................................22

INTRODUCTION
Project management refers to application of several skills, knowledge, processes and
experiences for achieving the specific objective as per the criteria of a particular project. It is all
about managing and executing all the activities involve within the project effectively as per the
finite timescale and budget. Project management is considered to be strategic approach which
focuses toward aligning all the available skills or resources in a manner that the project
requirement can be fulfilled effectively (Kerzner, 2017). The current report is based on a project
management plan of Eagle eye which is a global leader which offer range of threat detection and
screening technologies regarding transportation, military, resilience and security application.
Now, Eagle eye want to expand its business in Vancouver, Canada due to numerous of growth
opportunity present there. So, this project involves scope statement, planning and scheduling of
the project along with details about deliverables and responses of organisational units. It further
detail about the role of process improvement life-cycle, its role along with risks that may arise at
the time of execution of project.
MAIN BODY
a) Role of project manager during project planning and respond to situation
Project manager is a person who holds overall responsibility of a project i.e. from its
initiation, planning to its designing, execution, monitoring, managing and closing the project.
The project manager holds number of skills and capabilities which they use in order to
monitoring the team and available resources for ensuring that efforts must get6 aligned in right
direction toward the accomplishment of project objective (Meredith, Mantel and Shafer, 2017).
Eagle eye is a firm that deal in threat detecting and screening the technology that are
related with the military, security, resilience and technology application. Recently it get a large
client based in Canada and with the mutual consent of stakeholder they are planning to relocate
their headquarter within Canada which will start operating its business by 1st January, 2020. The
total budget for this relocation project would be 10 million USD and this involve relocation of
several operations such as accounting, finance, customer service, Research and development etc.
Hence, in order to start this relocating business, the project manager is require to develop a
detailed plan that support in explaining each and every action to be taken into consideration. For
this following are certain role that project manager has to perform throughout this project,
Project management refers to application of several skills, knowledge, processes and
experiences for achieving the specific objective as per the criteria of a particular project. It is all
about managing and executing all the activities involve within the project effectively as per the
finite timescale and budget. Project management is considered to be strategic approach which
focuses toward aligning all the available skills or resources in a manner that the project
requirement can be fulfilled effectively (Kerzner, 2017). The current report is based on a project
management plan of Eagle eye which is a global leader which offer range of threat detection and
screening technologies regarding transportation, military, resilience and security application.
Now, Eagle eye want to expand its business in Vancouver, Canada due to numerous of growth
opportunity present there. So, this project involves scope statement, planning and scheduling of
the project along with details about deliverables and responses of organisational units. It further
detail about the role of process improvement life-cycle, its role along with risks that may arise at
the time of execution of project.
MAIN BODY
a) Role of project manager during project planning and respond to situation
Project manager is a person who holds overall responsibility of a project i.e. from its
initiation, planning to its designing, execution, monitoring, managing and closing the project.
The project manager holds number of skills and capabilities which they use in order to
monitoring the team and available resources for ensuring that efforts must get6 aligned in right
direction toward the accomplishment of project objective (Meredith, Mantel and Shafer, 2017).
Eagle eye is a firm that deal in threat detecting and screening the technology that are
related with the military, security, resilience and technology application. Recently it get a large
client based in Canada and with the mutual consent of stakeholder they are planning to relocate
their headquarter within Canada which will start operating its business by 1st January, 2020. The
total budget for this relocation project would be 10 million USD and this involve relocation of
several operations such as accounting, finance, customer service, Research and development etc.
Hence, in order to start this relocating business, the project manager is require to develop a
detailed plan that support in explaining each and every action to be taken into consideration. For
this following are certain role that project manager has to perform throughout this project,
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

Planning and defining the scope of the project.
Determining number of activities to be performed in project and arranging them in
sequential manner.
Planning the resources and manpower required for executing the project.
Developing schedule and execution duration of each activity.
Estimating the cost required and developing the budget.
Analysing the risk involved and actions to be taken for dealing with them.
Executing the work and performing team leadership for ensuring effective performance
of each task.
Monitoring and controlling the actions.
These all are major roles that project manager has to perform while working over the
relocation project of Eagle eye. But while performing this project number of situations may arise
in front of project manager that may influence the final outcome of project (Fleming and
Koppelman, 2016). Hence in order to deal with those situations a regular evaluation of project
activities will be performed to detect errors if any so that timely actions can be taken into
consideration. On the other side a reserve fund will be kept aside so that at the time of
contingency actions can be taken into consideration.
b) 'Performance, time, scope and cost' requirement can support in helping or adversely affecting
project and scope of current project
Project management plan is defined as a formal document which is used by a project
manager in order to define some set of guidelines which help in explaining the team members in
detail manner about how the project will be executed. In addition to this the project management
plan also contains a detail about some set of attributes that forms up a significant part of a project
such as Performance, Cost, Scope and Time. These all factors play a significant role within
planning and execution of the project and also have the capability to either succeed or fail the
project (Mir and Pinnington, 2014). The project manager of Eagle eye relocation must focus
toward firstly evaluating these factors while creating a project management plan for assuring
about the positive outcome of the project. These factors can be better understood using following
point:
Performance :- It plays a significant role within the actual execution of the project and
ensuring desired outcome. Under this section the project manager is responsible for
Determining number of activities to be performed in project and arranging them in
sequential manner.
Planning the resources and manpower required for executing the project.
Developing schedule and execution duration of each activity.
Estimating the cost required and developing the budget.
Analysing the risk involved and actions to be taken for dealing with them.
Executing the work and performing team leadership for ensuring effective performance
of each task.
Monitoring and controlling the actions.
These all are major roles that project manager has to perform while working over the
relocation project of Eagle eye. But while performing this project number of situations may arise
in front of project manager that may influence the final outcome of project (Fleming and
Koppelman, 2016). Hence in order to deal with those situations a regular evaluation of project
activities will be performed to detect errors if any so that timely actions can be taken into
consideration. On the other side a reserve fund will be kept aside so that at the time of
contingency actions can be taken into consideration.
b) 'Performance, time, scope and cost' requirement can support in helping or adversely affecting
project and scope of current project
Project management plan is defined as a formal document which is used by a project
manager in order to define some set of guidelines which help in explaining the team members in
detail manner about how the project will be executed. In addition to this the project management
plan also contains a detail about some set of attributes that forms up a significant part of a project
such as Performance, Cost, Scope and Time. These all factors play a significant role within
planning and execution of the project and also have the capability to either succeed or fail the
project (Mir and Pinnington, 2014). The project manager of Eagle eye relocation must focus
toward firstly evaluating these factors while creating a project management plan for assuring
about the positive outcome of the project. These factors can be better understood using following
point:
Performance :- It plays a significant role within the actual execution of the project and
ensuring desired outcome. Under this section the project manager is responsible for
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

deciding some standards of performance that are being expected from employees. This
will help in determining that the operations are being executed in right direction and as
per the requirement. With the help of this a regular check can also be made over planned
and executed work so that the errors can be identified or rectified easily. But on the other
side, if the performance standards are not maintained in advanced then it will affect the
quality of operation execution and at the same time may also influence the final outcome
of the project. Additionally, it also become difficult for them to identify the area where
the performance of workers is lacking behind.
Cost :- It is also one among the factor within the project management plan of Eagle eye
relocation project and without cost it is not possible to execute the plan. This factor
involves estimating the amount which a project is require in order to arrange resources,
executing each activity and finishing the project successfully. The accurate estimation of
cost may support project manager of Eagle eye relocation project in performing the tasks
smoothly without any kind of risk (Schwalbe, 2015). But on the other side if the cost is
not estimated effectively at the time of project planning or not even managed while
execution of project then it may lead to loss of company. At the same time if it is not
managed properly then it may lead to delay of the project due to over spending of cost or
exceeding of budgeted cost. The estimated amount for this project of Eagle eye relocation
project is 10 million US dollar.
Scope :- This element describe about the objective of a particular project and what are
some opportunities that the execution of particular project will bring to the organisation.
The scope of a project plays a wider role as it help in determining the sources through
which the return can be collected over the investments made on execution of the project.
By defining the scope, it become easier for the Eagle eye to determine the benefits that
they avail once its business get relocated to Canada (Too and Weaver, 2014). On the
other side, if the scope is not defined appropriately at the starting of project then it
became quite difficult to get maximum outcome out of efforts of employees.
Time :- Each project is required to be get accomplished within a specific time period.
This element plays a significant role in directing the people to accomplish its project
within set time period in order to gain maximum benefit from it. As per the given case
study of Eagle eye, it is planning to relocate its business to Canada which it wants to be
will help in determining that the operations are being executed in right direction and as
per the requirement. With the help of this a regular check can also be made over planned
and executed work so that the errors can be identified or rectified easily. But on the other
side, if the performance standards are not maintained in advanced then it will affect the
quality of operation execution and at the same time may also influence the final outcome
of the project. Additionally, it also become difficult for them to identify the area where
the performance of workers is lacking behind.
Cost :- It is also one among the factor within the project management plan of Eagle eye
relocation project and without cost it is not possible to execute the plan. This factor
involves estimating the amount which a project is require in order to arrange resources,
executing each activity and finishing the project successfully. The accurate estimation of
cost may support project manager of Eagle eye relocation project in performing the tasks
smoothly without any kind of risk (Schwalbe, 2015). But on the other side if the cost is
not estimated effectively at the time of project planning or not even managed while
execution of project then it may lead to loss of company. At the same time if it is not
managed properly then it may lead to delay of the project due to over spending of cost or
exceeding of budgeted cost. The estimated amount for this project of Eagle eye relocation
project is 10 million US dollar.
Scope :- This element describe about the objective of a particular project and what are
some opportunities that the execution of particular project will bring to the organisation.
The scope of a project plays a wider role as it help in determining the sources through
which the return can be collected over the investments made on execution of the project.
By defining the scope, it become easier for the Eagle eye to determine the benefits that
they avail once its business get relocated to Canada (Too and Weaver, 2014). On the
other side, if the scope is not defined appropriately at the starting of project then it
became quite difficult to get maximum outcome out of efforts of employees.
Time :- Each project is required to be get accomplished within a specific time period.
This element plays a significant role in directing the people to accomplish its project
within set time period in order to gain maximum benefit from it. As per the given case
study of Eagle eye, it is planning to relocate its business to Canada which it wants to be

get finished within 6 months i.e. from 1st July to 31st December. Hence the project
manager is required to delegate time to number of activities that it is to be performed so
that work can get accomplished before deadline (Teller, Kock and Gemünden, 2014).
This schedule of time for each activity support in guiding and directing the team
members regarding the duration in which they have to complete their work which ensure
timely completion of the project. But on the other side if the time schedule of each
activity is not presented effectively then it may lead to delay in completion of project
which further increase the cost of the project.
These are some crucial factors that required to be consider while formulating planning for
the project as it helps in successfully completion of the project. Despite of this the main scope ad
cost of this project for Eagle eye is mentioned below:
Scope of project for Eagle eye:-
“The Eagle eye has wider scope for the execution of the project, as by relocating its
business within Canada it become easier to expand the customers base as it recently made a
broader client base their while operating in New York. This geographical gap may affect the
quality of services and communication between clients but establishing its presence in Canada it
become easier to operate business effectively and retaining the client for longer bases. Despite of
this, with the referral of current clients in Canada it become easier for Eagle eye to expand its
approach to new clients' too.”
Estimated dates and milestones
The estimation of time which required to perform a particular task is very crucial as it
help in ensuring that the activities can be executed in effective manner by providing a guidance
regarding the time duration in which a particular task is to be completed. On the other side,
milestones are certain levels of a particular project which help in determining that whether
everything is moving smoothly or facing certain issues (Joslin, and Müller, 2015). In order to
represent the dates and milestones of Eagle eye relocation project, Gantt chart will be used which
help in presentation of set of activities to be performed along with their starting and end dates.
The estimated dates and milestones are mentioned below:
manager is required to delegate time to number of activities that it is to be performed so
that work can get accomplished before deadline (Teller, Kock and Gemünden, 2014).
This schedule of time for each activity support in guiding and directing the team
members regarding the duration in which they have to complete their work which ensure
timely completion of the project. But on the other side if the time schedule of each
activity is not presented effectively then it may lead to delay in completion of project
which further increase the cost of the project.
These are some crucial factors that required to be consider while formulating planning for
the project as it helps in successfully completion of the project. Despite of this the main scope ad
cost of this project for Eagle eye is mentioned below:
Scope of project for Eagle eye:-
“The Eagle eye has wider scope for the execution of the project, as by relocating its
business within Canada it become easier to expand the customers base as it recently made a
broader client base their while operating in New York. This geographical gap may affect the
quality of services and communication between clients but establishing its presence in Canada it
become easier to operate business effectively and retaining the client for longer bases. Despite of
this, with the referral of current clients in Canada it become easier for Eagle eye to expand its
approach to new clients' too.”
Estimated dates and milestones
The estimation of time which required to perform a particular task is very crucial as it
help in ensuring that the activities can be executed in effective manner by providing a guidance
regarding the time duration in which a particular task is to be completed. On the other side,
milestones are certain levels of a particular project which help in determining that whether
everything is moving smoothly or facing certain issues (Joslin, and Müller, 2015). In order to
represent the dates and milestones of Eagle eye relocation project, Gantt chart will be used which
help in presentation of set of activities to be performed along with their starting and end dates.
The estimated dates and milestones are mentioned below:
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

c) Planning and scheduling of project help in successful implementation
The planning and scheduling plays a significant role within the execution of the project
effectively as it provide an idea regarding the direction toward which the work can be proceed
that support in getting a successful implementation of project (Turner, 2017) . These both are
consider as main part of project management which focuses toward presenting how things can
work and how things can be managed to extract best outcomes. By performing proper planning
and scheduling of the project, Eagle eye will get following benefits which support in effective
completion of its relocation project,
By performing project scheduling it become easier to represent the entire project for
guiding the work being done by the worker and in what manner that contribute toward
providing assurance that it gets conducted in right direction (Todorović and et. al., 2015).
In addition to this it also provides a standard and time against which the outcome can be
compared or measured to determine the flow of work.
It also supports in determining the interdependencies among different resources as well as
tasks that are require to complete the project effectively. This support the Eagle eye in
arranging all the resources that are required to perform tasks effectively priori to
execution of the project so that it can be executed without any kind of issues or delays
while performing tasks.
It also supports the project manager of Eagle eye in determining the time constraints and
other issues that may be found while execution of the project so that precautions can be
taken from very beginning of the work to avoid bottleneck issues. Additionally, they can
also plan actions to be taken for prospect risks.
Hence, from these benefits it can be said that planning and scheduling practices plays a
significant role within successful completion of the project as it helps in providing a pathway as
well as guidelines regarding the manner in which work is to be performed. Additionally, it also
provides a standards over which performance of team members can be measured to ensure that
work is executed in right direction.
For relocating its business to new location successfully i.e. Canada, eagle eye would be
required to firstly priorities the work which are crucial for the growth and success of a business.
These mainly includes,
The planning and scheduling plays a significant role within the execution of the project
effectively as it provide an idea regarding the direction toward which the work can be proceed
that support in getting a successful implementation of project (Turner, 2017) . These both are
consider as main part of project management which focuses toward presenting how things can
work and how things can be managed to extract best outcomes. By performing proper planning
and scheduling of the project, Eagle eye will get following benefits which support in effective
completion of its relocation project,
By performing project scheduling it become easier to represent the entire project for
guiding the work being done by the worker and in what manner that contribute toward
providing assurance that it gets conducted in right direction (Todorović and et. al., 2015).
In addition to this it also provides a standard and time against which the outcome can be
compared or measured to determine the flow of work.
It also supports in determining the interdependencies among different resources as well as
tasks that are require to complete the project effectively. This support the Eagle eye in
arranging all the resources that are required to perform tasks effectively priori to
execution of the project so that it can be executed without any kind of issues or delays
while performing tasks.
It also supports the project manager of Eagle eye in determining the time constraints and
other issues that may be found while execution of the project so that precautions can be
taken from very beginning of the work to avoid bottleneck issues. Additionally, they can
also plan actions to be taken for prospect risks.
Hence, from these benefits it can be said that planning and scheduling practices plays a
significant role within successful completion of the project as it helps in providing a pathway as
well as guidelines regarding the manner in which work is to be performed. Additionally, it also
provides a standards over which performance of team members can be measured to ensure that
work is executed in right direction.
For relocating its business to new location successfully i.e. Canada, eagle eye would be
required to firstly priorities the work which are crucial for the growth and success of a business.
These mainly includes,
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

Task force: - The Eagle eye is required to ensure that the it have adequate amount of
human resources that help it in executing the work effectively as per the task that are
required to perform for executing a particular project (Kerzner, 2018). Despite of this it
must also get a network of external partners such as designer, office mover, material
supplier, transport in-charge etc. so that operations can be executed smoothly.
Milestones: - It is a key factor that provide a mark toward the accomplishment of certain
phases. This support the Eagle eye project manager to get an idea regarding the success
or failure of project along with determining that each action get executed on timely
manner.
Resources: - The project manager must also ensure that resources remain available to
them before execution of project. At the same time, it must also focus toward arranging
the sources through which Eagle eye can get resources whenever it is required to them.
Fund:- Another major factor to be on priority is the budget plan and availability of
finance for executing the activities. The budget plan will help Eagle eye in getting an idea
regarding cost that activity required for its execution (Silvius and Schipper, 2014). On the
other side availability of fund will help project manager in arranging all the resources or
other material on timely manner which is required to execute project effectively.
Land and surroundings:- This is also a priority factor for Eagle eye as it remain crucial
for the company to relocate its business on right location where they can get a better flow
of business and also have adequate things available to them at less possible distance.
Additionally, this will also support it in ensuring that all the required stuff or material can
be made available to them at new location for offering its product or services.
d) WBS for the Eagle eye relocation project and dictionary
WBS structure
human resources that help it in executing the work effectively as per the task that are
required to perform for executing a particular project (Kerzner, 2018). Despite of this it
must also get a network of external partners such as designer, office mover, material
supplier, transport in-charge etc. so that operations can be executed smoothly.
Milestones: - It is a key factor that provide a mark toward the accomplishment of certain
phases. This support the Eagle eye project manager to get an idea regarding the success
or failure of project along with determining that each action get executed on timely
manner.
Resources: - The project manager must also ensure that resources remain available to
them before execution of project. At the same time, it must also focus toward arranging
the sources through which Eagle eye can get resources whenever it is required to them.
Fund:- Another major factor to be on priority is the budget plan and availability of
finance for executing the activities. The budget plan will help Eagle eye in getting an idea
regarding cost that activity required for its execution (Silvius and Schipper, 2014). On the
other side availability of fund will help project manager in arranging all the resources or
other material on timely manner which is required to execute project effectively.
Land and surroundings:- This is also a priority factor for Eagle eye as it remain crucial
for the company to relocate its business on right location where they can get a better flow
of business and also have adequate things available to them at less possible distance.
Additionally, this will also support it in ensuring that all the required stuff or material can
be made available to them at new location for offering its product or services.
d) WBS for the Eagle eye relocation project and dictionary
WBS structure

⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

WBS Dictionary
WBS
Level
WBS code WBS Name
1 1 Pre Project implementation
1.1 Investigating land
1.2 Risk analysis
1.3 Arranging raw material
1.4 Human resource required (procurement, construction and other
workers)
1.5 Preparing budget
1.6 Formulating plan
1.7 Arranging resources
1.8 Arranging warehouses
1.9 Scheduling the activities
1.10 Machineries required
2 2 Project implementation
2.1 Preparing the process plan
WBS
Level
WBS code WBS Name
1 1 Pre Project implementation
1.1 Investigating land
1.2 Risk analysis
1.3 Arranging raw material
1.4 Human resource required (procurement, construction and other
workers)
1.5 Preparing budget
1.6 Formulating plan
1.7 Arranging resources
1.8 Arranging warehouses
1.9 Scheduling the activities
1.10 Machineries required
2 2 Project implementation
2.1 Preparing the process plan

2.2 Formulating team
2.3 Arranging meeting
2.4 Employees capability analysis
2.5 Assigning work to employees
2.6 Assigning resources
2.7 Construction of building
3 3 Post project implementation
3.1 Furnishing of building
3.2 Shifting the office stuff
3.3 Evaluating building
3.4 Providing salary to workers
3.5 Handing over the work
3.6 Feedback from Eagle eye
e) Risk assessment and recommendation for responding to these risk
Risk assessment plays a significant role within a project by providing an idea regarding
the set of potential risks that may be faced within a project so that appropriate planning can be
made to deal with them prior to project execution (Alias and et. al., 2014). By getting an idea
regarding risk that may be faced by the Eagle eye while relocating its business, it become easier
to perform action effectively which help in avoiding such risks. Following are some of the major
risk that eagle eye may face while executing this project,
Risk Cause Before
control
Consequence
s
Responses After control
P I R=P*I P I R=P*I
Increased
expenses
The activities may
require more fund
to get accomplish
2 3 6 It may lead
to delay in
work or
For responding to
this financial risk,
project manager
1 2 2
2.3 Arranging meeting
2.4 Employees capability analysis
2.5 Assigning work to employees
2.6 Assigning resources
2.7 Construction of building
3 3 Post project implementation
3.1 Furnishing of building
3.2 Shifting the office stuff
3.3 Evaluating building
3.4 Providing salary to workers
3.5 Handing over the work
3.6 Feedback from Eagle eye
e) Risk assessment and recommendation for responding to these risk
Risk assessment plays a significant role within a project by providing an idea regarding
the set of potential risks that may be faced within a project so that appropriate planning can be
made to deal with them prior to project execution (Alias and et. al., 2014). By getting an idea
regarding risk that may be faced by the Eagle eye while relocating its business, it become easier
to perform action effectively which help in avoiding such risks. Following are some of the major
risk that eagle eye may face while executing this project,
Risk Cause Before
control
Consequence
s
Responses After control
P I R=P*I P I R=P*I
Increased
expenses
The activities may
require more fund
to get accomplish
2 3 6 It may lead
to delay in
work or
For responding to
this financial risk,
project manager
1 2 2
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide
1 out of 23
Related Documents
Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
Copyright © 2020–2025 A2Z Services. All Rights Reserved. Developed and managed by ZUCOL.