Standard Project Charter Template EduStream
Introduction (Business Analysis)
Project Title EduStream Pilot (Phase 1)
Reason for the
project
The prime objective of this project is to develop a streaming application
and solution to upgrade the way EdMI uploads its educational videos and
games. The high growth rate of internet users is a viable condition for the
implementation of a streaming solution for educational services. It would
help the EdMI to expand its market share in the educational industry and
generate better revenue from it. The streaming system will also improve
the efficiency and durability of the videos and the games developed by
EdMedia International. The data management services integrated with
this system provide better flexibility and knowledge generation to the
organization.
STAKEHOLDER ANALYSIS
PART 1: WHAT DO WE WANT FROM THIS PROJECT (Provide a short synopsis)
Description: The main objective of this streaming solution is to enhance the
distribution system of the educational products offered by EdMI. This application
will also be helpful to store and maintain the educational data generated by EdMI
using various data management technologies.
Background: This streaming solution is developed for EdMedia International Pty
Ltd. EdMI produces many educational videos and games for its customers and
distributes it through DVDs or Blue Ray. The market share occupied by EdMI is
decreasing over time. This is because the accessibility of their products by the
customers is less flexible. There is a need for a new media development solution.
Proposed Solution: To enhance the current distribution system and improve the
market position we propose a streaming software solution which will help in flexible
delivery and management of the education products and helps in knowledge
generation from customer data.
PART 2: WHAT DO OUR CLIENTS WANT FROM THIS PROJECT (Provide a short synopsis)
Description: The main requirement from this project is to have a streaming solution
which will help the organization in improving its product delivery system and
enhance the strength in the market. The application should be able to provide
solutions for data management and knowledge generation.
Background: The EdMI is an organization that develops educational media services
for the client which are distributed in the form of DVD and Blue Ray. The 40%
market share held by the organization is slowly eroding over time. It is time to
implement a flexible and efficient system based on the latest technologies.
Proposed Solution: To enhance the current distribution system and improve the
market position we propose a streaming software solution which will help in flexible
delivery and management of the education products and helps in knowledge
generation from customer data.
Seahorses© 2019 1
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Standard Project Charter Template EduStream
SWOT ANALYSIS
STRENGTHS WEAKNESSES
The good educational structure
provided by the company.
Quality assurance for the courses and
videos developed by the company.
Content developed by skilled and
experienced teachers who have
profound knowledge of the video topic.
The company has several years of
experience in the educational market.
High dependency on the teachers
working part-time in the company.
Dependency on the mediators to
distribute the DVDs and Blue Rays to
distant places.
Insufficiency or absence of library
facilities for its students and customers.
Less durability of the conventional
DVDs as compared to modern
technologies.
OPPORTUNITIES THREATS
An increasing number of students
enrolling in the educational institutes.
An improvement in the recognition of
the company name.
Expansion of the educational and
technological industries generates a
huge need for knowledge distribution.
Globalization and expansion in the
market.
Competition from the universities and
schools providing educational services
physically.
New entrants and already established
companies in the market that provide
educational streaming services.
The high initial cost of implementing
the streaming solution.
Less enrolment of students and less
demand in the market.
Preliminary Financial Analysis
ROM Budgetary Information (As specified for Assignment 1)
Costs (Expected year on year
costs)
Year 0 Year 1 Year 2 Year 3
$ 1,250,000 $ 580,000 $ 620,000 $ 680,000
Revenue (Expected year on
year revenue)
Year 0 Year 1 Year 2 Year 3
$ 250,000 $ 930,000 $ 1,400,000 $ 2,100,000
NPV $ 1,154,300 ROI 40% Payback Period 0.033333333
Assumptions Inflation Rate = 2%
Loan Interest Rate = 5.2% per annum
Rate on return = 7.20%
Project Planning (Overview)
Date of Authorisation 1 April 2019 (TBC)
Project Start Date 29 April 2019
Project End Date 1 May 2020
Schedule & Key
Milestones
Team Formation- 4/03/2019
Project Initiation and Task Assignment- 29/04/2019
Contracts signing- 24/06/2019
Finalizing project designs- 30/08/2019
Seahorses© 2019 2
Document Page
Standard Project Charter Template EduStream
Initiation of software development- 2/09/2019
Product Marketing- 9/09/2019
Beta launch (1st Pilot CDN)- 6/10/2019
Beta launch (2nd Pilot CDN)- 7/02/2020
Beta launch (3rd Pilot CDN)- 17/04/2019
Final project deployment- 1/05/2019
Closure- 1/06/2019
Project Deliverables Web & Software Application
Database and Cloud Services
Student consultancy
Technical flexibility to the organization
Customer-growth enhancement
Outsourcing of products and services.
Main project success
criteria (high level)
Better team relationships and coordination
Efficient planning and scheduling
Optimal design for the infrastructure and
Perfect integration of the planning and development phase
Efficient Scheduling
Effective capital investment
Risk mitigation and contingency plans
Defining Legal standards
Approach (high-level
overview)
For the success of this pilot project, it is necessary for a
proper project management plan and authorization of the
project members. The team formation will be a deciding
factor for the timely execution of the project. Therefore, a
good relationship between the team members is necessary.
For the services and requirements which are unable to be
fulfilled by the EdMI, a trusted sub-contractor will be hired
and the requirements will be outsourced from a trusted
organisation. Finally, a proper agreement and legal bond
signing will be done to validate the project participants of the
stakeholders and the sub-contractors.
Comments Successful project management is not only the responsibility
the project manager but also of the project member and staff.
Therefore, proper coordination and dedicated participation of
all the entities in the project is necessary.
See overleaf for Roles and Responsibilities Matrix
Seahorses© 2019 3
Document Page
Roles and Responsibilities Matrix EduStream
ROLES AND RESPONSIBILITIES MATRIX
The first two names are provided. Insert the remaining ones as specified in the Assignment 1 Scenario (remove this text and insert a preamble for the Board).
Name Role Responsible For Responsible To Contact Information (email/phone)
Shona Mayberry CEO Executive management of EdMI Board Not required in this assignment
Bill Shanks (CIO) Sponsor Overseeing the project CEO
(student’s name) Project Manager See the listing in Topic 1 CIO
Jill Mars Content Analyst Guides in the proper deployment and
verification of the educational content
Project Manager
Dan Collins Contractual manager
and legal expert
Legal agreements and contract
verification along with negotiation
CIO
Bill Haley Security Team
Manager
Handles issues related to privacy and
infrastructure security.
CIO & Project
Manager
Jerome Dons Sales Expert Sales planning & management Project manager
Doris Sykes Marketing Expert Marketing plan and management Project Manager
StreamTech Technical
Expert
Sub-contractor Provides technical services to the EdMI
project.
CIO & Project
Manager
Steve Robbie Supplier Supplies additional expertise and
services
Project Manager and
CIO
Shawn Morris Programmer and
Software Designer
Develops software design and coding. Project manager
Shane Williams Hardware Expert Manages and assures the proper
execution of the machines and hardware
components.
Project Manager
Seahorses© 2019 Page 4
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Signature Page EduStream
Note: This reflects a standard Charter signature sheet. For this assignment, it is not required.
Name Signature Date
Name Signature Date
Name Signature Date
Seahorses© 2019 Page 5
chevron_up_icon
1 out of 5
circle_padding
hide_on_mobile
zoom_out_icon
[object Object]