This project management assignment analyzes the rollout of POS scanners across multiple retail outlets. The report includes sections on MS Project tasks, interpretation of results, and a comprehensive project report. The report provides Gantt charts with critical paths and summary tasks, network diagrams, and cost reports to evaluate project duration, working days, and final costs. The project utilizes resource leveling techniques to address resource constraints, and the report details the impact of leveling on project duration and cost. Assumptions made for project scheduling are clearly outlined. The assignment provides a detailed breakdown of costs associated with different project phases, including hardware specifications, operating system, utilities, and system integration. The final cost is estimated to be $313,450. The project is expected to be completed in 230 working days.
Document Page
Running Head: PROJECT MANAGEMENT
Project Management
Name of the Student
Name of the University
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
1PROJECT MANAGEMENT
Table of Contents
Section A – MS Project Tasks and Interpretation of the Results....................................................2
Section B – Assignment Report.......................................................................................................6
Introduction and Assumptions.........................................................................................................6
Gantt Chart with Critical Path.........................................................................................................7
Network Diagram with Critical Path...............................................................................................8
Gantt Chart with Summary Tasks....................................................................................................9
Cost Report....................................................................................................................................10
Project Duration and Working Days..............................................................................................12
Final Cost.......................................................................................................................................18
Bibliography..................................................................................................................................22
Document Page
2PROJECT MANAGEMENT
Section A – MS Project Tasks and Interpretation of the Results
Importance of Summary Tasks:
Summary tasks in MS Project represent different phases in the project. Without summary
tasks, the work packages or activities will be clustered together and it will be impossible to
determine which task is to be executed in which phase.
Resource graphs showing over-allocations:
Figure 1 and 2: Resource Graphs
Document Page
3PROJECT MANAGEMENT
Source: Created by Author)
Resource Leveling:
There are different techniques to level resources so that there are no over-allocations in
the project. For this project, it has been analyzed that cost and time are not major constraints but
resource is a constraint. Hence, for resource leveling in the project, resource constrained leveling
technique has been utilized. The gantt chart before and after leveling of resources are shown in
the following diagrams.
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
4PROJECT MANAGEMENT
Figure 3 and 4: Gantt charts before and after Leveling
Source: Created by Author)
Effects of Leveling on Duration and Cost:
Before Leveling After Leveling
Duration = 210 days Duration = 230 days
Cost = $308,500 Cost = $313,450
Document Page
5PROJECT MANAGEMENT
Cost Reports:
Figure 5: Task Cost Report
Source: Created by Author)
From the task cost report, it can be seen that the hardware specifications work is the most
expensive phase and the utilities is the least expensive phase. It is required to monitor the
spending in order to ensure no additional costs are required.
Document Page
6PROJECT MANAGEMENT
Figure 6: Resource Cost Report
Source: Created by Author)
From the resource cost report, it is seen that the developers DEV) have the highest
wages for working in the project. They also have maximum duties in the project that will result
in maximum work hours and wages.
Section B – Assignment Report
Introduction and Assumptions
This particular project is based on the rolling out of a POS scanners required by a
particular group of client. This project covers the entire stage of production to development of
the particular product. The assignment mainly focuses on the scheduling of the development and
rolling out process and also estimates resource requirements and budget required for the project.
In order to schedule the project, some assumptions have been made that are listed as
follows.
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
7PROJECT MANAGEMENT
It has been assumed that the project can be initiated by 10th July 2020.
It has been assumed that in case of bug detection, it will not take more than 2
weeks to remove the bugs.
It has been assumed that all the human resources will completely support their
project and will fulfill their daily work requirements during the project.
Gantt Chart with Critical Path
Figure 1: Gantt Chart with Critical Path
Document Page
8PROJECT MANAGEMENT
Source: Created by Author)
Network Diagram with Critical Path
Figure 2: Network Diagram with Critical Path
Source: Created by Author)
Document Page
9PROJECT MANAGEMENT
Gantt Chart with Summary Tasks
Figure 3: Gantt Chart with Summary Tasks
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
10PROJECT MANAGEMENT
Source: Created by Author)
Cost Report
WBS Task Name Predecessors Resource Names Cost
0 Roll Out POS Scanners $308,500.00
HW 1.0 Hardware Specifications
Mobile Site
Office, Office
equipment
$103,625.00
HW 1.1 Hardware Specifications DS $12,000.00
HW 1.2 Hardware Design 2 DS $16,000.00
HW 1.3 Hardware Documentation 3 DOC $1,600.00
HW 1.4 Procure Circuit Boards 4 PUR $9,600.00
HW 1.5 Build Prototypes 4 DEV, DS $20,400.00
HW 1.6 Test Prototypes 6 DEV, DS, TT $9,600.00
HW 1.7 Pre-Production Models 5,7 DEV, DS $20,400.00
OP 1.0 Operating System
Mobile Site
Office, Office
equipment
$69,500.00
OP 1.1 Kernel specification 8 DEV, DS $6,800.00
Document Page
11PROJECT MANAGEMENT
OP 1.2 Drivers $11,200.00
OP
1.2.1
Disk drivers 10 DEV $5,600.00
OP
1.2.2
I/O drivers 10 DEV $5,600.00
OP 1.3 Code Software $41,600.00
OP
1.3.1
Code software 10 CD $9,600.00
OP
1.3.2
Code interfaces 12,13,15 CD $6,400.00
OP
1.3.3
Document software 15,16 DOC $3,200.00
OP
1.3.4
Beta test software 12,13,17 DEV, TT $22,400.00
UT 1.0 Utilities
Mobile Site
Office, Office
equipment
$53,050.00
UT 1.1 Utilities specifications 8 DS $4,000.00