Engineering Management and Project Organization Report
VerifiedAdded on 2022/12/15
|25
|2540
|227
Report
AI Summary
This report provides a comprehensive overview of engineering management and project organization, focusing on the New East London River Crossing project. It begins with a program Gantt chart, illustrating the project timeline, phases, and involved parties based on the RIBA Plan of Works. The report then delves into detailed cost information, including the unit costs of various personnel (e.g., project manager, architect, engineers) and their allocation across different tasks within the work breakdown structure. The cost analysis covers tasks from strategic definition and project briefing to concept design and technical design, providing a breakdown of costs associated with each phase. The document includes tables that show task durations, resource allocation, and associated costs, offering insights into project planning, execution, and financial management. Overall, the report highlights the critical aspects of project management in engineering, including scheduling, resource allocation, and cost control, making it a valuable resource for students studying related subjects.

Running Head: ENGINEERING MANAGEMENT AND PROJECT ORGANISATION
Engineering Management and Project Organisation
Name of the Student
Name of the University
Engineering Management and Project Organisation
Name of the Student
Name of the University
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.

1ENGINEERING MANAGEMENT AND PROJECT ORGANISATION
1. Program Gantt Chart (RIBA Plan of Works)
The program Gantt chart is shown in the following diagram.
1. Program Gantt Chart (RIBA Plan of Works)
The program Gantt chart is shown in the following diagram.

2ENGINEERING MANAGEMENT AND PROJECT ORGANISATION

3ENGINEERING MANAGEMENT AND PROJECT ORGANISATION
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.

4ENGINEERING MANAGEMENT AND PROJECT ORGANISATION

5ENGINEERING MANAGEMENT AND PROJECT ORGANISATION
Figure 1: Gantt Chart for the Program Showing Time Constraints and Parties
Involved
(Source: Created by Author)
2. Cost Information
The cost of the project has been determined considering the unit costs of the
involved personnel as shown in the following table.
Resource Name Type Max. Units Std. Rate
Figure 1: Gantt Chart for the Program Showing Time Constraints and Parties
Involved
(Source: Created by Author)
2. Cost Information
The cost of the project has been determined considering the unit costs of the
involved personnel as shown in the following table.
Resource Name Type Max. Units Std. Rate

6ENGINEERING MANAGEMENT AND PROJECT ORGANISATION
Client Assistant Work 100% $50.00/wk
Project Manager Work 100% $500.00/wk
Design Manager Work 100% $450.00/wk
Architect Work 100% $450.00/wk
Building Services Engineer Work 100% $450.00/wk
Civil and Structural Engineer Work 100% $450.00/wk
Finance Management
Consultant Work 100% $200.00/wk
Head of Constructions Work 100% $300.00/wk
Contract Manager Work 100% $200.00/wk
WHS Consultant Work 100% $250.00/wk
These resources are then allocated to the work breakdown structure to
determine the project costs as follows.
Task Name Duration Resource Names Cost
New East London River Crossing
Design RIBA Plan of Work 106 wks $103,100.00
Strategic Definition 17 wks $8,550.00
Hand Out Project Primary
Requirements and Business Case to
Facilitate the Development of
2 wks Client Assistant $100.00
Client Assistant Work 100% $50.00/wk
Project Manager Work 100% $500.00/wk
Design Manager Work 100% $450.00/wk
Architect Work 100% $450.00/wk
Building Services Engineer Work 100% $450.00/wk
Civil and Structural Engineer Work 100% $450.00/wk
Finance Management
Consultant Work 100% $200.00/wk
Head of Constructions Work 100% $300.00/wk
Contract Manager Work 100% $200.00/wk
WHS Consultant Work 100% $250.00/wk
These resources are then allocated to the work breakdown structure to
determine the project costs as follows.
Task Name Duration Resource Names Cost
New East London River Crossing
Design RIBA Plan of Work 106 wks $103,100.00
Strategic Definition 17 wks $8,550.00
Hand Out Project Primary
Requirements and Business Case to
Facilitate the Development of
2 wks Client Assistant $100.00
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

7ENGINEERING MANAGEMENT AND PROJECT ORGANISATION
Strategic Brief
Discussion of Business Case and
Strategic Brief in Workshops 3 wks Project Manager $1,500.00
Discuss Assembling
Requirements and Considerations for
the Project Team
2 wks Project Manager $1,000.00
Establish Project Programme 2 wks Project Manager $1,000.00
Collate Feedback from previous
projects 1 wk Project Manager $500.00
Contribution to Development of
Strategic Brief 1 wk
Design Manager,
Building Services
Engineer
$900.00
Provide Inputs for Modification in
Project Program 1 wk Design Manager $450.00
Supply Ideas and Data from
Previous Similar Projects 1 wk Design Manager,
Architect $900.00
Contribution to Development of
Strategic Brief 2 wks
Architect, Civil
and Structural
Engineer
$1,800.00
Contribution to the Development
of Cost Information in the Strategic
Brief
2 wks
Finance
Management
Consultant
$400.00
Preparation and Brief 34 wks $17,450.00
Develop Project Brief 3 wks Client Assistant, $1,650.00
Strategic Brief
Discussion of Business Case and
Strategic Brief in Workshops 3 wks Project Manager $1,500.00
Discuss Assembling
Requirements and Considerations for
the Project Team
2 wks Project Manager $1,000.00
Establish Project Programme 2 wks Project Manager $1,000.00
Collate Feedback from previous
projects 1 wk Project Manager $500.00
Contribution to Development of
Strategic Brief 1 wk
Design Manager,
Building Services
Engineer
$900.00
Provide Inputs for Modification in
Project Program 1 wk Design Manager $450.00
Supply Ideas and Data from
Previous Similar Projects 1 wk Design Manager,
Architect $900.00
Contribution to Development of
Strategic Brief 2 wks
Architect, Civil
and Structural
Engineer
$1,800.00
Contribution to the Development
of Cost Information in the Strategic
Brief
2 wks
Finance
Management
Consultant
$400.00
Preparation and Brief 34 wks $17,450.00
Develop Project Brief 3 wks Client Assistant, $1,650.00

8ENGINEERING MANAGEMENT AND PROJECT ORGANISATION
Project Manager
Identify Project Objectives 1 wk Client Assistant,
Project Manager $550.00
Define Quality Objectives 1 wk Client Assistant,
Project Manager $550.00
Define Project Outcomes 1 wk Client Assistant,
Project Manager $550.00
Determine Sustainability
Aspirations 1 wk Client Assistant,
Project Manager $550.00
Determine Project Budget 2 wks Client Assistant,
Project Manager $1,100.00
Define Other Parameters 2 wks Client Assistant,
Project Manager $1,100.00
Undertake Workshops as
Specified in Project Briefs 1 wk Project Manager $500.00
Define Roles using Contractual
Tree and Assemble Project Team
Members
1 wk Project Manager $500.00
Develop Responsibility Matrix for
Assigning Specific Duties 1 wk Project Manager $500.00
Conduct Feasibility Study 2 wks Project Manager $1,000.00
Undertake Risk Assessment and
Develop Strategies for Project
Execution
1 wk Project Manager $500.00
Project Manager
Identify Project Objectives 1 wk Client Assistant,
Project Manager $550.00
Define Quality Objectives 1 wk Client Assistant,
Project Manager $550.00
Define Project Outcomes 1 wk Client Assistant,
Project Manager $550.00
Determine Sustainability
Aspirations 1 wk Client Assistant,
Project Manager $550.00
Determine Project Budget 2 wks Client Assistant,
Project Manager $1,100.00
Define Other Parameters 2 wks Client Assistant,
Project Manager $1,100.00
Undertake Workshops as
Specified in Project Briefs 1 wk Project Manager $500.00
Define Roles using Contractual
Tree and Assemble Project Team
Members
1 wk Project Manager $500.00
Develop Responsibility Matrix for
Assigning Specific Duties 1 wk Project Manager $500.00
Conduct Feasibility Study 2 wks Project Manager $1,000.00
Undertake Risk Assessment and
Develop Strategies for Project
Execution
1 wk Project Manager $500.00

9ENGINEERING MANAGEMENT AND PROJECT ORGANISATION
Review the Overall Performance
Progress of Project Team 2 wks Project Manager $1,000.00
Contribution towards the
Modification of Project Brief 1 wk Design Manager $450.00
Further Development of Project
Team 1 wk Design Manager $450.00
Contribute to preparation of
Handover Strategy and Risk
Assessments
1 wk Design Manager $450.00
Comment on Project Programme 1 wk Design Manager $450.00
Review the Overall Performance
Progress of Design Team 1 wk Design Manager $450.00
Contribution towards the
Modification of Project Brief 1 wk Architect $450.00
Discuss project with appropriate
planning authority 1 wk Architect $450.00
Undertake Feasibility Studies 3 wks Architect $1,350.00
Prepare Site Information report 3 wks Architect $1,350.00
Contribute to Site Information
report 1 wk
Architect, Building
Services
Engineer, Civil
and Structural
Engineer
$1,350.00
Prepare Project Budget in
consultation with client
1 wk Finance
Management
$200.00
Review the Overall Performance
Progress of Project Team 2 wks Project Manager $1,000.00
Contribution towards the
Modification of Project Brief 1 wk Design Manager $450.00
Further Development of Project
Team 1 wk Design Manager $450.00
Contribute to preparation of
Handover Strategy and Risk
Assessments
1 wk Design Manager $450.00
Comment on Project Programme 1 wk Design Manager $450.00
Review the Overall Performance
Progress of Design Team 1 wk Design Manager $450.00
Contribution towards the
Modification of Project Brief 1 wk Architect $450.00
Discuss project with appropriate
planning authority 1 wk Architect $450.00
Undertake Feasibility Studies 3 wks Architect $1,350.00
Prepare Site Information report 3 wks Architect $1,350.00
Contribute to Site Information
report 1 wk
Architect, Building
Services
Engineer, Civil
and Structural
Engineer
$1,350.00
Prepare Project Budget in
consultation with client
1 wk Finance
Management
$200.00
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.

10ENGINEERING MANAGEMENT AND PROJECT ORGANISATION
Consultant
Concept Design 55 wks $34,900.00
Contribute to Health & Safety
Strategy as required 2 wks
Architect, Building
Services
Engineer, Civil
and Structural
Engineer, Client
Assistant, Head of
Constructions,
Contract
Manager, Finance
Management
Consultant, WHS
Consultant,
Design Manager,
Project Manager
$6,600.00
Provide information for and
contribute to contents of Project
Execution Plan as required
1 wk
Architect, Building
Services
Engineer, Civil
and Structural
Engineer, Client
Assistant, Head of
Constructions,
Contract
Manager, Finance
Management
Consultant, WHS
Consultant,
Design Manager,
$3,300.00
Consultant
Concept Design 55 wks $34,900.00
Contribute to Health & Safety
Strategy as required 2 wks
Architect, Building
Services
Engineer, Civil
and Structural
Engineer, Client
Assistant, Head of
Constructions,
Contract
Manager, Finance
Management
Consultant, WHS
Consultant,
Design Manager,
Project Manager
$6,600.00
Provide information for and
contribute to contents of Project
Execution Plan as required
1 wk
Architect, Building
Services
Engineer, Civil
and Structural
Engineer, Client
Assistant, Head of
Constructions,
Contract
Manager, Finance
Management
Consultant, WHS
Consultant,
Design Manager,
$3,300.00

11ENGINEERING MANAGEMENT AND PROJECT ORGANISATION
Project Manager
Contribute to development of
Final Project Brief 1 wk
Architect, Building
Services
Engineer, Civil
and Structural
Engineer, Client
Assistant, Head of
Constructions,
Contract
Manager, Finance
Management
Consultant, WHS
Consultant,
Design Manager,
Project Manager
$3,300.00
Analyze Concept Design
Proposal 1 wk Client Assistant $50.00
Approve Concept Design and
Add to Project Brief 1 wk Client Assistant $50.00
Analyze Project Strategies 1 wk Client Assistant $50.00
Re-evaluate Concept Design 2 wks Project Manager $1,000.00
Develop Final Project Brief 2 wks Project Manager $1,000.00
Define Handover Strategy and
Risks Along with Project Team 1 wk Project Manager $500.00
Finalize Execution Plan for the
Project 1 wk Project Manager $500.00
Project Manager
Contribute to development of
Final Project Brief 1 wk
Architect, Building
Services
Engineer, Civil
and Structural
Engineer, Client
Assistant, Head of
Constructions,
Contract
Manager, Finance
Management
Consultant, WHS
Consultant,
Design Manager,
Project Manager
$3,300.00
Analyze Concept Design
Proposal 1 wk Client Assistant $50.00
Approve Concept Design and
Add to Project Brief 1 wk Client Assistant $50.00
Analyze Project Strategies 1 wk Client Assistant $50.00
Re-evaluate Concept Design 2 wks Project Manager $1,000.00
Develop Final Project Brief 2 wks Project Manager $1,000.00
Define Handover Strategy and
Risks Along with Project Team 1 wk Project Manager $500.00
Finalize Execution Plan for the
Project 1 wk Project Manager $500.00

12ENGINEERING MANAGEMENT AND PROJECT ORGANISATION
Analyze Project Program and
Discussion with Team 1 wk Project Manager $500.00
Review Design Program and Cost
Information 1 wk Project Manager $500.00
Analsis of Progress 1 wk Project Manager $500.00
Review Proposal with Design
Team 1 wk Design Manager $450.00
Develop Strategy for
Sustainability, Operations and
Maintenance
2 wks Design Manager $900.00
Develop Design Program in
Consultation with Other Design
Teams
3 wks Design Manager $1,350.00
Comment on Cost Information 1 wk Design Manager $450.00
Review Design Team
Performance 1 wk Design Manager $450.00
Develop Architectural Concept
Design for the Project Using All
Predermined Conditions in the
Project Brief
5 wks Architect $2,250.00
Liaise with planning authorities as
required 1 wk Architect $450.00
Submit Stage 3 Planning
Application 1 wk Architect $450.00
Consult with Third Party and 1 wk Architect $450.00
Analyze Project Program and
Discussion with Team 1 wk Project Manager $500.00
Review Design Program and Cost
Information 1 wk Project Manager $500.00
Analsis of Progress 1 wk Project Manager $500.00
Review Proposal with Design
Team 1 wk Design Manager $450.00
Develop Strategy for
Sustainability, Operations and
Maintenance
2 wks Design Manager $900.00
Develop Design Program in
Consultation with Other Design
Teams
3 wks Design Manager $1,350.00
Comment on Cost Information 1 wk Design Manager $450.00
Review Design Team
Performance 1 wk Design Manager $450.00
Develop Architectural Concept
Design for the Project Using All
Predermined Conditions in the
Project Brief
5 wks Architect $2,250.00
Liaise with planning authorities as
required 1 wk Architect $450.00
Submit Stage 3 Planning
Application 1 wk Architect $450.00
Consult with Third Party and 1 wk Architect $450.00
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

13ENGINEERING MANAGEMENT AND PROJECT ORGANISATION
Research and Development Teams
Development of Stage Design
with Assistance of Lead Designer 1 wk Architect $450.00
Review Cost Information and
Update the Same 1 wk Architect $450.00
Develop New Concept Design for
Building Services 5 wks Building Services
Engineer $2,250.00
Consult with Third Party and
Research and Development Teams 1 wk Building Services
Engineer $450.00
Development of Stage Design
with Assistance of Lead Designer 1 wk Building Services
Engineer $450.00
Provide information for
preparation of Cost Information and
Project Strategies
1 wk Building Services
Engineer $450.00
Develop New Concept Design for
Building Services 5 wks
Civil and
Structural
Engineer
$2,250.00
Consult with Third Party and
Research and Development Teams 1 wk
Civil and
Structural
Engineer
$450.00
Development of Stage Design
with Assistance of Lead Designer 1 wk
Civil and
Structural
Engineer
$450.00
Review Cost Information and
Update the Same
1 wk Civil and
Structural
$450.00
Research and Development Teams
Development of Stage Design
with Assistance of Lead Designer 1 wk Architect $450.00
Review Cost Information and
Update the Same 1 wk Architect $450.00
Develop New Concept Design for
Building Services 5 wks Building Services
Engineer $2,250.00
Consult with Third Party and
Research and Development Teams 1 wk Building Services
Engineer $450.00
Development of Stage Design
with Assistance of Lead Designer 1 wk Building Services
Engineer $450.00
Provide information for
preparation of Cost Information and
Project Strategies
1 wk Building Services
Engineer $450.00
Develop New Concept Design for
Building Services 5 wks
Civil and
Structural
Engineer
$2,250.00
Consult with Third Party and
Research and Development Teams 1 wk
Civil and
Structural
Engineer
$450.00
Development of Stage Design
with Assistance of Lead Designer 1 wk
Civil and
Structural
Engineer
$450.00
Review Cost Information and
Update the Same
1 wk Civil and
Structural
$450.00

14ENGINEERING MANAGEMENT AND PROJECT ORGANISATION
Engineer
Develop Preliminary Expenditure
Details 1 wk
Finance
Management
Consultant
$200.00
Development of Appropriate
Construction Strategy 1 wk Head of
Constructions $300.00
Update Necessary WHS Strategy
as per Guidelines 1 wk WHS Consultant $250.00
Consult Leaders As Necessary 1 wk Project Manager $500.00
Provide information as set out in
the Design Responsibility Matrix
incorporating Information Exchanges
in accordance with Design
Programme
1 wk Project Manager $500.00
Developed Design 36 wks $20,000.00
Update Necessary WHS Strategy
as per Guidelines 1 wk
Architect, Building
Services
Engineer, Civil
and Structural
Engineer, Client
Assistant, Head of
Constructions,
Contract
Manager, Finance
Management
Consultant, WHS
Consultant,
$3,300.00
Engineer
Develop Preliminary Expenditure
Details 1 wk
Finance
Management
Consultant
$200.00
Development of Appropriate
Construction Strategy 1 wk Head of
Constructions $300.00
Update Necessary WHS Strategy
as per Guidelines 1 wk WHS Consultant $250.00
Consult Leaders As Necessary 1 wk Project Manager $500.00
Provide information as set out in
the Design Responsibility Matrix
incorporating Information Exchanges
in accordance with Design
Programme
1 wk Project Manager $500.00
Developed Design 36 wks $20,000.00
Update Necessary WHS Strategy
as per Guidelines 1 wk
Architect, Building
Services
Engineer, Civil
and Structural
Engineer, Client
Assistant, Head of
Constructions,
Contract
Manager, Finance
Management
Consultant, WHS
Consultant,
$3,300.00

15ENGINEERING MANAGEMENT AND PROJECT ORGANISATION
Design Manager,
Project Manager
Update Project Execution Plan 1 wk
Architect, Building
Services
Engineer, Civil
and Structural
Engineer, Client
Assistant, Head of
Constructions,
Contract
Manager, Finance
Management
Consultant, WHS
Consultant,
Design Manager,
Project Manager
$3,300.00
Update Design Proposal 1 wk Client Assistant $50.00
Sign-off Developed Design 1 wk Client Assistant $50.00
Update Project Strategies As
Required 1 wk Client Assistant $50.00
Monitor progress of developing
design 1 wk Project Manager $500.00
Update Handover and Risk
Strategies 1 wk Project Manager $500.00
Update Execution Plan of the
Project 1 wk Project Manager $500.00
Design Manager,
Project Manager
Update Project Execution Plan 1 wk
Architect, Building
Services
Engineer, Civil
and Structural
Engineer, Client
Assistant, Head of
Constructions,
Contract
Manager, Finance
Management
Consultant, WHS
Consultant,
Design Manager,
Project Manager
$3,300.00
Update Design Proposal 1 wk Client Assistant $50.00
Sign-off Developed Design 1 wk Client Assistant $50.00
Update Project Strategies As
Required 1 wk Client Assistant $50.00
Monitor progress of developing
design 1 wk Project Manager $500.00
Update Handover and Risk
Strategies 1 wk Project Manager $500.00
Update Execution Plan of the
Project 1 wk Project Manager $500.00
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.

16ENGINEERING MANAGEMENT AND PROJECT ORGANISATION
Review and Update Project
Program 1 wk Project Manager $500.00
Comment on stage Design
Programme and Cost Information 1 wk Project Manager $500.00
Manage Change Control process 1 wk Project Manager $500.00
Review Performance of Project
Team 1 wk Project Manager $500.00
Review and Update Design
Proposal 1 wk Design Manager $450.00
Develop Strategy for
Sustainability, Operations and
Maintenance
1 wk Design Manager $450.00
Update Stage Design Program 1 wk Design Manager $450.00
Review and Update Cost
Information 1 wk Design Manager $450.00
Review Performance of Project
Team 1 wk Design Manager $450.00
Update Architectural Design as
Required 1 wk Architect $450.00
Consult with Leaders of the
Project 1 wk Architect $450.00
Submit Planning Application 1 wk Architect $450.00
Review and Update Project
Program 1 wk Project Manager $500.00
Comment on stage Design
Programme and Cost Information 1 wk Project Manager $500.00
Manage Change Control process 1 wk Project Manager $500.00
Review Performance of Project
Team 1 wk Project Manager $500.00
Review and Update Design
Proposal 1 wk Design Manager $450.00
Develop Strategy for
Sustainability, Operations and
Maintenance
1 wk Design Manager $450.00
Update Stage Design Program 1 wk Design Manager $450.00
Review and Update Cost
Information 1 wk Design Manager $450.00
Review Performance of Project
Team 1 wk Design Manager $450.00
Update Architectural Design as
Required 1 wk Architect $450.00
Consult with Leaders of the
Project 1 wk Architect $450.00
Submit Planning Application 1 wk Architect $450.00

17ENGINEERING MANAGEMENT AND PROJECT ORGANISATION
Consult with Third Party and
Research and Development Teams 1 wk Architect $450.00
Update Stage Design Program 1 wk Architect $450.00
Updates Cost Information in
Project Brief 1 wk Architect $450.00
Develop Building Services Design
and Plan 1 wk
Civil and
Structural
Engineer
$450.00
Consult with Third Party and
Research and Development Teams 1 wk
Civil and
Structural
Engineer
$450.00
Update Stage Design Program 1 wk
Civil and
Structural
Engineer
$450.00
Updates Cost Information in
Project Brief 1 wk
Civil and
Structural
Engineer
$450.00
Develop Coordinated and
Updated Proposal for Structural
Design
1 wk
Civil and
Structural
Engineer
$450.00
Consult with Third Party and
Research and Development Teams 1 wk Building Services
Engineer $450.00
Update Stage Design Program 1 wk Building Services
Engineer $450.00
Updates Cost Information in 1 wk Finance $200.00
Consult with Third Party and
Research and Development Teams 1 wk Architect $450.00
Update Stage Design Program 1 wk Architect $450.00
Updates Cost Information in
Project Brief 1 wk Architect $450.00
Develop Building Services Design
and Plan 1 wk
Civil and
Structural
Engineer
$450.00
Consult with Third Party and
Research and Development Teams 1 wk
Civil and
Structural
Engineer
$450.00
Update Stage Design Program 1 wk
Civil and
Structural
Engineer
$450.00
Updates Cost Information in
Project Brief 1 wk
Civil and
Structural
Engineer
$450.00
Develop Coordinated and
Updated Proposal for Structural
Design
1 wk
Civil and
Structural
Engineer
$450.00
Consult with Third Party and
Research and Development Teams 1 wk Building Services
Engineer $450.00
Update Stage Design Program 1 wk Building Services
Engineer $450.00
Updates Cost Information in 1 wk Finance $200.00

18ENGINEERING MANAGEMENT AND PROJECT ORGANISATION
Project Brief Management
Consultant
Update preliminary Cost
information 1 wk
Finance
Management
Consultant
$200.00
Update Construction Strategy 1 wk WHS Consultant $250.00
Update WHS Strategy 1 wk WHS Consultant $250.00
Assist Project Leads 1 wk Head of
Constructions $300.00
Develop Plan for Information
Exchange 1 wk Building Services
Engineer $450.00
Technical Design 34 wks $22,200.00
Contribute to Health & Safety
Strategy as required 1 wk
Architect, Building
Services
Engineer, Civil
and Structural
Engineer, Client
Assistant, Head of
Constructions,
Contract
Manager, Finance
Management
Consultant, WHS
Consultant,
Design Manager,
Project Manager
$3,300.00
Project Brief Management
Consultant
Update preliminary Cost
information 1 wk
Finance
Management
Consultant
$200.00
Update Construction Strategy 1 wk WHS Consultant $250.00
Update WHS Strategy 1 wk WHS Consultant $250.00
Assist Project Leads 1 wk Head of
Constructions $300.00
Develop Plan for Information
Exchange 1 wk Building Services
Engineer $450.00
Technical Design 34 wks $22,200.00
Contribute to Health & Safety
Strategy as required 1 wk
Architect, Building
Services
Engineer, Civil
and Structural
Engineer, Client
Assistant, Head of
Constructions,
Contract
Manager, Finance
Management
Consultant, WHS
Consultant,
Design Manager,
Project Manager
$3,300.00
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

19ENGINEERING MANAGEMENT AND PROJECT ORGANISATION
Provide information for and
contribute to contents of Project
Execution Plan as required
1 wk
Architect, Building
Services
Engineer, Civil
and Structural
Engineer, Client
Assistant, Head of
Constructions,
Contract
Manager, Finance
Management
Consultant, WHS
Consultant,
Design Manager,
Project Manager
$3,300.00
Comment on Technical Design
proposals as requested 1 wk Building Services
Engineer $450.00
Comment on updated Project
Strategies as requested 1 wk Building Services
Engineer $450.00
Monitor progress of developing
design 1 wk Building Services
Engineer $450.00
Update Handover and Risk
Strategies 1 wk Head of
Constructions $300.00
Update Execution Plan of the
Project 1 wk Head of
Constructions $300.00
Update Stage Design Program 1 wk Head of
Constructions $300.00
Manage Change Control process 1 wk Head of $300.00
Provide information for and
contribute to contents of Project
Execution Plan as required
1 wk
Architect, Building
Services
Engineer, Civil
and Structural
Engineer, Client
Assistant, Head of
Constructions,
Contract
Manager, Finance
Management
Consultant, WHS
Consultant,
Design Manager,
Project Manager
$3,300.00
Comment on Technical Design
proposals as requested 1 wk Building Services
Engineer $450.00
Comment on updated Project
Strategies as requested 1 wk Building Services
Engineer $450.00
Monitor progress of developing
design 1 wk Building Services
Engineer $450.00
Update Handover and Risk
Strategies 1 wk Head of
Constructions $300.00
Update Execution Plan of the
Project 1 wk Head of
Constructions $300.00
Update Stage Design Program 1 wk Head of
Constructions $300.00
Manage Change Control process 1 wk Head of $300.00

20ENGINEERING MANAGEMENT AND PROJECT ORGANISATION
Constructions
Review Performance of Project
Team 1 wk Head of
Constructions $300.00
Review of Technical Design for
the Project 1 wk
Civil and
Structural
Engineer
$450.00
Develop Strategy for
Sustainability, Operations and
Maintenance
1 wk
Civil and
Structural
Engineer
$450.00
Update Stage Design Program 1 wk
Civil and
Structural
Engineer
$450.00
Review Performance of Project
Team 1 wk
Civil and
Structural
Engineer
$450.00
Assist Project Leads 1 wk Architect $450.00
Develop Plan for Information
Exchange 1 wk Architect $450.00
Submit Building Regulations
Submission (Building Warrant in
Scotland)
1 wk Building Services
Engineer $450.00
Consult with Third Party and
Research and Development Teams 1 wk Building Services
Engineer $450.00
Update Plan for Stage Design 1 wk Building Services $450.00
Constructions
Review Performance of Project
Team 1 wk Head of
Constructions $300.00
Review of Technical Design for
the Project 1 wk
Civil and
Structural
Engineer
$450.00
Develop Strategy for
Sustainability, Operations and
Maintenance
1 wk
Civil and
Structural
Engineer
$450.00
Update Stage Design Program 1 wk
Civil and
Structural
Engineer
$450.00
Review Performance of Project
Team 1 wk
Civil and
Structural
Engineer
$450.00
Assist Project Leads 1 wk Architect $450.00
Develop Plan for Information
Exchange 1 wk Architect $450.00
Submit Building Regulations
Submission (Building Warrant in
Scotland)
1 wk Building Services
Engineer $450.00
Consult with Third Party and
Research and Development Teams 1 wk Building Services
Engineer $450.00
Update Plan for Stage Design 1 wk Building Services $450.00

21ENGINEERING MANAGEMENT AND PROJECT ORGANISATION
Engineer
Provide information for update of
Project Strategies 1 wk Building Services
Engineer $450.00
Liaise with specialist
subcontractors as necessary 1 wk Building Services
Engineer $450.00
Update Technical Design and
Information Exchange Plan 1 wk Building Services
Engineer $450.00
Consultation with Third Party
Regarding Project 1 wk Building Services
Engineer $450.00
Update Plan for Stage Design 1 wk
Finance
Management
Consultant
$200.00
Update Cost Information in
Project Brief 1 wk
Finance
Management
Consultant
$200.00
Liaise with specialist
subcontractors as necessary 1 wk Head of
Constructions $300.00
Update Technical Design and
Information Exchange Plan 1 wk
Civil and
Structural
Engineer
$450.00
Consult with Third Party and
Research and Development Teams 1 wk
Civil and
Structural
Engineer
$450.00
Update Cost Information in
Project Brief
1 wk Finance
Management
$200.00
Engineer
Provide information for update of
Project Strategies 1 wk Building Services
Engineer $450.00
Liaise with specialist
subcontractors as necessary 1 wk Building Services
Engineer $450.00
Update Technical Design and
Information Exchange Plan 1 wk Building Services
Engineer $450.00
Consultation with Third Party
Regarding Project 1 wk Building Services
Engineer $450.00
Update Plan for Stage Design 1 wk
Finance
Management
Consultant
$200.00
Update Cost Information in
Project Brief 1 wk
Finance
Management
Consultant
$200.00
Liaise with specialist
subcontractors as necessary 1 wk Head of
Constructions $300.00
Update Technical Design and
Information Exchange Plan 1 wk
Civil and
Structural
Engineer
$450.00
Consult with Third Party and
Research and Development Teams 1 wk
Civil and
Structural
Engineer
$450.00
Update Cost Information in
Project Brief
1 wk Finance
Management
$200.00
Secure Best Marks with AI Grader
Need help grading? Try our AI Grader for instant feedback on your assignments.

22ENGINEERING MANAGEMENT AND PROJECT ORGANISATION
Consultant
Update Construction Strategy 1 wk Project Manager $500.00
Prepare Building Contract, agree
with contractor and arrange
completion
1 wk Project Manager $500.00
Update WHS Strategy 1 wk Project Manager $500.00
Assist Project Leads 1 wk Head of
Constructions $300.00
Update Technical Design and
Information Exchange Plan 1 wk
Architect, Building
Services
Engineer, Civil
and Structural
Engineer, Client
Assistant, Head of
Constructions,
Contract
Manager, Finance
Management
Consultant, WHS
Consultant,
Design Manager,
Project Manager
$3,300.00
Consultant
Update Construction Strategy 1 wk Project Manager $500.00
Prepare Building Contract, agree
with contractor and arrange
completion
1 wk Project Manager $500.00
Update WHS Strategy 1 wk Project Manager $500.00
Assist Project Leads 1 wk Head of
Constructions $300.00
Update Technical Design and
Information Exchange Plan 1 wk
Architect, Building
Services
Engineer, Civil
and Structural
Engineer, Client
Assistant, Head of
Constructions,
Contract
Manager, Finance
Management
Consultant, WHS
Consultant,
Design Manager,
Project Manager
$3,300.00

23ENGINEERING MANAGEMENT AND PROJECT ORGANISATION
Bibliography
Harrison, F. and Lock, D., 2017. Advanced project management: a structured approach.
Routledge.
Kerzner, H. and Kerzner, H.R., 2017. Project management: a systems approach to
planning, scheduling, and controlling. John Wiley & Sons.
Mir, F.A. and Pinnington, A.H., 2014. Exploring the value of project management: linking
project management performance and project success. International journal of project
management, 32(2), pp.202-217.
Schwalbe, K., 2015. Information technology project management. Cengage Learning.
Bibliography
Harrison, F. and Lock, D., 2017. Advanced project management: a structured approach.
Routledge.
Kerzner, H. and Kerzner, H.R., 2017. Project management: a systems approach to
planning, scheduling, and controlling. John Wiley & Sons.
Mir, F.A. and Pinnington, A.H., 2014. Exploring the value of project management: linking
project management performance and project success. International journal of project
management, 32(2), pp.202-217.
Schwalbe, K., 2015. Information technology project management. Cengage Learning.

1 out of 25

Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
© 2024 | Zucol Services PVT LTD | All rights reserved.