Developing an Enhanced System for Project Management in Organizations
VerifiedAdded on 2020/04/01
|19
|2646
|49
AI Summary
The assignment delves into the strategic planning and execution of an innovative ride-sharing project for RALS. It involves developing and implementing an advanced IT system featuring a mobile app, online payment processing, customer tracking via GPS, and data analytics for operational insights. The case study emphasizes the importance of strategic information systems, risk management, and effective resource allocation in achieving project success. Drawing on extensive research and expert analyses, it examines critical factors contributing to the efficient deployment of these technologies and highlights methodologies that ensure robust system performance and user satisfaction.

Running head: PROJECT MANAGEMENT
Project Management
Name of the Student:
Student ID:
Name of the University:
Author’s note:
Project Management
Name of the Student:
Student ID:
Name of the University:
Author’s note:
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

1PROJECT MANAGEMENT
1. Part One: MOV - Measurable Organisational Value
The strategy, customer, financial, operational, and social is the desired area of impact for the
RALS ticket system development project. These factors are explained below,
Area of
impact
Description Ranking
Financial the money related framework can be clarified as the operations of the
procedures for the improvement of the operations for coordinating the
advancement of the operations and suggesting the consummation of the
undertaking
1st
Customer the customers can be comprehended as the framework range of raising
different sorts of questions brought by the general population up in connection
to the framework and task created for RALS
2nd
Operational the operational procedures would be inferred for shaping the security of the
operations and its reconciliation of the procedure for the adjustment of the
procedures of the association4th
3rd
Strategy the strategy can be characterized for affecting the operations of the venture of
RALS by building up some successful and enhanced operations
4th
Social the operational procedures would be suggested for building up the security of
the operations and its combination of the procedures
5th
o Better – The RALS venture had seen the advancement of another framework for
expanding the proficiency of work by data administration
1. Part One: MOV - Measurable Organisational Value
The strategy, customer, financial, operational, and social is the desired area of impact for the
RALS ticket system development project. These factors are explained below,
Area of
impact
Description Ranking
Financial the money related framework can be clarified as the operations of the
procedures for the improvement of the operations for coordinating the
advancement of the operations and suggesting the consummation of the
undertaking
1st
Customer the customers can be comprehended as the framework range of raising
different sorts of questions brought by the general population up in connection
to the framework and task created for RALS
2nd
Operational the operational procedures would be inferred for shaping the security of the
operations and its reconciliation of the procedure for the adjustment of the
procedures of the association4th
3rd
Strategy the strategy can be characterized for affecting the operations of the venture of
RALS by building up some successful and enhanced operations
4th
Social the operational procedures would be suggested for building up the security of
the operations and its combination of the procedures
5th
o Better – The RALS venture had seen the advancement of another framework for
expanding the proficiency of work by data administration

2PROJECT MANAGEMENT
o Faster – The RALS undertaking would help in incorporating the operations of the venture
and advancement of the expanded speed of operations
o Cheaper – The RALS task would help in dealing with the data on a solitary database and
subsequently it would diminish the general cost of the data framework administration
o Do more – The framework usage at RALS would incorporate the data of the RALS and it
would help in building up the more intelligent procedures of the association.
Rank Impact Metrics Timeframe
1 Financial Money Profit and Revenue era 6 months
2 Customer Number of clients returning to the association for their
administrations
2 months
3 Operational Less Consumption of time for the finishing of the hierarchical
operations
2 months
4 Strategy The volunteers would get followed because of the utilization of
the framework created in RALS
1 month
5 Social Volunteers would have the capacity to get associated with the
clients
3 months
o Faster – The RALS undertaking would help in incorporating the operations of the venture
and advancement of the expanded speed of operations
o Cheaper – The RALS task would help in dealing with the data on a solitary database and
subsequently it would diminish the general cost of the data framework administration
o Do more – The framework usage at RALS would incorporate the data of the RALS and it
would help in building up the more intelligent procedures of the association.
Rank Impact Metrics Timeframe
1 Financial Money Profit and Revenue era 6 months
2 Customer Number of clients returning to the association for their
administrations
2 months
3 Operational Less Consumption of time for the finishing of the hierarchical
operations
2 months
4 Strategy The volunteers would get followed because of the utilization of
the framework created in RALS
1 month
5 Social Volunteers would have the capacity to get associated with the
clients
3 months
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

3PROJECT MANAGEMENT
2. Part Two: Define Scope and produce a Scope Management Plan
Scope Definition: The undertaking of RALS Ticketing System advancement would help in
building up the change of the operations of the Globex for following client's and volunteer's data
by the assistance of framework created.
Requirements: The requirements of the project include both project team and materials for the
development of the project operations. The requirements of the project are,
Resource Name Type
Budgeter Work
Computer Devices Material
Documenter Work
IT Engineer Work
Network Components Material
Planner Work
Project Manager Work
Storage Material
System Analyst Work
Tester Work
Wireless routers Material
In-scope and out of scope items of the project: The in-scope things of the RALS venture are
get ready for the operations of the undertaking, improvement of the RALS Ticketing System,
increment of effectiveness of the administration of the data about volunteers, and helping for
2. Part Two: Define Scope and produce a Scope Management Plan
Scope Definition: The undertaking of RALS Ticketing System advancement would help in
building up the change of the operations of the Globex for following client's and volunteer's data
by the assistance of framework created.
Requirements: The requirements of the project include both project team and materials for the
development of the project operations. The requirements of the project are,
Resource Name Type
Budgeter Work
Computer Devices Material
Documenter Work
IT Engineer Work
Network Components Material
Planner Work
Project Manager Work
Storage Material
System Analyst Work
Tester Work
Wireless routers Material
In-scope and out of scope items of the project: The in-scope things of the RALS venture are
get ready for the operations of the undertaking, improvement of the RALS Ticketing System,
increment of effectiveness of the administration of the data about volunteers, and helping for
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

4PROJECT MANAGEMENT
operational and key advancement. The out of degree things of the RALS venture incorporate
upkeep exercises, conveyance of the materials, and preparing of the labourers in Globex
Deliverables of the project: The deliverables for the RALS venture are,
a. Project Plan and Resource Allocation Plan
b. Project Documents including Initiation and Charter Documentation
c. Scope Verification Plan
d. System Design and Implementation Plan
e. Testing Results
Acceptance Criteria:
Checklist Item Checked
Advancement of the Project Plan
Improved Resource Allocation Plan
Closing down the Project Documents including Initiation and Charter
Documentation
Viable System Design
Well ordered usage design
Expected Test comes about
operational and key advancement. The out of degree things of the RALS venture incorporate
upkeep exercises, conveyance of the materials, and preparing of the labourers in Globex
Deliverables of the project: The deliverables for the RALS venture are,
a. Project Plan and Resource Allocation Plan
b. Project Documents including Initiation and Charter Documentation
c. Scope Verification Plan
d. System Design and Implementation Plan
e. Testing Results
Acceptance Criteria:
Checklist Item Checked
Advancement of the Project Plan
Improved Resource Allocation Plan
Closing down the Project Documents including Initiation and Charter
Documentation
Viable System Design
Well ordered usage design
Expected Test comes about

5PROJECT MANAGEMENT
List of resources:
Resource Name Tasks
Budgeter Client's requirement is analyzed
Budget for the project is developed
Outsourcing of the project materials
Computer Devices Installing hardware components
Documenter Making Initiation documents
Charter documentation
Making final documents
Review of documents
IT Engineer Storage is developed
Transfer of the data
Design analysis for the ticket system
Development of User interface
Coding and programming is done
Integration of ticket system with storage
Installing hardware components
Network Components Installing hardware components
Planner Project team is selected
Plan methodology is selected
Outline for the plan is developed
Project Manager Analysis of the project feasibility
Requirement Analysis
Project Meetings are held
Signing off the documents
List of resources:
Resource Name Tasks
Budgeter Client's requirement is analyzed
Budget for the project is developed
Outsourcing of the project materials
Computer Devices Installing hardware components
Documenter Making Initiation documents
Charter documentation
Making final documents
Review of documents
IT Engineer Storage is developed
Transfer of the data
Design analysis for the ticket system
Development of User interface
Coding and programming is done
Integration of ticket system with storage
Installing hardware components
Network Components Installing hardware components
Planner Project team is selected
Plan methodology is selected
Outline for the plan is developed
Project Manager Analysis of the project feasibility
Requirement Analysis
Project Meetings are held
Signing off the documents
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

6PROJECT MANAGEMENT
Review of the plan
Signing off the documents
Storage Storage is developed
System Analyst Design Platform is selected
Outline for the design is developed
Prototype is developed
Review of the prototype
Simulation of the completed design
Tester Black box testing
UX testing
Operations and tested
white box testing
Wireless routers Installing hardware components
Resource Name Type Initials Std. Rate
Budgeter Work B $60.00/hr
Computer Devices Material C $1,740.00
Documenter Work D $60.00/hr
IT Engineer Work I $95.00/hr
Network Components Material N $970.00
Review of the plan
Signing off the documents
Storage Storage is developed
System Analyst Design Platform is selected
Outline for the design is developed
Prototype is developed
Review of the prototype
Simulation of the completed design
Tester Black box testing
UX testing
Operations and tested
white box testing
Wireless routers Installing hardware components
Resource Name Type Initials Std. Rate
Budgeter Work B $60.00/hr
Computer Devices Material C $1,740.00
Documenter Work D $60.00/hr
IT Engineer Work I $95.00/hr
Network Components Material N $970.00
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

7PROJECT MANAGEMENT
Planner Work P $60.00/hr
Project Manager Work PM $100.00/hr
Storage Material S $2,320.00
System Analyst Work SA $90.00/hr
Tester Work T $85.00/hr
Wireless routers Material W $870.00
3. Part Three: Project Plan
WBS Task Name Duration Start Finish Predecessor
s Resource Names Cost
0
Developing
Ticketing System
for RALS
140
days
Mon
10/2/17
Fri
4/13/18 $99,980.00
1 Initial Phase 17 days Mon
10/2/17
Tue
10/24/17 $11,360.00
1.1
Analysis of
the project
feasibility
3 days Mon
10/2/17
Wed
10/4/17 Project Manager $2,400.00
1.2 Requirement
Analysis 5 days Thu
10/5/17
Wed
10/11/17 2 Project Manager $4,000.00
1.3
Making
Initiation
documents
4 days Thu
10/12/17
Tue
10/17/17 3 Documenter $1,920.00
1.4 Charter
documentation 3 days Wed
10/18/17
Fri
10/20/17 4 Documenter $1,440.00
Planner Work P $60.00/hr
Project Manager Work PM $100.00/hr
Storage Material S $2,320.00
System Analyst Work SA $90.00/hr
Tester Work T $85.00/hr
Wireless routers Material W $870.00
3. Part Three: Project Plan
WBS Task Name Duration Start Finish Predecessor
s Resource Names Cost
0
Developing
Ticketing System
for RALS
140
days
Mon
10/2/17
Fri
4/13/18 $99,980.00
1 Initial Phase 17 days Mon
10/2/17
Tue
10/24/17 $11,360.00
1.1
Analysis of
the project
feasibility
3 days Mon
10/2/17
Wed
10/4/17 Project Manager $2,400.00
1.2 Requirement
Analysis 5 days Thu
10/5/17
Wed
10/11/17 2 Project Manager $4,000.00
1.3
Making
Initiation
documents
4 days Thu
10/12/17
Tue
10/17/17 3 Documenter $1,920.00
1.4 Charter
documentation 3 days Wed
10/18/17
Fri
10/20/17 4 Documenter $1,440.00

8PROJECT MANAGEMENT
1.5 Project
Meetings are held 1 day Mon
10/23/17
Mon
10/23/17 5 Project Manager $800.00
1.6 Signing off
the documents 1 day Tue
10/24/17
Tue
10/24/17 6 Project Manager $800.00
M1 Initial Phase is
completed 0 days Tue
10/24/17
Tue
10/24/17 7 $0.00
2 Resource
Accumulation 19 days Wed
10/25/17
Mon
11/20/17 $9,120.00
2.1
Client's
requirement is
analyzed
5 days Wed
10/25/17
Tue
10/31/17 8 Budgeter $2,400.00
2.2 Project team
is selected 7 days Wed
11/1/17
Thu
11/9/17 10 Planner $3,360.00
2.3
Budget for the
project is
developed
4 days Fri
11/10/17
Wed
11/15/17 11 Budgeter $1,920.00
2.4
Outsourcing
of the project
materials
3 days Thu
11/16/17
Mon
11/20/17 12 Budgeter $1,440.00
M2 Accumulation
of the resources 0 days Mon
11/20/17
Mon
11/20/17 13 $0.00
3 Plan Phase 10 days Tue
11/21/17
Mon
12/4/17 $5,760.00
3.1
Plan
methodology is
selected
2 days Tue
11/21/17
Wed
11/22/17 14 Planner $960.00
3.2 Outline for the
plan is developed 5 days Thu
11/23/17
Wed
11/29/17 16 Planner $2,400.00
3.3 Review of the
plan 3 days Thu
11/30/17
Mon
12/4/17 17 Project Manager $2,400.00
M3 Plan is
completed 0 days Mon
12/4/17
Mon
12/4/17 18 $0.00
4 Design Phase 16 days Tue Tue $11,520.00
1.5 Project
Meetings are held 1 day Mon
10/23/17
Mon
10/23/17 5 Project Manager $800.00
1.6 Signing off
the documents 1 day Tue
10/24/17
Tue
10/24/17 6 Project Manager $800.00
M1 Initial Phase is
completed 0 days Tue
10/24/17
Tue
10/24/17 7 $0.00
2 Resource
Accumulation 19 days Wed
10/25/17
Mon
11/20/17 $9,120.00
2.1
Client's
requirement is
analyzed
5 days Wed
10/25/17
Tue
10/31/17 8 Budgeter $2,400.00
2.2 Project team
is selected 7 days Wed
11/1/17
Thu
11/9/17 10 Planner $3,360.00
2.3
Budget for the
project is
developed
4 days Fri
11/10/17
Wed
11/15/17 11 Budgeter $1,920.00
2.4
Outsourcing
of the project
materials
3 days Thu
11/16/17
Mon
11/20/17 12 Budgeter $1,440.00
M2 Accumulation
of the resources 0 days Mon
11/20/17
Mon
11/20/17 13 $0.00
3 Plan Phase 10 days Tue
11/21/17
Mon
12/4/17 $5,760.00
3.1
Plan
methodology is
selected
2 days Tue
11/21/17
Wed
11/22/17 14 Planner $960.00
3.2 Outline for the
plan is developed 5 days Thu
11/23/17
Wed
11/29/17 16 Planner $2,400.00
3.3 Review of the
plan 3 days Thu
11/30/17
Mon
12/4/17 17 Project Manager $2,400.00
M3 Plan is
completed 0 days Mon
12/4/17
Mon
12/4/17 18 $0.00
4 Design Phase 16 days Tue Tue $11,520.00
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

9PROJECT MANAGEMENT
12/5/17 12/26/17
4.1
Design
Platform is
selected
1 day Tue
12/5/17
Tue
12/5/17 19 System Analyst $720.00
4.2
Outline for the
design is
developed
3 days Wed
12/6/17
Fri
12/8/17 21 System Analyst $2,160.00
4.3 Prototype is
developed 7 days Mon
12/11/17
Tue
12/19/17 22 System Analyst $5,040.00
4.4 Review of the
prototype 2 days Wed
12/20/17
Thu
12/21/17 23 System Analyst $1,440.00
4.5
Simulation of
the completed
design
3 days Fri
12/22/17
Tue
12/26/17 24 System Analyst $2,160.00
M4 Complete
design is formed 0 days Tue
12/26/17
Tue
12/26/17 25 $0.00
5 Implementatio
n Phase 52 days Wed
12/27/17
Thu
3/8/18 $45,420.00
5.1 Storage is
developed 10 days Wed
12/27/17
Tue
1/9/18 26 IT Engineer,
Storage[1] $9,920.00
5.2 Transfer of
the data 5 days Wed
1/10/18
Tue
1/16/18 28 IT Engineer $3,800.00
5.3
Design
analysis for the
ticket system
4 days Wed
1/17/18
Mon
1/22/18 29 IT Engineer $3,040.00
5.4 Development
of User interface 6 days Tue
1/23/18
Tue
1/30/18 30 IT Engineer $4,560.00
5.5
Coding and
programming is
done
12 days Wed
1/31/18
Thu
2/15/18 31 IT Engineer $9,120.00
5.6
Integration of
ticket system with
storage
8 days Fri
2/16/18
Tue
2/27/18 32 IT Engineer $6,080.00
5.7 Installing 7 days Wed Thu 33 IT Engineer, $8,900.00
12/5/17 12/26/17
4.1
Design
Platform is
selected
1 day Tue
12/5/17
Tue
12/5/17 19 System Analyst $720.00
4.2
Outline for the
design is
developed
3 days Wed
12/6/17
Fri
12/8/17 21 System Analyst $2,160.00
4.3 Prototype is
developed 7 days Mon
12/11/17
Tue
12/19/17 22 System Analyst $5,040.00
4.4 Review of the
prototype 2 days Wed
12/20/17
Thu
12/21/17 23 System Analyst $1,440.00
4.5
Simulation of
the completed
design
3 days Fri
12/22/17
Tue
12/26/17 24 System Analyst $2,160.00
M4 Complete
design is formed 0 days Tue
12/26/17
Tue
12/26/17 25 $0.00
5 Implementatio
n Phase 52 days Wed
12/27/17
Thu
3/8/18 $45,420.00
5.1 Storage is
developed 10 days Wed
12/27/17
Tue
1/9/18 26 IT Engineer,
Storage[1] $9,920.00
5.2 Transfer of
the data 5 days Wed
1/10/18
Tue
1/16/18 28 IT Engineer $3,800.00
5.3
Design
analysis for the
ticket system
4 days Wed
1/17/18
Mon
1/22/18 29 IT Engineer $3,040.00
5.4 Development
of User interface 6 days Tue
1/23/18
Tue
1/30/18 30 IT Engineer $4,560.00
5.5
Coding and
programming is
done
12 days Wed
1/31/18
Thu
2/15/18 31 IT Engineer $9,120.00
5.6
Integration of
ticket system with
storage
8 days Fri
2/16/18
Tue
2/27/18 32 IT Engineer $6,080.00
5.7 Installing 7 days Wed Thu 33 IT Engineer, $8,900.00
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

10PROJECT MANAGEMENT
hardware
components 2/28/18 3/8/18
Computer
Devices[1],
Network
Components[1],
Wireless routers[1]
M5
New System
installed in
Globex
0 days Thu
3/8/18
Thu
3/8/18 34 $0.00
6 Testing Phase 20 days Fri
3/9/18
Thu
4/5/18 $13,600.00
6.1 Black box
testing 5 days Fri
3/9/18
Thu
3/15/18 35 Tester $3,400.00
6.2 UX testing 5 days Fri
3/16/18
Thu
3/22/18 37 Tester $3,400.00
6.3 Operations
and tested 5 days Fri
3/23/18
Thu
3/29/18 38 Tester $3,400.00
6.4 white box
testing 5 days Fri
3/30/18
Thu
4/5/18 39 Tester $3,400.00
M6 Results of
tests are compiled 0 days Thu
4/5/18
Thu
4/5/18 40 $0.00
7 Documentation
Phase 6 days Fri
4/6/18
Fri
4/13/18 $3,200.00
7.1 Making final
documents 3 days Fri
4/6/18
Tue
4/10/18 41 Documenter $1,440.00
7.2 Review of
documents 2 days Wed
4/11/18
Thu
4/12/18 43 Documenter $960.00
7.3 Signing off
the documents 1 day Fri
4/13/18
Fri
4/13/18 44 Project Manager $800.00
M7 Project is
closed 0 days Fri
4/13/18
Fri
4/13/18 45 $0.00
Gantt chart for the project is shown below,
hardware
components 2/28/18 3/8/18
Computer
Devices[1],
Network
Components[1],
Wireless routers[1]
M5
New System
installed in
Globex
0 days Thu
3/8/18
Thu
3/8/18 34 $0.00
6 Testing Phase 20 days Fri
3/9/18
Thu
4/5/18 $13,600.00
6.1 Black box
testing 5 days Fri
3/9/18
Thu
3/15/18 35 Tester $3,400.00
6.2 UX testing 5 days Fri
3/16/18
Thu
3/22/18 37 Tester $3,400.00
6.3 Operations
and tested 5 days Fri
3/23/18
Thu
3/29/18 38 Tester $3,400.00
6.4 white box
testing 5 days Fri
3/30/18
Thu
4/5/18 39 Tester $3,400.00
M6 Results of
tests are compiled 0 days Thu
4/5/18
Thu
4/5/18 40 $0.00
7 Documentation
Phase 6 days Fri
4/6/18
Fri
4/13/18 $3,200.00
7.1 Making final
documents 3 days Fri
4/6/18
Tue
4/10/18 41 Documenter $1,440.00
7.2 Review of
documents 2 days Wed
4/11/18
Thu
4/12/18 43 Documenter $960.00
7.3 Signing off
the documents 1 day Fri
4/13/18
Fri
4/13/18 44 Project Manager $800.00
M7 Project is
closed 0 days Fri
4/13/18
Fri
4/13/18 45 $0.00
Gantt chart for the project is shown below,

11PROJECT MANAGEMENT
ID Task
Mode
WBS Task Name Duration Start Finish Predecessors Resource Names Cost
0 0 Developing Ticketing
System for RALS
140 days Mon 10/2/17 Fri 4/13/18 $99,980.00
1 1 Initial Phase 17 days Mon 10/2/17 Tue 10/24/17 $11,360.00
2 1.1 Analysis of the project
feasibility
3 days Mon 10/2/17 Wed 10/4/17 Project
Manager
$2,400.00
3 1.2 Requirement Analysis 5 days Thu 10/5/17 Wed 10/11/17 2 Project Manager $4,000.00
4 1.3 Making Initiation documents4 days Thu 10/12/17 Tue 10/17/17 3 Documenter $1,920.00
5 1.4 Charter documentation 3 days Wed 10/18/17 Fri 10/20/17 4 Documenter $1,440.00
6 1.5 Project Meetings are held1 day Mon 10/23/17 Mon 10/23/17 5 Project Manager $800.00
7 1.6 Signing off the documents1 day Tue 10/24/17 Tue 10/24/17 6 Project Manager $800.00
8 M1 Initial Phase is completed0 days Tue 10/24/17 Tue 10/24/17 7 $0.00
9 2 Resource Accumulation 19 days Wed 10/25/17 Mon 11/20/17 $9,120.00
10 2.1 Client's requirement is
analyzed
5 days Wed 10/25/17 Tue 10/31/17 8 Budgeter $2,400.00
11 2.2 Project team is selected7 days Wed 11/1/17 Thu 11/9/17 10 Planner $3,360.00
12 2.3 Budget for the project
is developed
4 days Fri 11/10/17 Wed 11/15/17 11 Budgeter $1,920.00
13 2.4 Outsourcing of the
project materials
3 days Thu 11/16/17 Mon 11/20/17 12 Budgeter $1,440.00
14 M2 Accumulation of the resources0 days Mon 11/20/17 Mon 11/20/17 13 $0.00
15 3 Plan Phase 10 days Tue 11/21/17 Mon 12/4/17 $5,760.00
16 3.1 Plan methodology is selected2 days Tue 11/21/17 Wed 11/22/17 14 Planner $960.00
17 3.2 Outline for the plan is
developed
5 days Thu 11/23/17 Wed 11/29/17 16 Planner $2,400.00
18 3.3 Review of the plan 3 days Thu 11/30/17 Mon 12/4/17 17 Project Manager $2,400.00
19 M3 Plan is completed 0 days Mon 12/4/17 Mon 12/4/17 18 $0.00
20 4 Design Phase 16 days Tue 12/5/17 Tue 12/26/17 $11,520.00
21 4.1 Design Platform is selected1 day Tue 12/5/17 Tue 12/5/17 19 System Analyst $720.00
22 4.2 Outline for the design
is developed
3 days Wed 12/6/17 Fri 12/8/17 21 System Analyst $2,160.00
23 4.3 Prototype is developed 7 days Mon 12/11/17 Tue 12/19/17 22 System Analyst $5,040.00
24 4.4 Review of the prototype2 days Wed 12/20/17 Thu 12/21/17 23 System Analyst $1,440.00
25 4.5 Simulation of the
completed design
3 days Fri 12/22/17 Tue 12/26/17 24 System Analyst $2,160.00
26 M4 Complete design is formed0 days Tue 12/26/17 Tue 12/26/17 25 $0.00
27 5 Implementation Phase 52 days Wed 12/27/17 Thu 3/8/18 $45,420.00
28 5.1 Storage is developed 10 days Wed 12/27/17 Tue 1/9/18 26 IT Engineer,Storage[1] $9,920.00
29 5.2 Transfer of the data 5 days Wed 1/10/18 Tue 1/16/18 28 IT Engineer $3,800.00
30 5.3 Design analysis for the
ticket system
4 days Wed 1/17/18 Mon 1/22/18 29 IT Engineer $3,040.00
31 5.4 Development of User
interface
6 days Tue 1/23/18 Tue 1/30/18 30 IT Engineer $4,560.00
32 5.5 Coding and
programming is done
12 days Wed 1/31/18 Thu 2/15/18 31 IT Engineer $9,120.00
33 5.6 Integration of ticket
system with storage
8 days Fri 2/16/18 Tue 2/27/18 32 IT Engineer $6,080.00
34 5.7 Installing hardware
components
7 days Wed 2/28/18 Thu 3/8/18 33 IT
Engineer,Computer
Devices[1],Network
$8,900.00
35 M5 New System installed
in Globex
0 days Thu 3/8/18 Thu 3/8/18 34 $0.00
36 6 Testing Phase 20 days Fri 3/9/18 Thu 4/5/18 $13,600.00
37 6.1 Black box testing 5 days Fri 3/9/18 Thu 3/15/18 35 Tester $3,400.00
38 6.2 UX testing 5 days Fri 3/16/18 Thu 3/22/18 37 Tester $3,400.00
39 6.3 Operations and tested 5 days Fri 3/23/18 Thu 3/29/18 38 Tester $3,400.00
40 6.4 white box testing 5 days Fri 3/30/18 Thu 4/5/18 39 Tester $3,400.00
41 M6 Results of tests are compiled0 days Thu 4/5/18 Thu 4/5/18 40 $0.00
42 7 Documentation Phase 6 days Fri 4/6/18 Fri 4/13/18 $3,200.00
43 7.1 Making final documents3 days Fri 4/6/18 Tue 4/10/18 41 Documenter $1,440.00
44 7.2 Review of documents 2 days Wed 4/11/18 Thu 4/12/18 43 Documenter $960.00
45 7.3 Signing off the documents1 day Fri 4/13/18 Fri 4/13/18 44 Project Manager $800.00
46 M7 Project is closed 0 days Fri 4/13/18 Fri 4/13/18 45 $0.00
Project Manager
Project Manager
Documenter
Documenter
Project Manager
Project Manager
10/24
Budgeter
Planner
Budgeter
Budgeter
11/20
Planner
Planner
Project Manager
12/4
System Analyst
System Analyst
System Analyst
System Analyst
System Analyst
12/26
IT Engineer,Storage[1]
IT Engineer
IT Engineer
IT Engineer
IT Engineer
IT Engineer
IT Engineer,Computer Devices[1],Network Com
3/8
Tester
Tester
Tester
Tester
4/5
Documenter
Documenter
Project Manager
4/13
S T T S M W
Aug 20, '17 Nov 19, '17 Feb 18, '18 May 20, '18
ID Task
Mode
WBS Task Name Duration Start Finish Predecessors Resource Names Cost
0 0 Developing Ticketing
System for RALS
140 days Mon 10/2/17 Fri 4/13/18 $99,980.00
1 1 Initial Phase 17 days Mon 10/2/17 Tue 10/24/17 $11,360.00
2 1.1 Analysis of the project
feasibility
3 days Mon 10/2/17 Wed 10/4/17 Project
Manager
$2,400.00
3 1.2 Requirement Analysis 5 days Thu 10/5/17 Wed 10/11/17 2 Project Manager $4,000.00
4 1.3 Making Initiation documents4 days Thu 10/12/17 Tue 10/17/17 3 Documenter $1,920.00
5 1.4 Charter documentation 3 days Wed 10/18/17 Fri 10/20/17 4 Documenter $1,440.00
6 1.5 Project Meetings are held1 day Mon 10/23/17 Mon 10/23/17 5 Project Manager $800.00
7 1.6 Signing off the documents1 day Tue 10/24/17 Tue 10/24/17 6 Project Manager $800.00
8 M1 Initial Phase is completed0 days Tue 10/24/17 Tue 10/24/17 7 $0.00
9 2 Resource Accumulation 19 days Wed 10/25/17 Mon 11/20/17 $9,120.00
10 2.1 Client's requirement is
analyzed
5 days Wed 10/25/17 Tue 10/31/17 8 Budgeter $2,400.00
11 2.2 Project team is selected7 days Wed 11/1/17 Thu 11/9/17 10 Planner $3,360.00
12 2.3 Budget for the project
is developed
4 days Fri 11/10/17 Wed 11/15/17 11 Budgeter $1,920.00
13 2.4 Outsourcing of the
project materials
3 days Thu 11/16/17 Mon 11/20/17 12 Budgeter $1,440.00
14 M2 Accumulation of the resources0 days Mon 11/20/17 Mon 11/20/17 13 $0.00
15 3 Plan Phase 10 days Tue 11/21/17 Mon 12/4/17 $5,760.00
16 3.1 Plan methodology is selected2 days Tue 11/21/17 Wed 11/22/17 14 Planner $960.00
17 3.2 Outline for the plan is
developed
5 days Thu 11/23/17 Wed 11/29/17 16 Planner $2,400.00
18 3.3 Review of the plan 3 days Thu 11/30/17 Mon 12/4/17 17 Project Manager $2,400.00
19 M3 Plan is completed 0 days Mon 12/4/17 Mon 12/4/17 18 $0.00
20 4 Design Phase 16 days Tue 12/5/17 Tue 12/26/17 $11,520.00
21 4.1 Design Platform is selected1 day Tue 12/5/17 Tue 12/5/17 19 System Analyst $720.00
22 4.2 Outline for the design
is developed
3 days Wed 12/6/17 Fri 12/8/17 21 System Analyst $2,160.00
23 4.3 Prototype is developed 7 days Mon 12/11/17 Tue 12/19/17 22 System Analyst $5,040.00
24 4.4 Review of the prototype2 days Wed 12/20/17 Thu 12/21/17 23 System Analyst $1,440.00
25 4.5 Simulation of the
completed design
3 days Fri 12/22/17 Tue 12/26/17 24 System Analyst $2,160.00
26 M4 Complete design is formed0 days Tue 12/26/17 Tue 12/26/17 25 $0.00
27 5 Implementation Phase 52 days Wed 12/27/17 Thu 3/8/18 $45,420.00
28 5.1 Storage is developed 10 days Wed 12/27/17 Tue 1/9/18 26 IT Engineer,Storage[1] $9,920.00
29 5.2 Transfer of the data 5 days Wed 1/10/18 Tue 1/16/18 28 IT Engineer $3,800.00
30 5.3 Design analysis for the
ticket system
4 days Wed 1/17/18 Mon 1/22/18 29 IT Engineer $3,040.00
31 5.4 Development of User
interface
6 days Tue 1/23/18 Tue 1/30/18 30 IT Engineer $4,560.00
32 5.5 Coding and
programming is done
12 days Wed 1/31/18 Thu 2/15/18 31 IT Engineer $9,120.00
33 5.6 Integration of ticket
system with storage
8 days Fri 2/16/18 Tue 2/27/18 32 IT Engineer $6,080.00
34 5.7 Installing hardware
components
7 days Wed 2/28/18 Thu 3/8/18 33 IT
Engineer,Computer
Devices[1],Network
$8,900.00
35 M5 New System installed
in Globex
0 days Thu 3/8/18 Thu 3/8/18 34 $0.00
36 6 Testing Phase 20 days Fri 3/9/18 Thu 4/5/18 $13,600.00
37 6.1 Black box testing 5 days Fri 3/9/18 Thu 3/15/18 35 Tester $3,400.00
38 6.2 UX testing 5 days Fri 3/16/18 Thu 3/22/18 37 Tester $3,400.00
39 6.3 Operations and tested 5 days Fri 3/23/18 Thu 3/29/18 38 Tester $3,400.00
40 6.4 white box testing 5 days Fri 3/30/18 Thu 4/5/18 39 Tester $3,400.00
41 M6 Results of tests are compiled0 days Thu 4/5/18 Thu 4/5/18 40 $0.00
42 7 Documentation Phase 6 days Fri 4/6/18 Fri 4/13/18 $3,200.00
43 7.1 Making final documents3 days Fri 4/6/18 Tue 4/10/18 41 Documenter $1,440.00
44 7.2 Review of documents 2 days Wed 4/11/18 Thu 4/12/18 43 Documenter $960.00
45 7.3 Signing off the documents1 day Fri 4/13/18 Fri 4/13/18 44 Project Manager $800.00
46 M7 Project is closed 0 days Fri 4/13/18 Fri 4/13/18 45 $0.00
Project Manager
Project Manager
Documenter
Documenter
Project Manager
Project Manager
10/24
Budgeter
Planner
Budgeter
Budgeter
11/20
Planner
Planner
Project Manager
12/4
System Analyst
System Analyst
System Analyst
System Analyst
System Analyst
12/26
IT Engineer,Storage[1]
IT Engineer
IT Engineer
IT Engineer
IT Engineer
IT Engineer
IT Engineer,Computer Devices[1],Network Com
3/8
Tester
Tester
Tester
Tester
4/5
Documenter
Documenter
Project Manager
4/13
S T T S M W
Aug 20, '17 Nov 19, '17 Feb 18, '18 May 20, '18
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide
1 out of 19
Related Documents

Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
Copyright © 2020–2025 A2Z Services. All Rights Reserved. Developed and managed by ZUCOL.