This report details a project plan for establishing a new flight catering branch, encompassing various project management aspects. It begins with an introduction highlighting the importance of project management in today's complex environment. The report outlines project objectives, including timeline and budget estimation, work breakdown structure (WBS), critical path identification, and managerial aspects. The planning narrative covers project phases (initiation, planning, execution, and closure). The WBS breaks down tasks into manageable sub-activities with durations, start, and finish dates. A critical path network diagram and float period calculations are provided. Organization charts illustrate the project's structure, and discussions on potential organizational cultures and working methods are included. The project's budget is presented, followed by a conclusion summarizing the key findings and recommendations. The report aims to provide a sophisticated and executable project plan for the successful and efficient delivery of the project.
Document Page
Running head: ENVIRONMENTAL PROJECT MANAGEMENT
Environmental Project Management
Open a New Branch of Flight Catering Company
Name of the Student
Name of the University
Author Note
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
1ENVIRONMENTAL PROJECT MANAGEMENT: OPEN NEW BRANCH FOR FLIGHT CATERING
COMPANY
Table of Contents
Introduction......................................................................................................................................2
Planning Narrative...........................................................................................................................3
WBS.................................................................................................................................................4
Critical Path Network Diagram.......................................................................................................5
Float period calculation...................................................................................................................7
Organization charts i)....................................................................................................................10
Organization chart ii).....................................................................................................................11
Potential ‘cultures and’ and ‘methods of working’.......................................................................11
Budget of the Project.....................................................................................................................13
Conclusion.....................................................................................................................................16
Bibliography..................................................................................................................................18
Document Page
2ENVIRONMENTAL PROJECT MANAGEMENT: OPEN NEW BRANCH FOR FLIGHT CATERING
COMPANY
Introduction
Nowadays, the projects are being much complex and advanced than the previous projects
as the room for service improvement are being filled through innovation and implementation of
new services. Project management can play vital role in allowing the projects to be completed in
an efficient and effective manner and delivering the necessary outcomes. The project
management allows the project manager to accomplish the complex operational activities in far
better and efficient manner through providing better and simple strategies to meet the objectives
and goals. The selected project is to open new branch for flight catering company in an effective
and efficient manner. The aim of this report is to propose a sophisticated and executable project
plan for this project that can allow a pathway for the successful and efficient delivery of all the
operational activities in proper managerial aspects. Following are the objectives for the proposed
project:
To estimate the timeline and budget for the development of new branch for fight catering
company
To estimate the work breakdown structure and the critical path that can be followed for
prior delivery of the project
To manage the managerial aspects for the operational activities of entire project
To successfully develop new branch for fight catering company that can fulfil the
organization needs and requirements
To establish a mini rail system for transferring the food to the respective consumers
This report will be covering the project constraints and the pathway that can be followed
for successful accomplishment of the entire operational activities in a smooth and efficient
Document Page
3ENVIRONMENTAL PROJECT MANAGEMENT: OPEN NEW BRANCH FOR FLIGHT CATERING
COMPANY
manner. Strictly following the mentioned approaches will allow the project manager to deliver
the project in an efficient and effective manner.
Planning Narrative
The project plan will include the different phases considering initiation, planning,
execution, and closure in manner to assure that the project delivery can be made in a way that it
can fulfil the organizational needs and requirements. The project will have major activities and
sub-activities those have been demonstrated in the following table with the duration, start, and
finish dates:
WBS Task Name Duration Start Finish
1 Open a new branch of flight
catering company 143 days Thu 8/16/18 Mon 3/4/19
1.1 Project Initiation 42 days Thu 8/16/18 Fri 10/12/18
1.1.1 Business plan development 12 days Thu 8/16/18 Fri 8/31/18
1.1.2 Project Fund 15 days Mon 9/3/18 Fri 9/21/18
1.1.3 Project Budget 12 days Mon 9/3/18 Tue 9/18/18
1.1.4 Services and Goods
Contracts/procurements 10 days Mon 9/24/18 Fri 10/5/18
1.1.5 Project Scheduling 5 days Mon 10/8/18 Fri 10/12/18
1.2 Requirement Analysis 35 days Mon 10/15/18 Fri 11/30/18
1.2.1 Target Market Defining 7 days Mon 10/15/18 Tue 10/23/18
1.2.2 Location 6 days Wed 10/24/18 Wed 10/31/18
1.2.2.1 Sanitation Services 4 days Wed 10/24/18 Mon 10/29/18
1.2.2.2 Utilities 6 days Wed 10/24/18 Wed 10/31/18
1.2.3 Space management 15 days Thu 11/1/18 Wed 11/21/18
1.2.4 Staffing allocation 7 days Thu 11/22/18 Fri 11/30/18
1.3 Selection of Site 27 days Mon 12/3/18 Tue 1/8/19
1.3.1 Planning and Zoning 12 days Mon 12/3/18 Tue 12/18/18
1.3.2 Lease/Contract 15 days Wed 12/19/18 Tue 1/8/19
1.4 Catering Design 37 days Mon 12/3/18 Tue 1/22/19
1.4.1 Employee Selection 5 days Mon 12/3/18 Fri 12/7/18
1.4.2 Catering venue Design 32 days Mon 12/10/18 Tue 1/22/19
1.4.2.1 Interior design 12 days Mon 12/10/18 Tue 12/25/18
1.4.2.2 Exterior design 12 days Mon 12/10/18 Tue 12/25/18
1.4.2.3 Build Out 15 days Wed 12/26/18 Tue 1/15/19
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
4ENVIRONMENTAL PROJECT MANAGEMENT: OPEN NEW BRANCH FOR FLIGHT CATERING
COMPANY
1.4.2.4 Construction 20 days Wed 12/26/18 Tue 1/22/19
1.4.2.4.1 Interior 15 days Wed 12/26/18 Tue 1/15/19
1.4.2.4.2 Exterior 20 days Wed 12/26/18 Tue 1/22/19
1.4.2.4.3 Utilities 7 days Wed 12/26/18 Thu 1/3/19
1.5 Communication and food
travelling 23 days Fri 1/4/19 Tue 2/5/19
1.5.1 Mini rail system 12 days Fri 1/4/19 Mon 1/21/19
1.5.2 Staffing 6 days Tue 1/22/19 Tue 1/29/19
1.5.3 Merchandising 7 days Tue 1/22/19 Wed 1/30/19
1.5.4 Pricing 5 days Tue 1/22/19 Mon 1/28/19
1.5.5 Display merchandise 4 days Thu 1/31/19 Tue 2/5/19
1.6 Marketing 12 days Wed 2/6/19 Thu 2/21/19
1.6.1 Advertisement 12 days Wed 2/6/19 Thu 2/21/19
1.7 Grand Opening 7 days Fri 2/22/19 Mon 3/4/19
1.7.1 Guests Invitation 5 days Fri 2/22/19 Thu 2/28/19
1.7.2 Entertainment 7 days Fri 2/22/19 Mon 3/4/19
1.7.3 Catering 2 days Fri 2/22/19 Mon 2/25/19
WBS
Figure 1: WBS
(Source: Created by Author)
Document Page
5ENVIRONMENTAL PROJECT MANAGEMENT: OPEN NEW BRANCH FOR FLIGHT CATERING
COMPANY
Critical Path Network Diagram
Document Page
6ENVIRONMENTAL PROJECT MANAGEMENT: OPEN NEW BRANCH FOR FLIGHT CATERING
COMPANY
Figure 2: Network Diagram
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
7ENVIRONMENTAL PROJECT MANAGEMENT: OPEN NEW BRANCH FOR FLIGHT CATERING
COMPANY
(Source: Created by Author Using MS project and WBS Pro)
Float period calculation:
WBS Task Name Early Start Early Finish Late Start Late Finish Total
Slack
1
Open a new branch of
flight catering
company
Thu 8/16/18 Mon 3/4/19 Thu 8/16/18 Mon 3/4/19 0 days
1.1 Project Initiation Thu 8/16/18 Fri 10/12/18 Thu 8/16/18 Fri 10/12/18 0 days
1.1.1 Business plan
development Thu 8/16/18 Fri 8/31/18 Thu 8/16/18 Fri 8/31/18 0 days
1.1.2 Project Funding Mon 9/3/18 Fri 9/21/18 Mon 9/3/18 Fri 9/21/18 0 days
1.1.3 Project Budgeting Mon 9/3/18 Tue 9/18/18 Thu 9/20/18 Fri 10/5/18 13 days
1.1.4 Services and Goods
Contracts/procurements Mon 9/24/18 Fri 10/5/18 Mon 9/24/18 Fri 10/5/18 0 days
1.1.5 Project Scheduling Mon 10/8/18 Fri 10/12/18 Mon 10/8/18 Fri 10/12/18 0 days
1.2 Requirement
Analysis
Mon
10/15/18 Fri 11/30/18 Mon
10/15/18 Fri 11/30/18 0 days
1.2.1 Target Market
Definition
Mon
10/15/18 Tue 10/23/18 Mon
10/15/18 Tue 10/23/18 0 days
1.2.2 Location Wed
10/24/18
Wed
10/31/18
Wed
10/24/18
Wed
10/31/18 0 days
1.2.2.1 Sanitation
Services
Wed
10/24/18
Mon
10/29/18 Fri 10/26/18 Wed
10/31/18 2 days
1.2.2.2 Utilities Wed
10/24/18
Wed
10/31/18
Wed
10/24/18
Wed
10/31/18 0 days
1.2.3 Space Thu 11/1/18 Wed
11/21/18 Thu 11/1/18 Wed
11/21/18 0 days
1.2.4 Staffing Thu 11/22/18 Fri 11/30/18 Thu 11/22/18 Fri 11/30/18 0 days
1.3 Selection of Site Mon 12/3/18 Tue 1/8/19 Fri 1/25/19 Mon 3/4/19 39 days
1.3.1 Planning and
Zoning Mon 12/3/18 Tue 12/18/18 Fri 1/25/19 Mon 2/11/19 39 days
1.3.2 Lease/Contract Wed
12/19/18 Tue 1/8/19 Tue 2/12/19 Mon 3/4/19 39 days
1.4 Catering Design Mon 12/3/18 Tue 1/22/19 Mon 12/3/18 Mon 3/4/19 0 days
1.4.1 Employee Selection Mon 12/3/18 Fri 12/7/18 Mon 12/3/18 Fri 12/7/18 0 days
1.4.2 Catering venue
Design
Mon
12/10/18 Tue 1/22/19 Mon
12/10/18 Mon 3/4/19 0 days
1.4.2.1 Interior design Mon
12/10/18 Tue 12/25/18 Fri 1/25/19 Mon 2/11/19 34 days
1.4.2.2 Exterior design Mon
12/10/18 Tue 12/25/18 Mon
12/10/18 Tue 12/25/18 0 days
1.4.2.3 Build Out Wed
12/26/18 Tue 1/15/19 Tue 2/12/19 Mon 3/4/19 34 days
Document Page
8ENVIRONMENTAL PROJECT MANAGEMENT: OPEN NEW BRANCH FOR FLIGHT CATERING
COMPANY
1.4.2.4 Construction Wed
12/26/18 Tue 1/22/19 Wed
12/26/18 Mon 3/4/19 0 days
1.4.2.4.1 Interior Wed
12/26/18 Tue 1/15/19 Tue 2/12/19 Mon 3/4/19 34 days
1.4.2.4.2 Exterior Wed
12/26/18 Tue 1/22/19 Tue 2/5/19 Mon 3/4/19 29 days
1.4.2.4.3 Utilities Wed
12/26/18 Thu 1/3/19 Wed
12/26/18 Thu 1/3/19 0 days
1.5 Communication and
food travelling Fri 1/4/19 Tue 2/5/19 Fri 1/4/19 Mon 3/4/19 0 days
1.5.1 Mini rail system Fri 1/4/19 Mon 1/21/19 Fri 1/4/19 Mon 1/21/19 0 days
1.5.2 Staffing Tue 1/22/19 Tue 1/29/19 Mon 2/25/19 Mon 3/4/19 24 days
1.5.3 Merchandising Tue 1/22/19 Wed 1/30/19 Tue 1/22/19 Wed 1/30/19 0 days
1.5.4 Pricing Tue 1/22/19 Mon 1/28/19 Tue 2/26/19 Mon 3/4/19 25 days
1.5.5 Display
merchandise Thu 1/31/19 Tue 2/5/19 Thu 1/31/19 Tue 2/5/19 0 days
1.6 Marketing Wed 2/6/19 Thu 2/21/19 Wed 2/6/19 Thu 2/21/19 0 days
1.6.1 Advertisement Wed 2/6/19 Thu 2/21/19 Wed 2/6/19 Thu 2/21/19 0 days
1.7 Grand Opening Fri 2/22/19 Mon 3/4/19 Fri 2/22/19 Mon 3/4/19 0 days
1.7.1 Guests Invitation Fri 2/22/19 Thu 2/28/19 Tue 2/26/19 Mon 3/4/19 2 days
1.7.2 Entertainment Fri 2/22/19 Mon 3/4/19 Fri 2/22/19 Mon 3/4/19 0 days
1.7.3 Catering Fri 2/22/19 Mon 2/25/19 Fri 3/1/19 Mon 3/4/19 5 days
Document Page
9ENVIRONMENTAL PROJECT MANAGEMENT: OPEN NEW BRANCH FOR FLIGHT CATERING
COMPANY
Figure 3: Gantt Chart
(Source; Created by Author using MS Project)
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
10ENVIRONMENTAL PROJECT MANAGEMENT: OPEN NEW BRANCH FOR FLIGHT CATERING
COMPANY
Organization charts i)
Figure 4: Organizational structure I)
(Source: Created by Author)
Document Page
11ENVIRONMENTAL PROJECT MANAGEMENT: OPEN NEW BRANCH FOR FLIGHT CATERING
COMPANY
Organization chart ii)
Figure 5: Organization structure II)
(Source: http://www.bonaireinternationalairport.com/organizational-chart)
Potential ‘cultures and’ and ‘methods of working’
Most of the engineering and manufacturing sites are feeling difficulties in instilling a
culture of accountability and ownership in the employees. The potential culture change and
smooth method of working can be implemented for the accomplishment of this purpose and
leading the project constraints as per the planning. Healthy environment for the employees is
always beneficial for the successful and efficient delivery of the project and thus, it is one of the
crucial consideration that should be made for the management of the project operational
activities (Kovack 2015). Implementing accountability cultures can be helpful in leveraging the
external motivation techniques in manner to make sure that the employees’ accountability can be
hold by the manager throughout the project lifecycle. In manner to motivate employees to be