This project management assignment, created for Victoria University's EPM5700 course, presents a detailed project execution plan for building an Information Technology Center. The solution includes a project calendar, work breakdown structure (WBS), organization breakdown structure (OBS), and a responsibility assignment matrix (RAM). It outlines tasks, durations, and logical relationships, visualized through a Gantt chart. The assignment provides a cost estimation based on the WBS, a comprehensive risk register, and a schedule for subcontractors. Key elements involve initiation, planning, design, testing, and closing phases, encompassing land acquisition, resource allocation, and infrastructure configuration. The project addresses potential risks such as land acquisition challenges, resource scarcity, project delays, increasing costs, and political and market risks, along with mitigation strategies. The project culminates in stakeholder sign-off and post-maintenance planning, demonstrating a structured approach to project management principles.

Running head: PROJECT MANAGEMENT AND INFORMATION TECHNOLOGY
EPM5700 Project Management and Information Technology
Assignment 2
Stage 2
WBS and manual Scheduling
Name of Student-
Name of University-
Author’s Note-
EPM5700 Project Management and Information Technology
Assignment 2
Stage 2
WBS and manual Scheduling
Name of Student-
Name of University-
Author’s Note-
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

1PROJECT MANAGEMENT AND INFORMATION TECHNOLOGY
Table of Contents
Project Calendar...............................................................................................................................2
Work Breakdown Structure.............................................................................................................2
Organization Breakdown Structure.................................................................................................3
Responsibility Assignment Matrix..................................................................................................3
List of tasks, durations and logical relationship..............................................................................6
Execution program...........................................................................................................................9
Cost of the project............................................................................................................................9
Risk Register..................................................................................................................................11
Sub-contractors schedule...............................................................................................................18
Bibliography..................................................................................................................................20
Table of Contents
Project Calendar...............................................................................................................................2
Work Breakdown Structure.............................................................................................................2
Organization Breakdown Structure.................................................................................................3
Responsibility Assignment Matrix..................................................................................................3
List of tasks, durations and logical relationship..............................................................................6
Execution program...........................................................................................................................9
Cost of the project............................................................................................................................9
Risk Register..................................................................................................................................11
Sub-contractors schedule...............................................................................................................18
Bibliography..................................................................................................................................20

2PROJECT MANAGEMENT AND INFORMATION TECHNOLOGY
Project Calendar
Figure 1: Project calendar showing holidays
(Source: M S Project)
Work Breakdown Structure
Building Information
Technology Centre
Initiation phase
Scope development
plan
Land Choosing for
IT centre
Analysis of contract
signing and feasibility
Permission approval
Planning phase
Resource collection
analysis
Identification of
project deliverables
Mapping skills
Team allocation plan
Risk management
analysis
QS audit
Designing and
establishing phase
Reviewing phase of
contract
Requirement
identification
phase for
infrastructure
configuration
Settlement of
network channel,
hardware and
software
Testing phase
Unit test
Test for user
acceptance
Closing phase
Stakeholder signoff
Planning phase for
post maintainence
Project Calendar
Figure 1: Project calendar showing holidays
(Source: M S Project)
Work Breakdown Structure
Building Information
Technology Centre
Initiation phase
Scope development
plan
Land Choosing for
IT centre
Analysis of contract
signing and feasibility
Permission approval
Planning phase
Resource collection
analysis
Identification of
project deliverables
Mapping skills
Team allocation plan
Risk management
analysis
QS audit
Designing and
establishing phase
Reviewing phase of
contract
Requirement
identification
phase for
infrastructure
configuration
Settlement of
network channel,
hardware and
software
Testing phase
Unit test
Test for user
acceptance
Closing phase
Stakeholder signoff
Planning phase for
post maintainence
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

3PROJECT MANAGEMENT AND INFORMATION TECHNOLOGY
Figure 2: Work Breakdown Structure
(Source: M S Project)
Organization Breakdown Structure
Figure 3: Organization Breakdown Structure
(Source: Created by Author)
Responsibility Assignment Matrix
Task Name Project
Manager
Finance
Manager
System
Develop
er
Coder Teste
r
Applicatio
n
Programm
Contra
ctors
Sub-
Contra
Sponsor
Figure 2: Work Breakdown Structure
(Source: M S Project)
Organization Breakdown Structure
Figure 3: Organization Breakdown Structure
(Source: Created by Author)
Responsibility Assignment Matrix
Task Name Project
Manager
Finance
Manager
System
Develop
er
Coder Teste
r
Applicatio
n
Programm
Contra
ctors
Sub-
Contra
Sponsor
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

4PROJECT MANAGEMENT AND INFORMATION TECHNOLOGY
er ctors
Scope development
plan
R A C
C I C I I
Land Choosing for
IT center
R R I A
C C C I
Analysis of contract
signing and
feasibility
A I C
A C I R
Permission approval R A I C I R
Resource collection
analysis
R
A A I
Identification of
project deliverables
R I A A
C R I
Mapping skills I R A I A A
Team allocation
plan
A I A
I R
Risk management
analysis
A C I
A R
er ctors
Scope development
plan
R A C
C I C I I
Land Choosing for
IT center
R R I A
C C C I
Analysis of contract
signing and
feasibility
A I C
A C I R
Permission approval R A I C I R
Resource collection
analysis
R
A A I
Identification of
project deliverables
R I A A
C R I
Mapping skills I R A I A A
Team allocation
plan
A I A
I R
Risk management
analysis
A C I
A R

5PROJECT MANAGEMENT AND INFORMATION TECHNOLOGY
QS audit I A C I R A A
Reviewing phase of
contract
R A I
C R A I
Requirement
identification
A I R
A C A I
Phase for
infrastructure
configuration
A C I R
R A C
Settlement of
network channel,
hardware and
software
A I R A
A R I
Unit test C A A I R A I
Test for user
acceptance
A I I
R A A
Stakeholder signoff R C A A A I R
Planning phase for
post maintenance
C I R A
A C I
QS audit I A C I R A A
Reviewing phase of
contract
R A I
C R A I
Requirement
identification
A I R
A C A I
Phase for
infrastructure
configuration
A C I R
R A C
Settlement of
network channel,
hardware and
software
A I R A
A R I
Unit test C A A I R A I
Test for user
acceptance
A I I
R A A
Stakeholder signoff R C A A A I R
Planning phase for
post maintenance
C I R A
A C I
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

6PROJECT MANAGEMENT AND INFORMATION TECHNOLOGY
List of tasks, durations and logical relationship
Task Name Duration Start Finish
Logical
Relationship
Building Information Technology
Centre
150 days Mon 9/09/19
Tue
14/04/20
Initiation phase 12 days Mon 9/09/19
Tue
24/09/19
Scope development plan 7 days Mon 9/09/19
Tue
17/09/19
Land Choosing for IT center 4 days
Wed
18/09/19
Mon
23/09/19
FS (Finish
to Start)
Analysis of contract signing and
feasibility
2 days
Wed
18/09/19
Thu
19/09/19
SS (Start to
Start)
Permission approval 1 day
Tue
24/09/19
Tue
24/09/19
FF (Finish
to Finish)
Planning phase 47 days
Wed
25/09/19
Mon 2/12/19
Resource collection analysis 11 days
Wed
25/09/19
Thu
10/10/19
FS
List of tasks, durations and logical relationship
Task Name Duration Start Finish
Logical
Relationship
Building Information Technology
Centre
150 days Mon 9/09/19
Tue
14/04/20
Initiation phase 12 days Mon 9/09/19
Tue
24/09/19
Scope development plan 7 days Mon 9/09/19
Tue
17/09/19
Land Choosing for IT center 4 days
Wed
18/09/19
Mon
23/09/19
FS (Finish
to Start)
Analysis of contract signing and
feasibility
2 days
Wed
18/09/19
Thu
19/09/19
SS (Start to
Start)
Permission approval 1 day
Tue
24/09/19
Tue
24/09/19
FF (Finish
to Finish)
Planning phase 47 days
Wed
25/09/19
Mon 2/12/19
Resource collection analysis 11 days
Wed
25/09/19
Thu
10/10/19
FS
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

7PROJECT MANAGEMENT AND INFORMATION TECHNOLOGY
Identification of project
deliverables
8 days Fri 11/10/19
Tue
22/10/19
FS
Mapping skills 7 days Fri 11/10/19
Mon
21/10/19
FS
Team allocation plan 8 days
Wed
23/10/19
Fri 1/11/19 FF
Risk management analysis 9 days Mon 4/11/19 Fri 15/11/19 FS
QS audit 11 days
Mon
18/11/19
Mon 2/12/19 FS
Designing and establishing phase 77 days Tue 3/12/19
Wed
25/03/20
Reviewing phase of contract 4 days Tue 3/12/19 Fri 6/12/19 FS
Requirement identification 14 days Mon 9/12/19
Mon
30/12/19
FS
phase for infrastructure
configuration
32 days
Tue
31/12/19
Fri 14/02/20 FS
Settlement of network channel,
hardware and software
27 days
Mon
17/02/20
Wed
25/03/20
FS
Identification of project
deliverables
8 days Fri 11/10/19
Tue
22/10/19
FS
Mapping skills 7 days Fri 11/10/19
Mon
21/10/19
FS
Team allocation plan 8 days
Wed
23/10/19
Fri 1/11/19 FF
Risk management analysis 9 days Mon 4/11/19 Fri 15/11/19 FS
QS audit 11 days
Mon
18/11/19
Mon 2/12/19 FS
Designing and establishing phase 77 days Tue 3/12/19
Wed
25/03/20
Reviewing phase of contract 4 days Tue 3/12/19 Fri 6/12/19 FS
Requirement identification 14 days Mon 9/12/19
Mon
30/12/19
FS
phase for infrastructure
configuration
32 days
Tue
31/12/19
Fri 14/02/20 FS
Settlement of network channel,
hardware and software
27 days
Mon
17/02/20
Wed
25/03/20
FS

8PROJECT MANAGEMENT AND INFORMATION TECHNOLOGY
Testing phase 10 days
Thu
26/03/20
Wed 8/04/20
Unit test 3 days
Thu
26/03/20
Mon
30/03/20
FS
Test for user acceptance 7 days
Tue
31/03/20
Wed 8/04/20 FS
Closing phase 4 days Thu 9/04/20
Tue
14/04/20
Stakeholder signoff 3 days Thu 9/04/20
Mon
13/04/20
FS
Planning phase for post
maintenance
1 day
Tue
14/04/20
Tue
14/04/20
FS
Testing phase 10 days
Thu
26/03/20
Wed 8/04/20
Unit test 3 days
Thu
26/03/20
Mon
30/03/20
FS
Test for user acceptance 7 days
Tue
31/03/20
Wed 8/04/20 FS
Closing phase 4 days Thu 9/04/20
Tue
14/04/20
Stakeholder signoff 3 days Thu 9/04/20
Mon
13/04/20
FS
Planning phase for post
maintenance
1 day
Tue
14/04/20
Tue
14/04/20
FS
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide

9PROJECT MANAGEMENT AND INFORMATION TECHNOLOGY
Execution program
Figure 4: Gantt chart
(Source: Created by Author using MS Project)
Cost of the project
WBS Task Name Duration Cost
0
Building Information
Technology Centre
150 days
$137,155,680.00
1 Initiation phase 12 days $100,006,880.00
1.1 Scope development plan 7 days $4,480.00
Execution program
Figure 4: Gantt chart
(Source: Created by Author using MS Project)
Cost of the project
WBS Task Name Duration Cost
0
Building Information
Technology Centre
150 days
$137,155,680.00
1 Initiation phase 12 days $100,006,880.00
1.1 Scope development plan 7 days $4,480.00
Paraphrase This Document
Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser

10PROJECT MANAGEMENT AND INFORMATION TECHNOLOGY
1.2
Land Choosing for IT
center
4 days
$100,000,000.00
1.3
Analysis of contract
signing and feasibility
2 days
$1,920.00
1.4 Permission approval 1 day $480.00
2 Planning phase 47 days $27,280.00
2.1
Resource collection
analysis
11 days
$10,120.00
2.2
Identification of project
deliverables
8 days
$3,200.00
2.3 Mapping skills 7 days $6,440.00
2.4 Team allocation plan 8 days $3,200.00
2.5
Risk management
analysis
9 days
$4,320.00
2.6 QS audit 11 days $0.00
3
Designing and
establishing phase
77 days
$37,113,440.00
3.1 Reviewing phase of 4 days $1,440.00
1.2
Land Choosing for IT
center
4 days
$100,000,000.00
1.3
Analysis of contract
signing and feasibility
2 days
$1,920.00
1.4 Permission approval 1 day $480.00
2 Planning phase 47 days $27,280.00
2.1
Resource collection
analysis
11 days
$10,120.00
2.2
Identification of project
deliverables
8 days
$3,200.00
2.3 Mapping skills 7 days $6,440.00
2.4 Team allocation plan 8 days $3,200.00
2.5
Risk management
analysis
9 days
$4,320.00
2.6 QS audit 11 days $0.00
3
Designing and
establishing phase
77 days
$37,113,440.00
3.1 Reviewing phase of 4 days $1,440.00

11PROJECT MANAGEMENT AND INFORMATION TECHNOLOGY
contract
3.2
Requirement
identification
14 days
$8,960.00
3.3
phase for infrastructure
configuration
32 days
$23,040.00
3.4
Settlement of network
channel, hardware and
software
27 days
$37,080,000.00
4 Testing phase 10 days $5,760.00
4.1 Unit test 3 days $1,728.00
4.2 Test for user acceptance 7 days $4,032.00
5 Closing phase 4 days $2,320.00
5.1 Stakeholder signoff 3 days $1,920.00
5.2
Planning phase for post
maintenance
1 day
$400.00
Risk Register
Risk Risk Risk Description Likeli Impa Mitigation Plan
contract
3.2
Requirement
identification
14 days
$8,960.00
3.3
phase for infrastructure
configuration
32 days
$23,040.00
3.4
Settlement of network
channel, hardware and
software
27 days
$37,080,000.00
4 Testing phase 10 days $5,760.00
4.1 Unit test 3 days $1,728.00
4.2 Test for user acceptance 7 days $4,032.00
5 Closing phase 4 days $2,320.00
5.1 Stakeholder signoff 3 days $1,920.00
5.2
Planning phase for post
maintenance
1 day
$400.00
Risk Register
Risk Risk Risk Description Likeli Impa Mitigation Plan
⊘ This is a preview!⊘
Do you want full access?
Subscribe today to unlock all pages.

Trusted by 1+ million students worldwide
1 out of 22
Related Documents

Your All-in-One AI-Powered Toolkit for Academic Success.
+13062052269
info@desklib.com
Available 24*7 on WhatsApp / Email
Unlock your academic potential
Copyright © 2020–2025 A2Z Services. All Rights Reserved. Developed and managed by ZUCOL.