ERP System Development: Statement of Work for Health Industry Project

Verified

Added on  2023/06/16

|4
|1471
|375
Project
AI Summary
This project focuses on developing an ERP system for the health industry to manage services, equipment, and medicines efficiently. The project aims to improve data and service delivery through the application of project management concepts. It involves integrating a large amount of health industry data onto a single platform, utilizing hardware and software components such as computer devices, network applications, and testing software. The waterfall methodology is adopted for project completion, with key deliverables including project planning, resource planning, risk management, system designing, development, testing, and final documentation. The project spans from November 22, 2017, to May 29, 2018, and includes phases such as initial planning, system development, and project closure. The statement of work also identifies potential risks, stakeholders, applicable standards, acceptance criteria, and special requirements, emphasizing the importance of data privacy and security during data transfer and integration.
Document Page
Statement of Work Student Name:
Project Summary
Service Description
Deliverables
Deliverables Schedule:
Serial No. Project Deliverables Duration Start Finish
1 Initial Phase 12 days Wed 11/22/17 Thu 12/7/17
2 Planning Phase 6 days Fri 12/8/17 Fri 12/15/17
3 System Development 108 days Mon 12/18/17 Wed 5/16/18
4 Designing of the system 22 days Mon 12/18/17 Tue 1/16/18
5 Coding Phase 34 days Wed 1/17/18 Mon 3/5/18
6 Programming Phase 44 days Tue 3/6/18 Fri 5/4/18
7 System Integration 8 days Mon 5/7/18 Wed 5/16/18
8 Project Closure and 9 days Thu 5/17/18 Tue 5/29/18
The project is development of an ERP system for managing the information of the services, equipments, and
medicines in the health industry. The project would provide the development of the improvement of the
activities of the data and service delivery in the organization. The analysis of the project management
concepts would be implied for forming the development of the information system. The health organization
would require the use of advanced technology and process for the management of the huge amount of data
and information processing in the organization. The management of the operations would be eased due to the
implication of the effective and improved processing and development. The integrated data system would be
helpful in implying the effective data management for the health organization. The project would form the
integration of the operation and formation of the support and development for the health industries.
The scope of the project would involve the management of the large amount of data and information present
in the health industry on a single platform and the management of the effective and improved project
operations. The development of the project scope can be developed for the deployment of smart project
management concepts and principles for the development of the operations. The hardware requirements of
the project are the computer devices, network components, testing tools, storage database, equipments, and
basic infrastructure. The software requirements of the project are the network application, testing software,
programming platform, and operating system. The nature of work required for the project is IT based
software application development project and all activities are technology based. The waterfall methodology
would be followed for the completion of the project and development of the effective and improved
processes. The development of the project plan would include the following sub-components,
Project Planning
Project Resource Planning
Project Risk Management
System Designing
System Development
System Testing
Final Documentation
tabler-icon-diamond-filled.svg

Paraphrase This Document

Need a fresh take? Get an instant paraphrase of this document with our AI Paraphraser
Document Page
Documentation
Period of Performance:
The project is developed for completing the development of the ERP system for the health industry and it would
involve the following activities,
WBS Task Name Working hours Number of hours Start Finish
1 Initial Phase 8 hours 96 hours Wed 11/22/17 Thu 12/7/17
2 Planning Phase 8 hours 48 hours Fri 12/8/17 Fri 12/15/17
3 System
Development 3 hours 324 hours Mon 12/18/17 Wed 5/16/18
3.1 Designing of the
system 4 hours 88 hours Mon 12/18/17 Tue 1/16/18
3.2 Coding Phase 2 hours 68 hours Wed 1/17/18 Mon 3/5/18
3.3 Programming
Phase 2 hours 88 hours Tue 3/6/18 Fri 5/4/18
3.4 System
Integration 6 hours 48 hours Mon 5/7/18 Wed 5/16/18
4
Project Closure
and
Documentation
3 hours
27 hours
Thu 5/17/18 Tue 5/29/18
The project would carry on at the premise of the health industry and it would run from Wed 11/22/17 to Tue
5/29/18 (135 days).
Payment Schedule
The project is scheduled for the development of the effective and improved ERP system development and it is
based on fixed price term project contract. The software development projects require the cost payment at the
milestones.
The resources required for the project include project manager, developer, IT engineer, planner, budgeter,
analyst, database administrator, computer system, software, and hardware components. The overall cost of the
project comprises of the fixed cost of the materials and the salary given to the human resources of the project.
Sub-Contractors
The materials (computer system, network devices, and storage) and their delivery to the organization are being
outsourced to an external contractor.
Representatives
The project team representative includes,
Name Designation Signature
<<name of the student>> Project Manager <<name of the student>>
John Lewis IT engineer John Lewis
Andrew Evans Project Sponsor Andrew Evans
Katherine Beta Supplier (Contractor) Katherine Beta
SUB SECTIONS
Document Page
I. Risks and Assumptions:
The project is an IT based software development project and it would involve the use of advanced technology
for the integration of the operations. However, the use of the IT development would have to face the following
issues,
a. Delay in operations
b. Design issues
c. Over budget
d. Failure of Database Integration
The assumptions of the project are,
a) Resources would be available for the development of the project
b) Human resources for the project would work peacefully
c) Support of the clients would be developed for the integration of the operations.
II. Stakeholders:
The stakeholders of the project are,
Developer the software developer is the responsible for the development of the software and programming
the functions of the ERP system relevant for the health industry.
IT engineer the IT engineer is helpful for the major development of the system design and analyzing the
system requirement and configuration for the ERP system implication
Planner the planner is responsible for the developing the project plan for the ERP system implementation
and scheduling of the project
Budgeter the budgeter helps in forming the development of the project budget and resource allocation
Analyst the analyst is responsible for the analysis of the client’s requirements
Database administrator the database administrator develops a storage system and integrates the database
with the data available for Health Industry.
III. Applicable Standards:
The applicable standard for the development of the ERP system is ACS policies, principles, and rules. The
organization would have to follow the Australian WHS policies for ensuring the successful completion of the
project.
IV. Acceptance Criteria:
The acceptance criteria for the project of implementing ERP system are,
Successful functioning of ERP system
Completion of the project in estimated time and budget
Database would be helpful for easing the operations of the organization
V. Special Requirements or out of scope items:
The project needs to follow the Privacy and Security of the information while transferring the data from storage
to the integrated database of ERP. It is mandatory for ensuring that the violation of the privacy and infiltration
of the database would not occur.
Document Page
BIBLIOGRAPHY
Boyd, J., (2013). Statement of Work (SOW) iNEMI Board Assembly TIG Board Assembly and Test Process
Optimization.
Chan, S.M., (2017). Slurry Coating System Statement of Work and Specification (No. LLNL--TR-724537).
Lawrence Livermore National Lab.(LLNL), Livermore, CA (United States).
Fiaccadori, E., Pistolesi, V., Mariano, F., Mancini, E., Canepari, G., Inguaggiato, P., Pozzato, M. & Morabito,
S., (2015). Regional citrate anticoagulation for renal replacement therapies in patients with acute kidney
injury: a position statement of the Work Group “Renal Replacement Therapies in Critically Ill Patients”
of the Italian Society of Nephrology.
Housley, R., (2016). Statement of Work for Extensions to the IETF Datatracker for Author Statistics.
Kerzner, H., (2013). Project management: a systems approach to planning, scheduling, and controlling. John
Wiley & Sons.
Schenkman, B.L., (2017). Statement of Work Electrical Energy Storage System Installation at Sandia National
Laboratories (No. SAND2017-2728R). Sandia National Laboratories (SNL-NM), Albuquerque, NM
(United States).
Wade, F.E., (2017). B827 Chemical Synthhesis Project-Industrial Control System Integration-Statement of
Work & Specification with Attachments 1-14 (No. LLNL-SR-729705). Lawrence Livermore National
Laboratory (LLNL), Livermore, CA.
Webster, R. & Blatchford, P., (2015). Worlds apart? The nature and quality of the educational experiences of
pupils with a statement for special educational needs in mainstream primary schools. British
Educational Research Journal, 41(2), pp.324-342.